A production system and method for fully rolled polyester pre-oriented yarn

By monitoring and adjusting the temperature of the spinning assembly in the polyester pre-oriented wire production system in real time, and optimizing the tow forming time with the winding device, the problem of high breaking rate of the bottom layer of the polyester pre-oriented wire is solved, and product quality and production efficiency are improved. The stability of fiber physical indicators has been improved.

CN118668307BActive Publication Date: 2024-11-15TONGKUN GRP ZHEJIANG HENGTONG CHEM FIBER
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411154769.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-22
Publication Date
2024-11-15
Estimated Expiration
2044-08-22

AI Technical Summary

Technical Problem

During the processing of polyester pre-oriented wire, the bottom layer is severely broken, resulting in low production efficiency and unstable product quality. The existing technology is difficult to effectively solve the impact of spinneret temperature changes on the physical properties of fibers.

Method used

Design a production system for full-rolled polyester pre-oriented wire, including a metering pump control unit, a spinning assembly heating unit and a signal processing unit. By real-time monitoring and adjusting the spinneret temperature, the spinning assembly can quickly recover to the spinning assembly after stopping. Standard temperature, reduce temperature fluctuations, use winding devices to optimize the tow forming time, and improve the quality of the silk cake.

Benefits of technology

It effectively reduces the elastic breaking rate of polyester pre-oriented wire, improves product quality and production efficiency, ensures that the physical indicators of the bottom wire and the surface wire are close to consistency, and improves the reliability of the back weaving.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118668307B_ABST
    Figure CN118668307B_ABST
Patent Text Reader

Abstract

The present invention belongs to the technical field of chemical fiber textile, and relates to a production system and a production method of a full roll polyester pre-oriented yarn. The production system includes a metering pump, a spinning assembly, a metering pump control unit, a spinning assembly heating unit and a signal processing unit; the metering pump control unit is connected to the metering pump, and is used to adjust and display the polyester melt flow in real time; the spinning assembly heating unit is connected to the cavity of the spinning box body on which the spinning assembly is installed, and is used to heat the spinneret to the target temperature; the signal processing unit is connected to the metering pump control unit and the spinning assembly heating unit at the same time, and is used to start the spinning assembly heating unit when the polyester melt flow is 0, and turn off the spinning assembly heating unit when the polyester melt flow is greater than 0; the production method uses the production system to produce full roll polyester pre-oriented yarn. The present invention can reduce the difference in fiber physical indicators caused by the change in spinneret temperature, and reduce the bottom yarn breakage rate of polyester pre-oriented yarn cake.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of chemical fiber textiles and relates to a production system and a production method for fully rolled polyester pre-oriented yarns. Background Art

[0002] Polyester pre-oriented yarn (POY), also known as polyester partially oriented yarn, is a primary yarn obtained by high-speed spinning (spinning speed 2800-3600m / min). Compared with general polyester drawn yarn, polyester pre-oriented yarn has low orientation and low crystallinity, which is reflected in physical indicators such as low breaking strength, high breaking elongation, and poor dimensional stability. Therefore, it must be made into drawn textured yarn (DTY) through processes such as stretching, false twisting, and shaping to have certain physical and mechanical properties and meet the requirements of subsequent weaving.

[0003] In the process of processing polyester pre-oriented yarn into stretched and deformed yarn, the breakage rate directly affects the production efficiency of post-processing and the rate of high-quality products. According to the investigation, among the breakages in the processing of polyester pre-oriented yarn, the bottom breakage (referring to the breakage caused by the addition of elasticity within 1 kg of the remaining polyester pre-oriented yarn cake) accounts for more than 50%.

[0004] In the spinning process, especially for the production of polyester pre-oriented yarn cakes, the phenomenon of bottom-layer breakage is a problem that needs to be paid special attention. According to statistical analysis, about 50% of the bottom-layer breakage of polyester pre-oriented yarn cakes is caused by the first drop of the yarn cake after shoveling or regular operation. This is mainly because the stop operation during shoveling or regular operation can easily cause the temperature of the spinning assembly, especially the spinneret and its surrounding area, to drop significantly.

[0005] The decrease in the spinning assembly temperature will directly affect the physical properties of the fiber, resulting in longer elongation at break, greater thermal stress, and higher yarn unevenness. This change in physical properties is particularly evident in the bottom layer of yarn, resulting in significant differences in the physical indicators of the bottom layer of yarn and the surface layer of yarn. This difference is particularly fatal in the subsequent polyester pre-oriented yarn stretching process, because the excessive thermal stress can easily cause tension changes, leading to the occurrence of broken ends.

[0006] In order to restore the normal spinning temperature, the melt needs to flow continuously for a long time after the spinning stops. This process usually requires continuous production for a period of time before the spinning temperature can gradually return to the standard state. However, during this recovery period, since the spinning temperature does not meet the standard, the quality of the produced silk cakes is often unstable and cannot meet the production requirements, resulting in a large amount of waste silk consumption and product degradation.

