Power model predictive control method for energy storage power station considering battery characteristics
By establishing a battery state-of-charge monitoring model and implementing zoned power control, the impact of battery characteristics on the performance of electrochemical energy storage power stations has been addressed, enabling rapid response and improved economic efficiency of the power stations, and enhancing grid stability.
Patent Information
- Application Number
- CN202410581856.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-11
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-05-11
AI Technical Summary
Existing technologies cannot effectively consider the impact of battery characteristics on the performance and control strategies of electrochemical energy storage power stations, resulting in insufficient rapid response capability and economic efficiency of the power stations, and difficulty in balancing grid load and the volatility of renewable energy.
By establishing a State of Charge (SOC) monitoring model for energy storage power stations, the optimal control signal is solved online using a discrete method. Combined with a three-phase two-level grid-connected inverter, a power optimal control problem is constructed. Furthermore, a coordinated power control strategy is formulated based on the battery state of charge partitioning to prevent the state of charge from exceeding the limit, thus achieving online rolling optimization.
It improves the rapid response capability of electrochemical energy storage power stations and the economy of the power grid, enhances the stability and reliability of the power grid, and optimizes the power station's power control strategy.
Smart Images

Figure CN118523385B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of power systems, and in particular to a power model prediction control method for an energy storage power station taking into account battery characteristics. Background Art
[0002] With the rapid development of renewable energy and the construction of smart grids, electrochemical energy storage power stations, as a new type of energy storage equipment, have the advantages of fast response, high efficiency, and environmental protection. They are widely used in power grid dispatching, power load regulation, and smooth output of renewable energy. Electrochemical energy storage power stations are devices that use electrochemical reactions to convert electrical energy into chemical energy and store it, and then convert it into electrical energy to supply the power grid when needed. Electrochemical energy storage power stations usually use lithium-ion batteries, sodium-sulfur batteries, lead-acid batteries and other battery types. Lithium-ion batteries have high energy density, long cycle life, low self-discharge rate, and fast charge and discharge speed. Compared with other types of batteries, lithium-ion batteries also have lower environmental impact and higher safety performance, which can better meet the environmental protection and safety requirements of electrochemical energy storage power stations. In summary, lithium-ion batteries have high energy density, long life, fast charge and discharge, and good environmental safety performance, making them an ideal choice for electrochemical energy storage power stations. Therefore, the most widely used electrochemical energy storage battery in electrochemical energy storage power stations is lithium-ion battery. Therefore, the battery characteristics are one of the important factors affecting the performance of electrochemical energy storage power stations, and have an important impact on the battery's charge and discharge characteristics, cycle life, safety, etc. Therefore, the study of the power control strategy of electrochemical energy storage power stations based on the battery characteristics is of great significance.
[0003] The characteristics of the battery itself have a direct impact on the performance of the electrochemical energy storage power station. The charging and discharging characteristics of the battery determine the charging and discharging efficiency and rate of the electrochemical energy storage power station, the cycle life is related to the service life and economy of the power station, and the safety is directly related to the safe operation of the power station. Therefore, understanding the characteristics of the battery itself is of great significance for formulating a reasonable control strategy for the electrochemical energy storage power station. Secondly, the power control strategy of the electrochemical energy storage power station is the key to improving the flexibility and economy of the power station. In the grid dispatching and power load regulation, the electrochemical energy storage power station needs to respond quickly according to the needs of the grid and realize rapid charging and discharging to balance the grid load. The power control strategy can effectively improve the response speed and energy utilization rate of the power station, reduce the operating cost of the power station, and improve the economy of the power station. Finally, with the large-scale access of renewable energy to the grid, the demand for electrochemical energy storage power stations continues to increase. Renewable energy is intermittent and volatile, which brings challenges to the stability and safety of the power grid. As a flexible energy storage device, the electrochemical energy storage power station can effectively smooth the output of renewable energy and improve the reliability and stability of the power grid.
[0004] In summary, the battery characteristics have an important influence on the performance and control strategy of electrochemical energy storage power stations. It is of great significance to study the power control strategy of electrochemical energy storage power stations considering the battery characteristics. By deeply studying the relationship between the battery characteristics and the power control strategy of electrochemical energy storage power stations, it can provide important theoretical and technical support for the design, operation and management of electrochemical energy storage power stations, and promote the application and promotion of electrochemical energy storage power stations in the fields of power grid dispatching, power load regulation, and renewable energy consumption. Summary of the invention
[0005] The purpose of the present invention is to solve the above-mentioned problems and to provide a power model predictive control method for an energy storage power station taking into account the characteristics of the battery itself.
