Aluminum alloy workpiece forging machine

By using high-temperature resistant materials and automatic cooling systems in aluminum alloy forging machines, the problems of cooling water waste and environmental pollution in the existing technology are solved, rapid cooling of aluminum alloy workpieces and recycling of cooling water are realized, and production is improved Efficiency and environmental protection.

CN118477959BActive Publication Date: 2024-11-08JIANGSU HUALI PRECISION MASCH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410933743.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-12
Publication Date
2024-11-08
Estimated Expiration
2044-07-12

AI Technical Summary

Technical Problem

Existing aluminum alloy forging equipment consumes a lot of water during cooling and cannot be recycled, resulting in increased production costs and environmental impact.

Method used

Aluminum alloy workpiece forging machine was designed, using high-temperature resistant silicon carbide material to make a placement box, and the rapid cooling of aluminum alloy workpieces and the collection and reuse of cooling water are realized through lifting and cooling components. The cooling water is passed through the linkage component. Automatically control entry and discharge to ensure that the workpiece comes into contact with cooling water immediately after stamping to cool down.

Benefits of technology

It realizes rapid cooling of aluminum alloy workpieces and recycling of cooling water, saves water resources, reduces production costs, and reduces the impact on the environment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118477959B_ABST
    Figure CN118477959B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of aluminum alloy forging, and discloses an aluminum alloy workpiece forging and forming machine, comprising a base plate platform, a lifting platform is arranged on the top of the base plate platform, a forging plate is fixedly connected to the bottom side of the lifting platform, a placement box is arranged under the forging plate, and lifting components are arranged on both sides of the lifting platform, when the forging plate is stamped and lifted, the aluminum alloy workpiece can be moved to the right below the cooling component, and the cooling water in the cooling component can also enter the placement box to quickly cool down the aluminum alloy workpiece, and the used cooling water can also be collected and cooled and continue to enter the cooling component, so that the workpiece can be ensured to contact the cooling water immediately after stamping, and the temperature can be quickly reduced, which is helpful to solidify and stabilize its structure, collect and recycle the cooling water, and save water resources, the whole device has a compact structure, and the whole stamping process is smoother and more efficient.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of aluminum alloy forging, and specifically relates to an aluminum alloy workpiece forging molding machine. Background Art

[0002] Aluminum alloy workpiece forging machine is a special equipment used to process aluminum alloy materials. It can process aluminum alloy into workpieces of required shape and size through forging process. It applies pressure to aluminum alloy to make it plastically deform to obtain forgings with certain mechanical properties, shape and size. In the metal forging process, stamping is an indispensable process. It is necessary to use a stamping device to continuously stamp the metal body so that the metal is forged into shape.

[0003] The prior art also proposes some aluminum alloy forging solutions: for example, a patent application with publication number CN115255239A discloses a forging device for forging metal devices, which relates to the field of forging technology. The key points of its technical solution include: a forging table and a metal device, wherein the metal device is arranged on the forging table; a stamping machine, which is fixedly connected to the forging table, and heats the inside of the first melting furnace and the second melting furnace through a heating element and a heating tube, thereby achieving the effect that the metal debris generated during the stamping process of the metal device can be collected and processed twice, and the metal solution after the secondary processing can be mixed with the metal body according to the standard weight of the metal device production, thereby reducing the loss of raw materials and improving the production quality of the metal device.

[0004] After stamping and forging the aluminum alloy workpiece, the existing device needs to quickly cool the aluminum alloy workpiece to maintain the forged shape, but a large amount of cooling water is consumed in the cooling process, and the consumed cooling water cannot be recycled and reused, resulting in an increase in production costs. In addition, the cooling water may contain aluminum alloy fragments, and direct discharge will have an impact on the environment.

[0005] To this end: the present invention provides an aluminum alloy workpiece forging machine. Summary of the invention

[0006] In order to make up for the deficiencies of the prior art: solve at least one technical problem raised in the background technology.