[0007] In order to deal with the above problems, many companies have adopted the strategy of non-stop scraping to reduce the impact of stop on spinning temperature. However, when the production is not stopped, removing the silicone oil on the spinneret surface will also reduce the spinneret temperature, thereby affecting the physical indicators of the product.

[0008] Therefore, it is urgent to develop a production system and a production method for fully rolled polyester pre-oriented yarn to solve the above problems. Summary of the invention

[0009] The purpose of the present invention is to solve the problems existing in the prior art and to provide a production system and a production method for a fully rolled polyester pre-oriented yarn.

[0010] To achieve the above object, the technical solution adopted by the present invention is as follows:

[0011] A full-roll polyester pre-oriented yarn production system, comprising a metering pump, n spinning components, 1≤n≤16, a metering pump control unit, a spinning component heating unit and a signal processing unit;

[0012] The metering pump control unit is connected to the metering pump and is used for adjusting and displaying the polyester melt flow in real time;

[0013] The spinning assembly heating unit is connected to the cavity of the spinning box body on which the spinning assembly is installed, and is used to heat the spinneret to a target temperature, which is 103-105% of the spinning box body temperature;

[0014] The signal processing unit is connected to the metering pump control unit and the spinning assembly heating unit at the same time, and is used to start the spinning assembly heating unit when the polyester melt flow rate is 0, and to shut down the spinning assembly heating unit when the polyester melt flow rate is greater than 0.

[0015] As the preferred technical solution:

[0016] In the above-mentioned full-roll polyester pre-oriented yarn production system, the spinning assembly heating unit includes a heating system, a temperature detection unit, a temperature control meter and an air supply control unit;

[0017] The heating system includes a primary heat medium main pipe, an oil inlet pipe, n heat transfer coils, an oil outlet pipe, a recovery pipe, a pneumatic valve, and a pressure relief valve; the n heat transfer coils are respectively mounted on n spinning components; the primary heat medium main pipe, the oil inlet pipe, n heat transfer coils, the oil outlet pipe, and the recovery pipe are connected in sequence; the pneumatic valve is installed at the connection between the oil inlet pipe and the primary heat medium main pipe; the pressure relief valve is installed at the connection between the oil outlet pipe and the recovery pipe. When the oil pressure in the heat transfer coil exceeds 2MPa, the pressure relief valve starts to open to release pressure, so that the heat medium can flow into the recovery pipe;

[0018] The temperature detection unit is used to detect the real-time temperature of the spinneret and send it to the temperature control meter;

[0019] The temperature control meter is used to compare the real-time temperature of the spinneret with the target temperature, and then adjust the opening of the pneumatic valve through the air supply control unit, and then adjust the speed of the spinneret temperature rise through the heating system. When the real-time temperature is higher than the upper limit of the target temperature, the opening of the pneumatic valve is reduced. When the real-time temperature is lower than the lower limit of the target temperature, the opening of the pneumatic valve is increased. When the real-time temperature is within the target temperature range, the opening of the pneumatic valve is not adjusted.

[0020] In the above-mentioned full-roll polyester pre-oriented yarn production system, the temperature detection unit is a non-contact temperature measuring instrument.

[0021] In the above-mentioned full-roll polyester pre-oriented yarn production system, the air supply control unit includes an air supply valve, a motor and a motor control inverter;

[0022] The pneumatic valve, air supply valve, motor, motor control inverter and temperature control meter are connected in sequence;

[0023] The temperature controller adjusts the opening of the pneumatic valve through the air supply control unit, that is, the temperature controller changes the current signal sent to the motor control inverter, so that the motor control inverter controls the motor to drive the valve core of the air supply valve to move, adjust the opening of the air supply valve, and then adjust the opening of the pneumatic valve. When the current signal is 20mAh, the air supply valve is fully open, and when the current signal is 40mAh, the air supply valve is fully closed.

[0024] A full-roll polyester pre-oriented yarn production system as described above also includes a winding device; the winding device includes a turntable, a servo motor, spindle shaft I, spindle shaft II, motor I and motor II; the turntable is arranged vertically; the servo motor is used to drive the turntable to rotate 180° around its own center axis; spindle shaft I and spindle shaft II are perpendicular to the turntable and symmetrically distributed on the upper and lower sides of the center axis of the turntable; motor I is used to drive spindle shaft I to rotate around its own center axis; motor II is used to drive spindle shaft II to rotate around its own center axis.

[0025] In the above-mentioned full-roll polyester pre-oriented yarn production system, the signal processing unit is also used to start the motor I when the polyester melt flow rate is greater than 0.

