Post-evaluation method and post-evaluation system for IT project
Through multi-dimensional analysis and evaluation of IT project post-evaluation methods, the problem of insufficient IT project post-evaluation in existing technologies has been solved, a comprehensive assessment of project goals and benefits has been achieved, the scientific and technological R&D management mechanism has been improved, and a reference for decision-making departments has been provided. .
Patent Information
- Application Number
- CN202410872086.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-01
- Publication Date
- 2024-10-01
AI Technical Summary
The existing technology lacks a quantifiable IT project post-evaluation method. It is difficult to reflect the achievement of project goals through project information and form sufficient evaluation conclusions. It is also difficult to find the reasons for project success or failure and summarize experiences and lessons.
Provides a post-evaluation method for IT projects. By determining the weights of multiple post-evaluation indicators and the weights of sub-evaluation indicators, the evaluation data value is obtained, and the evaluation score of the project is calculated, thereby conducting multi-dimensional analysis and evaluation. This method includes evaluation of strategic value, business value, financial value and technical value, and supports a combination of quantitative and qualitative evaluation indicators.
It has achieved a comprehensive analysis and evaluation of the realization of IT project goals, benefits and impacts, improved the incentive and restraint mechanism for scientific and technological research and development, and formed a virtuous cycle of enterprise-level demand overall management and full life cycle management, providing reference for decision-making departments.
Smart Images

Figure CN118735301A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of project management, and in particular to a post-evaluation method and a post-evaluation system for an IT project. Background Art
[0002] An IT project is a process of developing, implementing or improving software or hardware using information technology and computer systems. However, existing technology research and development projects lack a quantifiable post-evaluation method. That is, after the project is officially completed and has been running for a period of time, the post-evaluation method in the existing technology does not design quantitative-based and qualitative-assisted evaluation indicators based on project information. Therefore, it is difficult to objectively reflect the achievement of project goals based on business and system operation data, facts, and internal and external effective information in project management, and the evaluation conclusions formed are not sufficient.
[0003] Therefore, a post-evaluation method for the project is needed to determine whether the expected project goals have been achieved, whether the main benefit indicators have been realized, find out the reasons for the success or failure of the project, summarize the lessons learned, provide timely and effective feedback, and improve the management level of future projects. Summary of the invention
[0004] The purpose of the embodiment of the present invention is to provide an IT project post-evaluation method and post-evaluation system, which analyzes, summarizes and evaluates the project's goal achievement, benefits and impact from multiple dimensions. Then, through the post-evaluation of scientific and technological research and development projects, the incentive and constraint mechanism of scientific and technological research and development is improved, a virtuous cycle of enterprise-level demand coordination management and scientific and technological research and development project full life cycle management is formed, and a reference is provided for decision-making departments and resource allocation departments.
[0005] In order to achieve the above-mentioned purpose, an embodiment of the present invention provides a post-evaluation method for an IT project, the post-evaluation method comprising: determining a first weight of each post-evaluation indicator among multiple post-evaluation indicators of the IT project, wherein each post-evaluation indicator includes multiple sub-evaluation indicators; determining a second weight of each sub-evaluation indicator among the multiple sub-evaluation indicators; obtaining an evaluation data value of each sub-evaluation indicator; and determining an evaluation score of the IT project based on the first weight, the second weight and the evaluation data value of each sub-evaluation indicator.
[0006] Optionally, the sub-evaluation indicators include mandatory indicators and optional indicators, and the multiple sub-evaluation indicators of each post-evaluation indicator are determined by the following method: the mandatory indicators corresponding to each post-evaluation indicator in the indicator warehouse are determined as sub-evaluation indicators of the corresponding post-evaluation indicator; and according to the application scenario of the IT project, the optional indicators corresponding to each post-evaluation indicator are set, and the optional indicators are determined as sub-evaluation indicators of the corresponding post-evaluation indicator.
[0007] Optionally, the multiple post-evaluation indicators include: strategic value indicators, business value indicators, financial value indicators, and technical value indicators.
