A hoisting device and hoisting method for shed tunnel construction
By changing the force direction of the sling and using the cable-retaining mechanism, the problem of excessive boom length and stuck steel beams during shed construction was solved, achieving a safer and more convenient steel beam extraction process.
Patent Information
- Application Number
- CN202411134058.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-19
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-08-19
AI Technical Summary
During shed construction, the existing hoisting method has the problem that the boom length is long and the steel beam is easy to get stuck with the formwork port, making the operation inconvenient.
Design a hoisting device that changes the force direction of the sling on the steel beam so that the steel beam remains horizontal when it is pulled away and reduces the length of the boom. A cable-retaining mechanism is used to tighten the sling and change the force direction. to avoid getting stuck.
It effectively reduces the risk of steel beams and formwork ports getting stuck, simplifies the operation process, and reduces the design length of the boom.
Smart Images

Figure CN118651782B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of lifting equipment, and in particular to a lifting device and a lifting method thereof for shed tunnel construction. Background Art
[0002] A tunnel is a shed-like tunnel, which is usually built on sections of road where rockfall is frequent (or landslides are possible) to protect the safety of vehicles or pedestrians.
[0003] For some roads or railways built beside mountains, the form of the tunnel is generally a cement slab on the top and hollow walls on both sides. The hollow walls can provide more sufficient light for the road or railway, and the cement slab on the top can deal with the risks of sudden landslides and falling rocks.
[0004] During construction, the side walls on both sides of the road or railway are usually constructed first, and the cement board is applied after the structure of the side walls on both sides is stable. In the process of applying the cement board, it is necessary to set up an arch frame at the bottom, and a wooden board is set on the top of the arch frame to facilitate the pouring of the cement board. The wooden board and the side walls on both sides are generally positioned by setting up small steel beams on the side walls on both sides, connecting the steel beams to the arch top through fine-rolled threaded steel, and then adjusting the height of the arch frame through the jack to make the wooden board flush with the top surface of the side wall. When pouring the cement board, the steel beam is isolated by the template, and the steel beam needs to be pulled out of the template after pouring. At present, a small lifting equipment is set up on the formed cement board for operation. The winch in the small lifting equipment is configured as a sliding structure. After the winch is connected to the steel beam, the winch is controlled to slide away from the shed hole to pull the steel beam out of the formwork. This requires a long boom, and the position of the winch and the winding speed of the winch need to be controlled during the extraction process to prevent the steel beam from getting stuck with the formwork port, or the steel beam at the formwork port needs to be pressed manually, which is inconvenient to operate. Summary of the invention
[0005] The present application provides a lifting device and a lifting method for shed tunnel construction. By changing the force direction of the sling on the steel beam, the steel beam can be kept in a horizontal state as much as possible when it is pulled out of the formwork. At the same time, based on the change in the force direction of the sling on the steel beam, the design length of the boom is reduced, thereby solving the defects of the current lifting method that the boom is too long and the steel beam is easily stuck with the formwork port.
[0006] This application is implemented through the following technical solutions:
[0007] In a first aspect, the present application provides a hoisting device for shed tunnel construction, comprising:
[0008] Support arm;
[0009] A boom connected to the support arm;
[0010] A winch, the winch being mounted on the boom;
[0011] A cable-resisting mechanism, the cable-resisting mechanism is connected to the boom, and the cable-resisting mechanism has a movable cable-resisting end;
[0012] In the working state, when the sling on the winch cooperates with the steel beam, the cable end can press against the sling between the boom and the steel beam to make the length direction of the sling section between the cable end and the steel beam tend to be horizontal.
[0013] The hoisting device for shed tunnel construction provided in the present application has the following characteristics: after the hoisting device on the winch cooperates with the steel beam, the sling between the steel beam and the winch is in a linear tensioned state, and after the sling at that end is tightened by the cable-resisting mechanism, the angle between the sling section between the cable-resisting end and the steel beam and the horizontal direction becomes smaller, that is, the force direction of the sling on the steel beam is changed, and when the steel beam is pulled out of the steel beam by the sling, the steel beam is closer to a horizontal state, thereby reducing the risk of the steel beam and the template port being stuck, and at the same time, after the force direction of the sling is changed by the cable-resisting mechanism, there is no need to increase the distance between the winch and the steel beam to make the force direction of the sling close to the horizontal direction, that is, the design length of the boom is reduced.
