Top beam and concrete support connecting joint construction method and joint structure

The buckle structure that combines prefabricated concrete supports with enclosure piles solves the problem that the concrete supports and crown beams cannot be separated after they are poured together. It realizes the reuse of concrete supports, reduces construction costs, and improves the environmental protection of urban rail transit. sex.

CN118727770APending Publication Date: 2024-10-01SHANDONG RAIL TRANSIT SURVEY & DESIGN INST CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411032581.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-10-01

Smart Images

  • Figure CN118727770A_ABST
    Figure CN118727770A_ABST
Patent Text Reader

Abstract

The invention relates to a top beam and concrete support connecting joint construction method and a joint structure, and the method comprises the following steps: hoisting a prefabricated concrete support, hoisting the end part of the concrete support to the top surface of a pre-constructed fender post, and enabling the end surface of the concrete support to be provided with a pull buckle structure; the contact area of the concrete support and the top face of the fender post avoids an anchoring part, used for stretching into the top beam, of the top of the fender post, after the concrete support is hoisted to the end to be matched with the top face of the fender post, the top beam is poured above the fender post and the pull buckle structure, and the anchoring part on the top of the fender post stretches into the top beam. And the top beam part corresponding to the pull buckle structure also forms a pull buckle structure, the pull buckle structures of the top beam and the concrete support are engaged and matched, cyclic utilization of the concrete support is achieved by adopting the construction method, and the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of rail transit construction, and in particular to a construction method and a node structure for connecting a crown beam and a concrete support. Background Art

[0002] The statements herein merely provide background information related to the present invention and do not necessarily constitute prior art.

[0003] When the first support of the urban rail transit deep foundation pit support structure is just excavated, the retaining structure is deformed toward the inside of the foundation pit due to the water and soil pressure from the outside, and the first support is under pressure. When the foundation pit is excavated to the lower part, under the action of water and soil pressure from the outside, the lower part of the retaining structure deforms toward the inside of the foundation pit, and the upper part deforms toward the outside of the foundation pit. At this time, the first support may be under tension. In order to make the support, crown beam, and retaining structure form a solid whole, the first support generally adopts cast-in-place concrete support. The concrete support steel bars and crown beam steel bars are anchored together and cast together. After the construction of the rail transit station structure is completed, the concrete support and crown beam are all chiseled out and discarded, resulting in huge engineering waste. Summary of the invention

[0004] In view of the deficiencies in the prior art, the purpose of the present invention is to provide a construction method for a connection node between a crown beam and a concrete support and a connection node structure, thereby achieving the reuse of the concrete support and reducing the construction cost.

[0005] In order to achieve the above object, the present invention is implemented through the following technical solutions:

[0006] In a first aspect, an embodiment of the present invention provides a method for constructing a connection node between a cap beam and a concrete support, comprising the following steps:

[0007] The prefabricated concrete support is hoisted, and the end of the concrete support is hoisted to the top surface of the pre-constructed retaining pile, wherein the end surface of the concrete support is provided with a draw buckle structure, and the contact area between the concrete support and the top surface of the retaining pile avoids the steel bars at the top of the retaining pile for extending into the crown beam.

[0008] After the concrete support is hoisted to the end and matched with the top surface of the retaining pile, a crown beam is cast above the retaining pile and the support buckle structure. The anchor on the top of the retaining pile extends into the crown beam, and the crown beam part corresponding to the support buckle structure also forms a buckle structure. The crown beam and the buckle structure of the concrete support are matched.

[0009] Optionally, before pouring the cap beam, an interface agent is applied to the surface of the buckle structure of the concrete support and the end surface of the concrete support.

[0010] In a second aspect, an embodiment of the present invention provides a method for constructing a connection node between a cap beam and a concrete support, comprising the following steps:

[0011] Casting a first crown beam portion on the top surface of the pre-constructed retaining pile, and the anchoring piece on the top of the retaining pile extends into the cast first crown beam portion;

[0012] The prefabricated concrete support is hoisted, and the end of the concrete support is hoisted to the top surface of the first crown beam portion, wherein the end surface of the concrete support is provided with a buckle structure;

[0013] After the concrete support is hoisted to the end and matched with the top surface of the first crown beam part, the second crown beam part is cast above the first crown beam part and the first buckle structure, and the second crown beam part corresponding to the buckle structure also forms a buckle structure, and the second concrete support and the buckle structure of the second crown beam part are matched.

[0014] Optionally, before pouring the second crown beam portion, an interface agent is applied to the surface of the buckle structure of the concrete support and the end surface of the concrete support.

[0015] Optionally, the buckle structure at the end of the concrete support includes a first protrusion arranged on the end surface of the concrete support, the first protrusion extends along the axial direction of the concrete support, and a second protrusion is vertically arranged at the outer end of the first protrusion.

