A construction method for permanent supporting wall with whole-row piles

Through the construction method of prefabricated formwork support and grouting between piles, the problems of unsolid bonding of the foundation pit support pile surface layer and long construction time are solved, and the leveling construction and rapid construction of the foundation pit support wall are realized, and the improvement of the improvement of the foundation pit support wall. Construction efficiency.

CN118531810BActive Publication Date: 2024-11-26SHANDONG UNIV +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410986103.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-23
Publication Date
2024-11-26
Estimated Expiration
2044-07-23

AI Technical Summary

Technical Problem

During the injection construction of traditional foundation pit support pile surface layer, the concrete and the foundation are not firmly bonded to the foundation surface due to uneven distance, unstable speed, and inappropriate concrete distribution, forming hollows, and building blocks in front of the support piles The wall leveling plan takes a long time and affects the progress of the project.

Method used

The construction method of prefabricated formwork support and pile grouting is adopted, and the prefabricated formwork and detachable side rails are fixed, so as to achieve the leveling construction of the support wall, ensuring good bonding between concrete and foundation surfaces, and improving construction efficiency through regional construction .

Benefits of technology

It solves the hollowing problem caused by traditional spray concrete surface layer, realizes rapid construction progress, saves time, and improves construction efficiency and flatness.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118531810B_ABST
    Figure CN118531810B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of foundation pit engineering, and specifically to a construction method of a permanent supporting wall of a whole row of piles, comprising the following steps: S1, supporting pile construction; S2, processing supporting piles; S3, determining the leveling position; S4, installing vertical side rails; S5, installing horizontal side rails; S6, supporting templates; S7, pouring mortar, and setting horizontal supports; S8, after the mortar reaches the strength requirement, the vertical side rails are removed from the supporting piles, the template is moved to the next construction area along the horizontal side rails, the vertical side rails are fixed on the supporting piles of the next construction area, and the template and the vertical side rails are connected; S9, steps S7-S8 are repeated until the supporting wall construction of the first layer of construction area is completed; S10, after the construction is completed, the side rails and templates are removed, the next layer of earthwork is excavated, and steps S2-S9 are repeated. The present invention adopts the method of template support and inter-pile grouting to achieve the leveling of the supporting wall, solves the hollowing problem caused by the traditional sprayed concrete surface layer, and improves the construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation pit engineering, and in particular to a construction method for a permanent supporting wall of a whole row of piles. Background Art

[0002] The traditional construction method of the support pile surface layer is to hang a steel mesh on the surface of the support pile after the foundation pit is excavated, and then spray the concrete surface layer. At present, some people have also proposed to build a retaining wall in front of the support pile, compact the fill between the retaining wall and the support pile, and use the retaining wall to level the pile row.

[0003] During the traditional surface spraying construction, if the distance between the spray gun and the base surface is uneven, the construction speed is too fast or too slow, the pressure is unstable, the concrete material ratio is not appropriate, the water-cement ratio is too high or too low, and inferior concrete materials are used, etc., it may cause the concrete to be poorly bonded to the base surface and form hollows. The solution of building a retaining wall in front of the support piles to level the support piles will take a lot of time, which is not conducive to the advancement of the project progress. Summary of the invention

[0004] In order to solve the problems existing in the background technology, the present invention proposes a construction method of a permanent supporting wall of a whole row of piles, which adopts the scheme of prefabricated formwork support and grouting between piles to construct and level the supporting wall, solves the problem of hollowing caused by the traditional shotcrete surface layer, and can quickly carry out construction and save time. The technical solution is as follows:

[0005] A construction method for a permanent retaining wall with a whole row of piles comprises the following steps:

[0006] S1. Support pile construction: Carry out the construction of support piles and water-stop curtains, and after the construction is completed, excavate the first layer of earthwork;

[0007] S2. Processing of support piles: After excavation is completed, the support piles are evaluated and the grinding range and depth are determined. After the determination is completed, the support piles protruding from the support wall are ground, and the soil between the piles is ground;

[0008] S3. Determine the leveling position: After the support pile is polished, the convex surface of the support pile is the leveling position;

[0009] S4. Install vertical side rails: removably install two vertical side rails on the supporting piles. The vertical side rails are used to fix the formwork. The distance between the two vertical side rails is not greater than the horizontal dimension of the formwork.