[0006] To achieve the above object, the technical solution adopted by the present invention is: comprising the following steps:
[0007] Step 1: Monitor the SOC of the energy storage power station system based on the prediction model to establish a suitable system model, and construct the power optimal control problem by calculating the power reference value under the SOC constraint condition;
[0008] Step 2: Discretize the continuous optimal control problem using a discrete method, then solve it online to obtain the optimal control PWM signal, and partially apply the obtained optimal control PWM signal to the three-phase two-level grid-connected inverter to control the discharge or charging process of the battery, so that the energy storage power station can absorb or provide power with the best efficiency and maximize the battery's charging and discharging capacity. This cycle is repeated to achieve online rolling optimization and optimal power control of the energy storage power station.
[0009] The two-level inverter has eight switching states, including six active voltage vectors and two zero voltage vectors.
[0010] The power prediction model of three-phase two-level grid-connected inverter is as follows:
[0011] State equation in the abc three-phase stationary coordinate system:
[0012]
[0013] Where: L is the actual filter inductance, R is the parasitic resistance, i a ,i b ,i c is the three-phase grid-connected current of a, b, c, u a ,u b ,u c The a, b, c bidirectional converter outputs three-phase voltage, e a , e b , e c is the three-phase grid-connected voltage of a, b, c;
[0014] The current state equation in the abc three-phase stationary coordinate system is transformed into the αβ two-phase coordinate system through Clark transformation:
[0015]
[0016] Where: i α ,i β is the grid-connected current in the αβ two-phase coordinate system, u α ,u β is the output voltage of the bidirectional converter in the αβ two-phase coordinate system, e α , e β is the grid-connected voltage in the αβ two-phase coordinate system;
[0017] The control object is the grid-connected power of the energy storage power station. The load current is discretized using the forward Euler formula, T s is the sampling time:
[0018]
[0019] Next, the instantaneous power rate of the energy storage power station is predicted:
[0020]
[0021] Where: p(k+1), q(k+1) are the active power and reactive power of the energy storage power station at time k+1.
[0022] Step 3: Establish a suitable objective function and bring various switch states into the objective function in turn; enable the energy storage power station to absorb or provide power at the best efficiency and maximize the battery's charging and discharging capacity. The specific contents are as follows:
[0023] The power model predictive control strategy of the electrochemical energy storage power station considering the battery characteristics can be realized by solving the following objective function:
[0024]
[0025] Where P ref ,Q ref is the reference active power and reactive power of the energy storage power station, P, Q are the instantaneous active power and reactive power of the energy storage power station; α, β are the weight coefficients of the two objective functions of minimum power error and minimum energy loss, respectively.
[0026] Step 5: Select the switch state corresponding to the vector that minimizes the objective function by enumeration to control the next control cycle.
[0027] Furthermore, the specific contents of the SOC limitation of energy storage batteries are as follows: according to the dispatching instructions, the information of each PCS is stored through the blockchain. On the basis of clarifying the power demand of the power grid, the regional dispatching layer comprehensively considers the intrinsic characteristics of the energy storage battery, that is, the energy storage charge state management.
[0028] According to the state of SOC, the battery SOC is partitioned, the output target of each interval is determined, and the corresponding coordinated power control strategy is formulated to complete the power control of the energy storage power station. The power control command is distributed to each PCS, and each PCS is proportionally distributed according to the SOC of the energy storage battery group.
[0029] The energy storage battery SOC restrictions are as follows:
[0030] SOC min ≤SOC(t)≤SOC max (1)
[0031] Where: SOC min is the lower limit of battery SOC; SOC max The upper limit of battery SOC;
[0032] According to the battery charging and discharging efficiency and regulation ability, SOC is divided into 0~SOC min , SOC min ~SOC low , SOC low ~SOC high , SOC high ~SOC max , SOC max ~100% of these 5 intervals, including SOC low and SOC high They are the lower and upper limits of SOC when the battery is working normally. When SOC exceeds these two limits, that is, SOC is within SOC min ~SOC low Interval and SOC high ~SOC max The power of the energy storage battery pack will be limited when the SOC is within the SOC range. min ~SOC low In the SOC range, the energy storage battery pack has strong charging regulation capability but insufficient discharge capability. If the energy storage battery pack is discharged, the discharge power should be reduced to avoid a rapid drop in SOC. high ~SOC max In the SOC range, the energy storage battery pack has strong discharge regulation ability and insufficient charging ability. If the energy storage battery pack is charged, the charging power should be reduced to avoid a rapid increase in SOC. low ~SOC highDuring this period, the energy storage battery pack has strong charging and discharging regulation capabilities, which is an ideal working area for the energy storage battery pack.