[0008] Optionally, the mandatory indicators include: strategic compliance corresponding to the strategic value indicators; patent application evaluation, information security evaluation, production incident evaluation, implementation management effect, and architecture management effect corresponding to the technical value indicators; operation and maintenance cost execution deviation and R&D cost execution deviation corresponding to the financial value indicators; and user satisfaction corresponding to the business value indicators.
[0009] Optionally, obtaining the evaluation data value of each sub-evaluation indicator includes: obtaining the evaluation data value of each sub-evaluation indicator through online connection, data entry or expert online scoring.
[0010] Optionally, determining the first weight of each of the multiple post-evaluation indicators of the IT project includes: determining one or more first post-evaluation indicators among the multiple post-evaluation indicators, and determining the post-evaluation indicators among the multiple post-evaluation indicators except the first post-evaluation indicator as second post-evaluation indicators; determining the third weight of each of the one or more first post-evaluation indicators, and determining the sum of 1 minus the third weight as a fourth weight; and evenly distributing the fourth weight among the second post-evaluation indicators.
[0011] Optionally, determining the second weight of each sub-evaluation indicator among the multiple sub-evaluation indicators includes: determining one or more first sub-evaluation indicators among the multiple sub-evaluation indicators, and determining the sub-evaluation indicators among the multiple sub-evaluation indicators except the first sub-evaluation indicators as second sub-evaluation indicators; determining the fifth weight of each first sub-evaluation indicator among the one or more first sub-evaluation indicators, and determining the sum of 1 minus the third weight as the sixth weight; and evenly distributing the sixth weight among the second sub-evaluation indicators.
[0012] On the other hand, the present invention also provides a post-evaluation system for an IT project, the post-evaluation system comprising: a first determination device for determining a first weight of each post-evaluation indicator among multiple post-evaluation indicators of the IT project, wherein each post-evaluation indicator includes multiple sub-evaluation indicators; a second determination device for determining a second weight of each sub-evaluation indicator among the multiple sub-evaluation indicators; a data acquisition device for acquiring an evaluation data value of each sub-evaluation indicator; and a third determination device for determining an evaluation score of the IT project based on the first weight, the second weight and the evaluation data value of each sub-evaluation indicator.
[0013] On the other hand, the present invention further provides a machine-readable storage medium, on which instructions are stored, and the instructions are used to enable a machine to execute: the post-evaluation method of an IT project as described above.
[0014] On the other hand, the present invention further provides a processor for running a program, wherein the program, when run, is used to execute: the post-evaluation method for IT projects as described above.
[0015] On the other hand, the present invention further provides a computer program product, comprising a computer program, which, when executed by a processor, implements: the post-evaluation method for IT projects as described above.
[0016] Through the above technical solution, the post-evaluation method provided by the present invention analyzes, summarizes and evaluates the project's goal achievement, benefits and impact from multiple dimensions. Furthermore, through the post-evaluation of scientific and technological research and development projects, the incentive and constraint mechanism of scientific and technological research and development is improved, forming a virtuous cycle of enterprise-level demand coordination management and scientific and technological research and development project full life cycle management, providing reference for decision-making departments and resource allocation departments.
[0017] Other features and advantages of the embodiments of the present invention will be described in detail in the subsequent detailed description. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The accompanying drawings are used to provide a further understanding of the embodiments of the present invention and constitute a part of the specification. Together with the following specific implementations, they are used to explain the embodiments of the present invention, but do not constitute a limitation on the embodiments of the present invention. In the accompanying drawings:
[0019] Figure 1 It is a flowchart of a post-evaluation method of an IT project provided according to an embodiment of the present invention;
[0020] Figure 2 is a structural diagram of a post-evaluation system for an IT project provided according to an embodiment of the present invention;
[0021] Figure 3 It is a schematic diagram of the internal structure of a computer device provided according to an embodiment of the present application.
[0022] Description of Reference Numerals
[0023] 200-performance testing device; 210-first determination device; 220-second determination device; 230-data acquisition device;
[0024] A01-processor; A02-network interface; A03-internal memory; A04-display screen; A05-input device; A06-non-volatile storage medium;
[0025] B01- Operating system; B02- Computer program. DETAILED DESCRIPTION
[0026] The specific implementation of the embodiment of the present invention is described in detail below in conjunction with the accompanying drawings. It should be understood that the specific implementation described here is only used to illustrate and explain the embodiment of the present invention, and is not used to limit the embodiment of the present invention.