[0010] S5. Install the transverse side rails: install the two transverse side rails on the top and bottom of the support piles respectively in a detachable manner, and the distance between the upper and lower transverse side rails shall not be greater than the vertical dimension of the template;

[0011] S6. Supporting formwork: Sliding the prefabricated retaining wall formwork on two horizontal side rails, the two ends of the retaining wall are fixedly connected to the vertical side rails, and the supporting position of one formwork is one construction area;

[0012] S7, pouring mortar and setting lateral support: pouring mortar between the formwork and the supporting piles, while constructing the anchor cables in this construction area. After the anchor cable construction is completed, the waist beam in this construction area is constructed;

[0013] S8. After the mortar reaches the strength requirement, the vertical side rails are removed from the supporting piles, the template is moved horizontally along the horizontal side rails to the next construction area, and then the vertical side rails are fixed to the supporting piles of the next construction area, connecting the template and the vertical side rails;

[0014] S9, repeat steps S7-S8 until the support wall construction of the first layer construction area is completed;

[0015] S10, after the construction is completed, the horizontal side rails, vertical side rails and formwork are removed, and the excavation of the next layer of earthwork is continued, and steps S2-S9 are repeated.

[0016] Preferably, the vertical side rails are made of angle steel, and the vertical side rails are fixed to the supporting piles by expansion bolts.

[0017] Preferably, a fixed steel buckle is fixed on the vertical side rail, a bolt is slidably provided inside the fixed steel buckle, a connecting hole is provided on the template, and when the template is installed, the threaded end of the bolt passes through the template connecting hole, and one end of the bolt passing through the connecting hole is threadedly connected with a nut.

[0018] Preferably, the transverse side rails are made of angle steel, and the transverse side rails are fixed to the supporting piles by expansion bolts.

[0019] Preferably, each construction area includes two adjacent supporting piles, and the two vertical side rails are respectively installed on the two supporting piles.

[0020] Preferably, each construction area includes three adjacent support piles, and two vertical side rails are respectively installed on the first and third support piles in this area.

[0021] The present invention has the following beneficial effects: the present invention adopts the scheme of prefabricated formwork support and grouting between piles to realize the construction of the supporting wall, and can ensure the flatness of the supporting wall, solves the hollowing problem caused by the traditional shotcrete surface layer, and solves the problem of high requirements on operation and materials during construction. In addition, the present invention has a simple structure, is easy to implement, can be constructed quickly, saves time, and thus improves construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of the position relationship between the transverse side rail and the supporting piles of the present invention;

[0023] Figure 2 It is a longitudinal cross-sectional view of the support pile and the transverse side rail of the present invention;

[0024] Figure 3 It is a transverse cross-sectional view of the support pile and the vertical side rail of the present invention;

[0025] Figure 4 It is a schematic diagram of the position relationship of the support piles, the horizontal side rails, the vertical side rails and the template of the present invention;

[0026] Figure 5 It is a schematic diagram of the fixed steel buckle structure of the present invention.

[0027] Numbers in the figure: 1. Support piles; 2. Horizontal side rails; 3. Vertical side rails; 4. Formwork; 5. Expansion bolts; 6. Fixed steel buckles; 61. Notches; 62. Slide grooves; 63. Sliding space; 7. Water-stop curtain; 8. Bolts. DETAILED DESCRIPTION

[0028] In order to make the present invention clearer and more understandable, the technical solution of the present invention is further described in detail below in combination with the accompanying drawings and embodiments. It should be understood that the given embodiment is only one of the implementation methods and does not represent all embodiments.

[0029] In this article, the terms "upper, lower" and the like are established based on the positional relationship shown in the drawings. Depending on the different drawings, the corresponding positional relationship may also change accordingly. Therefore, they cannot be understood as an absolute limitation on the scope of protection.