[0033] Furthermore, the SOC is used as a power regulation feedback quantity to control the energy storage battery pack to work in an ideal range, and the charging and discharging power of the battery pack is adjusted in real time according to the range where the battery SOC is located to prevent the SOC from exceeding the limit;
[0034] Introducing SOC constraint adjustment coefficient K SOC , K in charging and discharging states SOC The expressions of are shown in formula (2) and formula (3) respectively:
[0035]
[0036] in
[0037]
[0038]
[0039] Therefore, the charging and discharging power of the energy storage battery pack considering the SOC constraint can be obtained as shown in formula (5):
[0040] P* b,SOC (t)=(f c K SOC,c +f d K SOC,d ) b (t) (5)
[0041] Where: P* b,SOC (t) is the corrected energy storage target power f considering only the SOC constraint c and f d It is the energy storage charge and discharge flag, and its value is determined by the following formula:
[0042]
[0043] Compared with the prior art, the present invention has the following beneficial effects:
[0044] The state of charge of the energy storage battery is divided according to its charge and discharge characteristics, and the power control strategy should consider different energy storage state of charge constraints. In order to control the energy storage battery group to work in the ideal range, the state of charge of the energy storage battery can be used as the power regulation feedback, and the battery group charge and discharge power is adjusted in real time according to the range where the energy storage battery state of charge is located to prevent the energy storage battery state of charge from exceeding the limit. Within a certain safety range, in order to enable the energy storage power station to complete power output in the shortest time, the rapid power output problem is converted into an output tracking problem, and the optimal rapid power control strategy at each moment is obtained. Through this electrochemical energy storage power station power control strategy that considers the characteristics of the battery itself, the rapid response capability of the energy storage power station can be greatly enhanced, and the economy and stability of the power grid can be improved. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] Figure 1 This is a typical structural diagram of the electrochemical energy storage power station of the present invention;
[0046] Figure 2 It is a state partition diagram of the SOC of the present invention;
[0047] Figure 3 It is the constrained MPC principle of the present invention;
[0048] Figure 4 This is a block diagram of the power model prediction control of the energy storage power station considering the battery characteristics of the present invention;
[0049] Figure 5 The bidirectional AC / DC converter grid-connected topology of the present invention;
[0050] Figure 6 This is a power model prediction control flow chart of the present invention. DETAILED DESCRIPTION
[0051] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.
[0052] See also Figure 1 As shown, the present invention provides a technical solution: a power model predictive control method for an energy storage power station taking into account the characteristics of the battery itself, wherein the electrochemical energy storage power station is composed of a unit battery system (actually a containerized battery energy storage system including a lithium battery pack, a battery management system, an energy conversion system, a control system and other equipment), an energy storage converter (PCS), a collector line, an in-station reactive power compensation device, an in-station step-up transformer, a station-level control system and the like.
[0053] The model is established by taking one of the energy storage related equipment of the 330kV Jianhang Energy Storage Power Station in Zhangye City, Gansu Province as an example. It is known that the capacity of the containerized battery energy storage group of the energy storage power station is 2.967MWh, which is composed of several battery packs with a voltage of 200.8V and a capacity of 61KWh (for multiple unit battery systems composed of energy storage batteries and converters of the same model and capacity, they can be multiplied to be equivalent to a unit battery group). Now the two containerized battery energy storage systems are regarded as a unit battery system model (because one round of energy storage related equipment includes two containerized battery energy storage systems, a PCS, a dry-type box transformer, a step-up transformer, and an LCL filter). The 1500KVA PCS converts the DC power output of the containerized battery energy storage system into AC power, which is then increased to 35KV by a 3150kVA dry-type box transformer and collected to the AC bus. After that, it is increased to 330KV by a step-up transformer and then connected to the grid. The structure of the energy storage power station is as follows: Figure 1 As shown;
[0054] Power model predictive control strategy for energy storage power station considering battery characteristics
[0055] Analysis of battery characteristics of energy storage power station
[0056] In the structure of energy storage power station, two battery packs are usually connected in series with a PCS to form a small unit, and a distributed control method is used to control the power of each PCS. Due to the heterogeneity of batteries in energy storage power stations, if power is directly allocated according to the requirements of the dispatching agency, the state of charge (SOC) of some batteries may exceed the limit, which is not conducive to the power regulation and economic use of energy storage power stations. In order to ensure that the energy storage battery group operates within a safe range, the SOC of the energy storage battery needs to be limited.
