An energy-saving optimization control method for air compression system based on terminal gas demand changes

By constructing a topological model of the air compressor system and a neural network to predict terminal gas demand and adjust the operating parameters of the air compressor system equipment, the problem of high energy consumption of the air compressor system in the existing technology has been solved, and the energy-saving optimization and gas demand of the air compressor system have been achieved. Accurate predictions.

CN118361386BActive Publication Date: 2024-10-22NANJING DEEPCTRLS TECHNOLOGIES CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410790644.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-19
Publication Date
2024-10-22
Estimated Expiration
2044-06-19

AI Technical Summary

Technical Problem

The existing air compressor system has a small energy saving effect when adjusting the number of air compressors started and the working efficiency of the frequency conversion unit, and fails to effectively consider the energy consumption issues caused by changes in cooling side control of the air compressor and changes in terminal air demand.

Method used

By constructing a topology model of the air compressor system and combining neural networks and LSTM networks, we can predict changes in terminal air demand in real time and adjust the operating parameters of air compressor units, drying units, cooling towers and cooling water pumps to optimize the energy consumption of the air compressor system. .

Benefits of technology

On the premise of meeting the actual demand for compressed air, it effectively reduces the energy consumption of the air compressor system, provides accurate prediction of air demand and exhaust pressure, and improves the energy-saving optimization effect of the air compressor system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118361386B_ABST
    Figure CN118361386B_ABST
Patent Text Reader

Abstract

The present invention discloses an energy-saving optimization control method for an air compression system based on changes in terminal gas demand, which predicts changes in gas demand caused by changes in the terminal gas user or other reasons in real time, and adjusts the air compressor unit, drying unit, cooling tower and cooling water pump at the same time according to the prediction results, thereby effectively reducing the energy consumption of the air compression system while meeting the actual demand for compressed air. The method is particularly used in an air compression system when multiple air compressor units are centrally connected or combined in multiple connection modes.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of air compressor energy saving, and in particular to an air compressor system energy saving optimization control method based on terminal gas demand changes. Background Art

[0002] The air compression system is mainly composed of compressors, coolers, drainers, gas storage tanks, gas filters, etc. Among them, the compressor is the core component of the air compression system. It compresses the air into high-pressure gas and provides it to various pneumatic equipment. The cooler is used to reduce the gas temperature, the drainer is used to remove moisture from the compressed air, the gas storage tank is used to store compressed air, and the gas filter is used to filter impurities in the air. Compressed air has been widely used in modern industries such as manufacturing, textiles, and medical care. How to reduce the energy consumption of air compression system operation has become an important issue that needs to be solved urgently.

[0003] The invention with patent publication number CN115933398A discloses an air compressor system linkage control energy-saving method and system based on the Internet of Things, including the establishment of an Internet of Things platform system, and the energy-saving method includes the following steps: S1. Establishing a compressed air preparation system operation monitoring platform based on the Internet of Things method, and the operation monitoring platform is electrically connected to each device in the Internet of Things platform system; S2. Collecting energy consumption data of each device in the system through Internet of Things technology; S3. Establishing an AI algorithm model of a compressed air group control system based on the Internet of Things platform system; S4. Based on the data collected in S2 and through the AI ​​algorithm model, establishing an efficiency curve model for each device in the system, and automatically optimizing it during operation; the operation monitoring platform is composed of a control system function module, an energy management module, and a system health management module. The method and system proposed in the invention can accurately fit and match the compressed air supply curve with the terminal demand, ensuring that the system stably supplies production needs while reducing energy waste caused by excessive output. However, the above-mentioned energy-saving method of linkage control of air compressor system based on Internet of Things achieves energy saving by adjusting the number of air compressor startups and the working efficiency of the frequency conversion unit. This method saves less energy. The efficiency curve model established based on AI algorithm model data has a large deviation from the actual equipment data and does not take into account the control of the air compressor cooling side.

[0004] The invention with patent publication number CN117869256A discloses a method, device, system, equipment and medium for regulating the flow of cooling water pump of air compressor. First, the exhaust temperature value, the temperature difference between the inlet water temperature and the wet bulb temperature, the return water temperature value, and the loading operation time and unloading operation time are extracted. Then, when the temperature difference is normal and the exhaust temperature value is out of the preset range, these data are imported into the cooling water pump frequency prediction model pre-trained based on the machine learning algorithm, and the current pump applicable frequency estimation value of the air compressor cooling water pump is output. Finally, the estimation value is fed back to the air compressor controller as the target frequency, so that the air compressor controller adjusts the working frequency of the air compressor cooling water pump to the target frequency, so that the temperature of the air compressor host can be maintained stable, the operating conditions of the host can be improved, the operating efficiency of the host can be improved, and energy waste can be avoided. However, the invention only focuses on the frequency regulation of the cooling water pump, and does not consider the energy consumption of the entire air compressor system when the gas demand changes due to changes in the terminal gas user or other reasons. Summary of the invention

[0005] The purpose of the present invention is to provide an energy-saving optimization control method for an air compression system based on changes in terminal gas demand. By constructing an air compression system topology model, the changes in terminal gas demand caused by changes in the terminal gas main body and other reasons are predicted in real time. According to the prediction results, the air compressor unit, drying unit, cooling tower and cooling water pump are adjusted at the same time, and the energy consumption of the air compression system is effectively reduced while meeting the actual demand for compressed air. This method is particularly used in air compression systems such as when multiple air compressor units are centrally connected or combined in a variety of connection methods.

