A fully prefabricated low-rise assembled reinforced concrete frame and node structure
Through fully prefabricated low-rise prefabricated reinforced concrete frames and node structures, the component design and connection methods are optimized, and the problems of low prefabricated rate and complex nodes in prefabricated buildings are solved, achieving efficient and economical construction and structural durability improvement.
Patent Information
- Application Number
- CN202311587228.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-24
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2043-11-24
AI Technical Summary
The prefabrication rate of the structural main body in existing prefabricated buildings is low, resulting in high labor, cost and construction period during the construction process, complex node structures and prone to cracking, and lack of industrial construction methods with high prefabrication rate and economical security.
Adopt a fully prefabricated low-level prefabricated reinforced concrete frame and node structure. Through prefabricated independent foundation chassis and pier body, embedded steel bars and connecting bars are set up, and closed stirrups, steel ports, embedded slurry anchor casing and high-strength non-shrinkage Cement-based grouting materials are connected and poured, and structural components are optimized for rapid assembly.
The number of temporary support is reduced, the formwork support process is reduced, the cast-in-place operation is omitted, the construction efficiency and structural durability are improved, and rapid assembly and molding is achieved.
Smart Images

Figure CN118704601B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of prefabricated buildings, and in particular to a fully prefabricated low-rise prefabricated reinforced concrete frame and node structure. Background Art
[0002] There are still few cast-in-place industrialized structural systems. In terms of prefabricated housing construction, most project developers only use composite panels, prefabricated walls (columns) and prefabricated stairs to meet the requirements of the green building standards. The prefabrication rate of the main structure is still very low, and there are still many wet operations on site. In addition, the labor, cost and construction period consumed by most projects are higher than those of fully cast-in-place structures; some nodes are complex and cumbersome, and cracks often occur due to improper node treatment. There is still a lot of room for research on prefabricated structural systems that are suitable for construction capacity and economic level, especially the industrialized construction methods of prefabricated housing construction that are free of templates, have a high prefabrication rate, are economical and safe, and have a low material loss rate. Summary of the invention
[0003] The object of the present invention is to provide a fully prefabricated low-rise assembled reinforced concrete frame and node structure to solve the problems raised in the above background technology.
[0004] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a fully prefabricated low-rise assembled reinforced concrete frame, comprising a prefabricated independent foundation chassis portion and an upper prefabricated independent foundation pier body portion, wherein the interior of the prefabricated independent foundation chassis portion is provided with prefabricated independent foundation steel bars, the prefabricated independent foundation chassis portion is plugged with embedded column connecting bars, the prefabricated independent foundation pier body portion is plugged with embedded beam connecting bars, both sides of the prefabricated independent foundation pier body portion are provided with prefabricated beams, the top of the prefabricated independent foundation pier body portion is provided with prefabricated columns, the prefabricated independent foundation pier body portion is provided with embedded grout anchor sleeves, the embedded column connecting bars penetrate the embedded grout anchor sleeves, the two embedded column connecting bars are fixedly connected by closed stirrups, and the prefabricated independent foundation chassis portion is formed by assembling multiple layers of prefabricated independent chassis from top to bottom.
[0005] Preferably, the interior of the multi-layer prefabricated independent chassis is respectively provided with a first structural steel mesh and a second structural steel mesh, both of which are formed by the intersection of structural steel bars to form a mesh structure, and the prefabricated independent foundation steel mesh is formed by the intersection of stress-bearing steel bars to form a mesh structure.
[0006] Preferably, the multi-layer prefabricated independent chassis is provided with a first reserved tie bar grouting hole and a second reserved tie bar grouting hole, respectively, the interface between the upper and lower chassis is roughened, the multi-layer prefabricated independent chassis is provided with embedded hoop holes, and embedded column connecting bars are arranged through the embedded hoop holes.
[0007] A node structure of a fully prefabricated low-rise assembled reinforced concrete frame, wherein a steel groove is provided on one side of the prefabricated beam, and the prefabricated columns include upper columns and lower columns, the upper columns are plugged with upper column reserved connecting steel bars, and the lower columns are plugged with lower column reserved connecting steel bars.