[0014] In some optional embodiments, the cable-stopping mechanism is slidably connected to the boom, wherein there is a distance between the cable-stopping end and the boom.
[0015] In some optional embodiments, the claim mechanism includes:
[0016] a first connecting seat, the first connecting seat being slidably connected to the boom;
[0017] A cable-resisting rod, one end of which is connected to the first connecting seat, and the other end of which serves as the cable-resisting end.
[0018] In some optional embodiments, the cable-resisting rod is rotatably connected to the first connecting seat;
[0019] Wherein, a second connecting seat is arranged on the boom, the second connecting seat is slidably and rotatably connected to the cable-resisting rod, and the length of the first connecting seat is smaller than the length of the second connecting seat.
[0020] In some optional embodiments, a cable-resisting slider is arranged on the first connecting seat, a transmission threaded hole is constructed on the cable-resisting slider, a locking groove adapted to the cable-resisting slider is constructed on the boom, and a transmission screw cooperating with the transmission threaded hole is arranged in the locking groove.
[0021] In some optional embodiments, the boom is slidably connected to the support arm.
[0022] In some optional embodiments, the boom is provided with a sliding guide rail and a driving rack parallel to each other;
[0023] The support arm is provided with a slide frame;
[0024] The slide slot frame is provided with a slide slot adapted to the slide rail, and the slide slot frame is also provided with a gear motor matched with the drive rack transmission.
[0025] In some optional embodiments, a plurality of steel balls in contact with the sliding guide rail are arranged in the sliding groove through a groove locking ball process.
[0026] In some optional embodiments, an avoidance hole is constructed on the cable-resisting end, a cable-resisting pulley is rotatably arranged in the avoidance hole, and the sling of the winch is located in the avoidance hole and cooperates with the cable-resisting pulley.
[0027] In a second aspect, the present application provides a hoisting method for shed tunnel construction, which is implemented based on the hoisting device for shed tunnel construction described in the first aspect and includes the following contents:
[0028] Match the hoisting device on the winch with the steel beam;
[0029] Start the winch to tension the sling;
[0030] The cable-stopping mechanism is moved so that the cable-stopping end contacts the sling between the boom and the steel beam;
[0031] The cable-stopping mechanism is activated and the winch is released so that the cable-stopping end is pressed against the sling, thereby making the length direction of the sling section between the cable-stopping end and the steel beam tend to be horizontal;
[0032] Reel in the winch to remove the sling from the beam.
[0033] Compared with the prior art, this application has the following advantages and beneficial effects:
[0034] The present application provides a hoisting device and a hoisting method for shed tunnel construction. After the hoist on the winch cooperates with the steel beam, the sling between the steel beam and the winch is in a linear tensioned state. After the sling at that end is tightened by the cable-resisting mechanism, the angle between the sling section between the cable-resisting end and the steel beam and the horizontal direction becomes smaller, that is, the force direction of the sling on the steel beam is changed. When the steel beam is pulled out of the steel beam by the sling, the steel beam is closer to a horizontal state, thereby reducing the risk of the steel beam and the template port being stuck. At the same time, after the force direction of the sling is changed by the cable-resisting mechanism, there is no need to increase the distance between the winch and the steel beam to make the force direction of the sling close to the horizontal direction, that is, the design length of the boom is reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0035] In order to more clearly illustrate the technical solutions of the exemplary embodiments of the present application, the following briefly introduces the drawings required for use in the embodiments. It should be understood that the following drawings only illustrate certain embodiments of the present application and should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without creative work. In the drawings:
[0036] Figure 1 It is a schematic diagram of the first working state of the existing lifting device;
[0037] Figure 2 It is a schematic diagram of the second working state of the existing lifting device;
[0038] Figure 3 It is a schematic diagram of the third working state of the existing lifting device;
[0039] Figure 4 A schematic diagram of the structure of a hoisting device for shed tunnel construction provided in an embodiment of the present application;
[0040] Figure 5 A schematic diagram of the structure of the cable resistance mechanism provided in the embodiment of the present application;
[0041] Figure 6 A schematic diagram of the coordination structure of the cable-resisting mechanism and the boom provided in an embodiment of the present application;
[0042] Figure 7 A schematic diagram of the coordination structure of the boom and the support arm provided in an embodiment of the present application;
[0043] Figure 8 A schematic diagram of the side view structure of the boom provided in an embodiment of the present application;
[0044] Fig. 9 A schematic diagram of the structure of the slide frame provided in the embodiment of the present application;
[0045] Fig.10 A schematic diagram of the structure of the first working state of the hoisting device for shed tunnel construction provided in an embodiment of the present application;
[0046] Fig.11 A schematic diagram of the structure of the second working state of the hoisting device for shed tunnel construction provided in an embodiment of the present application;
[0047] Fig.12 A schematic diagram of the structure of the third working state of the hoisting device for shed tunnel construction provided in an embodiment of the present application;
[0048] Fig.13 for Figure 4 Schematic diagram of the enlarged structure at point A in the middle.