[0006] In order to achieve the above technical objectives, the technical solution adopted by the present invention is:

[0007] An air compression system energy-saving optimization control method based on terminal gas demand changes, characterized in that the air compression system energy-saving optimization control method comprises the following steps:

[0008] S1, build a topological model of the air compression system to be optimized. The equipment of the air compression system includes air compressor units, gas storage tanks, drying units and supporting cooling systems. The air compression system corresponds to multiple terminals, and each terminal corresponds to at least one gas-using device; collect historical operation data of each device in the air compression system;

[0009] S2, combining the historical operation data collected in step S1 and the physical property data of each device in the air compressor system, constructs the energy consumption model of each device in the air compressor system, including the air compressor energy consumption model , Drying unit energy consumption model and cooling system energy consumption model ;

[0010] S3, build a gas demand prediction model, collect the compressed air usage of each terminal in the current cycle, input it into the gas demand prediction model, predict the gas demand of each terminal in the next cycle, and obtain the compressed air demand of each terminal , calculate the total compressed air demand of all terminals , ;

[0011] S4, combined with the total compressed air demand , Compressed air output of each air compressor unit and the gas storage capacity of the gas tank , taking the minimum number of air compressor units in operation as the optimization goal, calculate the future cycle Changing trend of the number of operating internal air compressor units ;

[0012] S5: Analyze the main gas user combination, historical compressed air usage and historical exhaust pressure requirements of each terminal to obtain the gas usage type of each gas user, combined with the predicted future cycle Compressed air demand at each end , analyze and obtain the exhaust pressure requirement at each end of the next cycle , calculate the total exhaust pressure requirement of all terminals ;

[0013] S6, the exhaust pressure requirements of all terminals in the next cycle T , Total compressed air demand And the changing trend of the number of air compressor units in operation Input air compressor energy consumption model , taking the minimum total energy consumption of the air compressor unit as the optimization goal, the loading pressure setting value and the unloading pressure setting value of each air compressor unit are calculated;

[0014] S7, combined with the loading pressure setting value and unloading pressure setting value of each air compressor unit, import the energy consumption model of the drying unit , the dew point temperature of the compressed air in the next cycle T Make an estimate based on the dew point temperature of the compressed air Calculate the next cycle Changing trend of the number of internal drying units in operation ;

[0015] S8, the changing trend of the number of air compressor units in operation The measured value of the cooling water inlet tower temperature is imported into the cooling system energy consumption model , the total heat to be exchanged is obtained, and the minimum total energy consumption of the cooling system is taken as the optimization goal, and the future cycle is calculated Changing trend of the number of fans in cooling towers , the operating frequency of the cooling tower fan and the operating frequency of the cooling pump.

[0016] Furthermore, in step S3, the process of constructing a gas demand prediction model includes the following steps:

[0017] Construct a topological relationship between each terminal and all corresponding gas users; collect the compressed air usage sequence of each terminal and the compressed air usage sequence of each gas user corresponding to the terminal;

[0018] The compressed air usage sequence of each terminal and the compressed air usage sequence of each gas user corresponding to the terminal are divided into time periods, the compressed air usage sequence of the terminal and the compressed air usage sequence of each gas user in each time period are used as input, and the connectivity state of each gas user is used as output to generate a number of sample data;

[0019] A gas consumption decomposition model is constructed using a neural network model, and sample data is used to train and test the gas consumption decomposition model;

[0020] According to the combination of different gas users at each terminal, the LSTM network model is used to build a gas consumption prediction model; the input of the gas consumption prediction model is the compressed air usage sequence of the gas user combination in the previous period T, and the output is the compressed air usage sequence of the gas user combination in the next period T; the gas consumption prediction model of each gas user combination is trained using the collected historical compressed air usage sequence of each gas user combination;

[0021] When executing the gas consumption prediction of a certain terminal in actual production, the compressed air usage sequence of the previous period T with the current moment as the end point of the terminal is input into the gas consumption decomposition model, and the connectivity status of each gas-using entity corresponding to the terminal is output; then, for the combination of gas-using entities in the connectivity state, the gas consumption prediction model of the corresponding gas-using entity combination is called to output the compressed air usage sequence of the next period T with the current moment as the starting point.

[0022] Furthermore, in step S4, the minimum number of operating air compressor units is taken as the optimization goal, and the change trend of the number of operating air compressor units in the next cycle is calculated. The process includes the following steps:

[0023] S41, draw the compressed air demand total amount curve according to the time axis, remove and correct the burrs in the compressed air demand total amount curve based on the gas tank capacity, analyze the corrected compressed air demand total amount curve, and calculate the future cycle Divide into K time periods, and calculate the Gas characteristics are classified into adjacent periods. The gas consumption characteristics are different; according to the change trend of the number of air compressors required within a period of time, the gas consumption characteristics of each period are divided into the flat period, the stable rising period, the stable falling period, the sudden rising period and the sudden falling period; ;

[0024] S42, select one of the time periods in turn , determine the current period Gas consumption characteristics, if the current period The gas usage characteristic is a flat period, and the process goes to step S43; if the current period The gas consumption characteristic is in a stable rising period, and the process goes to step S44. If the gas consumption characteristic in the current period is The gas consumption characteristic is in a steady decline period, and the process goes to step S45; if the current period The gas consumption characteristic is a sudden increase period, and the process goes to step S46; if the gas consumption characteristic of the current period When the gas consumption characteristic is in a sudden drop period, the process goes to step S47;

[0025] S43, determine the total amount of compressed air missing in the gas tank , based on the current period Average gas consumption and the total amount of compressed air missing from the air tank The sum of is the estimated gas demand, combined with the compressed air output of each air compressor unit , calculate the time period Minimum number of air compressor units in operation ;

[0026] S44, determine the total amount of compressed air missing in the gas tank , in the current period Gas demand Add the total amount of compressed air missing from the air tank The corrected gas demand estimate function is obtained by combining the compressed air production of each air compressor unit , calculate the current period Changing trend of the number of air compressor units in operation And the startup time of the newly added air compressor unit;

[0027] S45, determine the total amount of remaining compressed air in the gas tank , in the current period Gas demand Subtract the remaining compressed air in the air tank , and obtain the corrected gas demand estimate function, combined with the compressed air output of each air compressor unit , calculate the current period Changing trend of the number of air compressor units in operation And the reduced shutdown time of each air compressor unit;

[0028] S46, determine the total amount of remaining compressed air in the gas tank , based on the peak gas consumption in the current period Subtract the remaining compressed air amount in the air tank The difference is the estimated gas demand, combined with the compressed air output of each air compressor unit. , calculate the time period Minimum number of air compressor units in operation , and recalculate the end time of the period, based on the next period Based on the gas usage characteristics, the number of operating air compressor units is adjusted at the end of the recalculated period;

[0029] S47, determine the total amount of remaining compressed air in the gas tank , based on the current period Peak gas consumption Subtract the remaining compressed air in the air tank The difference is the estimated gas demand, and the end time of the period is recalculated according to the next period. According to the gas consumption characteristics, the number of operating air compressor units is adjusted at the beginning of the recalculated period.

