A prefabricated beam yard high-efficiency positioning beam hanging device and use method
By using an efficient beam lifting and hanging device combined with mechanical clamping and positioning tracker in the prefabricated beam field, the problem of complex sliding and operation of prefabricated beams during transportation is solved, and safety and efficiency are improved.
Patent Information
- Application Number
- CN202411253612.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-09
- Publication Date
- 2024-11-22
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In bridge construction, during the lifting and hanging of prefabricated beams, the rope structure is prone to break, causing prefabricated beams to tilt and slide, which is complicated to operate, affecting safety and efficiency.
A prefabricated beam field efficient positioning beam lifting device is designed, and a combination of mechanical clamping and positioning tracker is used to realize mechanical clamping and visual positioning of prefabricated beams through the mobile vehicle and plywood structure to ensure beam lifting and hanging safety and efficiency.
It effectively reduces the sliding and operating time of prefabricated beams, improves the safety and efficiency of lifting beams, and ensures the stability and accuracy of prefabricated beams during transportation.
Smart Images

Figure CN118753996B_ABST
Abstract
Description
Technical Field
[0001] The invention discloses a high-efficiency positioning beam lifting and hanging device for a prefabricated beam yard and a use method thereof, belonging to the technical field of cranes. Background Art
[0002] At present, in bridge construction, prefabricated beams are generally prepared in factories and then transported to the construction site for installation and fixation according to the design requirements. At present, there are a large number of beams in the prefabricated beam yard. When transporting prefabricated beams, they are generally searched in the prefabricated beam yard first, and then the prefabricated beams are lifted and hung on the carriage of the transport vehicle in the prefabricated beam yard by a beam lifting crane, and then the prefabricated beams are transported to the construction site by the transport vehicle;
[0003] At present, cranes for lifting beams generally use rope structures to bundle and lift precast beams. However, due to factors such as relative movement between the rope structure and the edges of the precast beams, the rope structure is prone to breakage and the precast beams may tilt, resulting in a high probability of the precast beams slipping. In addition, the bundling operation of the rope structure is relatively complicated, which increases the process and time of lifting beams, affects the lifting beam effect, and has poor safety. Summary of the invention
[0004] In view of the problems in the prior art, the present invention provides a high-efficiency positioning beam lifting and hanging device for a prefabricated beam yard and a use method thereof.
[0005] The technical solution adopted by the present invention to solve the technical problem is: a prefabricated beam yard high-efficiency positioning beam lifting and hanging device, comprising a top plate, two A-shaped frames are symmetrically installed at the lower end of the top plate, two moving vehicles are symmetrically arranged at the lower ends of the two A-shaped frames, a first shaft is arranged in the middle of the lower end of the top plate, the outer end of the first shaft is rotatably connected to a function board, and the function board is attached to the lower end of the top plate, the function board is located between the two A-shaped frames, a lifting member is installed at the lower end of the function board, a driving member is arranged at the lower end of the lifting member, two clamping plates are symmetrically installed on the lower side of the driving member, a guide member is arranged at the outer end of the driving member, and the guide member is located outside the two clamping plates;
[0006] A second rectangular cylinder is installed at the inner end of the lower part of the two clamps, and a second bevel gear is arranged on the upper side of the two second rectangular cylinders. The inside of the two second rectangular cylinders are rotatably connected to the fourth roller, and the fourth roller extends out of the second rectangular cylinder toward the inner side, and the shafts of the two fourth rollers pass through the two second rectangular cylinders respectively and are connected to the two second bevel gears respectively. The two clamps are rotatably connected to the second rollers towards the inner end, and the second rollers are located on the upper side of the second rectangular cylinder, and the first bevel gear is arranged at the inner end of the two second rollers, and the lower right end of the first bevel gear is meshed with the upper left end of the second bevel gear, and the first driving device is installed at the outer end of the two clamps, and the output shafts of the two first driving devices pass through the two clamps respectively and are connected to the two second rollers respectively.
[0007] Furthermore, the interiors of the two second rectangular tubes are equidistantly connected to a plurality of third rollers, and the third rollers are located behind the fourth roller, and the plurality of third rollers extend inward from the second rectangular tube, and the two clamps are equidistantly connected to a plurality of first rollers toward the inner ends, and the first rollers are located behind the second rollers, and the plurality of first rollers are located on the upper side of the second rectangular tube.
[0008] Further, the driving member includes a first rectangular tube, the first rectangular tube is movably installed on the lower end of the lifting member, and the first rectangular tube is arranged horizontally, the left and right ends of the first rectangular tube are connected to the installation box, and the installation box is located on the upper side of the clamping plate, the two installation boxes are rotatably connected to the second bidirectional screw rods, and the second bidirectional screw rods are arranged along the length direction of the installation box, the rear outer ends of the two second bidirectional screw rods are threadedly connected to the first nut seat, the two first nut seats are respectively slidably connected in the two installation boxes, and the first nut seat extends out of the lower side of the installation box and is connected to the clamping plate located at the rear side;
[0009] The front outer ends of the two second bidirectional screws are threadedly connected to the second nut seats, and the two second nut seats are respectively slidably connected in the two mounting boxes, and the second nut seats extend out of the lower side of the mounting boxes and are connected to the clamping plate located on the front side, a sprocket is installed in the middle of the outer ends of the two second bidirectional screws, and the sprocket is located between the first nut seat and the second nut seat, the two sprockets are connected by a chain, and the chain passes through the first rectangular tube, a second driving device is arranged at the rear end of one of the mounting boxes, and the output shaft of the second driving device is connected to a second bidirectional screw.