[0007] The technical solution adopted by the present invention to solve its technical problems is: an aluminum alloy workpiece forging and forming machine described in the present invention includes a base plate table, a lifting platform is arranged on the top of the base plate table, a forging plate is fixedly connected to the bottom side of the lifting platform, a placement box is arranged below the forging plate, the aluminum alloy workpiece is placed inside the placement box, the placement box is made of high-temperature resistant silicon carbide material, lifting components are arranged on both sides of the lifting platform, the lifting components are used to drive the forging plate to rise or fall, a filter hole is opened on the bottom side of the placement box, a conveying component is arranged below the placement box, the conveying component is used to drive the placement box to move back and forth repeatedly, a cooling component is arranged above the placement box, the cooling component is used to cool the aluminum alloy workpiece inside the placement box.

[0008] Preferably, the lifting assembly includes two side seats, the two side seats are fixedly mounted on the top of the base platform, the inner walls of the two side seats are rotatably connected to threaded rods, the tops of the two threaded rods are fixedly connected to driven gears, both sides of the lifting platform are fixedly connected to internal threaded parts, the inner walls of the two internal threaded parts are respectively threadedly connected to the outer walls of the two threaded rods, the two internal threaded parts are respectively slidably connected to the inside of the two side seats, and a driving assembly is arranged above the lifting platform, and the driving assembly is used to drive the two driven gears to rotate simultaneously.

[0009] Preferably, the driving assembly includes a dual-output motor, a bracket plate is fixedly connected between the tops of the two side seats, the dual-output motor is fixedly installed on the top of the bracket plate, both ends of the output shaft of the dual-output motor are fixedly connected with driving gears, the teeth of the two driving gears are respectively meshed with the teeth of two driven gears, and the top of the bracket plate is symmetrically fixedly connected with clamping members, and the inner walls of the two clamping members are respectively rotatably connected to the outer walls of the output shafts at both ends of the dual-output motor.

[0010] Preferably, the conveying assembly includes two groups of inner shaft rollers, the outer walls of the two groups of inner shaft rollers are connected to the transmission belts, the tops of the two transmission belts are fixedly connected to the bottom of the placement box, and a transmission assembly is arranged between the lifting platform and the inner shaft rollers, and the transmission assembly is used to drive the placement box to move.

[0011] Preferably, the transmission assembly includes a rack plate 1, wherein a rotating rod 1 is fixedly connected between the two inner shaft rollers, a conveying gear is fixedly connected to the outer wall of the rotating rod 1, and the teeth of the conveying gear are meshed with the teeth of the rack plate 1.

[0012] Preferably, the outer wall of each group of the inner shaft rollers is rotatably connected to a connecting shaft rod, and each group of the connecting shaft rods is fixedly connected to each other. Two groups of clamping seats are fixedly installed on the top of the base platform, and the inner wall of each group of the clamping seats is rotatably connected to the outer wall shaft rods of two of the inner shaft rollers.

[0013] Preferably, the cooling assembly includes a water inlet bin, an outer wall of the water inlet bin is fixedly connected to a fixing ring, one side of the bracket plate is fixedly connected to one side of the fixing ring, the bottom of the water inlet bin is fixedly connected to a water outlet bin, the interior of the water outlet bin is rotatably connected to a blocking block, and a linkage assembly is provided between the lifting platform and the cooling assembly, and the linkage assembly is used to drive the blocking block to rotate 90 degrees.

[0014] Preferably, two rotating rods are fixedly connected on both sides of the blocking block, and the two rotating rods are plugged into the inner wall of the water outlet bin. Gears are fixedly connected at both ends of the two rotating rods. Two rack plates are fixedly connected on both sides of the lifting platform, and the teeth of the rack plate are meshed with the teeth of the gear. The teeth of the rack plate are half the number of the teeth of the gear.

[0015] Preferably, a condensation box is fixedly installed on the top of the base platform, and a condensation pipe is fixedly connected to the outer wall of the condensation box.

