HLC steel sheet pile foundation pit supporting system and construction method thereof

The combination of H-shaped steel and hot-rolled U-shaped steel sheet piles increases the stiffness of the steel sheet piles, solves the problems of high construction risk and high cost in foundation pit construction, and achieves fast and safe foundation pit excavation and support effects.

CN118727769APending Publication Date: 2024-10-01CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU SIXTH CONSTRUCTION CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411030969.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-10-01

AI Technical Summary

Technical Problem

In the construction of foundation pits, the construction of local pits has the problems of high risk, high cost and long construction period. The existing steel sheet piles have low stiffness and cannot meet the construction requirements in poor soil quality.

Method used

A combination of H-shaped steel and hot-rolled U-shaped steel sheet piles is used. The H-shaped steel is inserted and welded at intervals to increase the overall stiffness of the steel sheet piles and form an HLC steel sheet pile foundation pit support system. A self-propelled puller is used for construction to reduce support deformation. and construction period.

Benefits of technology

It realizes the excavation of deeper foundation pits without support, reduces construction risks and costs, shortens the construction period, is suitable for different types of foundation pit projects, and has high applicability and low cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118727769A_ABST
    Figure CN118727769A_ABST
Patent Text Reader

Abstract

The invention is suitable for the technical field of building construction, and provides an HLC steel sheet pile foundation pit supporting system which comprises H-shaped steel and hot-rolled U-shaped steel sheet piles, the H-shaped steel and the hot-rolled U-shaped steel sheet piles are used in a matched mode according to models, and the hot-rolled U-shaped steel sheet piles are connected in an end-to-end meshed mode to form an enclosing purlin. The method has the advantages of being high in applicability, rapid in construction, low in cost and standard in product, has the closed waterstop performance of hot-rolled U-shaped steel sheet piles, also has the large rigidity and small deformation of H-shaped steel, and can be suitable for different types of foundation pit projects; the construction speed is higher than that of a concrete rigid support, foundation pit excavation work can be conducted without increasing the strength of concrete, due to the fact that the rigidity of the steel sheet piles is large, the steel sheet piles can be used under the condition that no inner support is arranged, and the construction period is short; after the foundation pit backfilling is completed, the HLC steel sheet piles can be pulled out for turnover use, and the manufacturing cost is low; the two kinds of steel sheet piles are both of common models, are produced in batches under a strict quality management system in the whole process and have universality.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of building construction, and in particular relates to an HLC steel sheet pile foundation pit support system and a construction method thereof. Background Art

[0002] During the foundation pit construction process, there are certain difficulties in the construction of some local pits within the foundation pit. Such pits are small in area and shallow in depth, but because the foundation pit depth is locally deepened, when the pit bottom elevation is lower than the groundwater level, the construction risk is relatively high.

[0003] When the pit-in-pit is supported by a rigid underground continuous wall or concrete bored piles, the cost is high and the construction period is long. When ordinary Larsen steel sheet piles are used, although they have certain water-stopping properties, such steel sheet piles have low rigidity and large deformation. They cannot meet the construction requirements in conditions of poor soil quality, and it is necessary to add horizontal and oblique supports, which increases the difficulty of construction.

[0004] To this end, the present application provides a low-cost, recyclable, and high-rigidity HLC steel sheet pile construction method to meet the above-mentioned foundation pit construction needs. Summary of the invention

[0005] The purpose of the embodiment of the present invention is to provide an HLC steel sheet pile foundation pit support system, which aims to solve the problems existing in the above-mentioned background technology. Its characteristics are that H-shaped steel is inserted into the hot-rolled U-shaped steel sheet piles at intervals to increase the overall stiffness of the steel sheet piles and reduce the support deformation caused by soil pressure during the foundation pit excavation process. Deeper foundation pits and local pits can be excavated without support, thereby reducing the construction period and protecting construction safety.

[0006] The embodiment of the present invention is implemented as follows: an HLC steel sheet pile foundation pit support system includes H-shaped steel and hot-rolled U-shaped steel sheet piles, characterized in that the H-shaped steel and hot-rolled U-shaped steel sheet piles are used in combination according to the model, and the hot-rolled U-shaped steel sheet piles are engaged with each other end to end to form a surrounding purlin.

[0007] Preferably, the H-shaped steel is inserted into the inner side of the hot-rolled U-shaped steel sheet pile at intervals to increase the overall strength of the steel sheet pile.

[0008] Preferably, the H-shaped steel and the hot-rolled U-shaped steel sheet piles are fixed by welding to further increase the support rigidity.

