Roof extruded polystyrene board heat preservation construction method
Through detailed construction processes and bonding methods, the problem of difficulty in ensuring the construction progress and quality of roof extruded polystyrene boards has been solved, and fast and high-quality roof extruded polystyrene board insulation construction has been achieved.
Patent Information
- Application Number
- CN202410979051.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-22
- Publication Date
- 2024-10-01
AI Technical Summary
The existing technology lacks specialized construction methods for roofing extruded polystyrene boards, making it difficult to guarantee construction progress and quality.
The methods include water seepage test and no leakage inspection, base cleaning, detailed treatment of the inner and outer corners, application of cold base oil, paving of self-adhesive polymer modified asphalt waterproofing membrane, ceramsite concrete slope finding, and laying of extruded polystyrene sheets for insulation. The construction process of two-way steel bars inside the layer, cement mortar isolation layer and fine stone concrete ensures the integrity, bonding method and application method of the extruded board.
It realizes the rapid construction of roof extruded polystyrene boards, ensures the construction quality, and ensures the integrity, flatness and sealing of the boards.
Abstract
Description
Technical Field
[0001] The invention relates to a roof extruded polystyrene board insulation construction method, belonging to the technical field of building construction methods. Background Art
[0002] With the development of social economy, energy problems have become increasingly serious, both from the perspective of the entire international economic climate and China's macroeconomic trends. Building energy consumption has accounted for about 28% of the country's total energy consumption, so energy conservation is imperative. The country has accordingly formulated and issued a series of measures and regulations for energy conservation and emission reduction.
[0003] Building materials with energy-saving and environmental protection concepts are increasingly supported by the country and favored by the market, such as thermal insulation rock wool boards, modified foam water-heating insulation boards, extruded polystyrene boards, etc. Among them, extruded boards are widely used in dry wall insulation, flat concrete roofs and steel structure roofs, low-temperature storage floors, low-temperature floor radiant heating pipes, parking platforms, airport runways, highways and other fields for moisture-proof insulation, and control of ground frost heave. They are inexpensive and high-quality insulation and moisture-proof materials in the construction industry. However, when it is applied to roof insulation construction, there is currently no set of roof insulation construction methods for this material. It is difficult to ensure construction progress and quality using conventional roof construction methods. Summary of the invention
[0004] The purpose of the present invention is to provide a roof extruded polystyrene board insulation construction method, which can realize the rapid construction of the roof extruded polystyrene board and ensure the construction quality during the construction process.
[0005] The technical solution of the present invention is a roof extruded polystyrene board insulation construction method, which includes the following processes: water seepage test for leakage inspection → base cleaning → detail inspection and treatment of concave and convex corners → coating of cold primer → non-solidified asphalt → paving of self-adhesive polymer modified asphalt waterproofing membrane → ceramsite concrete slope adjustment → paving of extruded polystyrene board insulation layer → cement mortar isolation layer → fine stone concrete with bidirectional steel bars.
[0006] In the aforementioned roof extruded polystyrene board insulation construction method, the roof extruded polystyrene board is directly laid on the slope layer by means of adhesive dry laying, and the laying requirements are generally from bottom to top, in the horizontal direction; the integrity of each extruded board must be ensured during laying, and the board should not be broken or missing edges and corners. If there are missing edges and corners, or broken unevenly, they should be sawed flat before use; using the staggered splicing method, the edge thickness of adjacent extruded boards should be kept consistent, and the boards should be squeezed tightly without leaving gaps. If there are gaps between the boards, they can be filled with the same type of material; after the splicing is completed, the gaps should be filled with the same type of material.
[0007] In the aforementioned roof extruded polystyrene board insulation construction method, the bonding mortar of the roof extruded polystyrene board should ensure that no sand, accelerator, or antifreeze is added, and it should be placed in a cool place. The polymer mortar should be stirred and left to stand for 5 minutes, and then stirred again before use. The mortar should be mixed as it is used, and the stirred mortar should be used up within 2 hours.
[0008] In the aforementioned roof extruded polystyrene board insulation construction method, the extruded polystyrene board should be pasted horizontally from bottom to top; the vertical seams should be staggered by 1 / 2 of the board length row by row, and the local minimum staggered seam should be ≥100mm. If necessary, cutting should be carried out, and standard sizes should be used as much as possible, with a cutting size error of ±1.5mm.