[0016] Preferably, a connecting water pipe is fixedly connected to one side of the condensation box, a supporting frame is fixedly connected to one side of the base platform, the connecting water pipe is fixedly installed on one side of the supporting frame, the outlet of the connecting water pipe is located at the top of the water inlet bin, and a water pump is fixedly installed on the outer wall of the connecting water pipe.

[0017] The beneficial effects of the present invention are as follows:

[0018] 1. The aluminum alloy workpiece forging and molding machine described in the present invention: when the forging plate is raised after stamping, the aluminum alloy workpiece can be moved to the bottom of the cooling assembly, and the cooling water in the cooling assembly can enter the placement box to quickly cool the aluminum alloy workpiece. The used cooling water can also be collected and cooled and continue to enter the cooling assembly, which can ensure that the workpiece is immediately exposed to the cooling water after stamping, and the temperature is quickly reduced, which is helpful to solidify and stabilize its structure. The cooling water is collected and recycled, saving water resources. The entire device has a compact structure, and the entire stamping process is smoother and more efficient.

[0019] 2. An aluminum alloy workpiece forging machine described in the present invention: when the forging platen rises, the gear will be driven to rotate through the rack plate 2. Since the number of teeth on the rack plate 2 is half of the number of teeth on the gear, the gear will rotate degrees, and the blocking round block will be driven to rotate degrees through the rotating rod 2, so that cooling water can flow from the water outlet bin into the placement box. Conversely, when the forging platen descends, the blocking round block will rotate 90 degrees in the opposite direction, blocking the water outlet bin and preventing the cooling water from flowing out. The rotation of the blocking round block can be automatically controlled by the lifting and lowering of the lifting platform, thereby achieving the effect of cooling the aluminum alloy workpiece. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The present invention will be further described below in conjunction with the accompanying drawings.

[0021] Figure 1 It is an overall stereogram of the present invention;

[0022] Figure 2 It is a schematic diagram of the structure of the driving gear in the present invention;

[0023] Figure 3 It is a schematic diagram of the structure of the forging plate in the present invention;

[0024] Figure 4 It is a schematic diagram of the structure of the conveying gear in the present invention;

[0025] Figure 5 It is a schematic diagram of the second structure of the rack plate in the present invention;

[0026] Figure 6 It is a schematic diagram of the structure of the water pipe connection in the present invention;

[0027] Figure 7 It is a structural schematic diagram of the blocked circular block in the present invention.

[0028] In the figure: 1. bottom plate; 2. placement box; 3. filter hole; 4. lifting platform; 5. forging plate; 6. internal threaded part; 7. threaded rod; 8. side seat; 9. clamping part; 10. bracket plate; 11. driven gear; 12. dual output motor; 13. driving gear; 14. clamping seat; 15. inner shaft roller; 16. transmission belt; 17. rotating rod one; 18. conveying gear; 19. connecting shaft rod; 20. rack plate one; 21. rack plate two; 22. fixing ring; 23. water inlet tank; 24. water outlet tank; 25. blocking round block; 26. rotating rod two; 27. gear; 28. condensing box; 29. ​​condensing pipe; 30. supporting frame; 31. connecting water pipe; 32. water pump. DETAILED DESCRIPTION

[0029] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand: the present invention is further explained below in conjunction with specific implementation methods.

[0030] like Figures 1 to 7 As shown, the present invention provides a technical solution: an aluminum alloy workpiece forging and forming machine, comprising a base plate table 1, a lifting platform 4 is arranged on the top of the base plate table 1, a forging plate 5 is fixedly connected to the bottom side of the lifting platform 4, a placement box 2 is arranged below the forging plate 5, the aluminum alloy workpiece is placed inside the placement box 2, the placement box 2 is made of high-temperature resistant silicon carbide material, lifting components are arranged on both sides of the lifting platform 4, the lifting components are used to drive the forging plate 5 to rise or fall, a filter hole 3 is opened on the bottom side of the placement box 2, a conveying component is arranged below the placement box 2, the conveying component is used to drive the placement box 2 to move back and forth repeatedly, a cooling component is arranged above the placement box 2, and the cooling component is used to cool the aluminum alloy workpiece inside the placement box 2.

