Blast furnace tapping main channel structure and preparation method thereof
By introducing natural air cooling and ceramic insulation fiber layer into the blast furnace tap trench, the problems of insufficient cooling and insufficient blocking capacity of the traditional blast furnace tap trench are solved, and the temperature of the steel shell is reduced and the structural stability is improved. promote.
Patent Information
- Application Number
- CN202410824241.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-24
- Publication Date
- 2024-10-01
AI Technical Summary
The main tap trench of traditional blast furnaces has the problem of insufficient cooling, which causes the steel shell to be hot and prone to deformation and cracking. At the same time, the side walls, bottom corners and trench bottom have weak blocking capabilities for molten iron and air.
A blast furnace tapping main trench structure including prefabricated blocks, steel trough, insulation layer, permanent layer and air duct was designed. Natural wind cooling was achieved by setting up air ducts outside the steel trough, and the prefabricated block structure of the side walls and bottom corners was added to The blocking capability is enhanced and ceramic insulating fibers are arranged within the steel shell to reduce temperatures.
It effectively reduces the temperature of the steel shell, reduces the risk of deformation and cracking, and at the same time enhances the blocking ability of molten iron and air, improving the stability of the overall structure and construction convenience.
Smart Images

Figure CN118726677A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of a blast furnace iron-out main groove, and in particular to a blast furnace iron-out main groove structure and a preparation method thereof. Background Art
[0002] The blast furnace taphole is an important part of the blast furnace ironmaking system, and the most important one is the main taphole, which is responsible for transporting the mixture of high-temperature molten iron and slag out of the blast furnace, carrying and separating the molten iron and slag from the blast furnace. The separated molten iron flows to the ladle through the molten iron ditch, swing chute, etc., while the slag flows to the dry slag pit or water slag treatment system through the slag ditch;
[0003] The traditional main trench has the following defects: First, the main trench is designed as a heat transfer type. The main trench has no air cooling, and its overall structure cannot be effectively cooled. The temperature of the steel shell is high, and the steel shell is prone to deformation and cracking under long-term use. Second, there are gaps between the side walls, bottom corners and prefabricated blocks at the bottom of the traditional main trench, and the blocking ability of the molten iron and air is weak. Summary of the invention
[0004] The object of the present invention is to provide a main channel structure for blast furnace iron tapping to solve the problems raised in the above background technology.
[0005] In order to solve the above technical problems, the present invention provides the following technical solutions: a blast furnace iron-outlet main groove structure, comprising a prefabricated block, a positioning groove is provided on the outer wall on one side of the prefabricated block, a positioning block is provided on the outer wall on the other side of the prefabricated block, accommodating holes are provided on the outer walls on both sides of the prefabricated block, thermocouples are sleeved in the accommodating holes, permanent layers are provided on both sides of the prefabricated block, an insulation layer is provided on one side of the permanent layer, a steel trough is provided on one side of the insulation layer, a concrete layer is provided on one side of the steel trough, and an air duct is provided between the steel trough and the concrete layer.
[0006] Preferably, a working layer is provided on one side outer wall of the prefabricated block.
[0007] Preferably, a positioning plate is provided on the outer wall of the steel channel, and accommodating grooves are opened on the outer walls on both sides of the prefabricated block at positions corresponding to the positioning plates, and the positioning plates are arranged in the accommodating grooves.
[0008] Preferably, a first through hole is opened on an outer wall of one side of the permanent layer at a position corresponding to the accommodating hole, and the thermocouple is sleeved in the first through hole.
[0009] Preferably, second through holes are provided on the outer walls of both sides of the thermal insulation layer at positions corresponding to the first through holes, and the thermocouples are sleeved in the second through holes.
[0010] Preferably, third through holes are provided on the outer walls of both sides of the steel trough at positions corresponding to the second through holes, and the thermocouples are sleeved in the third through holes.
[0011] Preferably, bosses are provided on the outer walls on both sides of the prefabricated block.
[0012] A method for preparing a blast furnace iron tapping main groove structure comprises the following steps:
[0013] Step S1: Laying the bottom steel trough and setting the insulation layer;
[0014] Step S2: preparing a prefabricated block;
[0015] Step S3: pouring a permanent layer between the prefabricated blocks and the insulation layer;
[0016] Step S4: Install thermocouples on the outer walls of both sides of the prefabricated block.
[0017] Preferably, the preparation process of the permanent layer includes the following steps: making a steel shell layer; arranging ceramic thermal insulation fibers on the inner surface of the steel shell layer to form a ceramic thermal insulation fiber layer that is tightly fitted with the steel shell layer; arranging a preform layer with a predetermined thickness on the inner surface of the ceramic thermal insulation fiber layer, and the preform layer, the ceramic thermal insulation fiber layer and the steel shell layer together constitute the permanent layer of the iron outlet groove.
[0018] Preferably, the assembly process of the prefabricated blocks comprises the following steps:
[0019] Step (a) Laying a heat insulation layer on the bottom and side walls of the main trench steel shell;
[0020] Step (b) positioning and installing the permanent layer prefabricated blocks;
[0021] Step (c) installing a temperature measuring thermocouple;
[0022] Step (d) filling the gap behind the prefabricated part with a self-flowing castable material;
[0023] Step (e) Installation of the main groove working layer mold and pouring of the working layer.