[0008] Preferably, an upper column leg is provided at the bottom of the upper column, and a lower column connection interface keyway is provided at the bottom of the lower column, and the upper column leg and the lower column connection interface keyway are provided correspondingly.
[0009] Preferably, the steel groove comprises steel plates, two steel plates are connected by welding with bolts, the bottom of the steel groove is flush with the bottom of the prefabricated beam, and the component steel bars on the prefabricated column are connected by sleeve grouting.
[0010] Preferably, the prefabricated beams and prefabricated columns are provided with prefabricated panels, the middle prefabricated panel is welded to the prefabricated panels on both sides, the reserved steel bars on the prefabricated panels are connected by sleeve extrusion or welding, and the connection parts of the prefabricated panels are cast with high-strength non-shrinkage cement-based grouting material.
[0011] Preferably, a notch is provided at the plate end between the prefabricated plate and the prefabricated beam on the side, the reserved steel bars on the prefabricated plate and the reserved steel bars on the prefabricated beam are welded and connected, and the connection part of the notch is cast with cement-based grouting material.
[0012] Preferably, reserved grooves are reserved at the plate ends on both sides of the beam between the prefabricated plate and the middle prefabricated beam, plate surface steel bars are reserved at the positions of the reserved grooves, the overlapping plate surface steel bars are connected by welding, and the reserved groove connection parts are poured with cement-based grouting material.
[0013] Preferably, a steel bar joint is reserved between the prefabricated panel and the prefabricated column on the end plate surface, a supporting steel plate is provided at the bottom of the prefabricated column and the corresponding prefabricated panel, and the joint connection parts of the steel bar joint are cast with cement-based grouting material.
[0014] Compared with the prior art, the present invention has the following beneficial effects:
[0015] The present invention provides a low-rise assembled reinforced concrete frame structural system. By optimizing the design of all structural components, the assembly of all foundation components and upper main structural components can be realized. The application of this structural system can reduce the number of temporary supports in the construction process of the upper main structure, shorten the formwork support process, and omit a large number of cast-in-place operations existing in current assembled buildings, thereby facilitating the rapid assembly and molding of prefabricated components. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a structural schematic diagram of the connection between the independent foundation and the base beam of the present invention.
[0017] Figure 2 It is a schematic diagram of the structure between the independent foundations of the present invention.
[0018] Figure 3 It is a schematic diagram of the structure between the prefabricated independent basic chassis parts of the present invention.
[0019] Figure 4 It is a structural schematic diagram of the column-beam node assembly of the present invention.
[0020] Figure 5 It is a structural schematic diagram of the steel tongue and groove joint of the present invention.
[0021] Figure 6 It is a schematic structural diagram of the column-beam intermediate layer node connection of the present invention.
[0022] Figure 7 It is a schematic structural diagram of the top-level node connection of the column-beam of the present invention.
[0023] Figure 8 It is a structural schematic diagram of the beam-slab connection of the present invention.
[0024] Fig. 9 It is a schematic diagram of the structure of the connection between prefabricated panels of the present invention.
[0025] Fig.10 It is a schematic diagram of the structure of the connection between the columns and plates of the present invention.
[0026] In the figure: prefabricated independent foundation chassis part 1; prefabricated independent foundation steel bar 11; closed stirrup 12; first structural steel mesh 13; embedded hoop hole 14; first reserved tie bar grouting hole 15; second reserved tie bar grouting hole 16; second structural steel mesh 17; prefabricated beam 2; embedded beam connecting bar 21; prefabricated independent foundation pier body part 3; embedded column connecting bar 31; embedded grout anchor sleeve 32: prefabricated column 4; upper column leg 41; upper column reserved connecting steel bar 42; steel groove 51; lower column connection interface keyway 61; lower column reserved connecting steel bar 62; prefabricated plate 7; missing groove 71; steel plate 72; bolt 73; reserved slot 74; supporting steel plate 8. DETAILED DESCRIPTION
[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0028] See also Figures 1 to 10The present invention provides a technical solution: a fully prefabricated low-rise assembled reinforced concrete frame, comprising a prefabricated independent foundation chassis portion 1 and an upper prefabricated independent foundation pier portion 3, the interior of the prefabricated independent foundation chassis portion 1 is plugged with prefabricated independent foundation steel bars 11, the prefabricated independent foundation chassis portion 1 is plugged with embedded column connecting bars 31, the prefabricated independent foundation pier portion 3 is plugged with embedded beam connecting bars 21, prefabricated beams 2 are arranged on both sides of the prefabricated independent foundation pier portion 3, and a prefabricated column 4 is arranged on the top of the prefabricated independent foundation pier portion 3.