[0031] During operation: After stamping and forging the aluminum alloy workpiece, the existing device needs to quickly cool the aluminum alloy workpiece to maintain the shape after forging, but a large amount of cooling water is consumed during the cooling process, and the consumed cooling water cannot be recycled and reused, resulting in an increase in production costs. In addition, the cooling water may contain aluminum alloy fragments, and direct discharge will have an impact on the environment. Through the embodiment of this scheme, when it is used specifically, the aluminum alloy workpiece needs to be heated at a high temperature before forging to facilitate the deformation of the aluminum alloy workpiece during stamping and forging, and then Then, the aluminum alloy workpiece is placed in the placement box 2, and in the initial state, the placement box 2 is located directly below the cooling assembly, and then the lifting assembly is started to make the forging platen 5 descend, and during the forging platen 5 descending process, the placement box 2 can be moved to directly below the forging platen 5, and when the forging platen 5 continues to descend, the aluminum alloy workpiece in the placement box 2 can be stamped and forged. During the forging process, cooling water is added to the cooling assembly. After the forging is completed, the forging platen 5 is raised and reset by the lifting assembly. During the forging platen 5 ascending process In the embodiment, the placement box 2 can be moved to the bottom of the cooling assembly, and the cooling water in the cooling assembly can enter the placement box 2 during the rising process of the forging plate 5, so as to cool the aluminum alloy workpiece, and the treated cooling water can be collected and cooled and continued to be added to the cooling assembly, and then the next aluminum alloy workpiece to be forged is replaced, and the forging plate 5 is continued to be lowered and stamped through the lifting assembly. In the process of the placement box 2 moving to the bottom of the forging plate 5, the cooling water in the cooling assembly can automatically stop entering the placement box 2. Through the above embodiment, when the forging plate 5 is lifted after stamping, the aluminum alloy workpiece can be moved to the bottom of the cooling assembly, and the cooling water in the cooling assembly can enter the placement box 2 to quickly cool the aluminum alloy workpiece, and the used cooling water can also be collected and cooled and continue to enter the cooling assembly, which can ensure that the workpiece is in contact with the cooling water immediately after stamping, and the temperature is quickly reduced, which helps to solidify and stabilize its structure, collect and recycle the cooling water, save water resources, and the whole device has a compact structure, and the whole stamping process is smoother and more efficient.

[0032] like Figures 2 to 3 As shown, the lifting assembly includes two side seats 8, and the two side seats 8 are fixedly installed on the top of the base plate 1. The inner walls of the two side seats 8 are rotatably connected with threaded rods 7, and the tops of the two threaded rods 7 are fixedly connected with driven gears 11. Both sides of the lifting platform 4 are fixedly connected with internal threaded parts 6, and the inner walls of the two internal threaded parts 6 are respectively threadedly connected with the outer walls of the two threaded rods 7. The two internal threaded parts 6 are respectively slidably connected with the inside of the two side seats 8. A driving assembly is arranged above the lifting platform 4, and the driving assembly is used to drive the two driven gears 11 to rotate simultaneously.

[0033] During operation: start the driving assembly, and the two driven gears 11 rotate at the same time. Since the internal threaded part 6 slides in the inner wall of the side seat 8, when the driven gear 11 rotates, it can drive the internal threaded part 6 to move up and down, and drive the lifting platform 4 to move up and down through the forging pressure plate 5. During the descending process of the lifting platform 4, it is used to stamp and forge the aluminum alloy workpiece. During the ascending process of the lifting platform 4, it is used to reset and wait for preparation for stamping and forging the next aluminum alloy workpiece.