[0010] Further, the guide member includes a straight tube, which is rotatably connected to the middle part of the front end of the first rectangular tube, and the straight tube passes through the first rectangular tube, the straight tube is located on the inner side of the chain, the front and rear ends of the straight tube are both threadedly connected to the threaded rod, and the threaded rod extends into the straight tube, and the two threaded rods are both installed with limit boxes at the outer ends, and the limit box is located between the two installation boxes, and two telescopic rods are symmetrically installed between the limit box and the first rectangular tube, and the two telescopic rods are located on the left and right sides of the straight tube;
[0011] The two limit boxes are both fitted with straight plates at the outward ends, and the upper ends of the straight plates are hinged to the upper ends of the limit boxes. Inclined plates are arranged at the lower ends of the two straight plates, and the straight plates are located on the outside of the clamping plates. The two inclined plates are in a V-shaped structure that is wider at the bottom and narrower at the top. The outer end surfaces of the two inclined plates are both recessed inward to form a through groove, and the through groove passes through the inclined plates. A conveyor belt is movably installed in the through groove, and the conveyor belt extends out of the inclined plate toward the inside. The inner wall of the conveyor belt symmetrically engages with two rollers, and the two rollers are rotatably connected in the through groove.
[0012] Furthermore, the two straight plates are symmetrically slidingly connected to the two functional blocks at the inner ends, and the functional blocks are located in the limit box. The two limit boxes are symmetrically installed with two telescopic devices at the inner ends, and the telescopic devices are located between the straight tube and the telescopic rod. The movable part of the telescopic device passes through the limit box and is movably connected to the functional blocks, and the telescopic device is located outside the first rectangular tube.
[0013] Furthermore, solar panels are installed at the middle of the outer ends of the two installation boxes, and energy storage devices are arranged at the lower ends of the two solar panels, and the two energy storage devices are electrically connected to the two solar panels respectively. Positioning trackers are installed at the lower ends of the two energy storage devices, and the two positioning trackers are electrically connected to the two energy storage devices respectively. Two light boxes are symmetrically installed at the upper end of the top plate, and the two light boxes are arranged opposite to each other, and the two light boxes are electrically connected to the two energy storage devices respectively.
[0014] Further, the lifting member includes a rectangular frame, which is arranged between the function plate and the first rectangular cylinder, and the rectangular frame is arranged horizontally, the first bidirectional screw is rotatably connected in the rectangular frame, a third driving device is installed at the right end of the rectangular frame, and the output shaft of the third driving device is connected to the first bidirectional screw, the left outer end of the first bidirectional screw is equidistantly threadedly connected to a plurality of first sliders, and the first slider is slidably connected in the rectangular frame, and the right outer end of the first bidirectional screw is equidistantly threadedly connected to a plurality of second sliders, and the second slider is slidably connected in the rectangular frame;
[0015] A first arm is movably mounted on the upper ends of multiple first sliders, and the other ends of multiple first arms are movably set at the lower end of the function board; a second arm is movably mounted on the upper ends of multiple second sliders, and the other ends of multiple second arms are movably set at the lower end of the function board, and the first arm and the second arm are in a V-shaped structure that is wide at the top and narrow at the bottom; a fourth arm is movably mounted on the lower ends of multiple first sliders, and the other ends of multiple fourth arms are movably set at the upper end of the first rectangular tube; a third arm is movably mounted on the lower ends of multiple second sliders, and the other ends of multiple third arms are movably set at the upper end of the first rectangular tube, and the third arm and the fourth arm are in a V-shaped structure that is narrow at the top and wide at the bottom.
[0016] A method for efficiently positioning and hanging beams in a prefabricated beam yard, using any one of the above-mentioned efficient positioning and hanging beams devices in a prefabricated beam yard, comprises the following steps:
[0017] The first step is pre-processing. During the box girder production process in the prefabricated beam yard, two anti-metal RFID identification chips with basic digital information such as the bridge name are embedded in the box girder, and an electronic fence is set up in the beam storage area;
[0018] The second step is visual positioning. Input the corresponding prefabricated beam information on the APP and other terminals, and use the electronic fence to make the corresponding positioning tracker receive the information, and make the corresponding four mobile vehicles move. Then use the positioning tracker to capture the information on the anti-metal RFID identification chip, and then start the corresponding two light boxes, so that the light boxes can emit flashes to achieve visual and efficient positioning beam locating operations.
[0019] The third step is to hang the lifting beam. The first rectangular tube, two installation boxes, two clamping plates and other components are moved downward by the third driving device, the first bidirectional screw rod, multiple first arms, multiple first sliders, multiple second arms, multiple second sliders, multiple third arms and multiple fourth arms, so that the two second rectangular tubes are located on both sides of the prefabricated beam. Then, the second driving device, two second bidirectional screw rods, two sprocket wheels, chains, two first nut seats and two second nut seats are used to move the two clamping plates and the two second rectangular tubes inward, thereby clamping the prefabricated beam and lifting the clamped prefabricated beam.