[0057] Therefore, a power control strategy for energy storage power stations that takes into account the characteristics of the battery itself is proposed. According to the dispatching instructions, the information of each PCS is stored through the blockchain. On the basis of clarifying the power demand of the power grid, the regional dispatching layer comprehensively considers the characteristics of the energy storage battery, that is, the energy storage charge state management.
[0058] According to the state of SOC, the battery SOC is partitioned, the output target of each interval is determined, and the corresponding coordinated power control strategy is formulated to complete the power control of the energy storage power station. The power control command is distributed to each PCS, and each PCS is proportionally distributed according to the SOC of the energy storage battery group.
[0059] The energy storage battery SOC restrictions are as follows:
[0060] SOC min ≤SOC(t)≤SOC max (1)
[0061] Where: SOCmin is the lower limit of battery SOC; SOC max It is the upper limit of battery SOC.
[0062] According to the battery charging and discharging efficiency and regulation ability, SOC is divided into 0~SOC min , SOC min ~SOC low , SOC low ~SOC high , SOC high ~SOC max , SOC max ~100% of these 5 intervals, including SOC low and SOC high They are the lower and upper limits of SOC when the battery is working normally. When SOC exceeds these two limits, that is, SOC is within SOC min ~SOC low Interval and SOC high ~SOC max The power of the energy storage battery pack will be limited. min ~SOC low In the SOC range, the energy storage battery pack has strong charging regulation capability but insufficient discharge capability. If the energy storage battery pack is discharged, the discharge power should be reduced to avoid a rapid drop in SOC. high ~SOC max In the SOC range, the energy storage battery pack has strong discharge regulation ability and insufficient charging ability. If the energy storage battery pack is charged, the charging power should be reduced to avoid a rapid increase in SOC. low ~SOC high During this period, the energy storage battery pack has strong charging and discharging regulation capabilities, which is an ideal working area for the energy storage battery pack.
[0063] In order to control the energy storage battery pack to operate in an ideal range, the SOC can be used as a power regulation feedback variable to adjust the battery pack charging and discharging power in real time according to the battery SOC range to prevent the SOC from exceeding the limit.
[0064] Introducing SOC constraint adjustment coefficient K SOC , K in charging and discharging states SOC The expressions of are shown in formula (2) and formula (3) respectively:
[0065]
[0066] in
[0067]
[0068]
[0069] Therefore, the charging and discharging power of the energy storage battery pack considering the SOC constraint can be obtained as shown in formula (5):
[0070] P* b,SOC (t)=(f c K SOC,c +f d K SOC,d ) b (t) (5)
[0071] Where: P* b,SOC (t) is the corrected energy storage target power f considering only the SOC constraint c and f d It is the energy storage charge and discharge flag, and its value is determined by the following formula:
[0072]
[0073] The goal of optimizing the operation of the grid-side electrochemical energy storage power station should also consider the maximum energy efficiency of the entire station and the highest economy, which is also the optimization goal, which can be equivalent to the minimum charging and discharging loss of the station-side energy storage, that is, P loss Minimum. Assume that the energy storage power station has i PCSs, and the charging and discharging power of each PCS is P i , the energy efficiency of PCS at this charge and discharge power is η i , then the charging and discharging power loss of this PCS is The specific expression is as follows:
[0074]
[0075] Power model predictive control strategy for energy storage power station considering battery characteristics
[0076] Power Model Predictive Control Strategy
[0077] Model predictive control (MPC) is a special type of control method. Its current control action is obtained by solving a finite-time open-loop optimal control problem at each sampling instant. The current state of the process is used as the initial state of the optimal control problem, and the optimal control sequence obtained only implements the first control action. This is the biggest difference between it and those algorithms that use pre-calculated control laws. In essence, model predictive control solves an open-loop optimal control problem. Its core ideas are as follows Figure 3 shown.