[0026] In the above-mentioned full-roll polyester pre-oriented yarn production system, the signal processing unit is also used to count the running time of motor I, and when the value corresponding to the running time of motor I in units of min reaches the set value a, motor I is turned off and the servo motor and motor II are started; the setting method of the set value a is as follows:

[0027] The theoretical value of the time for cutting small rolls (i.e., the time for the yarn tow to be wound on the spindle shaft I after stopping and re-winding) is b=t1×[10%+(t2-10)×0.5%]-[t1×(Q-48)×0.3%], where t1 is the value corresponding to the full roll time in min (i.e., the time required for the polyester pre-oriented yarn to be continuously wound on a spindle shaft to reach the weight of the first-class product), t2 is the value corresponding to the stop time in min, and Q is the value corresponding to the polyester melt flow rate in g / min;

[0028] Tests show that if the polyester pre-oriented yarn is stopped for a long time and then rewound on a spindle to the full winding time, the quality of the polyester pre-oriented yarn is poor before the winding starts to reach 20% of the full winding time, and the quality of the polyester pre-oriented yarn is good or becomes good after reaching 20% ​​of the full winding time. After reaching 50% of the full winding time, the quality of the polyester pre-oriented yarn is good, so 20% of the full winding time and 50% of the full winding time can be used as reference standards; the goal of the present invention is to wind the polyester pre-oriented yarn with poor quality after stopping and re-winding on spindle I, and to wind the polyester pre-oriented yarn with good quality on spindle II, so the winding time of the yarn bundle on spindle I should not be less than 20% of the full winding time, and should not be more than 50% of the full winding time;

[0029] Assuming that the full winding time is 400 minutes, if the polyester pre-oriented yarn is continuously wound on a spindle for 400 minutes after the yarn is spun, the quality of the polyester pre-oriented yarn from 0 to 80 minutes is poor, and the quality of the polyester pre-oriented yarn from 200 to 400 minutes is good. Assuming that the quality of the polyester pre-oriented yarn from 80 to 100 minutes is poor, the quality of the polyester pre-oriented yarn from 100 to 200 minutes gradually improves. The goal of the present invention is to wind the polyester pre-oriented yarn from 0 to 100 minutes on spindle I, and then switch to spindle II and start timing from 0 minutes to the full winding time of 400 minutes.

[0030] The present invention has obtained a calculation formula for the theoretical value of the small bobbin cutting time through repeated experiments. However, if the set value of the small bobbin cutting time is directly set equal to the theoretical value of the small bobbin cutting time, sometimes the winding time of the tow on the spindle I may be less than 20% of the full bobbin time or more than 50% of the full bobbin time. To avoid this situation, after comparing the theoretical value of the small bobbin cutting time with 20% of the full bobbin time and 50% of the full bobbin time, the present invention limits the set value of the small bobbin cutting time in different cases. When the theoretical value of the small bobbin cutting time is less than 20% of the full bobbin time, the theoretical value of the small bobbin cutting time is set equal to 20% of the full bobbin time to cut off the polyester pre-oriented yarn with poor quality. When the theoretical value of the small bobbin cutting time is greater than 50% of the full bobbin time, the theoretical value of the small bobbin cutting time is set equal to 50% of the full bobbin time to avoid cutting off the polyester pre-oriented yarn with good quality and causing waste. When the theoretical value of the small bobbin cutting time is greater than or equal to 20% of the full bobbin time and less than or equal to 50% of the full bobbin time, the set value of the small bobbin cutting time is directly set equal to the theoretical value of the small bobbin cutting time. Therefore, the present invention controls: when b < t1×20%, let a = t1×20%; when t1×20% ≤ b ≤ t1×50%, let a = b; when b > t1×50%, let a = t1×50%.

[0031] The present invention also provides a production method for full bobbin polyester pre-oriented yarn, which uses a production system for full bobbin polyester pre-oriented yarn as described in any one of the above.

[0032] As a preferred technical solution:

[0033] For the production method of full bobbin polyester pre-oriented yarn as described above, the difference in breaking elongation between the bottom layer yarn and the surface layer yarn of the full bobbin polyester pre-oriented yarn is ≤ 2.8%, the difference in thermal stress between the bottom layer yarn and the surface layer yarn is ≤ 2.5% of the thermal stress central value, and the CV value of the evenness of the bottom layer yarn is ≤ 1.35%.