[0020] The fourth step is transportation. Four mobile vehicles are used to move the clamped prefabricated beam to the placement position, and then the transport vehicle is driven to the bottom of the clamped prefabricated beam and the clamped prefabricated beam is moved downward. Then the two conveyor belts are contacted with the two ends of the carriage of the transport vehicle and continue to move downward to rotate the clamped prefabricated beam, and then the clamped prefabricated beam is corrected. Two first driving devices, two first bevel gears, two second bevel gears, two second rollers, multiple first rollers, multiple third rollers and two fourth rollers are used to move the clamped prefabricated beam to the top of the carriage of the transport vehicle, and then the clamped prefabricated beam is placed on the carriage of the transport vehicle, and the clamping of the prefabricated beam is released, and then the transport vehicle is used to transport the prefabricated beam to the required position.
[0021] Beneficial effects of the present invention:
[0022] 1. The two clamping plates and the two second rectangular tubes are moved inward by using the third motor, two second bidirectional screws, two sprockets, chains, two first nut seats and two second nut seats to achieve mechanical clamping of the prefabricated beams, effectively reducing the probability of prefabricated beams slipping, effectively reducing the beam lifting and hanging process and time, effectively ensuring the beam lifting and hanging effect, and having high safety.
[0023] 2. Through the positioning tracker, the anti-metal RFID identification chip embedded in the prefabricated beam and two light boxes, visual and efficient positioning beam locating operation can be realized.
[0024] 3. By using two fourth motors, two first bevel gears and two second rollers, two second bevel gears and two fourth rollers, and with the assistance of multiple first rollers and multiple third rollers, the prefabricated beam is moved left and right to completely place the prefabricated beam on the carriage of the transport vehicle. The lifted and hung prefabricated beam can be mechanically adjusted to effectively reduce the probability of defects such as warping of the transport vehicle due to left and right misalignment between the prefabricated beam and the carriage of the transport vehicle, effectively ensure the lifting and hanging effect of the beam, and enable the prefabricated beam to be transported normally.
[0025] 4. Through the straight tube and two threaded rods, the two straight plates are moved relative to each other to adjust the distance between the two straight plates, effectively placing prefabricated beams on the carriages of transport vehicles of different widths, thereby expanding the scope of use and being highly practical.
[0026] 5. Through the electric push rod and functional block, the straight plate is rotated outward around the hinge to expose the clamping plate and other components. The clamping operation of the prefabricated beam can be observed in real time, which effectively reduces the probability of collision between the clamping plate and other components and the prefabricated beam to be clamped, and effectively ensures the lifting and hanging effect of the beam.
[0027] 6. Through two straight plates, two conveyor belts, two inclined plates and four rollers, the two threaded rods, the straight tube and the first rectangular tube and other components are rotated, so that the functional plate rotates around the first axis to achieve mechanical correction of the clamped prefabricated beam, effectively reduce the difficulty of the transport vehicle reversing to enter the clamped prefabricated beam directly below, effectively reduce the beam lifting process and time, and effectively ensure the beam lifting effect.
[0028] 7. Through two first L-shaped rods, two first plates, a lower round box, a second shaft, a second elastic member, two second L-shaped rods, two second plates, an upper round box, a first elastic member, a U-shaped positioning plate and an elastic clamping plate, the functional panels and other components can be effectively turned back to their original positions, and the functional panels and other components can be restricted in situ, effectively reducing the probability of self-rotation of the functional panels and other components, effectively ensuring the normal mechanical clamping of the precast beams on the precast beam yard, and effectively ensuring the beam lifting and hanging effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Other features, objects and advantages of the present invention will become more apparent from the detailed description of non-limiting embodiments made with reference to the following drawings:
[0030] Figure 1 It is a structural schematic diagram of a high-efficiency positioning beam lifting and hanging device for a prefabricated beam yard of the present invention;
[0031] Figure 2 It is a front view of a high-efficiency positioning beam lifting and hanging device for a prefabricated beam yard of the present invention;
[0032] Figure 3It is a cross-sectional view of a high-efficiency positioning beam lifting and hanging device for a prefabricated beam yard of the present invention;
[0033] Figure 4 It is an assembly diagram of a functional plate and a first rectangular tube in a precast beam yard high-efficiency positioning beam hanging device of the present invention;
[0034] Figure 5 It is a cross-sectional view of a first rectangular tube in a high-efficiency positioning beam lifting and hanging device for a precast beam yard of the present invention;
[0035] Figure 6 It is an assembly diagram of a clamping plate, a second bidirectional screw rod, a first nut seat and a second nut seat in a high-efficiency positioning beam lifting hanging device for a precast beam yard of the present invention;
[0036] Figure 7 It is an assembly diagram of the first rectangular tube and two straight plates in a high-efficiency positioning beam lifting and hanging device for a precast beam yard of the present invention;
[0037] Figure 8 It is an assembly diagram of a straight plate, a limit box, an electric push rod and a functional block in a high-efficiency positioning beam hanging device for a prefabricated beam yard of the present invention;
[0038] Fig. 9 It is an assembly diagram of a straight plate, a limit box, a straight tube and a threaded rod in a high-efficiency positioning beam hanging device for a prefabricated beam yard of the present invention;
[0039] Fig.10 It is a schematic diagram of another embodiment of a high-efficiency positioning beam lifting and hanging device for a precast beam yard of the present invention;
[0040] Fig.11 for Fig.10 A cross-sectional view of
[0041] Fig.12 for Fig.11 Enlarged view of part A in the middle;
[0042] Fig.13 It is an assembly diagram of a first L-shaped rod, a first plate, a second plate, an upper round box, a lower round box and a second L-shaped rod in a high-efficiency positioning beam hanging device for a precast beam yard of the present invention;
[0043] Fig.14 The present invention is a three-dimensional diagram of the top plate of a precast beam yard high-efficiency positioning beam hanging device.