[0030] Furthermore, in step S5, an exhaust pressure prediction model is constructed to predict the exhaust pressure in the next cycle. Exhaust pressure requirement at each end Prediction is carried out, specifically including: collecting the overall exhaust pressure sequence and compressed air usage sequence of each terminal and the individual exhaust pressure sequence of each gas user corresponding to the terminal; classifying the individual exhaust pressure sequence according to the gas usage type of the gas user in different application scenarios;

[0031] For different combinations of gas users, the overall exhaust pressure sequence and compressed air usage sequence of each terminal and the individual exhaust pressure sequence of each gas user corresponding to the terminal are divided into time periods, and the compressed air usage sequence and overall exhaust pressure sequence of the terminal in each time period are used as input, and the gas type combination of the terminal is used as output to generate a number of sample data;

[0032] The exhaust pressure classification model is constructed by using a neural network model, and the exhaust pressure classification model is trained and tested using sample data;

[0033] For each terminal different gas type combination, the LSTM network model is used to build an exhaust pressure prediction model; the input of the exhaust pressure prediction model is the compressed air usage sequence and the overall exhaust pressure sequence of the gas type combination in the previous period T, and the output is the exhaust pressure sequence of the main gas type combination in the next period T; the exhaust pressure prediction model of each gas type combination is trained using the collected historical compressed air usage sequence and the overall exhaust pressure sequence;

[0034] When performing gas pressure prediction for a certain terminal in actual production, the compressed air usage sequence and overall exhaust pressure sequence of the previous cycle T with the current moment as the end point of the terminal are input into the exhaust pressure classification model, and the gas type combination corresponding to the terminal is output; then, the exhaust pressure prediction model of the corresponding gas type combination is called to output the exhaust pressure sequence of the next cycle T with the current moment as the starting point.

[0035] Furthermore, the air compressor energy consumption model It includes: air compressor working condition generation unit, gas usage time division unit, and air compressor working condition screening unit;

[0036] The air compressor working condition generation unit is used to collect the exhaust pressure, compressed air volume and energy consumption values ​​of different air compressor units under different working conditions to generate working condition sample data;

[0037] The gas usage period division unit divides the future cycle T into several gas usage periods according to the number of air compressor units in operation and the usage, and according to the exhaust pressure demand , Total compressed air demand And the number of air compressor units in operation, filter all the operating condition combinations of air compressor units that meet the conditions;

[0038] The air compressor working condition screening unit calculates the compressed air volume and energy consumption value generated under the working condition combination of each air compressor unit screened out, and calculates the total compressed air volume and energy consumption value of all air use periods. Under the premise of selecting the operating condition combination of the air compressor unit in each gas usage period with the smallest total energy consumption value.

[0039] Furthermore, the cooling system energy consumption model It includes an optimal cooling condition setting unit, a heat calculation unit and a cooling condition screening unit;

[0040] The heat calculation unit is used to take the number of operating air compressor units and the measured value of the water temperature of the cooling water inlet tower as input parameters to estimate the total heat to be exchanged; the optimal cooling condition setting unit constructs a combination of operating conditions of the cooling tower and the cooling pump that meets the cooling demand for different total heat to be exchanged, calculates the energy consumption values ​​under different operating condition combinations, selects the operating condition combination of the cooling tower and the cooling pump with the smallest energy consumption value as the optimal operating condition for the total heat to be exchanged, and generates a query table of the total heat to be exchanged-optimal operating condition; the cooling condition screening unit is used to select the change trend of the number of operating air compressor units in the known Based on the measured value of the water temperature entering the cooling water tower, the heat calculation unit is called to estimate the total heat to be exchanged, and then the change trend of the operating condition combination of the cooling tower and the cooling pump in the next period T is obtained.

[0041] Compared with the prior art, the beneficial effects of the present invention are as follows: First, the energy-saving optimization control method of the air compression system based on the change of terminal gas demand of the present invention, through the constructed air compression system topology model, makes real-time predictions on the changes in gas demand caused by changes in the terminal gas users or other reasons, and adjusts the air compressor unit, drying unit, cooling tower and cooling water pump at the same time according to the prediction results, thereby effectively reducing the energy consumption of the air compression system while meeting the actual demand for compressed air.

[0042] Second, the energy-saving optimization control method of the air compression system based on the change of terminal gas demand of the present invention, according to the actual topological structure of the air compression system, combines the neural network and the LSTM network to construct a gas demand prediction model, and on this basis, constructs an exhaust pressure prediction model, and at the same time accurately predicts the compressed air demand and exhaust pressure, providing an effective data basis for the energy-saving optimization of the air compression system. BRIEF DESCRIPTION OF THE DRAWINGS

[0043] Figure 1 This is a flow chart of the energy-saving optimization control method of the air compression system based on the change of terminal gas demand of the present invention. DETAILED DESCRIPTION

[0044] The embodiments of the present invention are further described in detail below in conjunction with the accompanying drawings.