[0034] Beneficial effects:

[0035] By setting a metering pump control unit, a spinning pack heating unit, and a signal processing unit, the present invention can start the spinning pack heating unit when the polyester melt flow rate is 0 and turn off the heating unit when the flow rate is greater than 0, effectively maintaining the temperature stability of the spinning pack, reducing the difference in fiber physical indexes caused by the change in the spinneret plate temperature, reducing the false twist breakage rate of the bottom layer yarn of the polyester pre-oriented yarn cake, and improving the product quality and production efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 It is a schematic connection diagram of the spinning pack heating unit of the production system for full bobbin polyester pre-oriented yarn of the present invention with the spinning box and the metering pump equipped with the spinning pack (only 6 spinning packs are shown in the figure);

[0037] Figure 2A schematic diagram of the working process of a non-contact temperature measuring instrument, a temperature control meter, a motor, a motor control frequency converter, an air supply valve, and a pneumatic valve of a production system of a fully rolled polyester pre-oriented yarn of the present invention;

[0038] Among them, 1-oil inlet pipeline, 2-heat transfer coil, 3-oil outlet pipeline, 4-pneumatic valve, 5-spinning assembly, 6-metering pump, 7-polyester melt, 8-spinning box, 9-cavity, 10-pressure relief valve, 11-recovery pipeline, 12-primary heat medium main pipe. DETAILED DESCRIPTION

[0039] The present invention will be further described below in conjunction with specific embodiments. It should be understood that these embodiments are only used to illustrate the present invention and are not intended to limit the scope of the present invention. In addition, it should be understood that after reading the content taught by the present invention, those skilled in the art can make various changes or modifications to the present invention, and these equivalent forms fall within the scope limited by the appended claims of the application equally.

[0040] The following are the test methods for the relevant performance indicators in each embodiment:

[0041] Elongation at break: According to the standard "Test Method for Tensile Properties of Chemical Fiber Filaments" (GB / T 14344-2022), the YG023B-Ⅱ fully automatic single yarn strength tester was used to test the elongation at break of the yarn bundle. The specific process is as follows: first, the yarn bundle was placed in an environment with a temperature of (20±2)℃ and a humidity of (65±5)% for 4 hours; then, the fully automatic single yarn strength tester was used for tensile testing. Before the test, the clamping length of the yarn bundle was accurately set to (500±1.0) mm by the upper and lower clamps, and a pre-tension (0.05±0.005 cN / dtex) was applied by the manipulator to stabilize the yarn bundle; during the test, the lower clamp stretched the yarn bundle at a set speed (500 mm / min) at a uniform speed until the yarn bundle broke; during the stretching process, the force sensor recorded the data in real time, and the relationship curve between strength and elongation was drawn through the data collection system; finally, the elongation at break of the yarn bundle was obtained through data processing and analysis.

[0042] Thermal stress: According to the standard "Test Method for Dynamic Thermal Stress of Polyester Pre-oriented Yarn" (FZ / T 50051-2020), the test is carried out using a YG 367 thermal stress tester. The specific process is: first, the yarn bundle is placed in an environment with a temperature of (20±2)°C and a humidity of (65±5)% for 4 hours, and then the yarn bundle is passed through a heating device and a drawing device at a specific speed and pre-tension (the specific speed and pre-tension parameter settings are in accordance with Sections 8.1 and 8.3 of the standard) to test the tensile stress (i.e. thermal stress) generated by the yarn bundle being drawn under heating conditions.

[0043] Yarn unevenness: According to the Test Method for Yarn Unevenness of Chemical Fiber Filament - Capacitance Method (GB / T 14346-2015), the test is carried out using USTER5 Yarn Uniformity Tester. The specific process is as follows: first, place the yarn bundle at a temperature of (20±2)℃ and a humidity of (65±5)% for 2 hours, then pass the yarn bundle through the two electrodes of the capacitor at a uniform speed, and convert the mass in each equal interval into an electrical signal. The percentage of the standard deviation of all test electrical signals to the average value is the yarn unevenness; the test speed is 200m / min, and the yarn bundle test time is 2.5min.

[0044] A production system for fully wound polyester pre-oriented yarns, such as Figure 1 As shown, it includes a metering pump 6, n spinning components 5 (1≤n≤16), a metering pump control unit, a spinning component heating unit, a winding device and a signal processing unit;

[0045] The metering pump control unit is connected to the metering pump 6 and is used to adjust and display the flow rate of the polyester melt 7 in real time;

[0046] The spinning assembly heating unit is connected to the cavity 9 of the spinning box 8 on which the spinning assembly 5 is installed, and is used to heat the spinneret to a target temperature, which is 103-105% of the temperature of the spinning box 8;

[0047] The spinning assembly heating unit includes n heat-conducting coils 2, a primary heat medium main pipe 12, an oil inlet pipeline 1, an oil outlet pipeline 3, a recovery pipeline 11, a pneumatic valve 4, an air supply valve, a motor, a motor control frequency converter, a pressure relief valve 10, a non-contact thermometer and a temperature control meter; the n heat-conducting coils 2 are respectively mounted on n spinning assemblies 5; the primary heat medium main pipe 12, the oil inlet pipeline 1, the n heat-conducting coils 2, the oil outlet pipeline 3, and the recovery pipeline 11 are connected in sequence; the pneumatic valve 4 is installed at the connection between the oil inlet pipeline 1 and the primary heat medium main pipe 12; the pneumatic valve 4, the air supply valve, the motor, the motor control frequency converter and the temperature control meter are connected in sequence; the pressure relief valve 10 is installed at the connection between the oil outlet pipeline 3 and the recovery pipeline 11;