[0044] In the figure: 1, functional board, 2, top board, 3, A-shaped frame, 4, first rectangular tube, 5, straight board, 11, first arm, 12, first slider, 13, rectangular frame, 14, second arm, 15, second slider, 16, first bidirectional screw, 17, first motor, 18, third arm, 19, fourth arm, 21, light box, 22, first axis, 23, first L-shaped rod, 24, first board, 25, second board, 26, upper round box, 27, lower round box, 28, second L-shaped rod, 29, second axis, 31, mobile car, 41, straight tube, 42, installation box, 43, second motor, 44, clamping plate, 45, second rectangular tube, 46, telescopic rod, 47, Tai Solar panel, 48. Positioning tracker, 49. Threaded rod, 51. Limit box, 52. Electric push rod, 53. Conveyor belt, 54. Inclined plate, 55. Through slot, 56. Roller, 57. Functional block, 201. U-shaped positioning plate, 202. Elastic splint, 261. First elastic member, 271. Second elastic member, 421. Second bidirectional screw, 422. Sprocket, 423. Chain, 424. Third motor, 425. First nut seat, 426. Second nut seat, 441. First roller, 442. First bevel gear, 443. Second roller, 444. Fourth motor, 451. Third roller, 452. Fourth roller, 453. Second bevel gear. DETAILED DESCRIPTION
[0045] In order to make the technical means, creative features, objectives and effects achieved by the present invention easy to understand, the present invention is further explained below in conjunction with specific implementation methods.
[0046] Embodiment 1: Figure 1-Figure 6 As shown, a prefabricated beam yard efficient positioning beam lifting and hanging device is provided, including a top plate 2, an A-shaped frame 3 with two mobile vehicles 31 symmetrically arranged at two lower ends is symmetrically installed on the lower end of the top plate 2, the two A-shaped frames 3 are used in conjunction with each other to lift the top plate 2, and the four mobile vehicles 31 are used in conjunction with each other to realize the mobile operation, and a first shaft 22 is set on the middle part of the lower end of the top plate 2, and the top plate 2 and the function board 1 are rotatably connected through the first shaft 22, and then the function board 1 located between the two A-shaped frames 3 and attached to the lower end of the top plate 2 is rotatably connected to the outer end of the first shaft 22, and a mounting carrier is provided for the first support arm 11 and other components through the function board 1;
[0047] A first bidirectional screw 16 is rotatably connected in a rectangular frame 13 which is arranged transversely and located between the function plate 1 and the first rectangular tube 4. The first slider 12 and the second slider 15 are relatively moved by the first bidirectional screw 16. The fixed part of the third driving device whose output shaft is connected to the first bidirectional screw 16 is installed on the right end of the rectangular frame 13. The first bidirectional screw 16 is driven to rotate by the third driving device. The third driving device can adopt a first motor 17. A plurality of first sliders 12 which are slidably connected in the rectangular frame 13 are equidistantly threadedly connected to the left outer end of the first bidirectional screw 16. The first slider 12 is used to provide a mounting carrier for the first support arm 11 and other components. A plurality of second sliders 15 which are slidably connected in the rectangular frame 13 are equidistantly threadedly connected to the right outer end of the first bidirectional screw 16. The second slider 15 is used to provide a mounting carrier for the second support arm 14 and other components.