[0049] Marks and corresponding parts names in the attached drawings:
[0050] 1-support arm, 11-slide frame, 111-first section, 112-second section, 113-third section, 12-gear motor, 2-jib, 21-slide guide rail, 22-drive rack, 23-drive screw, 3-winch, 4-cable resistance mechanism, 41-first connecting seat, 42-cable resistance rod, 43-second connecting seat, 44-cable resistance slider, 45-cable resistance pulley, 46-avoidance hole, 5-cement board, 6-support base, 7-storage slot, 8-template, 9-steel beam. DETAILED DESCRIPTION
[0051] In order to make the objectives, technical solutions and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with examples and drawings. The illustrative implementation scheme of the present application and its description are only used to explain the present application and are not intended to limit the present application.
[0052] Attached Figure 1~Figure 3 The schematic diagram of the state structure of the existing small-scale lifting equipment for extracting the steel beam 9 in the template 8 is shown. The winch 3 is slidably arranged on the boom 2, that is, the winch 3 can slide along the length direction of the boom 2; during lifting, the winch 3 is first moved horizontally upward close to the end of the template 8 so that the sling of the winch 3 can cooperate with the steel beam 9. After the sling cooperates with the steel beam 9, the winch 3 is slid on the boom 2 to reduce the angle between the sling and the horizontal plane, that is, the force direction of the sling on the steel beam 9 is made closer to the horizontal direction. This requires the boom 2 to have a longer length. After the angle between the sling and the horizontal plane reaches the expected angle, the sling is wound up by the winch 3, and the sling can gradually extract the steel beam 9 from the template 8. Of course, as the steel beam 9 is gradually extracted, the angle between the sling and the horizontal plane will gradually increase. Therefore, while extracting the steel beam 9, the winch 3 must be slid on the boom 2 to maintain the angle between the sling and the horizontal plane, and the operation process is relatively inconvenient.
[0053] The existing method of extracting the steel beam has the disadvantages of long boom design and inconvenient operation. Figure 4 and Fig.13 An embodiment of the present application provides a hoisting device for shed tunnel construction, which includes a support arm 1, a suspension arm 2, a winch 3 and a cable-resisting mechanism 4.
[0054] The support arm 1 can be configured as a square column, the support arm 1 can be connected to the fixed facilities on the cement board 5, and can also be configured with a base. For example, a support base 6 can be connected to one end of the support arm 1 in the length direction, and the support base 6 can be configured as a direction plate. The support base 6 can be configured with walking rollers to facilitate the overall movement of the lifting device, wherein a storage groove 7 can be provided on the support base 6, and the storage groove 7 is used to store the pulled out steel beam 9. A counterweight can be provided in the storage groove 7 to ensure the stability of the lifting device during lifting.