[0048] like Figure 2 As shown, the non-contact temperature measuring instrument is used to detect the real-time temperature of the spinneret and send it to the temperature control meter; the temperature control meter is used to compare the real-time temperature of the spinneret with the target temperature, and then change the current signal sent to the motor control inverter, so that the motor control inverter controls the motor to drive the valve core of the air supply valve to move, adjust the opening of the air supply valve, and then adjust the opening of the pneumatic valve 4;

[0049] When the flow rate of the polyester melt 7 is 0 (i.e., stop operation), the working process of the non-contact temperature measuring instrument, the temperature control meter, the motor control inverter, the motor, the air supply valve, and the pneumatic valve 4 is as follows:

[0050] a. The non-contact thermometer detects the real-time temperature of the spinneret and sends the data to the temperature control meter;

[0051] b. The temperature control meter receives the real-time temperature data of the spinneret and compares the real-time temperature with the target temperature;

[0052] If the real-time temperature is lower than the lower limit of the target temperature, the temperature control meter increases the current signal sent to the motor control inverter. After receiving the signal to increase the current, the motor control inverter controls the motor to drive the valve core of the air supply valve to move, thereby increasing the opening of the air supply valve, thereby increasing the opening of the pneumatic valve 4, and heating the spinneret until the real-time temperature reaches within the target temperature range, and then returns to step a;

[0053] If the real-time temperature is higher than the upper limit of the target temperature, the temperature control meter reduces the current signal sent to the motor control inverter. After receiving the signal to reduce the current, the motor control inverter controls the motor to drive the valve core of the air supply valve to move, thereby reducing the opening of the air supply valve, thereby reducing the opening of the pneumatic valve 4, and cooling the spinneret until the real-time temperature reaches within the target temperature range, and then returns to step a;

[0054] If the real-time temperature is within the target temperature range, the temperature control meter maintains the current signal currently sent to the motor control inverter and returns to step a;

[0055] The winding device comprises a turntable, a servo motor, a spindle shaft I, a spindle shaft II, a motor I and a motor II; the turntable is arranged vertically; the servo motor is used to drive the turntable to rotate 180° around its own central axis; the spindle shaft I and the spindle shaft II are perpendicular to the turntable and symmetrically distributed on the upper and lower sides of the central axis of the turntable; the motor I is used to drive the spindle shaft I to rotate around its own central axis; the motor II is used to drive the spindle shaft II to rotate around its own central axis;

[0056] The signal processing unit is connected to the metering pump control unit and the spinning assembly heating unit at the same time. On the one hand, it is used to start the spinning assembly heating unit when the flow rate of the polyester melt 7 is 0, and to turn off the spinning assembly heating unit and start the motor I when the flow rate of the polyester melt 7 is greater than 0; on the other hand, it is used to count the running time of the motor I, and when the value corresponding to the running time of the motor I in units of min reaches the set value a, the motor I is turned off and the servo motor and the motor II are started; wherein, the setting method of the set value a is as follows:

[0057] Let b = t1 × [10% + (t2-10) × 0.5%] - [t1 × (Q-48) × 0.3%], where t1 is the value corresponding to the full roll time in min, t2 is the value corresponding to the stop time in min, and Q is the value corresponding to the polyester melt flow rate in g / min;

[0058] When b < 20%×t1, let a = 20%×t1; when 20%×t1 ≤ b ≤ 50%×t1, let a = b; when b > 50%×t1, let a = 50%×t1.

[0059] Example 1

[0060] A production method of full - roll polyester pre - oriented yarn uses the production system of full - roll polyester pre - oriented yarn as described above. The specific process flow is: PTA + EG for slurry preparation (the mass ratio of PTA is 69wt%) → first esterification → second esterification → pre - polycondensation → final polycondensation → polyester melt transportation → metering pump → extrusion through spinneret (including the heating unit of the spinning pack) → cooling → oiling → winding and forming.

[0061] Among them, the relevant parameters of the production system of full - roll polyester pre - oriented yarn are: n equals 1.

[0062] The relevant process parameters are: the temperature of the spinning box is 292°C, the pump supply is 34.2 g / min, the full - roll time is 375 min, the stop time is 15 min, the target temperature is 300.76°C (i.e., 103% of the spinning box temperature), and the small - roll winding time after threading is 75 min (i.e., after threading, it winds continuously on spindle I for 75 min, then switches to spindle II and starts timing from 0 min again until continuous winding for 375 min).