[0048] A plurality of first arms 11 whose other ends are movably arranged at the lower end of the function board 1 are respectively movably installed on the upper ends of a plurality of first sliders 12, and the first sliders 12 are connected to the function board 1 through the first arms 11, and a plurality of second arms 14 whose other ends are movably arranged at the lower end of the function board 1 and are arranged in a V-shaped structure with the first arms 11 being wide at the top and narrow at the bottom are respectively movably installed on the upper ends of a plurality of second sliders 15, and the second sliders 15 are connected to the function board 1 through the second arms 14, and then a plurality of fourth arms 19 whose other ends are movably arranged at the upper end of the first rectangular tube 4 are respectively movably installed on the lower ends of the plurality of first sliders 12, and the first sliders 12 are connected to the first rectangular tube 4 through the fourth arms 19, and a plurality of third arms 18 whose other ends are movably arranged at the upper end of the first rectangular tube 4 and are arranged in a V-shaped structure with the fourth arms 19 being narrow at the top and wide at the bottom are respectively movably installed on the lower ends of the plurality of second sliders 15, and the second sliders 15 are connected to the first rectangular tube 4 through the third arms 18;
[0049] The left and right ends of the first rectangular tube 4 arranged transversely are connected to two installation boxes 42 located on the upper side of the clamping plate 44, respectively. The installation boxes 42 provide installation carriers for the second bidirectional screws 421 and other components. The two second bidirectional screws 421 arranged along the length direction of the installation boxes 42 are respectively rotated and connected inside the two installation boxes 42. The first nut seat 425 and the second nut seat 426 are relatively moved by the second bidirectional screws 421, and the two nut seats extending out of the installation boxes 42, which are respectively slidably connected in the two installation boxes 42, are relatively moved. The first nut seats 425 on the lower side of 42 and connected to the clamping plate 44 on the rear side are respectively threadedly connected to the rear outer ends of the two second bidirectional screws 421, and the clamping plate 44 on the rear side is moved through the first nut seats 425, and then the two second nut seats 426 extending from the lower side of the installation box 42 and connected to the clamping plate 44 on the front side, which are respectively slidably connected to the two installation boxes 42 and extend out of the lower side of the installation box 42 and connected to the clamping plate 44 on the front side, are respectively threadedly connected to the front outer ends of the two second bidirectional screws 421, and the clamping plate 44 on the front side is moved through the second nut seats 426;
[0050] The two sprockets 422 located between the first nut seat 425 and the second nut seat 426 are respectively installed on the middle parts of the outer ends of the two second bidirectional screws 421, and the two sprockets 422 are connected by a chain 423 that penetrates the first rectangular tube 4. The two sprockets 422 and the chain 423 are used in conjunction with each other to make the second bidirectional screws 421 rotate synchronously, and the fixing part of the second driving device whose output shaft is connected to a second bidirectional screw 421 is set on the rear end of a mounting box 42, and the corresponding second bidirectional screw 421 is driven to rotate through the second driving device. The second driving device can use a third motor 424, and then the two second rectangular tubes 45 are respectively installed on the inner ends of the lower parts of the two clamping plates 44, and a mounting carrier is provided for the fourth roller 452 and other components through the second rectangular tube 45;
[0051] The two fourth rollers 452 extending from the second rectangular tube 45 toward the inside are respectively rotatably connected to the inside of the two second rectangular tubes 45, and the precast beam is moved through the fourth roller 452. The shafts of the two fourth rollers 452 pass through the two second rectangular tubes 45 respectively and are respectively connected to the two second bevel gears 453 located on the upper sides of the second rectangular tubes 45, and the fourth rollers 452 are rotated through the second bevel gears 453, and the two second rollers 443 located on the upper sides of the second rectangular tubes 45 are respectively rotatably connected to the inner ends of the two clamping plates 44, and the precast beam is moved through the second rollers 443. Then, the two first bevel gears 442 whose lower right ends are meshed with the upper left ends of the second bevel gears 453 are respectively arranged on the inner ends of the two second rollers 443, and the first bevel gears 442 and the second bevel gears 453 are used in conjunction with each other to make the second rollers 443 and the fourth rollers 452 rotate synchronously;
[0052] The fixed parts of the first driving device with two output shafts passing through the clamping plates 44 and connected to the second rollers 443 are respectively installed on the outward ends of the two clamping plates 44, and the second rollers 443 are driven to rotate through the first driving device. The first driving device can use a second motor 43, and a plurality of third rollers 451 located at the rear side of the fourth roller 452 and extending from the inside of the second rectangular cylinder 45 are evenly rotated and connected inside the two second rectangular cylinders 45. A plurality of first rollers 441 located at the rear side of the second roller 443 and located on the upper side of the second rectangular cylinder 45 are evenly rotated and connected at the inner ends of the two clamping plates 44. The first rollers 441 and the third rollers 451 are used in combination to assist the movement of the precast beam.
[0053] Two solar panels 47 are respectively installed on the middle part of the outer ends of the two installation boxes 42, and electricity is generated through the solar panels 47 through solar energy. Two battery storage devices electrically connected to the solar panels 47 are respectively set on the lower ends of the two solar panels 47. The battery storage devices provide electric energy for the positioning tracker 48 and the light box 21. Then, the two positioning trackers 48 electrically connected to the battery storage devices are respectively installed on the lower ends of the two battery storage devices, and the two light boxes 21 electrically connected to the battery storage devices arranged opposite to each other are symmetrically installed on the upper end of the top plate 2. The light box 21 is used in conjunction with the positioning tracker 48 to realize visual and efficient positioning beam finding operations.