[0009] In the aforementioned roof extruded polystyrene board insulation construction method, the adhesive mortar should be applied on the extruded polystyrene board, not on the base layer, and the glue coating area should be ≥40%. When the size is 50mm×10mm, the peripheral glue coating is adopted; when the size is 100mm×10mm and the center distance is 200mm, the middle point coating is adopted; when the size is 10mm×10mm and the strip spacing is 50mm, the strip coating method is adopted, and the side shall not be coated with glue.
[0010] In the aforementioned roof extruded polystyrene board insulation construction method, the extruded polystyrene board should be pasted immediately after being coated with glue, gently rubbed and slid into place, and flattened with a ruler. Local pressure is prohibited.
[0011] In the aforementioned roof extruded polystyrene board insulation construction method, the boards should be squeezed tightly, adjacent boards should be flush, the gap between boards should be ≤2mm, and the height difference between boards should be ≤1.5mm; when the gap between boards is larger than 2mm, it should be filled with insulation strips and should not be filled directly with glue; when the height difference between boards is larger than 1.5mm, they should be polished flat and the residual glue should be scraped off immediately after gluing.
[0012] Beneficial effects of the present invention: Compared with the prior art, the present invention provides a detailed description of the process flow of extruded polystyrene boards, bonding methods, usage and application methods of adhesives, extruded polystyrene boards and other aspects. By carrying out construction in accordance with the above-mentioned process requirements of the present invention, rapid construction of roof extruded polystyrene board insulation construction projects can be achieved, and construction quality can be guaranteed. DETAILED DESCRIPTION
[0013] The present invention will be further described below in conjunction with the embodiments, but they are not intended to limit the present invention.
[0014] The embodiment of the present invention: the construction process of roof extruded polystyrene board insulation engineering mainly involves the following aspects: Material preparation: According to the overall construction schedule and the material and labor analysis in the construction budget, prepare the material usage plan required for the project and make preliminary preparations for material preparation and supply.
[0015] Organize the materials to enter the site in batches according to the plan. After the materials enter the site, the construction party and the construction party jointly take samples, and the supervision party witnesses the sampling and inspection. They are allowed to be used only after the inspection meets the requirements of the specifications. Calculate the required materials according to the waterproofing area to ensure that the reserved materials can meet the needs of on-site construction to the maximum extent.
[0016] First of all, the base needs to be cleaned without dust, oil, or other materials. Clean the dust and impurities on the surface of the base first. If the base is uneven or has gaps, we can fill it with putty and then use cement mortar to level it. After the base is dry, lay the insulation extruded board.
[0017] Roof insulation extruded board is a hard board made of polystyrene resin, which is continuously extruded and foamed by a process. It has a closed bubble structure inside, and has the characteristics of heat insulation, insulation, high rigidity, translucency, water resistance and chemical corrosion resistance.
[0018] Roof insulation board process flow: After the water seepage test, check for leakage → clean the base → check and treat the details such as the inner and outer corners → apply cold primer → 2.0 thick non-curing asphalt → lay 3.0 thick self-adhesive polymer modified asphalt waterproof membrane → ceramsite concrete slope → lay 50mm thick extruded polystyrene board insulation layer → 20 thick 20 thick 1:3 cement mortar isolation layer → 40mm thick C20 fine stone concrete with Ф6 (level 3) @250 bidirectional steel bars, and set 20 wide partition joints according to the longitudinal and transverse directions of 6M, recessed 40, fill the joints with asphalt paste, and make a cloth and two coating covering strips with a width of 300mm on the seam edge.
[0019] Construction requirements: 1) Adopt the bonding dry paving method and directly pave it on the slope layer. The paving requirements are generally from bottom to top, paving in the horizontal direction; when paving, the integrity of each extruded board must be ensured, and the board should not be broken or missing edges and corners. If there are missing edges and corners, or broken unevenly, they should be sawed flat before use. When using the staggered splicing method, the edge thickness of adjacent extruded boards should be consistent, and the boards should be squeezed tightly without leaving gaps. If there are gaps between the boards, they can be filled with the same type of material. After the splicing is completed, the gaps should be filled with the same type of material to ensure the closure of the entire plane, which can be insulated, water-resistant, and chemically resistant.
[0020] 2) Make sure that no other additives such as sand, accelerator, antifreeze agent, etc. are added to the adhesive mortar, and place it in a cool place. Stir the polymer mortar, let it stand for 5 minutes, and stir it again before use. The mortar should be mixed as it is used, and the stirred mortar should be used up within 2 hours.