[0016] Optionally, the first protrusion is arranged at the lower part of the end surface of the concrete support, and the bottom surface of the first protrusion is flush with the bottom surface of the concrete support.

[0017] Optionally, the inner side surface of the second protrusion forms a set acute angle with the axis of the second protrusion, and the distance between the top end and the concrete support end surface is smaller than the distance between the bottom end and the concrete support end surface.

[0018] Optionally, the buckle structure at the end of the concrete support is integrally cast with the concrete support.

[0019] Optionally, the retaining piles are of reinforced concrete structure, with internal steel bars extending above the top surface of the retaining piles, and the steel bars above the top surface of the retaining piles serve as anchors.

[0020] In a third aspect, an embodiment of the present invention provides a connection node structure between a crown beam and a concrete support, which is constructed using the construction method for a connection node between a crown beam and a concrete support described in the first aspect or the second aspect.

[0021] The beneficial effects of the present invention are as follows:

[0022] 1. The construction method of the crown beam and concrete support node of the present invention is that the concrete support is prefabricated, and a buckle structure is provided at its end. The crown beam is cast after it is hoisted to the top surface of the retaining pile, or the first crown beam part is cast on the top surface of the retaining pile in advance, and the second crown beam part is cast after the end of the concrete support is hoisted to the top surface of the first crown beam part. When the crown beam is cast on the buckle structure, the buckle structure is also formed. The crown beam and the concrete support cooperate with each other through the buckle. When the retaining pile is deformed outward, the tensile force can be borne by the buckle structure. When the retaining pile is deformed inward, the pressure is borne by the end face of the concrete support. Since the crown beam and the concrete support are not cast in one piece, after the subsequent construction is completed, the crown beam can be chiseled out and the concrete support can be recycled for reuse, which greatly reduces the construction cost.

[0023] 2. The construction method of the crown beam and concrete support node of the present invention is to apply an interface agent on the surface of the buckle structure of the concrete support and the end face of the concrete support, and then cast the crown beam or the second crown beam part. When the crown beam or the second crown beam part is removed later, it is convenient to separate the concrete support from the crown beam or the second crown beam part. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] The accompanying drawings in the specification, which constitute a part of the present invention, are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute improper limitations on the present invention.

[0025] Figure 1 is a flow chart of the construction method of embodiment 1 of the present invention;

[0026] Figure 2 It is a top view of the connection node between the crown beam and the concrete support after the construction of Example 1 of the present invention is completed;

[0027] Figure 3 The present invention Figure 2 A-direction cross-sectional diagram;

[0028] Figure 4 is a flow chart of the construction method of embodiment 2 of the present invention;

[0029] Figure 5 This is a schematic diagram of the connection node between the red lotus crown beam and the concrete support after construction is completed in Example 2 of the present invention;

[0030] Among them, 1. concrete support, 2. buckle structure, 3. crown beam, 4. retaining piles, 5. first crown beam part, 6. second crown beam part. DETAILED DESCRIPTION

[0031] Example 1

[0032] This embodiment provides a construction method for connecting a crown beam with a concrete support. Figure 1 As shown, the following steps are included:

[0033] Step 1: Pre-construct the retaining pile 4. The top of the retaining pile 4 is provided with an anchor extending above the top surface of the retaining pile. The anchor is used to extend into the crown beam 3 to achieve anchoring and fixation of the retaining pile 4 and the crown beam 3. In this embodiment, the retaining pile 4 adopts a reinforced concrete pile. The top of the steel bar in the retaining pile 4 extends above the top surface of the retaining pile 4, and the part of the steel bar located above the top surface of the retaining pile 4 forms an anchor.

[0034] Step 2: hoist the prefabricated concrete support 1 so that the end of the concrete support 1 matches the top surface of the retaining pile 4.

[0035] In this embodiment, the concrete support 1 adopts a reinforced concrete structure and is prefabricated in a factory. After prefabrication, it is transported to the construction site for use.

[0036] The end face of the concrete support 1 is provided with a buckle structure 2, which is integrally cast with the concrete support 1. The buckle structure 2 adopts an L-shaped structure, including a first protrusion and a second protrusion. The inner end of the first protrusion is vertically and integrally connected to the end face of the concrete support 1, and the outer end of the first protrusion is vertically provided with a second protrusion, and the second protrusion is extended upward. In this embodiment, the inner end of the first protrusion is arranged at the lower part of the end face of the concrete support, and its bottom surface is flush with the bottom surface of the concrete support.