[0029] The prefabricated independent foundation pier body 3 is provided with a pre-embedded grouting anchor sleeve 32, the pre-embedded column connecting reinforcement 31 is arranged through the pre-embedded grouting anchor sleeve 32, and the two pre-embedded column connecting reinforcements 31 are fixedly connected by closed hoop reinforcements 12. The prefabricated independent foundation chassis part 1 is formed by assembling a multi-layer prefabricated independent chassis from top to bottom, and the first structural steel mesh 13 and the second structural steel mesh 17 are respectively inserted into the interior of the multi-layer prefabricated independent chassis. The first structural steel mesh 13 and the second structural steel mesh 17 are formed by the cross-section of structural steel bars to form a mesh structure, and the prefabricated independent foundation steel bars 11 are formed by the cross-section of stressed steel bars to form a mesh structure, and the first reserved tie bar grouting hole 15 and the second reserved tie bar grouting hole 16 are respectively provided on the multi-layer prefabricated independent chassis, and the pre-embedded hoop hole 14 is provided on the multi-layer prefabricated independent chassis, and the pre-embedded column connecting reinforcement 31 is arranged through the pre-embedded hoop hole 14.
[0030] The prefabricated independent foundation is divided into two parts: the prefabricated independent foundation chassis part 1 and the prefabricated independent foundation pier body part 3. The chassis and the pier body can be prefabricated separately according to the transportation and hoisting construction conditions. The main function of the pier body is to serve as the core area of the connection node between the upper column and the horizontal connecting beam. The cross-sectional area is larger than the upper prefabricated column 4. The pier body can also adjust the length according to the depth of the bearing layer to meet the design elevation of the top of the connecting beam, and the corresponding connecting steel bars are pre-embedded in the pier body.
[0031] After the independent foundation positioning construction is completed, when the prefabricated beam 2 is connected to the independent foundation, bricks or cement blocks are used as supports. After the elevation of the connecting beam is adjusted, the steel slurry anchor is overlapped or welded, and then the prefabricated column is constructed to connect with the foundation. After the construction is completed and the upper prefabricated column 4 is effectively supported, the gap between the prefabricated beam 2 and the independent foundation is filled with grouting.
[0032] The gaps around the single-base foundation are filled with grout or grouting to ensure that the joints are firmly connected and prevent the intrusion of groundwater or moisture, protecting the steel bars from rust, thereby improving the durability of the concrete structure. Grouting joints use high-strength non-shrinkage cement-based grouting materials, which have good fluidity, high bonding strength, and high early strength. The self-weight grouting method can be used.
[0033] A steel groove 51 is installed on one side of the prefabricated beam 2, and the prefabricated column 4 includes an upper column and a lower column. The upper column is plugged with an upper column reserved connecting steel bar 42, and the lower column is plugged with a lower column reserved connecting steel bar 62. The bottom of the upper column is fixedly connected with an upper column leg 41, and a lower column connection interface key groove 61 is opened at the bottom of the lower column, and the upper column leg 41 and the lower column connection interface key groove 61 are correspondingly arranged.
[0034] The steel groove 51 includes a steel plate 72, and the two steel plates 72 are welded and connected by bolts 73. The bottom of the steel groove 51 is flush with the bottom of the precast beam 2. The component steel bars on the precast column 4 are connected by extruded sleeves, and the component steel bars on the precast column 4 are connected by sleeve grouting.
[0035] In the node structure of the precast column 4 and the precast beam 2, a pair of steel plates 72 are pre-buried at the bottom of the precast beam 2 as a steel groove 51. The steel groove 51 is borne by two steel plates 72 to carry the construction load, which can reduce the number of temporary supports used during the beam construction process.