[0024] Compared with the prior art, the beneficial effects achieved by the present invention are as follows: an air duct is arranged outside the steel trough of the present invention, and the steel shell is cooled in the form of natural air cooling, so the temperature of the steel shell is effectively reduced, reducing the risk of deformation and cracking of the steel shell during long-term use, while reducing the heat storage of the overall structure, slowing down the thermal melting loss of the main groove, and increasing the overall stability of the prefabricated blocks through the integrated prefabricated block structure of the side walls, bottom corners, and groove bottom, while facilitating on-site construction and installation, and a closed structure is arranged between the prefabricated blocks to increase the resistance of molten iron and air passing through the structure, thereby enhancing the blocking ability of the combined prefabricated blocks to molten iron and air. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0026] Figure 1 It is a schematic diagram of the overall three-dimensional structure of the present invention;
[0027] Figure 2 It is a schematic diagram of the overall front view structure of the present invention;
[0028] Figure 3 It is a schematic diagram of the overall front view cutaway structure of the present invention;
[0029] Figure 4 for Figure 3 Schematic diagram of the enlarged structure of the A area in the middle;
[0030] Figure 5 It is a schematic diagram of the three-dimensional structure of the prefabricated block of the present invention;
[0031] Figure 6 for Figure 5 Schematic diagram of the enlarged structure of area B in the middle.
[0032] In the figure: 1. prefabricated block; 2. positioning groove; 3. positioning block; 4. boss; 5. receiving groove; 6. receiving hole; 7. insulation layer; 8. steel groove; 9. positioning plate; 10. permanent layer; 11. air duct; 12. concrete layer; 13. thermocouple; 14. first through hole; 15. second through hole; 16. third through hole; 17. working layer. DETAILED DESCRIPTION
[0033] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0034] See also Figure 1-6, an embodiment of the present invention: a blast furnace iron-outlet main groove structure, comprising a prefabricated block 1, a positioning groove 2 is provided on the outer wall of one side of the prefabricated block 1, a positioning block 3 is provided on the outer wall of the other side of the prefabricated block 1, a receiving hole 6 is provided on the outer walls of both sides of the prefabricated block 1, a thermocouple 13 is sleeved in the receiving hole 6, a permanent layer 10 is provided on both sides of the prefabricated block 1, a thermal insulation layer 7 is provided on one side of the permanent layer 10, a steel trough 8 is provided on one side of the thermal insulation layer 7, a concrete layer 12 is provided on one side of the steel trough 8, and an air duct 11 is provided between the steel trough 8 and the concrete layer 12; a working layer 17 is provided on the outer wall of one side of the prefabricated block 1, and the working layer 17 is used to receive molten iron; a positioning plate 9 is provided on the outer wall of the steel trough 8, and the outer walls of both sides of the prefabricated block 1 correspond to the positioning plate 9 A receiving groove 5 is provided at the position, and a positioning plate 9 is arranged in the receiving groove 5, and the receiving groove 5 and the positioning plate 9 are used for installation and positioning; a first through hole 14 is provided on the outer wall of one side of the permanent layer 10 at a position corresponding to the receiving hole 6, and the thermocouple 13 is sleeved in the first through hole 14; a second through hole 15 is provided on the outer walls of both sides of the thermal insulation layer 7 at a position corresponding to the first through hole 14, and the thermocouple 13 is sleeved in the second through hole 15; a third through hole 16 is provided on the outer walls of both sides of the steel groove 8 at a position corresponding to the second through hole 15, and the thermocouple 13 is sleeved in the third through hole 16, and the first through hole 14, the second through hole 15 and the third through hole 16 are used to install the thermocouple 13; bosses 4 are provided on the outer walls of both sides of the prefabricated block 1, and the bosses 4 are convenient for carrying and moving the prefabricated block 1;
[0035] Working principle: When assembling the present invention, first lay the bottom steel trough 8 and set the insulation layer 7, then set the prefabricated block 1 through the positioning plate 9 on the steel trough 8 and the receiving groove 5 on the prefabricated block 1, then pour the permanent layer 10 between the prefabricated block 1 and the insulation layer 7, and then install the thermocouple 13 through the first through hole 14, the second through hole 15, the third through hole 16 and the receiving hole 6. According to the height of the slag iron liquid level in the main groove, a replaceable partitioned temperature measuring thermocouple 13 is set, and a temperature monitoring system is configured to monitor the working layer 17 in real time. The lining temperature provides a reference for the melting condition of the working layer 17. The precast blocks 1 are interlocked head to tail through the positioning grooves 2 and the positioning blocks 3. The gap behind the rearmost precast block 1 is filled with self-flowing castable material. Finally, the working layer 17 is set, and the concrete layer 12 is poured on both sides. When in use, natural wind is introduced through the air duct 11 for cooling, which reduces the temperature of the steel trough 8 and the risk of deformation and cracking of the steel trough 8 due to long-term use. At the same time, the heat storage of the overall structure is reduced, and the thermal melting loss of the main groove is slowed down. The boss 4 is convenient for carrying and moving the precast blocks 1.