[0037] The inner side surface of the second protrusion forms a set acute angle with the axis of the second protrusion, and is an inclined surface. The distance between the top end and the end surface of the concrete support 1 is smaller than the distance between the bottom end and the end surface of the concrete support 1.

[0038] After the crown beam 3 is cast above the buckle structure 2, a buckle structure matching the buckle structure 2 at the end of the concrete support 1 can be formed. The crown beam 3 and the buckle structure at the end of the concrete support 1 are engaged with each other, so that the concrete support 1 can withstand pressure and tension.

[0039] In this embodiment, when the concrete support 1 is hoisted, the contact area with the top surface of the retaining pile 4 should avoid the steel bars above the top surface of the retaining pile 4 that serve as anchors. Therefore, for the retaining pile 4 that cooperates with the concrete support 1, there are requirements for the setting position of the steel bars that serve as anchors. The position must leave an area on the top surface of the retaining pile that cooperates with the concrete support 1. For the retaining pile 4 that does not cooperate with the concrete support 1, there are no requirements for the setting position of the steel bars that serve as anchors.

[0040] Step 3: After the concrete support 1 is hoisted into place, an interface agent is applied on the surface of the buckle structure 2 and the end face of the concrete support 1. After the interface agent is applied, a crown beam 3 is cast in the space above the retaining pile 4 and the buckle structure 2 of the concrete support 1. The inner side of the crown beam 3 fits with the end face of the concrete support 1, the outer side is flush with the outer side of the retaining pile 4, and the top surface is flush with the top surface of the concrete support 1. The steel bars extending above the top surface of the retaining pile 4 are buried in the crown beam 3 cast later, thereby realizing the anchoring and fixation of the retaining pile 4 and the crown beam 3.

[0041] After the crown beam 3 is cast, a buckle structure matching the buckle structure 2 of the concrete support 1 is formed. The two buckle structures engage with each other. When the retaining pile 4 deforms outward, the tensile force can be borne through the buckle structure. When the retaining pile 4 deforms inward, the pressure is borne through the end face of the concrete support 1.

[0042] like Figure 2-Figure 3 As shown, after the concrete of the crown beam 3 reaches the set strength, the construction of the connection node structure between the crown beam 3 and the concrete support 1 is completed.

[0043] After the concrete support 1 is used, the cap beam 3 can be chiseled off, and then the concrete support 1 can be recovered for reuse. Since the interface agent is applied, the cap beam 3 and the concrete support 1 can be easily separated.

[0044] The construction method of this embodiment solves the problem that the concrete support and the crown beam cannot be separated after being cast together. Through the connection method of the drawstring structure, in conjunction with the prefabricated concrete support 1, the concrete support 1 can be removed after the crown beam 3 is chiseled out after use, thereby achieving the recycling of the concrete support 1, which plays a beneficial role in the green, low-carbon, energy-saving and environmental protection of urban rail transit.

[0045] Example 2

[0046] This embodiment provides a construction method for a joint structure between a crown beam and a concrete support. Figure 4 As shown, the following steps are included:

[0047] Step a: Pre-construct the retaining pile 4. The top of the retaining pile 4 is provided with an anchor extending to above the top surface of the retaining pile. The anchor is used to extend into the crown beam to achieve anchoring and fixation of the retaining pile and the crown beam. In this embodiment, the retaining pile 4 adopts a reinforced concrete pile. The top of the steel bar in the retaining pile extends above the top surface of the retaining pile, and the part of the steel bar located above the top surface of the retaining pile forms an anchor.

[0048] Step b: Cast the first crown beam 5 on the top surface of the constructed retaining pile, and the steel bars extending above the top surface of the retaining pile 4 are buried in the first crown beam 5 cast later, thereby achieving the anchoring and fixation of the first crown beam 5 and the retaining pile 4. The inner side surface of the first crown beam 5 is flush with the inner side surface of the retaining pile 4, and the outer side surface is flush with the outer side surface of the retaining pile 4.

[0049] Step c: After the first crown beam portion 5 reaches the set strength, the concrete support 1 is hoisted so that the end of the concrete support 1 is matched with the top surface of the first crown beam portion 5, and the matching position is not required.

[0050] The end surface of the concrete support 1 is provided with a buckle structure 2, which is the same as the buckle structure in the embodiment 1 and will not be described again here.

[0051] Step d: Apply an interface agent on the surface of the buckle structure 2 of the concrete support 1 and the end surface of the concrete support 1. After the interface agent is applied, cast the second crown beam part 6 on the second crown beam part 5 and the buckle structure 2 of the concrete support 1. The top surface of the second crown beam part 6 is flush with the top surface of the concrete support 1, the inner side surface is in contact with the end surface of the concrete support 1, and the outer side surface is flush with the outer side surface of the retaining pile 4. The second crown beam part 6 and the first crown beam part 5 together constitute a crown beam. Figure 5 As shown, after the second crown beam portion 6 reaches the set strength, the construction of the connection node structure between the crown beam and the concrete support 1 is completed.