[0063] The finally obtained full - roll polyester pre - oriented yarn (i.e., the yarn on spindle II) has a specification of 135 dtex / 72f. The difference in breaking elongation between the bottom layer yarn and the surface layer yarn is 2.8%, the central value M of the thermal stress is 55 cN, the difference in thermal stress between the bottom layer yarn and the surface layer yarn is 1.3 cN, and the CV value of the evenness of the bottom layer yarn is 1.25%. During the subsequent texturing and over - tailing, the tension CV fluctuation of the full - roll polyester pre - oriented yarn (displayed by the tension TCS control system of the texturing machine) ≤ 3.0%, and the difference in T2 tension between the bottom layer yarn and the surface layer yarn (displayed by the tension TCS control system of the texturing machine) ≤ 5 cN.

[0064] Example 2

[0065] A production method of full - roll polyester pre - oriented yarn uses the production system of full - roll polyester pre - oriented yarn as described above. The specific process flow is: PTA + EG for slurry preparation (the mass ratio of PTA is 71wt%) → first esterification → second esterification → pre - polycondensation → final polycondensation → polyester melt transportation → metering pump → extrusion through spinneret (including the heating unit of the spinning pack) → cooling → oiling → winding and forming.

[0066] Among them, the relevant parameters of the production system of full - roll polyester pre - oriented yarn are: n equals 8.

[0067] The relevant process parameters are: spinning box temperature 290℃, pump supply 65.5g / min, full roll time 222min, stop time 23min, target temperature 304.5℃ (i.e. 105% of the spinning box temperature), and time for cutting small rolls after spinning-in 44.4min (i.e. after spinning-in, first wind continuously on spindle shaft I for 44.4min, then switch to spindle shaft II and restart the timing from 0min to continuous winding for 222min).

[0068] The specification of the final full-roll polyester pre-oriented yarn (i.e., the yarn on spindle shaft II) is 230dtex / 144f, the difference in elongation at break between the bottom yarn and the surface yarn is 1.9%, the thermal stress center value M is 105cN, the thermal stress difference between the bottom yarn and the surface yarn is 2.1cN, and the yarn unevenness CV value of the bottom yarn is 1.35%; the tension CV fluctuation of the full-roll polyester pre-oriented yarn during the subsequent texturing (displayed by the tension TCS control system of the texturing machine) is ≤3.0%, and the difference in T2 tension of the bottom yarn and the T2 tension of the surface yarn (displayed by the tension TCS control system of the texturing machine) is ≤5cN.

[0069] Example 3

[0070] A method for producing a full-roll polyester pre-oriented yarn, using the full-roll polyester pre-oriented yarn production system as described above, wherein the specific process flow is: PTA+EG slurry preparation (PTA accounts for 70wt% by mass) → first esterification → second esterification → pre-polycondensation → final polycondensation → polyester melt delivery → metering pump → spinneret extrusion (including spinning assembly heating unit) → cooling → oiling → winding and forming;

[0071] Among them, the relevant parameters of the production system of full-roll polyester pre-oriented yarn are: n equals 10;

[0072] The relevant process parameters are: spinning box temperature 293℃, pump supply 36.4g / min, full roll time 420min, stop time 10min, spinneret temperature 307.65℃, and time for cutting small rolls after spinning up 84min (that is, after spinning up, it is first wound on spindle shaft I for 84min, and then switched to spindle shaft II and the timing is restarted from 0min to 420min of continuous winding).

[0073] The specification of the final fully rolled polyester pre-oriented yarn (i.e., the yarn on spindle shaft II) is 138dtex / 144f, the difference in elongation at break between the bottom yarn and the surface yarn is 2.4%, the center value of thermal stress M is 60cN, the difference in thermal stress between the bottom yarn and the surface yarn is 1.4cN, and the CV value of the yarn unevenness of the bottom yarn is 0.97%; the tension CV fluctuation of the fully rolled polyester pre-oriented yarn during the subsequent texturing (displayed by the tension TCS control system of the texturing machine) is ≤3.0%, and the difference in T2 tension between the bottom yarn and the surface yarn (displayed by the tension TCS control system of the texturing machine) is ≤5cN.

[0074] Example 4

[0075] A method for producing a full-roll polyester pre-oriented yarn, using the full-roll polyester pre-oriented yarn production system as described above, wherein the specific process flow is: PTA+EG slurry preparation (PTA accounts for 70.5wt% by mass) → first esterification → second esterification → pre-polycondensation → final polycondensation → polyester melt delivery → metering pump → spinneret extrusion (including spinning assembly heating unit) → cooling → oiling → winding and forming;

[0076] Among them, the relevant parameters of the production system of full-roll polyester pre-oriented yarn are: n is equal to 12;

[0077] The relevant process parameters are: spinning box temperature 293℃, pump supply 76.7g / min, full roll time 205min, stop time 58min, target temperature 307.65℃ (i.e. 105% of the spinning box temperature), and time for cutting small rolls after spinning-in for 52min (i.e. after spinning-in, first wind continuously on spindle shaft I for 58min, then switch to spindle shaft II and restart the timing from 0min to continuous winding for 205min).