[0034] like Figures 2 to 3 As shown, the driving assembly includes a dual-output motor 12, a bracket plate 10 is fixedly connected between the tops of the two side ports 8, the dual-output motor 12 is fixedly installed on the top of the bracket plate 10, and both ends of the output shaft of the dual-output motor 12 are fixedly connected with driving gears 13, and the teeth of the two driving gears 13 are respectively meshed with the teeth of the two driven gears 11, and the top of the bracket plate 10 is symmetrically fixedly connected with clamping members 9, and the inner walls of the two clamping members 9 are rotatably connected to the outer walls of the output shafts at both ends of the dual-output motor 12.

[0035] During operation: start the dual-output motor 12, and the output shafts at both ends thereof will respectively drive the two driving gears 13 to rotate. When the two driving gears 13 rotate, they will respectively drive the two driven gears 11 to rotate at the same time, thereby realizing the rotation of the driven gears 11 to complete the lifting of the forging plate 5 to achieve the effect of stamping forging. The output shafts of the dual-output motor 12 are clamped by two clamping members 9 to maintain the stability of the meshing transmission.

[0036] like Figures 2 to 3 As shown, the conveying assembly includes two groups of inner shaft rollers 15, the outer walls of the two groups of inner shaft rollers 15 are connected to the transmission belts 16, the tops of the two transmission belts 16 are fixedly connected to the bottom of the placement box 2, and a transmission assembly is arranged between the lifting platform 4 and the inner shaft rollers 15, and the transmission assembly is used to drive the placement box 2 to move.

[0037] During operation: when the lifting assembly causes the lifting platform 4 to descend, the two sets of inner shaft rollers 15 will be driven to rotate through the transmission assembly. When the two sets of inner shaft rollers 15 rotate, they will drive the two transmission belts 16 to transmit and transport, so that the placement box 2 can be transported to the bottom of the forging plate 5. After the transportation is completed, the forging plate 5 descends to be able to stamp and forge the aluminum alloy workpiece inside the placement box 2. When the lowering assembly causes the lifting platform 4 to rise, the placement box 2 can be transported in the reverse direction to return to its original position and is located directly below the cooling assembly, which is convenient for cooling the aluminum alloy workpiece after stamping.

[0038] like Figure 4As shown, the transmission assembly includes a rack plate 20, wherein a rotating rod 17 is fixedly connected between the two inner shaft rollers 15, and a conveying gear 18 is fixedly connected to the outer wall of the rotating rod 17, and the teeth of the conveying gear 18 are meshed with the teeth of the rack plate 20.

[0039] During operation: when the forging platen 5 descends, the rack plate 20 will slowly descend and will mesh with the conveying gear 18 to rotate the conveying gear 18. When the conveying gear 18 rotates, it will drive the two inner shaft rollers 15 to rotate and make the two transmission belts 16 transmit and transport the work. When the two transmission belts 16 transmit and transport the work, they will drive the placement box 2 to move. When the placement box 2 moves to the bottom of the forging platen 5, the placement box 2 stops moving. When the forging platen 5 descends, the aluminum alloy workpiece is stamped and forged.

[0040] like Figure 4 As shown, the outer wall of each group of inner shaft rollers 15 is rotatably connected to a connecting shaft rod 19, and each group of connecting shaft rods 19 are fixedly connected to each other. Two groups of clamping seats 14 are fixedly installed on the top of the base plate platform 1, and the inner wall of each group of clamping seats 14 is rotatably connected to the outer wall shaft rods of two of the inner shaft rollers 15.

[0041] During operation: the inner shaft roller 15 arranged inside the transmission belt 16 prevents the transmission belt 16 from being deformed when the placement box 2 is punched, resulting in incomplete punching. Each group of inner shaft rollers 15 are fixedly connected and fixed by the connecting shaft rod 19, and the position of the transmission belt 16 is fixed by the clamping seat 14.