[0030] Combined with Figure 1 -Attached Figure 5 , a construction method of a permanent retaining wall with a whole row of piles, comprising the following steps:

[0031] S1, construction of support piles 1: construction of support piles 1 and water-stop curtain 7, and excavation of the first layer of earthwork after completion of the construction;

[0032] S2. Processing the support piles 1: After the excavation is completed, the condition of the support piles 1 is evaluated, including whether the surface is flat, whether there are cracks or damage, etc., and the grinding range and depth are determined. After the determination is completed, a suitable grinder is selected according to the size and shape of the support piles 1, and the support piles 1 protruding from the support wall are ground, and the soil between the piles is ground;

[0033] S3. Determine the leveling position: After the support pile 1 is polished, the convex surface of the support pile 1 is the leveling position;

[0034] S4. Install the vertical side rails 3: detachably install the two vertical side rails 3 on the support pile 1. The vertical side rails 3 are used to fix the template 4. The distance between the two vertical side rails 3 is not greater than the lateral dimension of the template 4. Specifically, the vertical side rails 3 are made of angle steel. The vertical side rails 3 are fixed to the support pile 1 by expansion bolts 5. The detachable installation of the vertical side rails 3 is achieved by removing or screwing the expansion bolts 5.

[0035] S5. Install the transverse side rails 2: The two transverse side rails 2 are detachably installed on the top and bottom of the support pile 1, respectively, and the spacing between the upper and lower transverse side rails 2 is not greater than the vertical dimension of the template 4; specifically, the transverse side rails 2 are made of angle steel, and the transverse side rails 2 are fixed to the support pile 1 by expansion bolts 5, and the detachable installation of the transverse side rails 2 is achieved by removing or screwing the expansion bolts 5; more specifically, the transverse side rails 2 are composed of a plurality of single-section side rails, each of which can be detached separately. When the construction of a construction area is completed, the single-section side rails of this area can be removed, which does not affect the construction of structures such as waist beams, further realizing the regionalization of construction and improving the flexibility and efficiency of construction;

[0036] S6. Supporting formwork 4: The prefabricated supporting wall formwork 4 is slidably set on the two horizontal side rails 2, and the two ends of the supporting wall are fixedly connected to the vertical side rails 3. The supporting position of a formwork 4 is a construction area; specifically, a fixed steel buckle 6 is fixed on the vertical side rail 3, and a bolt 8 is slidably arranged in the fixed steel buckle 6. A connecting hole is arranged on the formwork 4. When the formwork 4 is installed, the threaded end of the bolt 8 passes through the connecting hole of the formwork 4, and a nut is threadedly connected to one end of the bolt 8 passing through the connecting hole. The formwork 4 is fixedly connected to the fixed steel buckle 6 by tightening the nut; more specifically, the fixed steel buckle 6 is a steel member that is wide at the top and narrow at the bottom, and the wide part of the fixed steel buckle 6 is provided with A notch 61 with a diameter larger than the diameter of the head of the bolt 8, a sliding space 63 is vertically arranged inside the narrow part of the fixed steel buckle 6, and a slide groove 62 connected to the sliding space 63 is arranged on one side of the narrow part of the fixed steel buckle 6, the notch 61 is connected with the sliding space 63 and the slide groove 62, the radial dimension of the sliding space 63 is larger than the diameter of the head of the bolt 8, the radial dimension of the slide groove 62 is smaller than the diameter of the head of the bolt 8, and larger than the diameter of the rod of the bolt 8; during installation, the bolt 8 is placed into the fixed steel buckle 6 from the notch 61, and after being placed, the bolt 8 is moved to the sliding space 63, and the rod of the bolt 8 with a thread extends out of the fixed steel buckle 6 from the slide groove 62, so as to be conveniently connected with the template 4;

[0037] S7, pouring mortar and setting lateral support: pouring mortar between the formwork 4 and the support pile 1, while pouring, the construction of anchor cables in this construction area is carried out. After the anchor cable construction is completed, the construction of the waist beam in this construction area is carried out;

[0038] S8. After the mortar reaches the required strength, the vertical side rail 3 is removed from the support pile 1, the template 4 is moved laterally along the transverse side rail 2 to the next construction area, and the vertical side rail 3 is fixed on the support pile 1 of the next construction area, connecting the template 4 and the vertical side rail 3;

[0039] S9, repeat steps S7-S8 until the support wall construction of the first layer construction area is completed;

[0040] S10, after the construction is completed, the horizontal side rails 2, the vertical side rails 3 and the template 4 are removed, and the excavation of the next layer of earthwork is continued, and steps S2-S9 are repeated.