[0055] The boom 2 is connected to the support arm 1, and the boom 2 can be configured as a square rod. The arrangement of the length direction of the boom 2 and the length of the support column can be unlimited, for example, they can be overlapped, form an angle or be orthogonal. In actual implementation, the length direction of the boom 2 and the direction of the support column can be configured to be orthogonal to each other; wherein, when the support arm 1 is fixed on the cement board 5 or the support base 6 is located on the cement board 5, there is a spacing between the boom 2 and the board surface of the cement board 5.
[0056] The winch 3 is installed on the boom 2. The winch 3 can be installed at any position of the boom 2, as long as the winch 3 can maintain a sufficient lifting distance with the cement board 5 in the working state. In order to enable the winch 3 to have a larger initial horizontal distance with the steel beam 9 after the lifting device is in place, in actual implementation, the winch 3 can be installed at the end of the boom 2; or a guide pulley can be set at the end of the boom 2. At this time, the winch 3 can be set at any position on the boom 2, and the sling on the winch 3 can be passed around the guide pulley. Preferably, the winch 3 can be set at the end of the boom 2 opposite to the guide pulley. During the lifting process, the guide pulley will bear a large load. At this time, the weight of the winch 3 itself can play a certain load balancing role, sharing a certain torque for the connection between the boom 2 and the support arm 1.
[0057] The cable-resisting mechanism 4 is connected to the boom 2, and the cable-resisting mechanism 4 has a movable cable-resisting end, wherein the cable-resisting mechanism 4 and the boom 2 can be movably connected or fixedly connected. When the cable-resisting mechanism 4 and the boom 2 are fixedly connected, the cable-resisting end itself moves in the cable-resisting mechanism 4, that is, the cable-resisting end in the cable-resisting mechanism 4 is movably set; when the cable-resisting mechanism 4 and the boom 2 are movably connected, the cable-resisting end can be fixedly set in the cable-resisting mechanism 4, that is, the cable-resisting end is in an active state by the movement of the cable-resisting mechanism 4 on the boom 2. Of course, the cable-resisting end in the cable-resisting mechanism 4 can also be movably set, and the position of the cable-resisting end is jointly determined by the movement of the cable-resisting end itself and the movement of the cable-resisting mechanism 4 on the boom 2.
[0058] In the working state, when the sling on the winch 3 cooperates with the steel beam 9, the cable end can be pressed against the sling between the boom 2 and the steel beam 9 so that the length direction of the sling section between the cable end and the steel beam 9 tends to be horizontal.
[0059] The lifting device for shed tunnel construction provided in the embodiment of the present application, after the lifting device on the winch 3 cooperates with the steel beam 9, the sling between the steel beam 9 and the winch 3 is in a linear tensioned state, and after the sling at that end is tightened by the cable-resisting mechanism 4, the angle between the sling section between the cable-resisting end and the steel beam 9 and the horizontal direction becomes smaller, that is, the force direction of the sling on the steel beam 9 is changed, and when the steel beam 9 is pulled out of the steel beam 9 by the sling, the steel beam 9 is closer to the horizontal state, thereby reducing the risk of the steel beam 9 and the end of the template 8 being stuck, and at the same time, after the force direction of the sling is changed by the cable-resisting mechanism 4, there is no need to increase the distance between the winch 3 and the steel beam 9 to make the force direction of the sling close to the horizontal direction, that is, the design length of the boom 2 is reduced.
[0060] As mentioned above, the cable-resisting mechanism 4 and the boom 2 can be either fixedly connected or movably connected; when the cable-resisting mechanism 4 and the boom 2 are movably connected, the movement form of the cable-resisting mechanism 4 on the boom 2 is not limited, for example, it can be linear movement, curvilinear movement, circular movement, etc. In order to facilitate operation, in some optional embodiments, the cable-resisting mechanism 4 is slidably connected to the boom 2, wherein there is a distance between the cable-resisting end and the boom 2. In actual implementation, the sliding direction of the cable-resisting mechanism 4 on the boom 2 is along the length direction of the boom 2. In the working state, the cable-resisting end and the sling of the winch 3 are located in the same vertical plane. Therefore, when the cable-resisting mechanism 4 slides on the boom 2, the cable-resisting end can contact and press against the sling, and since there is a distance between the cable-resisting end and the boom 2, the angle between the cable segment between the cable-resisting end and the steel beam 9 and the horizontal plane will become smaller and smaller during the process of the cable-resisting end contacting the sling and continuing to slide; the larger the distance between the cable-resisting end and the boom 2, the better; for example, in the working state, the cable-resisting end can be flush with the top surface of the cement board 5, so that when the cable-resisting end presses against the sling, the angle between the cable segment between the cable-resisting end and the steel beam 9 and the horizontal plane is smaller, that is, the cable segment tends to be more horizontal, which is conducive to the smooth withdrawal of the steel beam 9.