[0078] The SOC state of the energy storage battery needs to be considered in the design of the power control strategy of the energy storage power station. MPC can consider the constraints at the current moment and in the prediction time domain, and can make full use of the information provided by the reference trajectory. The process of optimal power control of the electrochemical energy storage power station considering the characteristics of the battery itself can be roughly divided into three parts: prediction model, rolling optimization and feedback correction. Among them, the key to the prediction model MPC, iterative prediction and online rolling optimization are all centered around the prediction model. First, the SOC of the energy storage power station system is monitored based on the prediction model, and the power optimal control problem is constructed by calculating the power reference value under the SOC constraint. The continuous form of the optimal control problem is discretized using a discrete method, and then the optimal control PWM signal is obtained by online solution. The optimal control PWM signal is initially applied to the three-phase two-level grid-connected inverter to control the discharge or charging process of the battery, so that the energy storage power station can absorb or provide power with the best efficiency and maximize the battery's charging and discharging capacity. This cycle is repeated to achieve online rolling optimization and optimal power control of the energy storage power station. Since the MPC solution process is performed online, its solution efficiency will affect the actual control performance, so it is necessary to balance control accuracy and real-time performance. The power control block diagram of the energy storage power station proposed in this paper is as follows Figure 4 As shown;
[0079] The three-phase two-level grid-connected inverter is connected to the grid by a DC voltage source through a three-phase voltage-type inverter and an L-type filter. Its topology is as follows: Figure 5 As shown;
[0080] The switch devices of the same-phase bridge arm cannot be turned on at the same time. Assume that the switch signal 1 indicates that the upper bridge arm is turned on and the lower bridge arm is turned off, and the signal 0 indicates that the upper bridge arm is turned off and the lower bridge arm is turned on. The two-level inverter has eight switching states, including six active voltage vectors and two zero voltage vectors. The voltage vector and switch state summary table of the three-phase two-level grid-connected inverter is shown in Table 1. dc Voltage on both sides of the bidirectional converter, u a ,u b is the voltage of phase a and phase b, u 0 ~u 7 The 8 voltage vectors of the inverter are:
[0081] Table 1 Summary of voltage vector and switch status of bidirectional AC / DC converter
[0082]
[0083]
[0084] Power Model Predictive Control Strategy
[0085] The power prediction model of three-phase two-level grid-connected inverter is as follows:
[0086] State equation in the abc three-phase stationary coordinate system:
[0087]
[0088] Where: L is the actual filter inductance, R is the parasitic resistance, i a ,i b ,i c is the three-phase grid-connected current of a, b, c, u a ,u b ,u c The a, b, c bidirectional converter outputs three-phase voltage, e a , e b , e c is the three-phase grid-connected voltage of a, b, c.
[0089] The current state equation in the abc three-phase stationary coordinate system is transformed into the αβ two-phase coordinate system through Clark transformation:
[0090]
[0091] Where: i α ,i β is the grid-connected current in the αβ two-phase coordinate system, u α ,u β is the output voltage of the bidirectional converter in the αβ two-phase coordinate system, e α , e β is the grid-connected voltage in the αβ two-phase coordinate system.
[0092] The control object is the grid-connected power of the energy storage power station. The load current is discretized using the forward Euler formula, T s is the sampling time:
[0093]
[0094] Next, the instantaneous power rate of the energy storage power station is predicted:
[0095]
[0096] Where: p(k+1), q(k+1) are the active power and reactive power of the energy storage power station at time k+1.
[0097] In order to enable the energy storage power station to provide or output power at the best efficiency, the optimal power control problem is transformed into an output tracking problem, that is, the energy storage power station power can reach the reference active and reactive power under its SOC constraint as quickly as possible, and the square error integral of the predicted instantaneous power and the reference power is minimized as the performance indicator function. The power model predictive control strategy of the electrochemical energy storage power station considering the battery body characteristics can be achieved by solving the following objective function:
[0098]
[0099] Where P ref ,Q ref is the reference active power and reactive power of the energy storage power station, P, Q are the instantaneous active power and reactive power of the energy storage power station.