[0045] See also Figure 1 The present invention discloses an energy-saving optimization control method for an air compression system based on changes in terminal gas demand, and the energy-saving optimization control method for an air compression system comprises the following steps:

[0046] S1, construct a topological model of the air compression system to be optimized. The equipment of the air compression system includes an air compressor unit, a gas storage tank, a drying unit and a supporting cooling system. The air compression system corresponds to multiple terminals, and each terminal corresponds to at least one gas-using device; collect the historical operation data of each device in the air compression system. In practical applications, the supporting equipment of the air compression system is not limited to the aforementioned types, but also includes filtering equipment, oil-gas separation equipment, etc. Some of the equipment and the air compressor unit are one-to-one matching settings. When the air compressor is shut down, these supporting equipment will also shut down to save energy. Some equipment energy consumption is turned on for a long time, and the energy consumption is relatively fixed. In practical applications, the drying unit and the air compressor are not necessarily one-to-one matching settings. The working state of the drying unit is more related to the parameters of the compressed air; regarding cooling, the air compressor unit itself needs a cooling system. This type of cooling system is matched with the air compressor unit, and the drying unit also needs a cooling system. The cooling system in the present invention refers to the former, that is, the optimization of the control parameters of the cooling system is directly related to the number of air compressor units in operation, and the precise control of the number of air compressor units in operation is closely related to the prediction results of the terminal gas demand. Therefore, the present invention takes the terminal gas consumption as a benchmark and adjusts the working conditions of the air compressor unit, drying unit and cooling system (cooling tower and cooling water pump) of the air compression system, so that the air compression system can reduce power consumption as much as possible while meeting the terminal gas demand.

[0047] S2, combining the historical operation data collected in step S1 and the physical property data of each device in the air compressor system, constructs the energy consumption model of each device in the air compressor system, including the air compressor energy consumption model , Drying unit energy consumption model and cooling system energy consumption model .

[0048] Air compressor energy consumption model The input is the exhaust pressure requirement of all terminals , Total compressed air demand And the changing trend of the number of air compressor units in operation , the output is the loading pressure setting value and unloading pressure setting value of each compressor unit.

[0049] Energy consumption model of drying unit The input is the loading pressure setting value and unloading pressure setting value of each air compressor unit, and the output is the future cycle Changing trend of the number of internal drying units in operation .

[0050] Cooling system energy consumption model The input is the changing trend of the number of air compressor units in operation And the cooling water inlet tower water temperature measurement value, output the next cycle Changing trend of the number of fans in cooling towers , the operating frequency of the cooling tower fan and the operating frequency of the cooling pump.

[0051] S3, build a gas demand prediction model, collect the compressed air usage of each terminal in the current cycle, input it into the gas demand prediction model, and predict the future cycle. The gas demand of each terminal is predicted to obtain the compressed air demand of each terminal. and total compressed air demand , .

[0052] There are various ways to connect air compressors and gas-using equipment, and not every gas-using equipment is always connected. In theory, one air compressor can drive 3-5 gas-using equipment to work at the same time. For large-volume gas-using occasions, multiple air compressors will be centrally connected and then connected to multiple gas-using equipment through gas storage tanks. If you want to achieve effective energy saving in the air compression system, it is crucial to predict the terminal gas demand in the future.

[0053] This embodiment uses the most complex and currently most ineffective energy-consuming situation of centralized connection (after multiple air compressor units are connected to each other, the compressed air generated is transferred in the gas storage tank and then connected to different gas users or gas user combinations through various terminals) as an example to illustrate the subsequent energy-saving optimization method. For other situations, for example, for directly connected air compressors (or multiple air compressors in series) and gas users, as long as the gas user needs gas, the air compressor unit needs to be turned on. In terms of energy-saving processing, it is only necessary to consider how the loading pressure and unloading pressure setting values ​​of a single air compressor body can save as much energy as possible while meeting the needs of the gas user.

[0054] Preferably, the process of constructing a gas demand forecasting model using a neural network model and an LSTM network model includes the following steps:

[0055] Construct a topological relationship between each terminal and all corresponding gas users; collect the compressed air usage sequence of each terminal and the compressed air usage sequence of each gas user corresponding to the terminal;

[0056] The compressed air usage sequence of each terminal and the compressed air usage sequence of each gas user corresponding to the terminal are divided into time periods, the compressed air usage sequence of the terminal and the compressed air usage sequence of each gas user in each time period are used as input, and the connectivity state of each gas user is used as output to generate a number of sample data;

[0057] A gas consumption decomposition model is constructed using a neural network model, and sample data is used to train and test the gas consumption decomposition model;

[0058] According to the combination of different gas users at each terminal, the LSTM network model is used to build a gas consumption prediction model; the input of the gas consumption prediction model is the compressed air usage sequence of the gas user combination in the previous period T, and the output is the compressed air usage sequence of the gas user combination in the next period T; the gas consumption prediction model of each gas user combination is trained using the collected historical compressed air usage sequence of each gas user combination;

[0059] When performing gas consumption prediction for a certain terminal in actual production, the compressed air consumption sequence of the previous cycle T with the current moment as the end point of the terminal is input into the gas consumption decomposition model, and the connectivity status of each gas-using subject corresponding to the terminal is output; then for the gas-using subject combination in the connectivity state, the gas consumption prediction model of the corresponding gas-using subject combination is called to output the compressed air consumption sequence of the next cycle T with the current moment as the starting point. The sum of the compressed air consumption of all terminals is taken as the total compressed air consumption.

[0060] S4, combined with the total compressed air demand , Compressed air output of each air compressor unit and the gas storage capacity of the gas tank , taking the minimum number of air compressor units in operation as the optimization goal, calculate the future cycle Changing trend of the number of operating internal air compressor units .

[0061] Assume that multiple air compressors are centrally connected, corresponding to the same air storage tank and multiple terminals. When the air compressor is not working, the air storage tank can be used as a gas source. When the air compressor is working, the air storage tank can help the entire system achieve gas balance. Therefore, in this step, for one of the air compressor sets, according to the total amount of compressed air demand , Compressed air output of each air compressor unit and the gas storage capacity of the gas tank , the changing trend of the number of air compressor units in operation in the next cycle can be calculated , so that the sum of the compressed air output of the air compressor unit in each period The following conditions must be met: In the formula , is the maximum gas storage capacity of the gas tank.