[0052] After the concrete support is used, the second crown beam portion 6 can be chiseled off, and then the concrete support 1 can be recovered for reuse. Since the interface agent is applied, the second crown beam portion 6 and the concrete support 1 can be easily separated.

[0053] The construction method of this embodiment solves the problem that the concrete support and the crown beam cannot be separated after being cast together. Through the connection method of the drawstring structure, in conjunction with the prefabricated concrete support 1, the concrete support 1 can be taken out after the crown beam is chiseled out after use, thereby achieving the recycling of the concrete support 1, which plays a beneficial role in the green, low-carbon, energy-saving and environmental protection of urban rail transit.

[0054] Example 3

[0055] This embodiment provides a connection node structure between a crown beam and a concrete support, such as Figure 2-Figure 3 As shown, it is constructed using the construction method of the crown beam and concrete support connection node described in Example 1.

[0056] Example 4

[0057] This embodiment provides a connection node structure between a crown beam and a concrete support, such as Figure 5 As shown, it is constructed using the construction method of the crown beam and concrete support connection node described in Example 2.

[0058] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A construction method for connecting a crown beam with a concrete support node. It is characterized in that The following steps are involved: The prefabricated concrete support is hoisted, and the end of the concrete support is hoisted to the top surface of the pre-constructed retaining pile, wherein the end surface of the concrete support is provided with a buckle structure, and the contact area between the concrete support and the top surface of the retaining pile avoids the anchor piece at the top of the retaining pile for extending into the crown beam; After the concrete support is hoisted to the end and matched with the top surface of the retaining pile, the crown beam is cast above the retaining pile and the buckle structure. The anchor on the top of the retaining pile extends into the crown beam, and the part of the crown beam corresponding to the buckle structure also forms a buckle structure. The crown beam and the buckle structure of the concrete support are engaged with each other.

2. A construction method for connecting a crown beam to a concrete support as claimed in claim 1, It is characterized in that Before pouring the crown beam, apply interface agent on the surface of the buckle structure of the concrete support and the end face of the concrete support.

3. A construction method for connecting a crown beam with a concrete support node. It is characterized in that The following steps are involved: Casting a first crown beam portion on the top surface of the pre-constructed retaining pile, and the anchoring piece on the top of the retaining pile extends into the cast first crown beam portion; The prefabricated concrete support is hoisted, and the end of the concrete support is hoisted to the top surface of the first crown beam portion, wherein the end surface of the concrete support is provided with a buckle structure; After the concrete support is hoisted to the end and matched with the top surface of the first crown beam part, the second crown beam part is cast above the first crown beam part and the first buckle structure, and the second crown beam part corresponding to the buckle structure also forms a buckle structure, and the second concrete support and the buckle structure of the second crown beam part are engaged with each other.

4. A construction method for connecting a crown beam with a concrete support as claimed in claim 3, It is characterized in that Before pouring the second crown beam, apply interface agent on the surface of the buckle structure of the concrete support and the end face of the concrete support.

5. A construction method for a connection node between a crown beam and a concrete support as claimed in claim 1 or 3, It is characterized in that The buckle structure at the end of the concrete support comprises a first protrusion arranged on the end surface of the concrete support, the first protrusion extends along the axial direction of the concrete support, and a second protrusion is vertically arranged at the outer end of the first protrusion.

6. A construction method for connecting a crown beam with a concrete support as claimed in claim 5, It is characterized in that The first protrusion is arranged at the lower part of the end surface of the concrete support, and the bottom surface of the first protrusion is flush with the bottom surface of the concrete support.

7. A construction method for connecting a crown beam with a concrete support as claimed in claim 5, It is characterized in that The inner side surface of the second protrusion forms a set acute angle with the axis of the second protrusion, and the distance between the top end and the concrete support end surface is smaller than the distance between the bottom end and the concrete support end surface.

8. A construction method for a connection node between a crown beam and a concrete support as claimed in claim 1 or 3, It is characterized in that The buckle structure at the end of the concrete support is integrally cast with the concrete support.

9. A construction method for a connection node between a crown beam and a concrete support as claimed in claim 1 or 3, It is characterized in that The retaining pile adopts a reinforced concrete structure, and the internal steel bars thereof extend above the top surface of the retaining pile, and the steel bar portion above the top surface of the retaining pile serves as an anchor.

10. A connection node structure between a crown beam and a concrete support, It is characterized in that The method for connecting a crown beam and a concrete support is used for construction.