[0027] Method Embodiment
[0028] The present invention first provides a post-evaluation method 100 for an IT project, such as Figure 1 As shown, the post-evaluation method 100 may include steps S110 - S140 .
[0029] Step S110 , determining a first weight of each post-evaluation indicator among a plurality of post-evaluation indicators of the project.
[0030] In one embodiment, the multiple post-evaluation indicators may include: strategic value indicators, business value indicators, financial value indicators, technical value indicators, etc. The above-mentioned post-evaluation indicators can be managed. For example, for the project information in the list, the maintenance interface of the project can be entered through the entrance of the "Maintenance" button. Then, the basic information of the post-evaluation model of the multiple post-evaluation indicators can be displayed and maintained, and the post-evaluation indicators can be configured in the post-evaluation model, such as adding, modifying, and removing existing post-evaluation indicators.
[0031] In addition, in one embodiment, step S110 may include steps S111 - S113 .
[0032] Step S111, determining one or more first post-evaluation indicators among a plurality of post-evaluation indicators, and determining the post-evaluation indicators other than the first post-evaluation indicators among the plurality of post-evaluation indicators as second post-evaluation indicators;
[0033] Step S112, determining a third weight of each of the one or more first post-evaluation indicators, and determining a sum of 1 minus the third weight as a fourth weight; and
[0034] Step S113, evenly distributing the fourth weight among the second post-evaluation indicators.
[0035] For example, the requirement classification tag field of project classification tag management. According to the above steps, you can first select a dimension (such as technical value indicator) as the first post-evaluation indicator; then set a weight for it, for example, set it to 40% as the third weight; finally, use the remaining three dimensions (strategic value indicator, business value indicator, financial value indicator) as the second post-evaluation indicators, and divide the remaining fourth weight 60% equally, so that the weight of each second post-evaluation indicator is 20% each.
[0036] Each post-evaluation indicator can include multiple sub-evaluation indicators, and the sub-evaluation indicators can include mandatory indicators and optional indicators. Mandatory indicators are required to be selected by default for all projects; optional indicators are added by managers of each business department.
[0037] In one embodiment, multiple sub-evaluation indicators of each post-evaluation indicator may be determined in the following manner:
[0038] 1) determining the mandatory indicators corresponding to each post-evaluation indicator in the indicator bin as sub-evaluation indicators of the corresponding post-evaluation indicator; and
[0039] 2) According to the application scenario of the project, set the optional indicators corresponding to each post-evaluation indicator, and determine the optional indicators as sub-evaluation indicators of the corresponding post-evaluation indicators.
[0040] In one embodiment, the mandatory indicators corresponding to the strategic value indicators may include: strategic compliance, etc.; the optional indicators corresponding to the strategic value indicators may include: brand value, etc. The mandatory indicators corresponding to the technical value indicators may include: patent application evaluation, information security evaluation, production event evaluation, implementation management effect, architecture management effect, etc. The mandatory indicators corresponding to the financial value indicators may include: operation and maintenance cost execution deviation, R&D cost execution deviation, etc. The mandatory indicators corresponding to the business value indicators may include: user satisfaction, etc.; the optional indicators corresponding to the business value indicators may include: automatic processing rate, platform support capability, enhanced risk control capability, etc.
[0041] Among them, the meaning of strategic compliance is: implementing the fintech strategy, improving the level of IT integration of the group, and supporting the formation of a fintech platform for the group's asset management. The data source of this indicator is, for example, the company's own data management system and the company's regular data reports. The evaluation method of this indicator is, for example, success evaluation. The target level of this indicator is, for example, to support the group integration of the company, which has been promoted and applied in the headquarters and various subsidiaries. It is an important technological means for the headquarters' strategic department to help improve the group's IT integration level and consolidate the headquarters' strategic support.