[0054] When in use, the solar panel 47 converts sunlight into electrical energy, and stores the converted electrical energy in the electrical storage device, which provides electrical energy for the light box 21 and the positioning tracker 48. The positioning tracker 48 captures the signal of the anti-metal RFID identification chip embedded in the prefabricated beam, and then accurately locates the longitude and latitude, and then moves the four mobile vehicles 31 to move the first rectangular tube 4 to the top of the corresponding prefabricated beam, and at the same time makes the two light boxes 21 flash, so as to realize the visual and efficient positioning beam-finding operation;
[0055] Then, the first motor 17 is started to drive the first bidirectional screw 16 to rotate, thereby causing the plurality of first sliders 12 and the plurality of second sliders 15 to move outward, thereby causing the plurality of lower portions of the first support arms 11 and the plurality of lower portions of the second support arms 14 to move outward, and causing the plurality of first support arms 11 and the plurality of second support arms 14 to move downward, and at the same time causing the plurality of upper portions of the third support arms 18 and the plurality of upper portions of the fourth support arms 19 to move outward, and causing the plurality of lower portions of the third support arms 18 and the plurality of lower portions of the fourth support arms 19 to move downward, thereby causing the first rectangular tube 4 to move downward, thereby causing the two clamping plates 44 and the two second rectangular tubes 45 to move downward, thereby causing the two second rectangular tubes 45 to be located on opposite sides of the precast beam;
[0056] Then, the third motor 424 is started to drive the corresponding second bidirectional screw 421 and the sprocket 422 to rotate, and the other second bidirectional screw 421 and the sprocket 422 are rotated under the transmission of the chain 423, so that the two second bidirectional screws 421 rotate synchronously, so that the two first nut seats 425 and the two second nut seats 426 move inward, and then the two clamping plates 44 move inward, so that the two second rectangular tubes 45 move inward, and the plurality of third rollers 451 and the fourth rollers 452 contact with the outer end of the precast beam, so as to achieve mechanical clamping of the precast beam, effectively reduce the probability of the precast beam slipping, effectively reduce the beam hanging process and time, effectively ensure the beam hanging effect, and have high safety;
[0057] After the third rollers 451 and the fourth rollers 452 are in contact with the outer ends of the precast beams, the first rollers 441 and the second rollers 443 are in contact with the lower ends of the wings of the precast beams, and then the first motor 17, the first bidirectional screw 16, the first sliders 12, the second sliders 15, the first arms 11, the second arms 14, the third arms 18 and the fourth arms 19 are used to move the first rectangular tube 4 upward, thereby lifting and hanging the clamped precast beams, and then moving the clamped precast beams to the placement position by four moving vehicles 31;
[0058] Then the transport vehicle is driven to the bottom of the lifted and suspended precast beam. If the precast beam and the carriage of the transport vehicle are misaligned to the left and right, the two fourth motors 444 are started to drive the two first bevel gears 442 and the two second rollers 443 to rotate, and the two second bevel gears 453 are rotated, so that the two fourth rollers 452 are rotated, and with the assistance of the multiple first rollers 441 and the multiple third rollers 451, the precast beam is moved to the left and right, and the lifted and suspended precast beam is moved to the top of the carriage of the transport vehicle.
[0059] Then, the first motor 17, the first bidirectional screw 16, multiple first sliders 12, multiple second sliders 15, multiple first arms 11, multiple second arms 14, multiple third arms 18 and multiple fourth arms 19 are used to move the first rectangular tube 4 downward, thereby moving the lifted and suspended prefabricated beam downward and contacting with the carriage of the transport vehicle, and then through the third motor 424, two second bidirectional screws 421, two sprockets 422, chains 423, two first nut seats 425 and two second nut seats 426, the two clamping plates 44 and the two second rectangular tubes 45 are moved outward, thereby releasing the clamping of the prefabricated beam, so that the prefabricated beam can be completely placed on the carriage of the transport vehicle, and the lifted and suspended prefabricated beam can be mechanically adjusted, effectively reducing the probability of defects such as the transport vehicle tilting due to the left and right misalignment between the prefabricated beam and the carriage of the transport vehicle, effectively ensuring the beam lifting and hanging effect, and allowing the prefabricated beam to be transported normally.
[0060] Embodiment 2: A third motor 424, two second bidirectional screws 421, two sprockets 422, a chain 423, two first nut seats 425, two second nut seats 426, two clamps 44 and two second rectangular cylinders 45 are used to mechanically clamp the precast beam, and then the clamped precast beam is moved to the placement position, and then the transport vehicle is reversed to the bottom of the lifted and suspended precast beam, and the precast beam is placed on the carriage of the transport vehicle. However, when the transport vehicle is reversed to the bottom of the precast beam, it is easy for the carriage of the transport vehicle and the lifted and suspended precast beam to form an angle, resulting in multiple reverse operations generally required to ensure normal placement of the precast beam, and novice drivers have to perform more reverse operations, the operation difficulty is relatively complicated, and the lifting process and time of the precast beam will be increased.