[0009] A construction method of an HLC steel sheet pile foundation pit support system, comprising the following steps: (1) Level the site, measure and lay out the lines, and set up measurement marks at the edge of the foundation pit; (2) Install steel guide rails at the steel sheet pile injection location to ensure the accuracy of steel sheet pile injection; (3) Determine whether to conduct drilling operations based on soil conditions. Drilling operations are performed using a spiral drill with a drill bit diameter smaller than the effective width of the hot-rolled U-shaped steel sheet pile. Determine whether to conduct drilling operations at intervals based on soil conditions. (4) Use a steel sheet pile driving and pulling machine to insert hot-rolled U-shaped steel sheet piles; (5) After the hot-rolled U-shaped steel sheet pile construction is completed, the H-shaped steel is constructed using a steel sheet pile driving and pulling machine; (6) After the HLC steel sheet pile construction is completed, foundation pit excavation, main structure and waterproofing construction are carried out.

[0010] Preferably, after the main structure and waterproofing construction are completed, the foundation pit is backfilled, and after the backfilling is completed, the steel sheet piles are pulled out by a steel sheet pile driving and pulling machine, and the foundation pit construction is completed.

[0011] An HLC steel sheet pile foundation pit support system and a construction method thereof provided by an embodiment of the present invention have the following advantages: 1. High applicability: The HLC steel sheet pile construction method, which combines H-shaped steel and hot-rolled U-shaped steel sheet piles, has both the closed water-stopping property of hot-rolled U-shaped steel sheet piles and the greater rigidity and smaller deformation of H-shaped steel, and can be applied to different types of foundation pit projects; 2. Fast construction: The steel sheet pile construction adopts a self-propelled driving and pulling machine, which has a faster construction speed than the concrete rigid support. The foundation pit excavation can be carried out without waiting for the concrete strength to increase. Since the steel sheet pile has a large rigidity, it can be used without internal support, and the construction period is short; 3. Low cost: After the foundation pit is backfilled, the HLC steel sheet pile can be pulled out for turnover, and the cost is low; 4. Product standardization: Both types of steel sheet piles are common models, mass-produced under a full-process and strict quality management system, and are universal. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 A top view of an HLC steel sheet pile foundation pit support system provided by an embodiment of the present invention; Figure 2 A side view of an HLC steel sheet pile foundation pit support system provided by an embodiment of the present invention; Figure 3 A rendering of an HLC steel sheet pile foundation pit support system provided by an embodiment of the present invention; Figure 4 It is a process flow chart of the present invention.

[0013] In the attached figure: 1-H-shaped steel; 2-hot-rolled U-shaped steel sheet pile. DETAILED DESCRIPTION

[0014] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention.

[0015] The specific implementation of the present invention is described in detail below in conjunction with specific embodiments.

[0016] like Figure 1-Figure 3 As shown, it is a structural diagram of an HLC steel sheet pile foundation pit support system provided by an embodiment of the present invention, comprising an H-shaped steel 1 and a hot-rolled U-shaped steel sheet pile 2, wherein the H-shaped steel 1 and the hot-rolled U-shaped steel sheet pile 2 are used in combination according to the model, and the hot-rolled U-shaped steel sheet pile 2 is engaged end to end to form a surrounding purlin; wherein the two types of steel sheet piles can be selected according to the foundation pit depth and soil quality, and are suitable for foundation pit excavation work of different depths and geological conditions.

[0017] The present invention provides an HLC steel sheet pile foundation pit support system and a construction method thereof, which have the characteristics of high applicability, fast construction, low cost and standardized products. The HLC steel sheet pile construction method using a combination of an H-shaped steel 1 and a hot-rolled U-shaped steel sheet pile 2 has both the closed water-stopping property of the hot-rolled U-shaped steel sheet pile 2 and the greater rigidity of the H-shaped steel 1, with less deformation, and can be applicable to different types of foundation pit projects; the steel sheet pile construction adopts a self-propelled driving and pulling machine, and the construction speed is faster than that of concrete rigid support, and the foundation pit excavation work can be carried out without waiting for the concrete strength to increase. Since the steel sheet pile has greater rigidity, it can be used without internal support, and the construction period is short; after the foundation pit is backfilled, the HLC steel sheet pile can be pulled out for turnover, and the cost is low; both types of steel sheet piles are common models, mass-produced under a full-process and strict quality management system, and have universality.

[0018] In one embodiment of the present invention, the H-shaped steel 1 has a large rigidity and can meet the soil pressure requirement of foundation pit support; after the hot-rolled U-shaped steel sheet piles 2 form a surrounding purlin, they can not only be used for water stopping, but also prevent soil loss between the steel sheet piles.

[0019] like Figure 1 As shown, as a preferred embodiment of the present invention, the H-shaped steel 1 is inserted into the inner side of the hot-rolled U-shaped steel sheet pile 2 at intervals to increase the overall strength of the steel sheet pile.