[0042] Brand value means the reputation of the enterprise in the industry. The data source of this indicator is, for example, the enterprise's own data management system and the enterprise's regular data reports. The evaluation method of this indicator is, for example, success evaluation. The target level of this indicator is, for example, to form a benchmark enterprise in the field of science and technology in the industry (such as the asset management industry) and to form a distinctive corporate identity within the enterprise group.
[0043] The meaning of automatic processing rate is to improve the automatic processing rate, effectively reduce manual processing scenarios, break the data silos of subsidiaries, and achieve data connectivity. The data source of this indicator is, for example: the company's own data management system. The evaluation method of this indicator is, for example: comparative analysis, statistical prediction, and survey experience. The target level of this indicator is, for example: the value and proportion of reduced manual processing scenarios.
[0044] The meaning of platform support capability is to enhance the platform support capability, achieve breakthroughs in investment management functions, support investment decisions, real-time net value, fast transactions, risk control priority, etc. The data source of this indicator is, for example, the enterprise's own data management system. The evaluation method of this indicator is, for example, comparative analysis, statistical prediction, and survey experience. If there is no quantitative indicator for the target level of this indicator, it is recommended to use expert scoring to set the target and evaluate it.
[0045] The meaning of enhancing risk control capability is to improve risk control capabilities before, during and after investment through real-time valuation, fund position monitoring, limit management, portfolio simulation, public opinion monitoring and performance attribution and other functions. The data source of this indicator is, for example, the company's own data management system. The evaluation method of this indicator is, for example, comparative analysis, statistical forecasting, and survey experience. The target level of this indicator is, for example, to control the amount of fund risk before, during and after investment to the set amount, or reduce the set percentage. It can also be evaluated by the achievement rate of active investment management risk fund management level.
[0046] The meaning of internal employee satisfaction is to conduct an internal employee satisfaction survey through the enterprise employee feedback channel module. The data source of this indicator is, for example, the feedback channel module (crowd innovation platform). The evaluation method of this indicator is, for example, questionnaire scoring. The target level of this indicator is, for example, the questionnaire is designed on a percentage basis, and the score is the average score of the valid questionnaires.
[0047] Step S120: determining a second weight of each sub-evaluation indicator among the plurality of sub-evaluation indicators.
[0048] In one embodiment, step S120 may include steps S121 - S123 .
[0049] Step S121, determining one or more first sub-evaluation indicators from a plurality of sub-evaluation indicators, and determining sub-evaluation indicators other than the first sub-evaluation indicator from the plurality of sub-evaluation indicators as second sub-evaluation indicators;
[0050] Step S122, determining a fifth weight of each of the one or more first sub-evaluation indicators, and determining a sum of 1 minus the third weight as a sixth weight; and
[0051] Step S123: Evenly distribute the sixth weight among the second sub-evaluation indicators.
[0052] For example, you can follow the above steps and first select a sub-evaluation indicator in a certain dimension (such as the technical value indicator in the technical value indicator) as the first sub-evaluation indicator; then set a weight for it, for example, set it to 40% as the fifth weight; finally, use the remaining four sub-evaluation indicators (information security evaluation, production incident evaluation, implementation management effect, architecture management effect) as the second sub-evaluation indicators, and divide the remaining sixth weight of 60% equally, so that the weight of each second sub-evaluation indicator is 15% each.
[0053] Step S130, obtaining the evaluation data value of each sub-evaluation indicator.
[0054] In one embodiment, step S130 may include: obtaining the evaluation data value of each sub-evaluation indicator through online connection, data entry or expert online scoring.
[0055] Specifically, for the indicator values obtained online, they can be directly obtained through docking. For the indicators that cannot be obtained online, and the evaluation and handling positions of the project requirements, click the data filling button in the list to enter the corresponding project indicator data filling interface. In addition, this step also supports setting experts to score, and the scores of the corresponding indicators are obtained after weight calculation based on the results of the expert scoring. The scores of the indicators are calculated according to the selected weight template.
[0056] It is worth noting that the acquisition, storage, use, and processing of data in the technical solution of this application are in compliance with the relevant provisions of national laws and regulations.
[0057] Step S140, determining the evaluation score of the project according to the first weight, the second weight and the evaluation data value of each sub-evaluation indicator.