[0061] In some optional embodiments, please refer to Figure 5 and Figure 6The cable-resisting mechanism 4 may include a first connecting seat 41 and a cable-resisting rod 42; the first connecting seat 41 is slidably connected to the boom 2; one end of the cable-resisting rod 42 is connected to the first connecting seat 41, and the other end serves as a cable-resisting end. The first connecting seat 41 may be constructed as a rod-shaped body, and a cable-resisting slider 44 may be disposed on the first connecting seat 41. The cable-resisting slider 44 may be a component connected to the first connecting seat 41 alone, or may be derived from the first connecting seat 41, that is, the cable-resisting slider 44 and the first connecting seat 41 may be configured as an integrally formed structure, and a transmission threaded hole is constructed on the cable-resisting slider 44. Accordingly, a locking groove is constructed on the boom 2, and the cross-sectional shape of the locking groove is adapted to the cross-sectional shape of the cable-resisting slider 44. The length direction of the locking groove is parallel to the length direction of the boom 2, so that the cable-resisting slider 44 can slide in the locking groove along the length direction of the boom 2, and a transmission screw 23 is disposed in the locking groove, and the transmission screw 23 cooperates with the transmission threaded hole on the cable-resisting slider 44. The transmission screw 23 can be equipped with a motor or a rotating handle, so that the cable-resisting slider 44 can be moved back and forth in the locking groove by rotating the transmission screw 23. The length direction of the first connecting seat 41 can be perpendicular to the length direction of the boom 2, and the length direction of the cable-resisting rod 42 can be perpendicular to the length direction of the first connecting seat 41, so that there is a sufficient distance between the cable-resisting end and the boom 2; the length direction of the first connecting seat 41 can also form an angle with the length direction of the boom 2, so that there can be a larger distance between the cable-resisting end and the boom 2, that is, in the working state, the length direction of the boom 2 is located in the horizontal plane, and when the length direction of the first connecting seat 41 forms an angle with the length direction of the boom 2, the length direction of the cable-resisting rod 42 also forms an angle with the horizontal plane.
[0062] As described above, the larger the distance between the cable-resisting rod 42 and the boom 2, the more the sling can tend to be horizontal when the cable-resisting end is pressed against the sling. However, the larger distance between the cable-resisting rod 42 and the boom 2 will also occupy more space. At the same time, the larger the distance between the cable-resisting rod 42 and the boom 2, the more it will affect the lifting height. That is, when the steel beam 9 is lifted after being pulled out, the end of the steel beam 9 away from the sling can usually be kept in a state manually so that the length direction of the steel beam 9 tends to be horizontal, thereby preventing the steel beam 9 from swinging due to lack of constraint after it leaves the template 8, that is, the steel beam 9 remains in a horizontal state during the lifting process. Therefore, the relatively low height of the cable-resisting rod 42 will easily interfere with the steel beam 9, resulting in insufficient lifting height of the steel beam 9. Therefore, in some optional embodiments, please refer to Figure 5 , Fig.10 , Fig.11 and Fig.12The cable-retaining rod 42 is rotatably connected to the first connecting seat 41. In actual implementation, a first rotating shaft can be provided on the first connecting seat 41, and the axial direction of the first rotating shaft is perpendicular to the length direction of the first connecting seat 41. A first rotating hole rotatably matched with the first rotating shaft is provided on the cable-retaining rod 42 so that the cable-retaining rod 42 can rotate freely around one end thereof; wherein, a second connecting seat 43 is provided on the boom 2, and the second connecting seat 43 can also be constructed as a rod-shaped body, and the second connecting seat 43 can be vertically connected to the boom 2. The second connecting seat 43 and the boom 2 can be fixedly connected or detachably connected, and the second connecting seat 43 is located on one side of the length direction of the locking slide groove, and there is a spacing between the second connecting seat 43 and the locking slide groove, and the second connecting seat 43 is slidably and rotatably connected to the cable-retaining rod 42. In actual