[0036] The two steel plates 72 are welded and connected by bolts 73 in the middle. The bottom of the steel groove 51 of the precast beam 2 is flush with the bottom of the precast beam 2. During on-site construction, the precast beam 2 is hoisted onto the pre-buried steel pad of the precast column 4, and the elevation of the precast beam 2 is adjusted to the designed elevation. Then, a temporary support is set up for the precast beam 2 to prevent it from tipping over. The arrangement of the steel bars at the bottom of the beam is checked before anchoring. If there is a conflict with the upper column legs, the steel bars are bent on site to bypass the legs. Finally, the upper precast column is installed. After the legs are embedded in the key slots, the plane positioning and verticality of the upper vertical components are adjusted. After installation, the vertical steel bars are connected.
[0037] For the prefabricated column 4, the component reinforcement connection method usually uses reinforcement with a diameter of not less than 20 mm, which can be connected by extrusion sleeve or sleeve grouting. For reinforcement with a diameter less than 20 mm, welding or sleeve grouting can be used.
[0038] Precast panels 7 are provided on the precast beams 2 and precast columns 4. The middle precast panel 7 is welded to the precast panels 7 on both sides. The reserved steel bars on the precast panels 7 are connected by sleeve extrusion or welding. The connection parts of the precast panels 7 are cast with high-strength non-shrinkage cement-based grouting material.
[0039] The connection of the steel bars between the middle prefabricated plate 7 and the prefabricated plates 7 on both sides adopts 10d single-sided welding or 5d double-sided welding. The reserved steel bar length is guaranteed to meet the requirements of on-site welding or sleeve extrusion connection. After the connection is completed, high-strength non-shrinkage cement-based grouting material is used for pouring at the connection position.
[0040] A notch 71 is reserved at the plate end between the precast plate 7 and the precast beam 2 on the side, and the reserved steel bars on the precast plate 7 are welded and connected at the notch. A full-length structural longitudinal reinforcement is arranged between the reserved U-shaped steel bars in the notch 71 on the precast beam 2, and the full-length structural longitudinal reinforcement is placed above the plate steel bars, and the connection part of the notch 71 is cast with cement-based grouting material.
[0041] The connection between the prefabricated plate 7 and the prefabricated beam 2 on the side is achieved by reserving a certain size of notch 71 at the plate end. A certain length of the plate reinforcement at the position of the notch 71 is reserved. The welding method is 10d single-sided welding or 5d double-sided welding. After welding, the connection part of the notch 71 is poured with high-strength non-shrinkage cement-based grouting material.
[0042] A reserved slot 74 is reserved at the plate ends on both sides of the beam between the precast plate 7 and the middle precast beam 2. Plate surface reinforcement is reserved at the position of the reserved slot 74. The overlapped plate surface reinforcement is connected by welding, and the connection part of the reserved slot 74 is poured with cement-based grouting material.
[0043] The prefabricated plate 7 connected to the middle prefabricated beam 2 is prepared by reserving grooves 74 on the plate ends on both sides of the beam. The plate surface reinforcement is reserved at the positions of the reserved grooves 74. After the prefabricated plates on both sides above the beam are hoisted into place, the overlapping plate surface reinforcement is welded or sleeve extruded. After the connection is completed, the grooved connection part is poured with high-strength non-shrinkage cement-based grouting material.
[0044] A steel bar joint is reserved between the precast panel 7 and the precast column 4 at the end plate surface, and a supporting steel plate 8 is arranged at the bottom of the precast column 4 and the corresponding precast panel 7, and the joint connection part of the steel bar joint is poured with cement-based grouting material.
[0045] The vertical components between the precast plate 7 and the precast column 4 are connected, and a certain length of steel bar joints are reserved on the end plate surface. At the same time, the supporting steel plate 8 is embedded at the bottom of the precast plate 7 corresponding to the precast column 4. After the connection is completed, the joint is poured with high-strength non-shrinkage cement-based grouting material.