[0058] Specifically, the evaluation data values of multiple sub-evaluation indicators in each post-evaluation indicator are multiplied by their corresponding second weights and then summed to obtain the score of each post-evaluation indicator, and then the score of each post-evaluation indicator is multiplied by its corresponding first weight and then summed to obtain the evaluation score of the project.
[0059] In one embodiment, according to the above four dimensions of strategic value, business value, financial value, and technical value, the dimension weights are set to a1, a2, a3, and a4, respectively, where a1+a2+a3+a4=100%.
[0060] Then, the first indicator of the strategic value dimension is set to A11, and the corresponding weight is a11; until the nth indicator of the strategic value dimension is set to A1n, and the corresponding weight is a1n. Among them, a11+a12…+a1n=100%.
[0061] And, the first indicator of the business value dimension is set to A21, and the corresponding weight is a21; until the nth indicator of the business value dimension is set to A2n, and the corresponding weight is a2n. Among them, a21+a22...+a2n=100%.
[0062] And, the first indicator of the financial value dimension is set to A31, and the corresponding weight is a31; until the nth indicator of the financial value dimension is set to A3n, and the corresponding weight is a3n. Among them, a31+a32...+a3n=100%.
[0063] And, the first indicator of the technical value dimension is set to A41, and the corresponding weight is a41; until the nth indicator of the technical value dimension is set to A4n, and the corresponding weight is a4n. Among them, a41+a42...+a4n=100%.
[0064] Finally, the sum M of the indicator scores calculated by the above indicators is the evaluation score of the project:
[0065] M=(A11*a11+A12*a12+……+A1n*a1n)*a1+
[0066] (A21*a21+A22*a22+……+A2n*a2n)*a2+
[0067] (A31*a31+A32*a32+……+A3n*a3n)*a3+
[0068] (A41*a41+A42*a42+……+A4n*a4n)*a4.
[0069] In addition, after step S140, the post-evaluation method 100 of the present invention may further include:
[0070] 1) Evaluate working papers.
[0071] The post-assessment handling post of the project demand department clicks the maintenance button in the list to enter the corresponding project assessment work paper filling interface. Then, you can fill in the assessment work paper through the project post-assessment work paper maintenance and management function entrance. Through this step, the post-assessment working group and the post-assessment comprehensive administrator can view and download all work papers. The post-assessment handling post and the post-assessment review post can also view and download all the work papers of the department. Improve the evaluation efficiency of post-evaluation through information sharing.
[0072] 2) Evaluation report output.
[0073] You can output the evaluation report through the post-project evaluation report maintenance and management function portal. For example, you can export the evaluation report in PDF format and generate the evaluation indicator table as an attachment.
[0074] The beneficial effects of the post-evaluation method provided by the embodiment of the present invention are:
[0075] The present invention can analyze, summarize and evaluate the project's goal achievement, benefits and impact from four dimensions: "strategic value, business value, financial value and technical value". This can determine whether the project's expected goals have been achieved, whether the main benefit indicators have been achieved, find out the reasons for the project's success or failure, summarize the lessons learned, and provide timely and effective feedback to improve the management level of future projects.
[0076] The present invention can also design evaluation indicators with quantitative as the main and qualitative as the auxiliary according to project information, based on the data and facts of business and system operation and internal and external valid information in project management, objectively reflect the achievement of project goals and prudently form evaluation conclusions.
[0077] Through the above-mentioned method, the present invention improves the incentive and constraint mechanism of scientific and technological research and development through post-evaluation of scientific and technological research and development projects, forms a virtuous cycle of enterprise-level demand coordination management and scientific and technological research and development project full life cycle management, and provides reference for decision-making departments and resource allocation departments.
[0078] Device Embodiment
[0079] On the other hand, the present invention also provides an IT project post-evaluation system 200, such as Figure 2 As shown, the post-evaluation system may include:
[0080] A first determining means 210, for determining a first weight of each post-evaluation indicator among a plurality of post-evaluation indicators of a project, wherein each post-evaluation indicator may include a plurality of sub-evaluation indicators;
[0081] The second determining means 220 is used to determine a second weight of each sub-evaluation indicator among the plurality of sub-evaluation indicators;
[0082] The data acquisition device 230 is used to acquire the evaluation data value of each sub-evaluation indicator; and
[0083] The third determining means 240 is used to determine the evaluation score of the project according to the first weight, the second weight and the evaluation data value of each sub-evaluation indicator.