[0062] As a preferred example, in step S4, the minimum number of air compressor units in operation is taken as the optimization goal, and the calculation results for the next cycle are Changing trend of the number of operating internal air compressor units The process includes the following steps:

[0063] S41, draw the total demand curve of compressed air according to the time axis, and remove and correct the burrs in the total demand curve of compressed air in combination with the capacity of the air storage tank. Since the air storage tank also has the function of redundancy for air compressor failure, in actual application, at least a part of the compressed air will be retained in the air storage tank as redundant air supply when the air compressor fails. Therefore, before analyzing the number of air compressors required, the burrs in the total demand curve of compressed air are first removed and corrected. For example, through the total demand curve of compressed air, we know that there will be a peak in the compressed air consumption at a certain moment, but the compressed air consumption demand will soon return to normal. In this case, the compressed air in the air storage tank can be used as a supplement, without having to increase the number of air compressors for this peak, reducing the additional energy consumption generated when the air compressor is frequently switched on and off. Similarly, in the case of a sudden drop in compressed air consumption, it can be stored in the air storage tank as additional storage air. Since the duration of the burr is very short, the compressed air consumption generated is usually relatively small, and the air storage tank can fully handle such small sudden demands. Conversely, if the change in the total compressed air demand curve exceeds the range that the gas storage tank can handle, it is necessary to further optimize the operation by adjusting the number of air compressor units. Specifically, the corrected total compressed air demand curve is analyzed and the next cycle is calculated. Divide into K time periods , and for each period The gas usage characteristics are classified. The gas usage characteristics of adjacent time periods are different. According to the change trend of the number of air compressors required within a period of time, the gas usage characteristics of the time period are divided into the flat period, the stable rising period, the stable falling period, the sudden rising period and the sudden falling period. ;

[0064] For example, if the number of air compressors remains stable over multiple consecutive time periods, it is defined as a flat period; if the number of air compressors maintains an upward trend over multiple consecutive time periods, and the increase in two adjacent time periods is not large (such as a difference of only 1 unit), it is defined as a stable increase period; similarly, if the number of air compressors maintains a downward trend over multiple consecutive time periods, and the decrease in two adjacent time periods is not large (such as a difference of only 1 unit), it is defined as a stable decrease period; and if the number of air compressors increases / decreases greatly over multiple consecutive time periods, it is defined as a sudden increase / drop period. In actual applications, whether the specific amplitude of the difference in increase or decrease meets the definition of stability needs to be defined based on the actual base number of air compressors used. In addition, in actual applications, the duration of the cycle and time period is also determined based on actual conditions. For scenarios where the use of compressed air is relatively stable, the duration of the cycle T and the time period can be longer. For scenarios where the use of compressed air increases significantly, the duration of the cycle T and the time period is shorter.

[0065] S42, select one of the time periods in turn , determine the current period Gas consumption characteristics, if the current period The gas usage characteristic is a flat period, and the process goes to step S43; if the current period The gas consumption characteristic is in a stable rising period, and the process goes to step S44. If the gas consumption characteristic in the current period is The gas consumption characteristic is in a steady decline period, and the process goes to step S45; if the current period The gas consumption characteristic is a sudden increase period, and the process goes to step S46; if the gas consumption characteristic of the current period When the gas consumption characteristic is in a sudden drop period, the process goes to step S47;

[0066] S43, determine the total amount of compressed air missing in the gas tank , based on the current period Average gas consumption and the total amount of compressed air missing from the air tank The sum of is the estimated gas demand, combined with the compressed air output of each air compressor unit , calculate the time period Minimum number of air compressor units in operation ;

[0067] S44, determine the total amount of compressed air missing in the gas tank , in the current period Gas demand Add the total amount of compressed air missing from the air tank The corrected gas demand estimate function is obtained by combining the compressed air production of each air compressor unit , calculate the current period The changing trend of the number of air compressor units in operation And the startup time of the newly added air compressor unit;

[0068] S45, determine the total amount of remaining compressed air in the gas tank , in the current period Gas demand Subtract the remaining compressed air in the air tank , and obtain the corrected gas demand estimate function, combined with the compressed air output of each air compressor unit , calculate the current period Changing trend of the number of air compressor units in operation And the reduced shutdown time of each air compressor unit;

[0069] S46, determine the total amount of remaining compressed air in the gas tank , based on the peak gas consumption in the current period Subtract the remaining compressed air amount in the air tank The difference is the estimated gas demand, combined with the compressed air output of each air compressor unit. , calculate the time period Minimum number of air compressor units in operation , and recalculate the end time of the period, based on the next period Based on the gas usage characteristics, the number of operating air compressor units is adjusted at the end of the recalculated period;

[0070] S47, determine the total amount of remaining compressed air in the gas tank , based on the peak gas consumption in the current period Subtract the remaining compressed air in the air tank The difference is the estimated gas demand, and the end time of the period is recalculated according to the next period. According to the gas consumption characteristics, the number of operating air compressor units is adjusted at the beginning of the recalculated period.

[0071] S5: Analyze the main gas user combination, historical compressed air usage and historical exhaust pressure requirements of each terminal to obtain the gas usage type of each gas user, combined with the predicted future cycle Compressed air demand at each end , analyze the next cycle Exhaust pressure requirement at each end , calculate the total exhaust pressure requirement of all terminals .