[0036] Among them, the preparation process of the permanent layer includes the following steps: making a steel shell layer; arranging ceramic insulation fibers on the inner surface of the steel shell layer to form a ceramic insulation fiber layer that is tightly fitted with the steel shell layer; arranging a preform layer with a predetermined thickness on the inner surface of the ceramic insulation fiber layer, and the preform layer, the ceramic insulation fiber layer and the steel shell layer together constitute the permanent layer of the iron outlet groove.
[0037] The assembly process of the prefabricated blocks includes the following steps:
[0038] Step (a) Laying a heat insulation layer on the bottom and side walls of the main trench steel shell;
[0039] Step (b) positioning and installing the permanent layer prefabricated blocks;
[0040] Step (c) installing a temperature measuring thermocouple;
[0041] Step (d) filling the gap behind the prefabricated part with a self-flowing castable material;
[0042] Step (e) Installation of the main groove working layer mold and pouring of the working layer.
[0043] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0044] The device embodiments described above are merely illustrative, wherein the units described as separate components may or may not be physically separated, and the components displayed as units may or may not be physical units, that is, they may be located in one place, or they may be distributed on multiple network units. Some or all of the modules may be selected according to actual needs to achieve the purpose of the scheme of this embodiment. Ordinary technicians in this field can understand and implement it without paying creative labor.
[0045] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present invention.
Claims
1. A blast furnace iron-out main channel structure, comprising a prefabricated block (1), characterized in that: A positioning groove (2) is provided on one outer wall of the prefabricated block (1), a positioning block (3) is provided on the other outer wall of the prefabricated block (1), receiving holes (6) are provided on both outer walls of the prefabricated block (1), thermocouples (13) are sleeved in the receiving holes (6), permanent layers (10) are provided on both sides of the prefabricated block (1), a thermal insulation layer (7) is provided on one side of the permanent layer (10), a steel groove (8) is provided on one side of the thermal insulation layer (7), a concrete layer (12) is provided on one side of the steel groove (8), and an air duct (11) is provided between the steel groove (8) and the concrete layer (12).
2. A blast furnace iron tapping main channel structure according to claim 1, characterized in that: A working layer (17) is provided on one side outer wall of the prefabricated block (1).
3. A blast furnace iron tapping main channel structure according to claim 1, characterized in that: A positioning plate (9) is arranged on the outer wall of the steel groove (8), and accommodating grooves (5) are opened on the outer walls on both sides of the prefabricated block (1) at positions corresponding to the positioning plates (9), and the positioning plates (9) are arranged in the accommodating grooves (5).
4. A blast furnace iron tapping main channel structure according to claim 1, characterized in that: A first through hole (14) is provided on one side outer wall of the permanent layer (10) at a position corresponding to the accommodating hole (6), and the thermocouple (13) is sleeved in the first through hole (14).
5. A blast furnace iron tapping main channel structure according to claim 1, characterized in that: Second through holes (15) are provided on the outer walls of both sides of the thermal insulation layer (7) at positions corresponding to the first through holes (14), and the thermocouple (13) is sleeved in the second through holes (15).
6. A blast furnace iron tapping main channel structure according to claim 1, characterized in that: Third through holes (16) are provided on the outer walls of both sides of the steel groove (8) at positions corresponding to the second through holes (15), and the thermocouple (13) is sleeved in the third through holes (16).
7. A blast furnace iron tapping main channel structure according to claim 2, characterized in that: Bosses (4) are provided on the outer walls on both sides of the prefabricated block (1).
8. A method for preparing a main channel structure for blast furnace iron tapping, characterized in that: The following steps are involved: Step S1: Laying the bottom steel trough (8) and setting the insulation layer (7); Step S2: preparing a prefabricated block (1); Step S3: pouring a permanent layer (10) between the prefabricated block (1) and the insulation layer (7); Step S4: Install thermocouples (13) on the outer walls of both sides of the prefabricated block (1).
9. The method for preparing a blast furnace iron tapping main channel structure according to claim 8, characterized in that: The preparation process of the permanent layer includes the following steps: making a steel shell layer; arranging ceramic insulation fibers on the inner surface of the steel shell layer to form a ceramic insulation fiber layer that is tightly fitted with the steel shell layer; arranging a preform layer with a predetermined thickness on the inner surface of the ceramic insulation fiber layer, and the preform layer, the ceramic insulation fiber layer and the steel shell layer together constitute the permanent layer of the iron outlet groove.
10. The method for preparing a blast furnace iron-tapping main channel structure according to claim 8, characterized in that: The assembly process of the prefabricated block (1) comprises the following steps: Step (a) Laying a heat insulation layer on the bottom and side walls of the main trench steel shell; Step (b) positioning and installing the permanent layer prefabricated blocks; Step (c) installing a temperature measuring thermocouple; Step (d) filling the gap behind the prefabricated part with a self-flowing castable material; Step (e) Installation of the main groove working layer mold and pouring of the working layer.