[0061] In order to solve the above problems, Figure 1 , Figure 2 , Figure 3 , Figure 4 , Figure 5 , Figure 7 , Figure 8 and Fig. 9 As shown, the straight tube 41 that passes through the first rectangular tube 4 and is located on the inner side of the chain 423 is rotatably connected to the middle part of the front end of the first rectangular tube 4, and a mounting carrier is provided for the threaded rod 49 through the straight tube 41, and two threaded rods 49 extending into the straight tube 41 are respectively threadedly connected to the front and rear ends of the straight tube 41, and the limit box 51 is connected to the straight tube 41 through the threaded rod 49, and then the two limit boxes 51 located between the two installation boxes 42 are respectively installed on the outward ends of the two threaded rods 49, and the straight plate 5 is restricted by the limit box 51, and the two telescopic rods 46 located on the left and right sides of the straight tube 41 are symmetrically installed between the limit box 51 and the first rectangular tube 4, and the movement of the limit box 51 is guided by the telescopic rod 46;
[0062] The two upper ends of the straight plates 5 hinged to the upper ends of the limit boxes 51 are respectively fitted on the outward ends of the two limit boxes 51, and the straight plates 5 are used to provide a mounting carrier for the inclined plates 54, and the two inclined plates 54 with a V-shaped structure that is wide at the bottom and narrow at the top and located on the outer sides of the clamping plates 44 are respectively arranged on the lower ends of the two straight plates 5, and the inclined plates 54 are used to provide a processing carrier for the through grooves 55, and the outer end surfaces of the two inclined plates 54 are both recessed inward to form through grooves 55 that penetrate the inclined plates 54, and the through grooves 55 provide installation space for components such as rollers 56, and then the conveyor belt 53 extending from the inclined plates 54 to the inside is movably installed in the through grooves 55, and the guiding performance is achieved through the conveyor belt 53, and the two rollers 56 symmetrically meshed on the inner wall of the conveyor belt 53 are both rotatably connected in the through grooves 55, and the two rollers 56 are used in combination to enable the conveyor belt 53 and the inclined plates 54 to be movably installed;
[0063] Two functional blocks 57 located in the limit box 51 are symmetrically slidably connected to the inner end of the straight plate 5 through slide rails. The two functional blocks 57 are used in combination to push the straight plate 5, and the two telescopic devices are located between the straight tube 41 and the telescopic rod 46 and on the outside of the first rectangular tube 4. The fixed parts of the telescopic devices whose movable parts pass through the limit box 51 and are movably connected to the functional blocks 57 are symmetrically installed on the inner end of the limit box 51. The functional blocks 57 are driven to move forward and backward through the telescopic devices. The telescopic devices can use electric push rods 52.
[0064] Before use, the straight cylinder 41 is rotated first, so that the two threaded rods 49 move relative to each other, thereby making the two straight plates 5 move relative to each other, so as to adjust the distance between the two straight plates 5, effectively placing prefabricated beams on carriages of transport vehicles with different widths, thereby increasing the scope of use and being highly practical.
[0065] Before the first rectangular tube 4 moves downward to clamp, the electric push rod 52 is first started, and then the function block 57 is driven to move outward, so that the straight plate 5 rotates outward around the hinge to expose the clamping plate 44 and other components, so that the clamping operation of the prefabricated beam can be observed in real time, effectively reducing the probability of collision between the clamping plate 44 and other components and the prefabricated beam to be clamped, and effectively ensuring the lifting beam hanging effect;
[0066] Then, the clamping plate 44 and other components are moved downward, and the precast beam is mechanically clamped. Then, the electric push rod 52 and the functional block 57 are used to rotate the straight plate 5 back to its original position and limit it with the limit box 51. Then, the precast beam is lifted and hung and moved. Then, the transport vehicle is driven to the bottom of the lifted and hung precast beam, and then the clamped precast beam is moved downward to the carriage of the transport vehicle for placement.
[0067] If there is an angle between the carriage of the transport vehicle and the clamped precast beam, during the downward movement of the clamped precast material, the two conveyor belts 53 first contact the opposite ends of the carriage of the transport vehicle and make the precast beam continue to move downward, and the two conveyor belts 53 respectively move relative to the opposite ends of the carriage of the transport vehicle, and make the two straight plates 5 rotate, and then make the two threaded rods 49, the straight cylinder 41 and the first rectangular cylinder 4 and other components rotate, so that the functional plate 1 rotates around the first axis 22, so as to achieve mechanical correction of the clamped precast beam, effectively reduce the difficulty of the transport vehicle reversing to enter the clamped precast beam directly below, effectively reduce the beam lifting process and time, and effectively ensure the beam lifting effect.
[0068] Embodiment three: Two straight plates 5 and inclined plates 54 are used to rotate the clamping structure formed by two mounting boxes 42, two clamping plates 44 and two second rectangular tubes 45, so as to correct the clamped precast beams and facilitate placing the clamped precast beams on the carriage of the transport vehicle. Since the functional plate 1 is rotatably connected to the top plate 2 through the first axis 22, the corrected clamping structure is prone to automatic phenomenon after returning to its original position, which will affect the subsequent mechanical clamping of the precast beams on the precast beam yard.