[0084] Other beneficial effects of the post-evaluation system for IT projects of the present invention can be found in the above description of the post-evaluation method for IT projects, which will not be described in detail here.
[0085] An embodiment of the present invention further provides a machine-readable storage medium, on which instructions are stored, and the instructions are used to enable a machine to execute: the post-evaluation method for IT projects as described above.
[0086] An embodiment of the present invention provides a processor, wherein the processor is used to run a program, wherein the program, when being run, is used to execute: the post-evaluation method for an IT project as described above.
[0087] In one embodiment, a computer device is provided. The computer device may be a terminal, and its internal structure diagram may be as follows: Figure 3 As shown. The computer device includes a processor A01, a network interface A02, a display screen A04, an input device A05 and a memory (not shown in the figure) connected through a system bus. Among them, the processor A01 of the computer device is used to provide computing and control capabilities. The memory of the computer device includes an internal memory A03 and a non-volatile storage medium A06. The non-volatile storage medium A06 stores an operating system B01 and a computer program B02. The internal memory A03 provides an environment for the operation of the operating system B01 and the computer program B02 in the non-volatile storage medium A06. The network interface A02 of the computer device is used to communicate with an external terminal through a network connection. When the computer program is executed by the processor A01, a post-evaluation method of an IT project is implemented. The display screen A04 of the computer device can be a liquid crystal display or an electronic ink display, and the input device A05 of the computer device can be a touch layer covered on the display screen, or a key, trackball or touchpad set on the computer device housing, or an external keyboard, touchpad or mouse, etc.
[0088] Those skilled in the art will understand that Figure 3 The structure shown in the figure is only a block diagram of a part of the structure related to the solution of the present application, and does not constitute a limitation on the computer device to which the solution of the present application is applied. The specific computer device may include more or fewer components than those shown in the figure, or combine certain components, or have a different arrangement of components.
[0089] In one embodiment, the post-evaluation system 200 of the IT project provided by the present application can be implemented in the form of a computer program. Figure 3 The computer device shown in the figure is run. The memory of the computer device can store various program modules constituting the post-evaluation system 200 of the IT project. The computer program composed of various program modules enables the processor to execute the steps of the post-evaluation method of the IT project in various embodiments of the present application described in this specification.
[0090] Figure 3 The computer device shown can be Figure 2In the IT project post-evaluation system 200 shown, the first determining device 210 executes step S110 , the second determining device 220 executes step S120 , the data acquiring device 230 executes step S130 , and the third determining device 240 executes step S140 .
[0091] In one embodiment, the present application also provides a computer program product, which, when executed on a data processing device, is suitable for executing a program for initializing the following method steps:
[0092] 1) determining a first weight of each post-evaluation indicator among a plurality of post-evaluation indicators of the project, wherein each post-evaluation indicator includes a plurality of sub-evaluation indicators;
[0093] 2) determining a second weight of each sub-evaluation indicator in the plurality of sub-evaluation indicators;
[0094] 3) Obtaining the evaluation data value of each sub-evaluation indicator; and
[0095] 4) Determine the evaluation score of the project based on the first weight, the second weight and the evaluation data value of each sub-evaluation indicator.
[0096] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.
[0097] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.
[0098] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.
[0099] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.
[0100] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.
[0101] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.
[0102] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tape magnetic disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.
[0103] It should be noted that in the embodiments of the present application, certain software, components, models and other existing solutions in the industry may be mentioned, and they should be regarded as exemplary. Their purpose is only to illustrate the feasibility of implementing the technical solution of the present application, but it does not mean that the applicant has or will necessarily use the solution.
[0104] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.
[0105] The above are only embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various changes and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included within the scope of the claims of the present application.