[0042] like Figures 5 to 7 As shown, the cooling assembly includes a water inlet bin 23, the outer wall of which is fixedly connected to a fixing ring 22, one side of the bracket plate 10 is fixedly connected to one side of the fixing ring 22, the bottom of the water inlet bin 23 is fixedly connected to a water outlet bin 24, the interior of the water outlet bin 24 is rotatably connected to a blocking block 25, and a linkage assembly is provided between the lifting platform 4 and the cooling assembly, which is used to drive the blocking block 25 to rotate 90 degrees.

[0043] During operation: after the stamping of the aluminum alloy workpiece in the placement box 2 is completed, the lifting platform 4 will transport the aluminum alloy workpiece to the bottom of the water outlet bin 24 through the conveying assembly and the transmission assembly during the rising process. When the placement box 2 slowly moves to the bottom of the outlet bin 24, the blocking round block 25 will be driven to rotate 90 degrees through the linkage assembly. When the placement box 2 is moved, the blocking round block 25 will be perpendicular to the inside of the outlet bin 24. Therefore, the cooling water in the water inlet bin 23 will fall into the placement box 2 through the outlet bin 24 to cool the aluminum alloy workpiece. After the cooling is completed, the next aluminum alloy workpiece is replaced. When the lifting platform 4 descends for stamping, the blocking round block 25 will be rotated 90 degrees through the linkage assembly. At this time, the placement box 2 leaves the bottom of the outlet bin 24 and the blocking round block 25 blocks the outlet bin 24, and the cooling water cannot flow out. Through the above embodiment, the rotation of the blocking round block 25 can be automatically controlled by the lifting and lowering of the lifting platform 4, thereby achieving the effect of cooling the aluminum alloy workpiece.

[0044] like Figures 5 and 6 As shown, rotating rods 26 are fixedly connected to both sides of the blocking block 25, and the rotating rods 26 are plugged into the inner wall of the water outlet bin 24. Gears 27 are fixedly connected to both ends of the two rotating rods 26. Rack plates 21 are fixedly connected to both sides of the lifting platform 4, and the teeth of the rack plate 21 are meshed with the teeth of the gear 27. The teeth of the rack plate 21 are half the number of teeth of the gear 27.

[0045] During operation: When the forging plate 5 rises, the gear 27 will be driven to rotate through the rack plate 21. Since the number of teeth of the rack plate 21 is half of the number of teeth of the gear 27, the gear 27 will rotate 90 degrees, and the blocking block 25 will be driven to rotate 90 degrees through the rotating rod 26, so that the cooling water can flow from the water outlet bin 24 into the placement box 2. Conversely, when the forging plate 5 descends, the blocking block 25 will rotate 90 degrees in the opposite direction, so that the water outlet bin 24 is blocked and the cooling water cannot flow out.

[0046] like Figure 1 and Figure 6 As shown, a condensation box 28 is fixedly installed on the top of the base platform 1, and condensation pipes 29 are fixedly connected to the outer walls of the condensation box 28.

[0047] During operation: when the placement box 2 is located below the cooling assembly to cool the workpiece, the cooling water will flow into the condensation box 28 through the filter hole 3 after cooling, and the cooling water can be cooled through the condensation pipe 29 for continued use.

[0048] like Figure 1 and Figure 6As shown, a connecting water pipe 31 is fixedly connected to one side of the condensation box 28, a supporting frame 30 is fixedly connected to one side of the base platform 1, the connecting water pipe 31 is fixedly installed on one side of the supporting frame 30, the outlet of the connecting water pipe 31 is located at the top of the water inlet bin 23, and a water pump 32 is fixedly installed on the outer wall of the connecting water pipe 31.

[0049] During operation: after the cooling water cools down, it will pass through the water pump 32 so that the cooling water can re-enter the water inlet tank 23 through the connecting water pipe 31, thereby realizing the reuse of the cooling water.