[0078] The specification of the final full-roll polyester pre-oriented yarn (i.e., the yarn on spindle shaft II) is 280dtex / 288f, the difference in elongation at break between the bottom yarn and the surface yarn is 2.7%, the thermal stress center value M is 110cN, the thermal stress difference between the bottom yarn and the surface yarn is 2.7cN, and the yarn unevenness CV value of the bottom yarn is 1.02%; the tension CV fluctuation of the full-roll polyester pre-oriented yarn during the subsequent texturing is ≤3.0% (displayed by the tension TCS control system of the texturing machine), and the difference in T2 tension between the bottom yarn and the surface yarn (displayed by the tension TCS control system of the texturing machine) is ≤5cN.

[0079] Example 5

[0080] A method for producing a full-roll polyester pre-oriented yarn, using the full-roll polyester pre-oriented yarn production system as described above, wherein the specific process flow is: PTA+EG slurry preparation (PTA accounts for 69.5wt% by mass) → first esterification → second esterification → pre-polycondensation → final polycondensation → polyester melt delivery → metering pump → spinneret extrusion (including spinning assembly heating unit) → cooling → oiling → winding and forming;

[0081] Among them, the relevant parameters of the production system of full-roll polyester pre-oriented yarn are: n is equal to 16;

[0082] The relevant process parameters are: spinning box temperature 289℃, pump supply 150.2g / min, full roll time 52min, stop time 46min, target temperature 303.45℃ (i.e. 105% of the spinning box temperature), and time for cutting small rolls after spinning-in 10.4min (i.e. after spinning-in, first wind continuously on spindle shaft I for 10.4min, then switch to spindle shaft II and restart the timing from 0min to continuous winding for 52min).

[0083] The specification of the final full-roll polyester pre-oriented yarn (i.e., the yarn on spindle shaft II) is 1050dtex / 192f, the difference in elongation at break between the bottom yarn and the surface yarn is 1.8%, the thermal stress center value M is 380cN, the thermal stress difference between the bottom yarn and the surface yarn is 5.9cN, and the yarn unevenness CV value of the bottom yarn is 1.33%; the tension CV fluctuation of the full-roll polyester pre-oriented yarn during the subsequent texturing is ≤3.0% (displayed by the tension TCS control system of the texturing machine), and the difference in T2 tension between the bottom yarn and the surface yarn (displayed by the tension TCS control system of the texturing machine) is ≤5cN.

[0084] Example 6

[0085] A method for producing a full roll of polyester pre-oriented yarn is basically the same as that in Example 5, except that the time for cutting the small rolls after spinning is 0 min.

[0086] The specification of the final full-roll polyester pre-oriented yarn (i.e., the yarn on spindle shaft II) is 1050dtex / 192f, the difference in elongation at break between the bottom yarn and the surface yarn is 3.8%, the center value of thermal stress M is 380cN, the difference in thermal stress between the bottom yarn and the surface yarn is 12.5cN, and the CV value of the yarn unevenness of the bottom yarn is 1.97%; the tension CV fluctuation of the full-roll polyester pre-oriented yarn during the subsequent texturing (displayed by the tension TCS control system of the texturing machine) is >3.0%, and the difference in T2 tension of the bottom yarn and the T2 tension of the surface yarn (displayed by the tension TCS control system of the texturing machine) is >5cN.

[0087] Comparative Example 1

[0088] A method for producing a full roll of polyester pre-oriented yarn is basically the same as that of Example 5, except that: there is no spinning component heating unit in the production system of the full roll of polyester pre-oriented yarn.

[0089] The specification of the final full-roll polyester pre-oriented yarn (i.e., the yarn on spindle shaft II) is 1050dtex / 192f, the difference in elongation at break between the bottom yarn and the surface yarn is 4.3%, the thermal stress center value M is 380cN, the thermal stress difference between the bottom yarn and the surface yarn is 13.6cN, and the yarn unevenness CV value of the bottom yarn is 1.98%; the tension CV fluctuation of the full-roll polyester pre-oriented yarn during the subsequent texturing (displayed by the tension TCS control system of the texturing machine) is >3.0%, and the difference in T2 tension of the bottom yarn and the T2 tension of the surface yarn (displayed by the tension TCS control system of the texturing machine) is >5cN.

[0090] By comparing Comparative Example 1 with Example 5, it can be seen that the difference in elongation at break, the difference in thermal stress, the CV value of the unevenness of the yarn between the bottom yarn and the surface yarn, as well as the CV fluctuation of the tension of the full-roll polyester pre-oriented yarn during the subsequent texturing, and the difference in the T2 tension of the bottom yarn and the T2 tension of the surface yarn all increased significantly. This is because the production system of the full-roll polyester pre-oriented yarn of Comparative Example 1 does not have a spinning component heating unit, and the temperature of the spinneret drops significantly after the stop operation, which directly leads to the long elongation at break, large thermal stress, and high unevenness of the yarn of the bottom yarn, resulting in significant differences in the physical indicators of the bottom yarn and the physical indicators of the full-roll polyester pre-oriented yarn; and the large thermal stress of the bottom yarn triggers the tension change in the subsequent texturing process.