implementation, a rotating slide groove can be provided on the cable-retaining rod 42, and the length direction of the rotating slide groove is perpendicular to the length direction of the first connecting seat 41. The length direction of the cable-resisting rod 42 is parallel, and a second rotating shaft is provided on the end of the second connecting seat 43 away from the boom 2, and the second rotating shaft cooperates with the rotating slide groove, so that the cable-resisting rod 42 can slide freely on the second connecting seat 43 along its length direction and can rotate around the axis of the second rotating shaft. The length of the first connecting seat 41 is smaller than the length of the second connecting seat 43, so that when the first connecting seat 41 slides on the boom 2 along the length direction of the boom 2, the angle between the cable-resisting rod 42 and the horizontal plane will become larger and larger, that is, the cable-resisting end on the cable-resisting rod 42 is farther and farther away from the boom 2 during the sliding process of the first connecting seat 41. When the steel beam 9 is pulled out, the first connecting seat 41 slides in the opposite direction, so that the distance between the cable-resisting end and the boom 2 becomes smaller and smaller, thereby reducing the space occupied by the cable-resisting rod 42 below the boom 2 and reducing the influence of the cable-resisting rod 42 on the lifting height of the steel beam 9.
[0063] In some optional embodiments, another winch 3 may be provided on the boom 2, that is, two winches 3 are provided on the boom 2, and the relative positions of the two winches 3 are not limited. After the two winches 3 release the wires, the slings of the two winches 3 are spaced apart in the length direction of the boom 2. One of the winches 3 can be pulled out of the steel beam 9, and after the steel beam 9 is pulled out to the expected position, the sling of the other winch 3 cooperates with the steel beam 9, that is, the slings of the two winches 3 cooperate with the two ends of the length direction of the steel beam 9 respectively. After the steel beam 9 is pulled out, the slings of the two winches 3 constrain the state of the steel beam 9 so that the steel beam 9 remains in a horizontal state, and the two winches 3 are controlled to reel in the wires so that the slings have a certain tension, and then the two winches 3 are controlled to reel in the wires at the same time to realize the lifting operation of the steel beam 9.
[0064] Before the steel beam 9 is pulled out, during the cooperation process between the sling and the steel beam 9, it is necessary to move the entire lifting device so that the sling is close to the position of the steel beam 9 in the template 8 in the horizontal plane. After the sling and the steel beam 9 are cooperated, the entire lifting device is moved again so that the end of the boom 2 reaches a farther position. The operation is relatively cumbersome. Therefore, in some optional embodiments, it can be referred to Figure 7The boom 2 is slidably connected to the support arm 1. Specifically, the boom 2 can slide on the support arm 1 along its own length direction, so that the entire lifting device can be put in place and fixed first, and the relative position of the hanger and the steel beam 9 can be adjusted by controlling the boom 2 to slide on the support arm 1.
[0065] In actual implementation, Figure 7~Figure 9 As shown, the boom 2 can be provided with a sliding guide rail 21 and a driving rack 22 which are parallel to each other, wherein the cross-sectional shape of the boom 2 can be constructed as a rectangle, the number of the sliding guide rails 21 can be set to two and arranged at the edges of the upper and lower surfaces of the boom 2, the driving rack 22 is arranged on the side of the boom 2 close to the sliding guide rail 21, and the length direction of the sliding guide rail 21 is parallel to the length direction of the boom 2; a slide slot frame 11 is provided on the support arm 1, and the number of the slide slot frame 11 can be configured to be two, and the slide slot The frame 11 may include a first section 111, a second section 112 and a third section 113. The first section 111 and the third section 113 are respectively matched with two sliding rails. The third section 113 is constructed with a sliding groove. The third section 113 slides with the sliding guide rail 21 through the sliding groove. The second section 112 is provided with a gear motor 12. The gear motor 12 is matched with the driving rack 22 for transmission. Therefore, when the gear motor 12 rotates, the boom 2 can slide along its own length direction on the support arm 1 through the action of the gear transmission.