[0046] The present invention provides a low-rise assembled reinforced concrete frame structural system. By optimizing the design of all structural components, the assembly of all foundation components and upper main structural components can be realized. The application of this structural system can reduce the number of temporary supports in the construction process of the upper main structure, shorten the formwork support process, and omit a large number of cast-in-place operations existing in current assembled buildings, thereby facilitating the rapid assembly and molding of prefabricated components.
[0047] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A fully prefabricated low-rise assembled reinforced concrete frame, comprising a prefabricated independent foundation chassis portion (1) and an upper prefabricated independent foundation pier portion (3), characterized in that: The prefabricated independent foundation chassis part (1) is provided with a prefabricated independent foundation steel bar (11) inside, the prefabricated independent foundation chassis part (1) is plugged with a pre-buried column connecting bar (31), the prefabricated independent foundation pier body part (3) is plugged with a pre-buried beam connecting bar (21), both sides of the prefabricated independent foundation pier body part (3) are provided with prefabricated beams (2), the top of the prefabricated independent foundation pier body part (3) is provided with a pre-buried grout anchor sleeve (32), the pre-buried column connecting bar (31) is arranged through the pre-buried grout anchor sleeve (32), and the two pre-buried column connecting bars (31) are fixedly connected by a closed stirrup (12). The prefabricated independent foundation chassis part (1) is formed by assembling multiple layers of prefabricated independent chassis from top to bottom. A steel groove (51) is provided on one side of the prefabricated beam (2). The prefabricated column (4) includes an upper column and a lower column. The upper column is plugged with an upper column reserved connection steel bar (42). The lower column is plugged with a lower column reserved connection steel bar (62). The bottom of the upper column is provided with an upper column leg (41). The bottom of the lower column is provided with a lower column connection interface keyway (61). The upper column leg (41) and the lower column connection interface keyway (61) are correspondingly arranged. The steel groove (51) includes a steel plate (72). Bolts ( 73) welding connection, the bottom of the steel groove (51) is flush with the bottom of the precast beam (2), the component steel bars on the precast column (4) are connected by sleeve grouting, the precast beam (2) and the precast column (4) are both provided with precast panels (7), the middle precast panel (7) is welded to the precast panels (7) on both sides, the reserved steel bars on the precast panels (7) are connected by sleeve extrusion or welding, the connection parts of the precast panels (7) are cast with high-strength non-shrinkage cement-based grouting material, the plate ends between the precast panels (7) and the side precast beams (2) are provided with notches (71), the reserved steel bars on the precast panels (7) are connected to the reserved steel bars on the precast beams (2) The precast panels (7) and the precast columns (4) are connected by welding, and the connection parts of the notches (71) are cast with cement-based grouting materials. The precast panels (7) and the middle precast beams (2) are connected by reserved grooves (74) on the ends of the beams on both sides. Plate surface reinforcements are reserved at the positions of the reserved grooves (74). The overlapped plate surface reinforcements are connected by welding, and the connection parts of the reserved grooves (74) are cast with cement-based grouting materials. A reinforcement joint is reserved on the end plate surface between the precast panels (7) and the precast columns (4). A supporting steel plate (8) is provided at the bottom of the precast columns (4) and the corresponding precast panels (7), and the connection parts at the joints of the reinforcement joints are cast with cement-based grouting materials.
2. A fully prefabricated low-rise assembled reinforced concrete frame according to claim 1, characterized in that: The interior of the multi-layer prefabricated independent chassis is respectively provided with a first structural steel mesh (13) and a second structural steel mesh (17); the interface between the upper and lower chassis is subjected to a rough surface treatment; the first structural steel mesh (13) and the second structural steel mesh (17) are both formed by the structural steel bars crossing to form a mesh structure; and the prefabricated independent foundation steel bars (11) are formed by the stress-bearing steel bars crossing to form a mesh structure.
3. A fully prefabricated low-rise assembled reinforced concrete frame according to claim 1, characterized in that: The multi-layer prefabricated independent chassis is respectively provided with a first reserved tie bar grouting hole (15) and a second reserved tie bar grouting hole (16), and the multi-layer prefabricated independent chassis is provided with a pre-buried hoop hole (14), and the pre-buried column connecting bar (31) is arranged through the pre-buried hoop hole (14).