Claims

1. A production system for a fully rolled polyester pre-oriented yarn, comprising a metering pump, n spinning components, 1≤n≤16, characterized in that: It also includes a metering pump control unit, a spinning pack heating unit and a signal processing unit; The metering pump control unit is connected to the metering pump and is used to adjust and display the polyester melt flow rate in real time; The spinning pack heating unit is connected to the cavity of the spinning box where the spinning pack is installed and is used to heat the spinneret plate to the target temperature, and the target temperature is 103-105% of the spinning box temperature; The spinning pack heating unit includes a heat supply system, a temperature detection unit, a temperature controller and a gas supply control unit; the heat supply system includes a primary heat medium main pipe, 1 oil inlet pipe, n heat conduction coils, 1 oil outlet pipe, a recovery pipe, a pneumatic valve, a pressure relief valve; the n heat conduction coils are respectively sleeved on the n spinning packs; the primary heat medium main pipe, the oil inlet pipe, the n heat conduction coils, the oil outlet pipe and the recovery pipe are connected in sequence; the pneumatic valve is installed at the connection of the oil inlet pipe and the primary heat medium main pipe; the pressure relief valve is installed at the connection of the oil outlet pipe and the recovery pipe; the temperature detection unit is used to detect the real-time temperature of the spinneret plate and send it to the temperature controller; the temperature controller is used to compare the real-time temperature of the spinneret plate with the target temperature and then adjust the opening of the pneumatic valve through the gas supply control unit. When the real-time temperature is higher than the upper limit of the target temperature, the opening of the pneumatic valve is reduced. When the real-time temperature is lower than the lower limit of the target temperature, the opening of the pneumatic valve is increased. When the real-time temperature is within the range of the target temperature, the opening of the pneumatic valve is not adjusted; The signal processing unit is connected to both the metering pump control unit and the spinning pack heating unit at the same time and is used to start the spinning pack heating unit when the polyester melt flow rate is 0, and to turn off the spinning pack heating unit when the polyester melt flow rate is greater than 0; the signal processing unit is also used to start Motor I when the polyester melt flow rate is greater than 0; The signal processing unit is also used to count the running time of Motor I, and when the value corresponding to the running time of Motor I in minutes reaches the set value a, turn off Motor I and start the servo motor and Motor II; Let b = t1×[10%+(t2 - 10)×0.5%]-[t1×(Q - 48)×0.3%], where t1 is the value corresponding to the full roll time in minutes, t2 is the value corresponding to the stop position time in minutes, and Q is the value corresponding to the polyester melt flow rate in g / min; When b < t1×20%, let a = t1×20%; when t1×20% ≤ b ≤ t1×50%, let a = b; when b > t1×50%, let a = t1×50%.

2. A fully rolled polyester pre-oriented yarn production system according to claim 1, characterized in that: The temperature detection unit is a non-contact temperature measuring instrument.

3. The production system of fully rolled polyester pre-oriented yarn according to claim 1, characterized in that: The gas supply control unit includes a gas supply valve, a motor and a motor control frequency converter; The pneumatic valve, the gas supply valve, the motor, the motor control frequency converter and the temperature controller are connected in sequence; The temperature controller adjusts the opening of the pneumatic valve through the gas supply control unit, that is, the temperature controller changes the current signal sent to the motor control frequency converter, so that the motor control frequency converter controls the motor to drive the valve core of the gas supply valve to move, adjusts the opening of the gas supply valve, and further adjusts the opening of the pneumatic valve.

4. A production system for fully rolled polyester pre-oriented yarn according to any one of claims 1 to 3, characterized in that: It also includes a winding device; the winding device includes a turntable, a servo motor, a spindle shaft I, a spindle shaft II, a motor I and a motor II; the turntable is arranged vertically; the servo motor is used to drive the turntable to rotate 180° around its own central axis; the spindle shaft I and the spindle shaft II are perpendicular to the turntable and are symmetrically distributed on the upper and lower sides of the central axis of the turntable; the motor I is used to drive the spindle shaft I to rotate around its own central axis; the motor II is used to drive the spindle shaft II to rotate around its own central axis.

5. A method for producing a fully rolled polyester pre-oriented yarn, characterized in that: A production system for fully rolled polyester pre-oriented yarn as described in claim 4 is used.

6. The method for producing a fully rolled polyester pre-oriented yarn according to claim 5, characterized in that: The difference in elongation at break between the bottom yarn and the surface yarn of the fully rolled polyester pre-oriented yarn is ≤2.8%, the difference in thermal stress between the bottom yarn and the surface yarn is ≤the thermal stress center value×2.5%, and the CV value of the yarn unevenness of the bottom yarn is ≤1.35%.