[0072] The exhaust pressure requirements of the same gas user in different application scenarios are not necessarily the same, but they are all related to the gas user's own properties and the changing trend of compressed air usage. Taking this into account, the present invention constructs an exhaust pressure prediction model to predict the exhaust pressure in the next cycle. Exhaust pressure requirement at each end Make predictions, specifically:

[0073] Collect the overall exhaust pressure sequence and compressed air usage sequence of each terminal and the individual exhaust pressure sequence of each gas user corresponding to the terminal; classify the individual exhaust pressure sequence according to the gas usage type of the gas user in different application scenarios;

[0074] For different combinations of gas users, the overall exhaust pressure sequence and compressed air usage sequence of each terminal and the individual exhaust pressure sequence of each gas user corresponding to the terminal are divided into time periods, and the compressed air usage sequence and overall exhaust pressure sequence of the terminal in each time period are used as input, and the gas type combination of the terminal is used as output to generate a number of sample data;

[0075] The exhaust pressure classification model is constructed by using a neural network model, and the exhaust pressure classification model is trained and tested using sample data;

[0076] For each terminal different gas type combination, the LSTM network model is used to build an exhaust pressure prediction model; the input of the exhaust pressure prediction model is the compressed air usage sequence and the overall exhaust pressure sequence of the gas type combination in the previous period T, and the output is the exhaust pressure sequence of the main gas type combination in the next period T; the exhaust pressure prediction model of each gas type combination is trained using the collected historical compressed air usage sequence and the overall exhaust pressure sequence;

[0077] When performing a gas pressure prediction for a certain terminal in actual production, the compressed air usage sequence and the overall exhaust pressure sequence of the previous cycle T with the current moment as the end point of the terminal are input into the exhaust pressure classification model, and the corresponding gas type combination of the terminal is output; then the exhaust pressure prediction model for the corresponding gas type combination is called, and the exhaust pressure sequence of the next cycle T with the current moment as the starting point is output. The sum of the exhaust pressures of all terminals is used as the total exhaust pressure demand of the air compression system.

[0078] After predicting the exhaust pressure of the air compressor system, the total amount of compressed air, and the changing trend of the number of operating air compressor units, the parameters of the air compressor unit, the drying unit, and the cooling system can be adjusted according to these predicted parameters to minimize the operating power consumption of the entire air compressor system. At present, in actual production, historical production data is usually summarized, and the empirical parameters of each air compressor unit, drying unit, and cooling system are fitted therefrom to generate a corresponding empirical parameter table. Therefore, for occasions where some control processes are not too complicated, the relevant empirical parameter table can be directly called according to the prediction results to automatically adjust the operating parameters of the air compressor unit, drying unit, and cooling system. In order to further save energy consumption, the present invention also proposes a more detailed control process. Specifically comprising the following steps:

[0079] S6, the exhaust pressure requirements of all terminals in the next cycle T , Total compressed air demand And the changing trend of the number of air compressor units in operation Input air compressor energy consumption model , taking the minimum total energy consumption of the air compressor unit in the future period T as the optimization goal, the loading pressure setting value and unloading pressure setting value of each air compressor unit are calculated.

[0080] Specifically, the air compressor energy consumption model It includes: an air compression working condition generating unit, a gas usage time period dividing unit and an air compression working condition screening unit.

[0081] The air compressor working condition generation unit is used to collect the exhaust pressure, compressed air volume and energy consumption values ​​of different air compressor units under different working conditions (intake valve opening, loading pressure setting value and unloading pressure setting value) to generate working condition sample data.

[0082] The gas usage period division unit divides the future cycle T into several gas usage periods according to the number of air compressor units in operation and the usage, and according to the exhaust pressure demand , Total compressed air demand And the number of air compressor units in operation, filter all the operating condition combinations of air compressor units that meet the conditions.

[0083] The air compressor working condition screening unit calculates the compressed air volume and energy consumption value generated under the working condition combination of each air compressor unit screened out, and calculates the total compressed air volume and energy consumption value of all air use periods. Under the premise of selecting the operating condition combination of the air compressor unit in each gas usage period with the smallest total energy consumption value.

[0084] S7, combined with the loading pressure setting value and unloading pressure setting value of each air compressor unit, import the energy consumption model of the drying unit , the dew point temperature of the compressed air in the next cycle T Make an estimate based on the dew point temperature of the compressed air Calculate the next cycle Changing trend of the number of internal drying units in operation And the operating frequency of the drying unit.

[0085] In order to simplify the model, in this embodiment, the operating frequency of all drying units is set to be the same. The more drying units are in operation, the stronger the drying capacity is. Under this premise, the energy consumption model of the drying unit is Based on the neural network construction, the dew point temperature corresponding to the combination of loading pressure setting value and unloading pressure setting value of different air compressor units is selected from the historical data, and the training samples are generated. The neural network is trained to obtain the energy consumption model of the drying unit. Import the loading pressure setting value and unloading pressure setting value of each air compressor unit in the future period T into the energy consumption model of the drying unit , get the dew point temperature of the compressed air in the next cycle T .

[0086] Collect the energy consumption values ​​of different drying unit operating conditions (number of units in operation and working frequency) corresponding to different compressed air dew point temperatures, and select the drying unit operating condition corresponding to the minimum energy consumption value as the optimal operating condition corresponding to the dew point temperature, so as to The changing trend of the corresponding optimal operating conditions is obtained by screening.

[0087] S8, the changing trend of the number of air compressor units in operation The measured value of the cooling water inlet tower temperature is imported into the cooling system energy consumption model , the total heat to be exchanged is converted, and the minimum total energy consumption of the cooling system is taken as the optimization goal, and the future cycle is calculated Changing trend of the number of fans in cooling towers And the operating frequency of the cooling pump.

[0088] The more air compressor units are in operation, the more heat is generated, and the greater the total heat that needs to be exchanged. The cooling system includes a cooling tower and a cooling pump. In practical applications, the cooling water flow is usually adjusted by controlling the operating frequency of the cooling pump, and the heat exchange efficiency of the cooling water per unit time is increased by increasing the number of cooling fans in the cooling tower. Therefore, the overall cooling system is determined by the cooling water flow of the cooling pump and the number of cooling fans. The temperature of the cooling water inlet tower water temperature measurement value is relatively fixed within the same time range. Therefore, the total heat to be exchanged is mainly determined by the number of operating dryer units.