[0066] No matter in which direction the boom 2 slides on the support arm 1, a structure similar to a cantilever beam will be formed. If the contact area between the sliding guide rail 21 and the slide slot frame 11 is too large, it is easy to get stuck. At the same time, the boom 2 may also cause vibration during the sliding process on the support arm 1. Therefore, in some optional embodiments, a plurality of steel balls in contact with the sliding guide rail 21 are arranged in the sliding groove through the groove locking ball process. The arrangement of the steel balls reduces the contact area on the one hand, and generates rolling friction after the steel balls contact the sliding guide rail 21 on the other hand, with less resistance, so that the boom 2 slides more smoothly on the support arm 1.
[0067] In some optional embodiments, see Figure 5 and Figure 6 The end of the cable is provided with an avoidance hole 46, in which a cable-resistance pulley 45 is rotatably arranged, and the sling of the winch 3 is located in the avoidance hole 46 and cooperates with the cable-resistance pulley 45. The setting of the avoidance hole 46 forms a certain limit for the sling. After the steel beam 9 is pulled out, if there is no need to keep it horizontal, the limit of the avoidance hole 46 can reduce the swing amplitude of the sling, and prevent the steel beam 9 from swinging greatly and colliding with other facilities. Among them, the setting of the cable-resistance pulley 45 can prevent the serious wear between the sling and the cable-resistance rod 42 that may occur during the process of pulling out the steel beam 9.
[0068] In a second aspect, an embodiment of the present application provides a hoisting method for shed tunnel construction, which is implemented based on the hoisting device for shed tunnel construction of the first aspect and includes the following contents:
[0069] S1. Match the lifting device on the winch 3 with the steel beam 9.
[0070] The lifting device of the hoist 3 can be configured as any existing lifting device that can cooperate with the end of the steel beam 9.
[0071] S2, start the winch 3 to tension the sling.
[0072] Among them, when the avoidance hole 46 and the cable-resisting pulley 45 are provided at the end of the cable-resisting rod 42, the sling does not need to be tensioned, but the relative stability of the sling and the steel beam 9 needs to be ensured.
[0073] S3, the cable-resisting mechanism 4 is moved so that the cable-resisting end contacts the sling between the boom 2 and the steel beam 9.
[0074] The screw can be rotated by shaking the handle or controlling the motor to rotate, so that the first connecting seat 41 moves in the length direction of the boom 2, and the cable end gradually approaches the cable along the length direction of the boom 2 and gradually decreases in vertical height to approach the steel beam 9 in the template 8 in the vertical direction.
[0075] S4, activate the cable-resisting mechanism 4 and release the winch 3 so that the cable-resisting end is pressed against the sling, so that the length direction of the sling section between the cable-resisting end and the steel beam 9 tends to be horizontal.
[0076] S5, reeling in the winch 3 to remove the sling from the steel beam 9.
[0077] In actual operation, when the boom 2 is slidably connected to the support arm 1, and after the sling is matched with the steel beam 9, the boom 2 can be operated to slide first to make one end of the boom 2 away from the steel beam 9, and then the cable-resisting mechanism 4 can be activated to make the cable-resisting end press against the sling, and finally the winch 3 can be controlled to reel in to achieve the withdrawal of the steel beam 9. In this way, the withdrawal of the steel beam 9 only depends on the force applied by the reeling of the winch 3, and the withdrawal process is more stable; the cable-resisting mechanism 4 can also be activated first to make the cable-resisting end press against the sling, and then the boom 2 can be controlled to slide on the support arm 1, so that the height of the cable-resisting end is easier to measure and control, and the operation process is relatively simpler.