[0020] In one embodiment of the present invention, H-shaped steels 1 are arranged at intervals and the greater rigidity of the H-shaped steels 1 is utilized. In addition to improving the overall rigidity, support deformation caused by soil pressure during foundation pit excavation can also be reduced.

[0021] like Figure 1As shown, as another preferred embodiment of the present invention, the H-shaped steel 1 and the hot-rolled U-shaped steel sheet pile 2 are fixed by welding so as to further increase the support stiffness.

[0022] In one example of the present invention, according to the soil conditions of the foundation pit and the groundwater conditions, the H-shaped steel 1 and the hot-rolled U-shaped steel sheet piles 2 can be selectively welded to enhance the overall rigidity of the foundation pit support.

[0023] A construction method of an HLC steel sheet pile foundation pit support system, comprising the following steps: (1) Level the site, measure and lay out the lines, and set up measurement marks at the edge of the foundation pit; (2) Install steel guide rails at the steel sheet pile injection location to ensure the accuracy of steel sheet pile injection; (3) Determine whether to conduct drilling operations based on soil conditions. Drilling operations are performed using a spiral drill with a drill bit diameter smaller than the effective width of the hot-rolled U-shaped steel sheet pile 2. Determine whether to conduct drilling operations at intervals based on soil conditions; (4) Use a steel sheet pile driving and pulling machine to insert the hot-rolled U-shaped steel sheet pile 2; (5) After the construction of the hot-rolled U-shaped steel sheet pile 2 is completed, the H-shaped steel 1 is constructed using a steel sheet pile driving and pulling machine; (6) After the HLC steel sheet pile construction is completed, foundation pit excavation, main structure and waterproofing construction are carried out.

[0024] In one example of the present invention, after the main structure and waterproofing construction are completed, the foundation pit is backfilled, and after the backfilling is completed, the steel sheet piles are pulled out by a steel sheet pile driving and pulling machine, and the foundation pit construction is completed.

[0025] In summary, in the process of foundation pit support design, steel sheet piles of different specifications are generally selected according to the foundation pit safety level, pit top load, soil conditions, etc. to meet the foundation pit construction requirements. In addition, the H-shaped steel 1 and the hot-rolled U-shaped steel sheet pile 2 can be welded and connected according to the design requirements to increase the moment of inertia of the steel sheet pile, so that the overall cost is low, it can be used in a turnover manner, has high applicability, and uses standardized products to ensure construction quality.

[0026] It will be apparent to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be considered exemplary and non-restrictive in all respects, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims be included in the present invention.

[0027] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. An HLC steel sheet pile foundation pit support system, comprising H-shaped steel and hot-rolled U-shaped steel sheet piles, characterized in that: The H-shaped steel and hot-rolled U-shaped steel sheet piles are used in combination according to the model, and the hot-rolled U-shaped steel sheet piles are engaged with each other end to end to form a surrounding purlin.

2. The HLC steel sheet pile foundation pit support system according to claim 1, characterized in that: The H-shaped steel is inserted into the inner side of the hot-rolled U-shaped steel sheet pile at intervals to increase the overall strength of the steel sheet pile.

3. The HLC steel sheet pile foundation pit support system according to claim 1, characterized in that: The H-shaped steel and the hot-rolled U-shaped steel sheet piles are fixed by welding to further increase the support rigidity.

4. A construction method of an HLC steel sheet pile foundation pit support system according to any one of claims 1 to 3, characterized in that: These include: (1) Level the site, measure and lay out the lines, and set up measurement marks at the edge of the foundation pit; (2) Install steel guide rails at the steel sheet pile injection location to ensure the accuracy of steel sheet pile injection; (3) Determine whether to conduct drilling operations based on soil conditions. Drilling operations are performed using a spiral drill with a drill bit diameter smaller than the effective width of the hot-rolled U-shaped steel sheet pile. Determine whether to conduct drilling operations at intervals based on soil conditions. (4) Use a steel sheet pile driving and pulling machine to insert hot-rolled U-shaped steel sheet piles; (5) After the hot-rolled U-shaped steel sheet pile construction is completed, the H-shaped steel is constructed using a steel sheet pile driving and pulling machine; (6) After the HLC steel sheet pile construction is completed, foundation pit excavation, main structure and waterproofing construction are carried out.

5. The construction method of a HLC steel sheet pile foundation pit support system according to claim 4, characterized in that: After the main structure and waterproofing construction are completed, the foundation pit is backfilled. After the backfilling is completed, the steel sheet piles are pulled out by a steel sheet pile driving and pulling machine, and the foundation pit construction is completed.