[0100] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0101] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A power model predictive control method for an energy storage power station considering the battery characteristics, characterized in that: The following steps are included: Step 1: Monitor the SOC of the energy storage power station system based on the prediction model and establish a suitable system model. By calculating the power reference value under the SOC constraint and considering the power station energy efficiency, the power optimal control problem is constructed; The specific contents of SOC limitation of energy storage batteries are as follows: According to the dispatching instructions, the information of each PCS is stored through the blockchain. On the basis of clarifying the power demand of the power grid, the regional dispatching layer comprehensively considers the intrinsic characteristics of the energy storage battery, that is, the energy storage charge state management. According to the state of SOC, the battery SOC is partitioned, the output target of each interval is determined, and the corresponding coordinated power control strategy is formulated to complete the power control of the energy storage power station. The power control command is distributed to each PCS, and each PCS is proportionally distributed according to the SOC of the energy storage battery group. The energy storage battery SOC restrictions are as follows: (1) Where: is the battery SOC lower limit; The upper limit of battery SOC; According to the battery charging and discharging efficiency and regulation ability, SOC is divided into , , , , These 5 intervals, including They are the lower and upper limits of SOC when the battery is working normally. When SOC exceeds these two limits, that is, SOC is Interval and range, the power of the energy storage battery pack will be limited; when the SOC is In the range, the energy storage battery pack has strong charging regulation ability and insufficient discharge ability. If the energy storage battery pack is discharged, the discharge power should be reduced to avoid a rapid decrease in SOC. When the SOC is In the range, the energy storage battery pack has strong discharge regulation ability and insufficient charging ability. If the energy storage battery pack is charged, the charging power should be reduced to avoid a rapid increase in SOC. When the SOC is In the interval, the energy storage battery pack has strong charging and discharging regulation capabilities, which is an ideal working area for the energy storage battery pack; Use SOC as the power regulation feedback to control the energy storage battery pack to work in the ideal range, as follows: Adjust the battery pack charging and discharging power in real time according to the battery SOC range to prevent SOC from exceeding the limit; Introducing SOC constraint adjustment coefficient , charging state and discharging state The expressions of are shown in formula (2) and formula (3): (2) in (3) (4) Therefore, the charging and discharging power of the energy storage battery pack considering the SOC constraint can be obtained as shown in formula (5): (5) Where: is the corrected energy storage target power considering only the SOC constraint It is the energy storage charge and discharge flag, and its value is determined by the following formula: (6) The goal of optimizing the operation of the electrochemical energy storage power station on the grid side should also consider the maximum energy efficiency and the highest economy of the whole station, which is also the optimization goal, which can be equivalent to the minimum charging and discharging loss of the station-side energy storage, that is, Minimum; Assuming the energy storage power station has PCS, the charging and discharging power of each PCS is , the energy efficiency of PCS under this charge and discharge power is , then the charging and discharging power loss of this PCS is , the specific expression is as follows: (7) Step 2: Discretize the continuous optimal control problem using a discrete method, then solve it online to obtain the optimal control PWM signal, and partially apply the obtained optimal control PWM signal to the three-phase two-level grid-connected inverter to control the discharge or charging process of the battery, so that the energy storage power station can absorb or provide power with the best efficiency and maximize the battery's charging and discharging capacity. This cycle is repeated to achieve online rolling optimization and optimal power control of the energy storage power station. The two-level inverter has eight switching states, including six active voltage vectors and two zero voltage vectors. The power prediction model of three-phase two-level grid-connected inverter is as follows: State equation in the abc three-phase stationary coordinate system: (8) Where: L is the actual filter inductance, R is the parasitic resistance, is the three-phase grid-connected current of a, b, c, The a, b, c bidirectional converter outputs three-phase voltage. is the three-phase grid-connected voltage of a, b, c; The current state equation in the abc three-phase stationary coordinate system is transformed into Two-phase coordinate system: (9) Where: for The grid-connected current in the two-phase coordinate system is: for The output voltage of the bidirectional converter in the two-phase coordinate system, for Grid-connected voltage in two-phase coordinate system; The control object is the grid-connected power of the energy storage power station. The load current is discretized using the forward Euler formula. is the sampling time: (10) Next, the instantaneous power rate of the energy storage power station is predicted: (11) Where: for Active power and reactive power of energy storage power station at all times; Step 3: Establish a suitable objective function and bring various switch states into the objective function in turn; enable the energy storage power station to absorb or provide power at the best efficiency and maximize the battery's charging and discharging capacity. The specific contents are as follows: The power model predictive control strategy of the electrochemical energy storage power station considering the battery characteristics can be realized by solving the following objective function: (12) In the formula, are the reference active power and reactive power of the energy storage power station, is the instantaneous active power and reactive power of the energy storage power station; are the weight coefficients of the two objective functions of minimum power error and minimum energy loss respectively; Step 5: Select the switch state corresponding to the vector that minimizes the objective function by enumeration to control the next control cycle.