[0089] Cooling system energy consumption model It includes an optimal cooling condition setting unit, a heat calculation unit and a cooling condition screening unit. The heat calculation unit is used to take the number of operating air compressor units and the measured value of the cooling water inlet tower water temperature as input parameters to estimate the total amount of heat to be exchanged. The optimal cooling condition setting unit constructs a combination of operating conditions of the cooling tower and the cooling pump (the number of cooling fans and the operating frequency of the cooling pump) that meets the cooling demand for different total amounts of heat to be exchanged, calculates the energy consumption values ​​under different combinations of operating conditions, selects the operating condition combination of the cooling tower and the cooling pump with the smallest energy consumption value as the optimal operating condition for the total amount of heat to be exchanged, and generates a query table of the total amount of heat to be exchanged - optimal operating condition. The cooling condition screening unit calculates the changing trend of the number of operating air compressor units known to be Based on the measured value of the water temperature entering the cooling water tower, the heat calculation unit is first called to estimate the total heat to be exchanged, and then the change trend of the operating condition combination of the cooling tower and the cooling pump within the next period T is obtained.

[0090] Those skilled in the art should understand that the embodiments of the present application can be provided as methods, systems, or computer program products. Therefore, the present application can take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present application can take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code. The scheme in the embodiment of the present application can be implemented in various computer languages, for example, object-oriented programming language Java and literal scripting language JavaScript, etc. The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the process. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0091] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0092] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process in the computer or other programmable device. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0093] Although the preferred embodiments of the present application have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present application.

[0094] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.

Claims

1. An energy-saving optimization control method for an air compression system based on changes in terminal gas demand, characterized in that: The air compression system energy-saving optimization control method comprises the following steps: S1, build a topological model of the air compression system to be optimized. The equipment of the air compression system includes air compressor units, gas storage tanks, drying units and supporting cooling systems. The air compression system corresponds to multiple terminals, and each terminal corresponds to at least one gas-using device; collect historical operation data of each device in the air compression system; S2, combining the historical operation data collected in step S1 and the physical property data of each device in the air compressor system, constructs the energy consumption model of each device in the air compressor system, including the air compressor energy consumption model , Drying unit energy consumption model and cooling system energy consumption model ; S3, build a gas demand prediction model, collect the compressed air usage of each terminal in the current cycle, input it into the gas demand prediction model, predict the gas demand of each terminal in the next cycle, and obtain the compressed air demand of each terminal , calculate the total compressed air demand of all terminals , ; S4, combined with the total compressed air demand , Compressed air output of each air compressor unit and the gas storage capacity of the gas tank , taking the minimum number of air compressor units in operation as the optimization goal, calculate the future cycle Changing trend of the number of operating internal air compressor units ; S5: Analyze the main gas user combination, historical compressed air usage and historical exhaust pressure requirements of each terminal to obtain the gas usage type of each gas user, combined with the predicted future cycle Compressed air demand at each end , analyze the next cycle Exhaust pressure requirement at each end , calculate the total exhaust pressure requirement of all terminals ; S6, the exhaust pressure requirements of all terminals in the next cycle T , Total compressed air demand And the changing trend of the number of air compressor units in operation Input air compressor energy consumption model , taking the minimum total energy consumption of the air compressor unit as the optimization goal, the loading pressure setting value and the unloading pressure setting value of each air compressor unit are calculated; S7, combined with the loading pressure setting value and unloading pressure setting value of each air compressor unit, import the energy consumption model of the drying unit , the dew point temperature of the compressed air in the next cycle T Make an estimate based on the dew point temperature of the compressed air Calculate the next cycle Changing trend of the number of internal drying units in operation ; S8, the changing trend of the number of air compressor units in operation The measured value of the cooling water inlet tower temperature is imported into the cooling system energy consumption model , the total heat to be exchanged is obtained, and the minimum total energy consumption of the cooling system is taken as the optimization goal, and the future cycle is calculated Changing trend of the number of fans in cooling towers , the operating frequency of the cooling tower fan and the operating frequency of the cooling pump.

2. The air compression system energy-saving optimization control method based on terminal gas demand changes according to claim 1 is characterized in that: In step S3, the process of building a gas demand prediction model includes the following steps: Construct a topological relationship between each terminal and all corresponding gas users; collect the compressed air usage sequence of each terminal and the compressed air usage sequence of each gas user corresponding to the terminal; The compressed air usage sequence of each terminal and the compressed air usage sequence of each gas user corresponding to the terminal are divided into time periods, the compressed air usage sequence of the terminal and the compressed air usage sequence of each gas user in each time period are used as input, and the connectivity state of each gas user is used as output to generate a number of sample data; A gas consumption decomposition model is constructed using a neural network model, and sample data is used to train and test the gas consumption decomposition model; According to the combination of different gas users at each terminal, a gas consumption prediction model is constructed using the LSTM network model; the input of the gas consumption prediction model is the compressed air usage sequence of the gas user combination in the previous period T, and the output is the compressed air usage sequence of the gas user combination in the next period T; the gas consumption prediction model of each gas user combination is trained using the collected historical compressed air usage sequence of each gas user combination; when the gas consumption prediction of a certain terminal is performed in actual production, the compressed air usage sequence of the previous period T with the current moment as the end point of the terminal is input into the gas decomposition model, and the connectivity status of each gas user corresponding to the terminal is output; then for the gas user combination in the connectivity state, the gas consumption prediction model of the corresponding gas user combination is called, and the compressed air usage sequence of the next period T with the current moment as the starting point is output.