Claims
1. A post-evaluation method for an IT project, characterized in that: The post-evaluation method comprises: Determining a first weight of each post-evaluation indicator among a plurality of post-evaluation indicators of the IT project, wherein each post-evaluation indicator includes a plurality of sub-evaluation indicators; Determining a second weight of each sub-evaluation indicator in the plurality of sub-evaluation indicators; Obtaining the evaluation data value of each sub-evaluation indicator; and An evaluation score of the IT project is determined according to the first weight, the second weight, and the evaluation data value of each sub-evaluation indicator.
2. The post-evaluation method according to claim 1, characterized in that: The sub-evaluation indicators include mandatory indicators and optional indicators, and the multiple sub-evaluation indicators of each post-evaluation indicator are determined by the following method: Determine the mandatory indicators corresponding to each post-evaluation indicator in the indicator bin as sub-evaluation indicators of the corresponding post-evaluation indicator; and According to the application scenario of the IT project, a self-selected indicator corresponding to each post-evaluation indicator is set, and the self-selected indicator is determined as a sub-evaluation indicator of the corresponding post-evaluation indicator.
3. The post-evaluation method according to claim 2, characterized in that: The multiple post-evaluation indicators include: Strategic value indicators, business value indicators, financial value indicators, and technical value indicators.
4. The post-evaluation method according to claim 3, characterized in that: The required indicators include: The strategic conformity corresponding to the strategic value indicator; Patent application evaluation, information security evaluation, production incident evaluation, implementation management effect, and architecture management effect corresponding to the technical value indicators; The operation and maintenance cost execution deviation and the R&D cost execution deviation corresponding to the financial value indicator; and User satisfaction corresponding to the business value indicator.
5. The post-evaluation method according to claim 1, characterized in that: The step of obtaining the evaluation data value of each sub-evaluation indicator comprises: The evaluation data value of each sub-evaluation indicator is obtained through online connection, data entry or expert online scoring.
6. The post-evaluation method according to claim 1, characterized in that: Determining a first weight of each post-evaluation indicator of the IT project includes: Determining one or more first post-evaluation indicators among the plurality of post-evaluation indicators, and determining post-evaluation indicators other than the first post-evaluation indicators among the plurality of post-evaluation indicators as second post-evaluation indicators; determining a third weight of each of the one or more first post-evaluation indicators, and determining a sum of 1 minus the third weight as a fourth weight; and The fourth weight is evenly distributed among the second post-evaluation indicators.
7. The post-evaluation method according to claim 1, characterized in that: Determining the second weight of each sub-evaluation indicator in the plurality of sub-evaluation indicators comprises: Determine one or more first sub-evaluation indicators from the plurality of sub-evaluation indicators, and determine sub-evaluation indicators other than the first sub-evaluation indicators from the plurality of sub-evaluation indicators as second sub-evaluation indicators; determining a fifth weight of each of the one or more first sub-evaluation indicators, and determining a sum of 1 minus the third weight as a sixth weight; and The sixth weight is evenly distributed among the second sub-evaluation indicators.
8. A post-evaluation system for IT projects, characterized in that: The post-evaluation system comprises: A first determining means, for determining a first weight of each post-evaluation indicator among a plurality of post-evaluation indicators of the IT project, wherein each post-evaluation indicator includes a plurality of sub-evaluation indicators; A second determining means, configured to determine a second weight of each sub-evaluation indicator among the plurality of sub-evaluation indicators; A data acquisition device, used to acquire the evaluation data value of each sub-evaluation indicator; and The third determining means is used to determine the evaluation score of the IT project according to the first weight, the second weight and the evaluation data value of each sub-evaluation indicator.
9. A machine-readable storage medium, characterized in that: The machine-readable storage medium stores instructions, which are used to enable a machine to execute: a post-evaluation method for an IT project according to any one of claims 1-7.
10. A processor, characterized in that: Used to run a program, wherein the program, when run, is used to execute: a post-evaluation method for an IT project according to any one of claims 1-7.
11. A computer program product, comprising a computer program, characterized in that When the computer program is executed by a processor, the computer program implements: the post-evaluation method of an IT project according to any one of claims 1 to 7.