[0041] Specifically, each construction area includes two adjacent supporting piles 1, and two vertical side rails 3 are respectively installed on the two supporting piles 1. Or, each construction area includes three adjacent supporting piles 1, and two vertical side rails 3 are respectively installed on the first and third supporting piles 1 in this area, and mortar pouring between two supporting piles 1 can be carried out simultaneously. The number of supporting piles 1 in a construction area determines the span of the formwork 4, and thus determines the span of each construction area. A large span of the construction area can reduce the division of the construction area and improve construction efficiency. The number of supporting piles 1 in a construction area is adjusted according to actual conditions, and two or three supporting piles 1 are preferably used.

[0042] Specifically, construction of multiple construction areas can be carried out simultaneously, that is, multiple sets of vertical side rails 3 are laid, and construction of the construction areas is carried out synchronously, further shortening the construction time.

[0043] While embodiments of the present invention have been shown and described, it will be apparent to those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the invention, the scope of which is defined by the appended claims and their equivalents.

Claims

1. A construction method for a permanent retaining wall with a whole row of piles, characterized in that: The following steps are involved: S1. Construction of support piles (1): Construction of support piles (1) and water-stop curtains (7) is performed, and after completion of the construction, the first layer of earthwork is excavated; S2. Processing the support piles (1): After the excavation is completed, the condition of the support piles (1) is evaluated and the grinding range and depth are determined. After the determination is completed, the support piles (1) protruding from the support wall are ground, and the soil between the piles is ground; S3, determining the leveling position: after the support pile (1) is polished, the convex surface position of the support pile (1) is the leveling position; S4, installing the vertical side rails (3): detachably installing the two vertical side rails (3) on the support piles (1), the vertical side rails (3) being used to fix the formwork (4), and the distance between the two vertical side rails (3) being no greater than the lateral dimension of the formwork (4); A fixed steel buckle (6) is fixed on the vertical side rail (3), a bolt (8) is slidably provided inside the fixed steel buckle (6), a connecting hole is provided on the template (4), and when the template (4) is installed, the threaded end of the bolt (8) passes through the connecting hole of the template (4), and one end of the bolt (8) passing through the connecting hole is threadedly connected to a nut; S5. Installing the transverse side rails (2): installing the two transverse side rails (2) on the top and bottom of the support pile (1) in a detachable manner, respectively, and the distance between the upper and lower transverse side rails (2) is not greater than the vertical dimension of the template (4); S6, supporting the formwork (4): slidingly setting the prefabricated supporting wall formwork (4) on the two horizontal side rails (2), and fixing the two ends of the supporting wall with the vertical side rails (3). The supporting position of one formwork (4) is one construction area; S7, pouring mortar and setting lateral support: pouring mortar between the formwork (4) and the support pile (1), while constructing anchor cables in this construction area. After the anchor cable construction is completed, the waist beam in this construction area is constructed; S8. After the mortar reaches the required strength, the vertical side rail (3) is removed from the supporting pile (1), the template (4) is moved laterally along the transverse side rail (2) to the next construction area, and the vertical side rail (3) is fixed to the supporting pile (1) of the next construction area, connecting the template (4) and the vertical side rail (3); S9, repeat steps S7-S8 until the support wall construction of the first layer construction area is completed; S10, after the construction is completed, the horizontal side rails (2), the vertical side rails (3) and the template (4) are removed, and the excavation of the next layer of earthwork is continued, and steps S2-S9 are repeated.

2. The construction method of a permanent supporting wall of a whole row of piles according to claim 1, characterized in that: The vertical side rail (3) is made of angle steel, and the vertical side rail (3) is fixed to the support pile (1) by means of expansion bolts (5).

3. The construction method of a permanent retaining wall of a whole row of piles according to claim 1, characterized in that: The transverse side rail (2) is made of angle steel, and the transverse side rail (2) is fixed to the support pile (1) by means of expansion bolts (5).

4. The construction method of a permanent retaining wall of a whole row of piles according to claim 1, characterized in that: Each construction area comprises two adjacent support piles (1), and two vertical side rails (3) are respectively installed on the two support piles (1).

5. The construction method of a permanent retaining wall of a whole row of piles according to claim 1, characterized in that: Each construction area comprises three adjacent support piles (1), and two vertical side rails (3) are respectively installed on the first and third support piles (1) in this area.