3. The air compression system energy-saving optimization control method based on terminal gas demand changes according to claim 1 is characterized in that: In step S4, the minimum number of operating air compressor units is taken as the optimization goal, and the change trend of the number of operating air compressor units in the next cycle is calculated. The process includes the following steps: S41, draw the compressed air demand total amount curve according to the time axis, remove and correct the burrs in the compressed air demand total amount curve based on the gas tank capacity, analyze the corrected compressed air demand total amount curve, and calculate the future cycle Divide into K time periods , and for each period The gas usage characteristics are classified. The gas usage characteristics of adjacent time periods are different. According to the change trend of the number of air compressors required within a period of time, the gas usage characteristics of the time period are divided into the flat period, the stable rising period, the stable falling period, the sudden rising period and the sudden falling period. ; S42, select one of the time periods in turn , determine the current period Gas consumption characteristics, if the current period The gas usage characteristic is a flat period, and the process goes to step S43; if the current period The gas consumption characteristic is in a stable rising period, and the process goes to step S44. If the gas consumption characteristic in the current period is The gas consumption characteristic is in a steady decline period, and the process goes to step S45; if the current period The gas consumption characteristic is a sudden increase period, and the process goes to step S46; if the gas consumption characteristic of the current period When the gas consumption characteristic is in a sudden drop period, the process goes to step S47; S43, determine the total amount of compressed air missing in the gas tank , based on the current period Average gas consumption and the total amount of compressed air missing from the air tank The sum of is the estimated gas demand, combined with the compressed air output of each air compressor unit , calculate the time period Minimum number of air compressor units in operation ; S44, determine the total amount of compressed air missing in the gas tank , in the current period Gas demand Add the total amount of compressed air missing from the air tank The corrected gas demand estimate function is obtained by combining the compressed air production of each air compressor unit , calculate the current period Changing trend of the number of air compressor units in operation And the startup time of the newly added air compressor unit; S45, determine the total amount of remaining compressed air in the gas tank , in the current period Gas demand Subtract the remaining compressed air in the air tank , and obtain the corrected gas demand estimate function, combined with the compressed air output of each air compressor unit , calculate the current period Changing trend of the number of air compressor units in operation And the reduced shutdown time of each air compressor unit; S46, determine the total amount of remaining compressed air in the gas tank , based on the peak gas consumption in the current period Subtract the remaining compressed air amount in the air tank The difference is the estimated gas demand, combined with the compressed air output of each air compressor unit. , calculate the time period Minimum number of air compressor units in operation , and recalculate the end time of the period, based on the next period Based on the gas usage characteristics, the number of operating air compressor units is adjusted at the end of the recalculated period; S47, determine the total amount of remaining compressed air in the gas tank , based on the current period Peak gas consumption Subtract the remaining compressed air in the air tank The difference is the estimated gas demand, and the end time of the period is recalculated according to the next period. According to the gas consumption characteristics, the number of operating air compressor units is adjusted at the beginning of the recalculated period.

4. The air compression system energy-saving optimization control method based on terminal gas demand changes according to claim 1 is characterized in that: In step S5, the exhaust pressure prediction model is constructed to predict the exhaust pressure requirements of each end of the next cycle. Make predictions, including: Collect the overall exhaust pressure sequence and compressed air usage sequence of each terminal and the individual exhaust pressure sequence of each gas user corresponding to the terminal; classify the individual exhaust pressure sequence according to the gas usage type of the gas user in different application scenarios; For different combinations of gas users, the overall exhaust pressure sequence and compressed air usage sequence of each terminal and the individual exhaust pressure sequence of each gas user corresponding to the terminal are divided into time periods, and the compressed air usage sequence and overall exhaust pressure sequence of the terminal in each time period are used as input, and the gas type combination of the terminal is used as output to generate a number of sample data; The exhaust pressure classification model is constructed by using a neural network model, and the exhaust pressure classification model is trained and tested using sample data; For each terminal different gas type combination, the LSTM network model is used to build an exhaust pressure prediction model; the input of the exhaust pressure prediction model is the compressed air usage sequence and the overall exhaust pressure sequence of the gas type combination in the previous period T, and the output is the exhaust pressure sequence of the main gas type combination in the next period T; the exhaust pressure prediction model of each gas type combination is trained using the collected historical compressed air usage sequence and the overall exhaust pressure sequence; When performing gas pressure prediction for a certain terminal in actual production, the compressed air usage sequence and overall exhaust pressure sequence of the previous cycle T with the current moment as the end point of the terminal are input into the exhaust pressure classification model, and the gas type combination corresponding to the terminal is output; then, the exhaust pressure prediction model of the corresponding gas type combination is called to output the exhaust pressure sequence of the next cycle T with the current moment as the starting point.

5. The air compression system energy-saving optimization control method based on terminal gas demand changes according to claim 1 is characterized in that: Air compressor energy consumption model It includes: air compressor working condition generation unit, gas usage period division unit and air compressor working condition screening unit; the air compressor working condition generation unit is used to collect the exhaust pressure, compressed air volume and energy consumption value of different air compressor units under different working conditions, and generate working condition sample data; the gas usage period division unit divides the future cycle T into several gas usage periods according to the number of air compressor units in operation, and selects the gas usage periods according to the exhaust pressure demand. , Total compressed air demand The air compressor operating condition screening unit calculates the compressed air volume and energy consumption value generated under the selected operating condition combination of each air compressor unit, and calculates the total compressed air volume and energy consumption value of all air usage periods. Under the premise of selecting the operating condition combination of the air compressor unit in each gas usage period with the smallest total energy consumption value.

6. The air compression system energy-saving optimization control method based on terminal gas demand changes according to claim 1 is characterized in that: Cooling system energy consumption model The system comprises an optimal cooling condition setting unit, a heat calculation unit and a cooling condition screening unit; the heat calculation unit is used to take the number of operating air compressor units and the measured value of the water temperature of the cooling water inlet tower as input parameters to estimate the total amount of heat to be exchanged; the optimal cooling condition setting unit constructs a combination of operating conditions of the cooling tower and the cooling pump that meets the cooling demand for different total amounts of heat to be exchanged, calculates the energy consumption values ​​under different combinations of operating conditions, selects the combination of operating conditions of the cooling tower and the cooling pump with the smallest energy consumption value as the optimal operating condition for the total amount of heat to be exchanged, and generates a query table of the total amount of heat to be exchanged-optimal operating condition; the cooling condition screening unit calculates the change trend of the number of operating air compressor units in the known Based on the measured value of the water temperature entering the cooling water tower, the heat calculation unit is called to estimate the total heat to be exchanged, and then the change trend of the operating condition combination of the cooling tower and the cooling pump in the next period T is obtained.