[0021] 3) Extruded boards should be pasted horizontally from bottom to top. Vertical seams should be staggered by 1 / 2 board length row by row, and the local minimum staggered seam should not be less than 100mm. Cut when necessary, and try to use standard size, with a cutting size error of ±1.5mm.
[0022] 4) The adhesive mortar should be mixed with water in a certain proportion and stirred evenly until it reaches a certain consistency before it can be used; the adhesive mortar should be applied on the extruded board, not on the base layer, and the adhesive coating area should not be less than 40%. The adhesive coating method is to apply glue around the periphery (50mm×10mm), apply glue in the middle (100mm×10mm with a center distance of 200mm) or apply glue in strips (10mm×10mm with a strip spacing of 50mm), and glue shall not be applied on the side.
[0023] 5) After applying glue, the extruded board should be pasted immediately, gently rub and slide it into place, flatten it with a ruler, and do not press hard on some parts to ensure flatness and firm pasting.
[0024] 6) The boards should be squeezed tightly together, the adjacent boards should be flush, the gap between boards should not be greater than 2mm, and the height difference between boards should not be greater than 1.5mm. When the gap between boards is greater than 2mm, fill it with insulation strips, and do not use glue to fill the gap directly. If the height difference between boards is greater than 1.5mm, they should be polished and smooth, and the residual glue should be scraped off immediately after gluing.
Claims
1. A roof extruded polystyrene board insulation construction method, characterized in that: The following processes are included: water seepage test to check for leakage → base cleaning → detailed inspection and treatment of concave and convex corners → application of cold primer → non-curing asphalt → laying of self-adhesive polymer modified asphalt waterproof membrane → slope adjustment of expanded clay concrete → laying of extruded polystyrene board insulation layer → cement mortar isolation layer → fine stone concrete with bidirectional steel bars.
2. A roof extruded polystyrene board insulation construction method according to claim 1, characterized in that: The roof extruded polystyrene board is directly laid on the slope layer by means of adhesive dry laying. The laying requirements are generally from bottom to top and in the horizontal direction. The integrity of each extruded board must be ensured during laying. The board should not be broken or missing edges and corners. If there are missing edges and corners or uneven broken boards, they should be sawed flat before use. The staggered splicing method is used. The thickness of the edges of adjacent extruded boards should be consistent. The boards should be squeezed tightly without leaving gaps. If there are gaps between the boards, they can be filled with the same type of materials to make them dense. After the splicing is completed, the gaps should be filled with the same type of material.
3. A roof extruded polystyrene board insulation construction method according to claim 2, characterized in that: The bonding mortar of the roof extruded polystyrene board should ensure that no sand, accelerator or antifreeze is added, and it should be placed in a cool place. Stir the polymer mortar, let it stand for 5 minutes, and stir it again before use. The mortar should be mixed as it is used, and the stirred mortar should be used up within 2 hours.
4. A roof extruded polystyrene board insulation construction method according to claim 1, characterized in that: The extruded polystyrene boards should be pasted horizontally from bottom to top; the vertical seams should be staggered by 1 / 2 of the board length row by row, and the minimum local staggered seam should be ≥100mm. If necessary, they should be cut and standard sizes should be used as much as possible. The cutting size error is ±1.5mm.
5. A roof extruded polystyrene board insulation construction method according to claim 3, characterized in that: The adhesive paste should be applied on the extruded polystyrene board, not on the base layer, and the glue coating area should be ≥40%. When the size is 50mm×10mm, the peripheral glue coating should be adopted; when the size is 100mm×10mm and the center distance is 200mm, the middle point coating should be adopted; when the size is 10mm×10mm and the strip spacing is 50mm, the strip coating method should be adopted, and the side should not be glued.
6. A roof extruded polystyrene board insulation construction method according to claim 1, characterized in that: The extruded polystyrene board should be pasted immediately after being coated with glue, gently rubbed and slid into place, and flattened with a ruler. It is forbidden to press locally with force.
7. A roof extruded polystyrene board insulation construction method according to claim 1, characterized in that: The boards should be squeezed tightly together, adjacent boards should be flush, the gap between boards should be ≤2mm, and the height difference between boards should be ≤1.5mm; when the gap between boards is larger than 2mm, fill it with insulation strips and do not use glue to fill the gap directly; when the height difference between boards is larger than 1.5mm, they should be polished flat and the residual glue should be scraped off immediately after gluing.