[0050] Workflow: First, the aluminum alloy workpiece needs to be heated at high temperature before forging to facilitate the deformation of the aluminum alloy workpiece during stamping and forging. Then the aluminum alloy workpiece is placed in the placement box 2, and in the initial state, the placement box 2 is located directly below the cooling component. The dual output motor 12 is started, and the output shafts at both ends thereof will respectively drive the two driving gears 13 to rotate. When the two driving gears 13 rotate, they will respectively drive the two driven gears 11 to rotate at the same time. The two driven gears 11 rotate at the same time. Since the internal threaded part 6 slides in the inner wall of the side seat 8, when the driven gear 11 rotates, it can drive the internal threaded part 6 to rise and fall, and drive the lifting platform 4 to rise and fall through the forging plate 5. During the descent of the lifting platform 4, it is used to stamp and forge the aluminum alloy workpiece. During the ascent of the lifting platform 4, it is used to reset and wait for preparation for stamping and forging the next aluminum alloy workpiece.

[0051] Secondly, when the forging platen 5 descends, the rack plate 20 will slowly descend and will mesh with the conveying gear 18 to rotate the conveying gear 18. When the conveying gear 18 rotates, it will drive the two inner shaft rollers 15 to rotate. When the two sets of inner shaft rollers 15 rotate, they will drive the two transmission belts 16 to transmit and transport, so that the placement box 2 can be transported to the bottom of the forging platen 5. After the transportation is completed, the forging platen 5 continues to descend so that the aluminum alloy workpiece inside the placement box 2 can be stamped and forged. When the lowering assembly causes the lifting platform 4 to rise, the placement box 2 can be transported in the reverse direction to return to its original position.

[0052] Then, when the stamping of the aluminum alloy workpiece in the placement box 2 is completed, the lifting platform 4 will transport the aluminum alloy workpiece to the bottom of the water outlet bin 24 through the conveying assembly and the transmission assembly during the rising process. When the placement box 2 slowly moves to the bottom of the outlet bin 24, the blocking block 25 will be driven to rotate 90 degrees through the linkage assembly. When the placement box 2 is moved, the blocking block 25 will be perpendicular to the inside of the outlet bin 24. Therefore, the cooling water in the water inlet bin 23 will fall into the placement box 2 through the outlet bin 24 to cool the aluminum alloy workpiece. After the cooling is completed, the next aluminum alloy workpiece will be replaced. When the lifting platform 4 descends for stamping, the blocking block 25 will be rotated 90 degrees through the linkage assembly. At this time, the placement box 2 leaves the bottom of the outlet bin 24 and the blocking block 25 blocks the outlet bin 24, so that the cooling water cannot flow out. Conversely, when the forging plate 5 descends, the blocking block 25 will rotate 90 degrees in the opposite direction, so that the outlet bin 24 is blocked, and the cooling water cannot flow out.

[0053] Finally, when the placement box 2 is located under the cooling component to cool the workpiece, the cooling water will flow into the condensation box 28 through the filter hole 3 after cooling, and the cooling water will be cooled through the condenser 29. After the cooling water is cooled, it will pass through the water pump 32, so that the cooling water can re-enter the water inlet tank 23 through the connecting water pipe 31, thereby realizing the reuse of cooling water.