[0078] The above specific embodiments illustrate the implementation methods of the present application. Those skilled in the art can easily understand other advantages and effects of the present application from the contents disclosed in this specification. Although the description of the present application will be introduced in conjunction with some embodiments, this does not mean that the features of this application are limited to the implementation methods. On the contrary, the purpose of introducing the application in conjunction with the implementation methods is to cover other options or modifications that may be extended based on the claims of the present application. In order to provide an in-depth understanding of the present application, the above description contains many specific details. The present application can also be implemented without using these details. In addition, in order to avoid confusion or blurring the focus of the present application, some specific details will be omitted in the description. It should be noted that the embodiments in the present application and the features in the embodiments can be combined with each other without conflict.
[0079] It should be noted that in this specification, similar numbers and letters represent similar items in the above drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings. In the description of this application, it should be noted that the orientation or position relationship indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. is based on the orientation or position relationship shown in the drawings, which is only for the convenience of describing this application and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on this application. In addition, the terms "first" and "second" are only used for descriptive purposes and cannot be understood as indicating or implying relative importance. In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be directly connected, or indirectly connected through an intermediate medium, or it can be a connection between the two elements. For those skilled in the art, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0080] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.
Claims
1. A hoisting device for shed tunnel construction, characterized in that: include: Support arm (1); A suspension arm (2), the suspension arm (2) being slidably connected to the support arm (1); A hoist (3), the hoist (3) being mounted on the boom (2); A cable-resisting mechanism (4), the cable-resisting mechanism (4) comprising a first connecting seat (41) and a cable-resisting rod (42), the first connecting seat (41) being slidably connected to the boom (2); one end of the cable-resisting rod (42) being rotatably connected to the first connecting seat (41), and the other end being a cable-resisting end, a distance being provided between the cable-resisting end and the boom (2), wherein a second connecting seat (43) is provided on the boom (2), the second connecting seat (43) being slidably and rotatably connected to the cable-resisting rod (42), the length of the first connecting seat (41) being smaller than the length of the second connecting seat (43), a cable-resisting slider (44) being provided on the first connecting seat (41), a transmission threaded hole being configured on the cable-resisting slider (44), a locking groove being adapted to the cable-resisting slider (44) being configured on the boom (2), a transmission lead screw (23) being configured in the locking groove and being adapted to the transmission threaded hole; In the working state, when the sling on the hoist (3) cooperates with the steel beam (9), the rope end can be pressed against the sling between the boom (2) and the steel beam (9) so that the length direction of the sling section between the rope end and the steel beam (9) tends to be horizontal.
2. The hoisting device for shed tunnel construction according to claim 1 is characterized in that: The boom (2) is provided with a sliding guide rail (21) and a driving rack (22) which are parallel to each other; The support arm (1) is provided with a slide frame (11); The slide slot frame (11) is provided with a slide slot adapted to the slide rail (21), and the slide slot frame (11) is also provided with a gear motor (12) that is in transmission cooperation with the drive rack (22).
3. The hoisting device for shed tunnel construction according to claim 2 is characterized in that: A plurality of steel balls in contact with the sliding guide rail (21) are arranged in the sliding groove through a groove locking ball process.
4. The hoisting device for shed tunnel construction according to claim 1 is characterized in that: An avoidance hole (46) is formed on the end of the cable-resisting cable, a cable-resisting pulley (45) is rotatably arranged in the avoidance hole (46), and the sling of the hoist (3) is located in the avoidance hole (46) and cooperates with the cable-resisting pulley (45).
5. A hoisting method for shed tunnel construction, implemented based on the hoisting device for shed tunnel construction according to any one of claims 1 to 4, characterized in that: Includes the following: Match the lifting device on the winch (3) with the steel beam (9); Starting the winch (3) to tension the sling; The cable-resisting mechanism (4) is moved so that the cable-resisting end contacts the sling between the boom (2) and the steel beam (9); The cable-resisting mechanism (4) is activated and the winch (3) is released so that the cable-resisting end is pressed against the sling, thereby making the length direction of the sling section between the cable-resisting end and the steel beam (9) tend to be horizontal; The winch (3) is reeled in to allow the sling to be pulled away from the steel beam (9).
Citation Information
Patent Citations
Railway shed tunnel T-shaped beam hoisting construction method
CN113387277A
Large-span corrugated steel-concrete composite structure shed tunnel and construction method thereof
CN117449228A