[0054] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may be subject to various changes and improvements. These changes and improvements fall within the scope of the present invention. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. A forging machine for an aluminum alloy workpiece, comprising a base plate (1), Features: A lifting platform (4) is arranged on the top of the base plate platform (1), a forging plate (5) is fixedly connected to the bottom side of the lifting platform (4), a placement box (2) is arranged below the forging plate (5), the aluminum alloy workpiece is placed inside the placement box (2), the placement box (2) is made of high-temperature resistant silicon carbide material, lifting components are arranged on both sides of the lifting platform (4), the lifting components are used to drive the forging plate (5) to rise or fall, a filter hole (3) is opened on the bottom side of the placement box (2), a conveying component is arranged below the placement box (2), the conveying component is used to drive the placement box (2) to move back and forth repeatedly, a cooling component is arranged above the placement box (2), the cooling component is used to cool the aluminum alloy workpiece inside the placement box (2); The lifting assembly comprises two side opening seats (8), the two side opening seats (8) are fixedly mounted on the top of the bottom plate platform (1), the inner walls of the two side opening seats (8) are rotatably connected to threaded rods (7), the tops of the two threaded rods (7) are fixedly connected to driven gears (11), both sides of the lifting platform (4) are fixedly connected to internal threaded parts (6), the inner walls of the two internal threaded parts (6) are respectively threadedly connected to the outer walls of the two threaded rods (7), the two internal threaded parts (6) are respectively slidably connected to the inside of the two side opening seats (8), and a driving assembly is arranged above the lifting platform (4), the driving assembly is used to drive the two driven gears (11) to rotate simultaneously; The driving assembly comprises a dual-output motor (12), a bracket plate (10) is fixedly connected between the tops of the two side ports (8), the dual-output motor (12) is fixedly mounted on the top of the bracket plate (10), both ends of the output shaft of the dual-output motor (12) are fixedly connected with driving gears (13), the teeth of the two driving gears (13) are respectively meshed with the teeth of the two driven gears (11), the top of the bracket plate (10) is symmetrically fixedly connected with a clamping member (9), the inner walls of the two clamping members (9) are respectively rotatably connected to the outer walls of the output shafts at both ends of the dual-output motor (12); The conveying assembly comprises two groups of inner shaft rollers (15), the outer walls of the two groups of inner shaft rollers (15) are both transmission-connected with transmission belts (16), the tops of the two transmission belts (16) are both fixedly connected to the bottom of the placement box (2), and a transmission assembly is provided between the lifting platform (4) and the inner shaft rollers (15), and the transmission assembly is used to drive the placement box (2) to move; The transmission assembly comprises a rack plate 1 (20), wherein a rotating rod 1 (17) is fixedly connected between the two inner shaft rollers (15), a conveying gear (18) is fixedly connected to the outer wall of the rotating rod 1 (17), and the teeth of the conveying gear (18) are meshed with the teeth of the rack plate 1 (20); The outer wall of each group of the inner shaft rollers (15) is rotatably connected to a connecting shaft rod (19), and each group of the connecting shaft rods (19) are fixedly connected to each other. Two groups of clamping seats (14) are fixedly installed on the top of the bottom plate platform (1), and the inner wall of each group of the clamping seats (14) is rotatably connected to the outer wall shaft rods of two of the inner shaft rollers (15); The cooling component comprises a water inlet bin (23), the outer wall of the water inlet bin (23) is fixedly connected to a fixing ring (22), one side of the bracket plate (10) is fixedly connected to one side of the fixing ring (22), the bottom of the water inlet bin (23) is fixedly connected to a water outlet bin (24), the interior of the water outlet bin (24) is rotatably connected to a blocking round block (25), and a linkage component is provided between the lifting platform (4) and the cooling component, the linkage component is used to drive the blocking round block (25) to rotate 90 degrees; The two sides of the blocking round block (25) are fixedly connected to rotating rods (26), the rotating rods (26) are plugged into the inner wall of the water outlet bin (24), the two ends of the two rotating rods (26) are fixedly connected to gears (27), and the two sides of the lifting platform (4) are fixedly connected to rack plates (21), the teeth of the rack plates (21) are meshed with the teeth of the gears (27), and the number of teeth of the rack plates (21) is half the number of teeth of the gears (27).

2. The aluminum alloy workpiece forging machine according to claim 1, Features: A condensation box (28) is fixedly mounted on the top of the base plate platform (1), and condensation pipes (29) are fixedly connected to the outer walls of the condensation box (28).

3. The aluminum alloy workpiece forging machine according to claim 2, Features: A connecting water pipe (31) is fixedly connected to one side of the condensation box (28), a supporting frame (30) is fixedly connected to one side of the base platform (1), the connecting water pipe (31) is fixedly installed on one side of the supporting frame (30), an outlet of the connecting water pipe (31) is located at the top of the water inlet bin (23), and a water pump (32) is fixedly installed on the outer wall of the connecting water pipe (31).