[0069] In order to solve the above problems, Figure 10-Figure 14 As shown, the second shaft 29 arranged vertically is installed to the middle position of the upper end of the top plate 2, and a mounting carrier is provided for the upper round box 26 and other components through the second shaft 29, and the upper round box 26 and the lower round box 27 located at the lower side of the upper round box 26 are rotatably connected to the outer end of the second shaft 29, and a mounting carrier is provided for the second plate 25 and other components through the upper round box 26, and a mounting carrier is provided for the first plate 24 and other components through the lower round box 27, and then the first elastic member 261 connected to the inner wall of the upper round box 26 is installed on the outer end of the second shaft 29, and the upper round box 26 is rotated back to its original position through the first elastic member 261, and the first elastic member 261 can be a coil spring, and the second elastic member 271 connected to the inner wall of the lower round box 27 is installed on the outer end of the second shaft 29, and the lower round box 27 is rotated back to its original position through the second elastic member 271, and the second elastic member 271 can be a coil spring;
[0070] The two second plates 25 are respectively mounted on the left and right ends of the upper round box 26, and the second plates 25 are used to provide a mounting carrier for the second L-shaped rod 28, and the two first plates 24 are respectively set on the left and right ends of the lower round box 27, and the first plates 24 are used to provide a mounting carrier for the first L-shaped rod 23, and then the vertical parts of the two first L-shaped rods 23 respectively attached to the front and rear ends of the function board 1 are respectively mounted on the outward lower ends of the two first plates 24, and the first L-shaped rods 23 are used to restrict one direction of the function board 1, and the vertical parts of the two second L-shaped rods 28 respectively attached to the front and rear ends of the function board 1 are respectively mounted on the outward lower ends of the two second plates 25, and the second L-shaped rods 28 are used to restrict the other direction of the function board 1;
[0071] Two U-shaped positioning plates 201 that are respectively clamped with the vertical parts of the first L-shaped rod 23 and the second L-shaped rod 28 are symmetrically installed at the front and rear ends of the top plate 2. The four U-shaped positioning plates 201 are used in combination to position the two first L-shaped rods 23 and the two second L-shaped rods 28 with respect to the top plate 2, and two elastic clamping plates 202 with a V-shaped structure that is wide on the outside and narrow on the inside are symmetrically installed on the outward ends of the U-shaped positioning plates 201. The two elastic clamping plates 202 are used in combination to achieve a clamping connection between the first L-shaped rod 23 or the second L-shaped rod 28 and the U-shaped positioning plate 201.
[0072] When the functional plate 1 rotates forwardly around the first axis 22, the two first L-shaped rods 23 are pushed to rotate, and then the two first plates 24 are rotated, so that the lower round box 27 rotates around the second axis 29, and then the second elastic member 271 is contracted, so that the second elastic member 271 generates elastic force, and when the lifted and hung prefabricated beam is completely placed in the carriage of the transport vehicle, the first rectangular tube 4 and other components are moved upward back to their original positions;
[0073] Then, the first rectangular tube 4 and other components are pushed, and under the elastic force of the second elastic member 271, the lower round box 27, the two first plates 24 and the two first L-shaped rods 23 are rotated, so that the functional plate 1 is rotated, and the first L-shaped rod 23 is entered into the two elastic clamping plates 202 installed on the corresponding U-shaped positioning plate 201, so that the two elastic clamping plates 202 are deformed to the outer shape and generate elastic force, and then the vertical part of the first L-shaped rod 23 is clamped into the corresponding U-shaped positioning plate 201, and the elastic force of the two elastic clamping plates 202 clamps the first L-shaped rod 23;
[0074] When the functional plate 1 rotates in the opposite direction around the first axis 22, the two second L-shaped rods 28 are pushed to rotate, thereby rotating the two second plates 25, so that the upper round box 26 rotates around the second axis 29, thereby contracting the first elastic member 261, so that the first elastic member 261 generates elastic force. When the prefabricated beam lifted and hung is completely placed in the carriage of the transport vehicle, the first rectangular tube 4 and other components are moved upward.
[0075] Then, the first rectangular tube 4 and other components are pushed, and under the elastic force of the first elastic member 261, the upper round box 26, the two second plates 25 and the two second L-shaped rods 28 are rotated, so that the functional plate 1 is rotated, and the second L-shaped rod 28 is entered into the two elastic clamping plates 202 installed on the corresponding U-shaped positioning plate 201, so that the two elastic clamping plates 202 are deformed to the outer shape and generate elastic force, and then the vertical part of the second L-shaped rod 28 is clamped into the corresponding U-shaped positioning plate 201, and the elastic force of the two elastic clamping plates 202 clamps the first L-shaped rod 23;
[0076] It can effectively rotate the function board 1 and other components back to their original positions, and restrict the function board 1 and other components in place, effectively reduce the probability of self-rotation of the function board 1 and other components, effectively ensure the normal mechanical clamping of the precast beams on the precast beam yard, and effectively ensure the beam lifting and hanging effect.
[0077] A method for efficiently positioning and hanging beams in a prefabricated beam yard, using any one of the above-mentioned efficient positioning and hanging beams in a prefabricated beam yard, comprises the following steps:
[0078] The first step is pre-processing. During the box girder production process in the prefabricated beam yard, two anti-metal RFID identification chips with basic digital information such as the bridge name are embedded in the box girder, and an electronic fence is set up in the beam storage area;
[0079] The second step is visual positioning. Input the corresponding prefabricated beam information on the APP or other terminals, and use the electronic fence to make the corresponding positioning tracker 48 receive the information, and make the corresponding four mobile vehicles 31 move, and then use the positioning tracker 48 to capture the information on the anti-metal RFID identification chip, and then start the corresponding two light boxes 21, so that the light boxes 21 emit flashes, and realize visual and efficient positioning beam locating operation;
[0080] The third step is to hang the lifting beam. The first rectangular tube 4, two installation boxes 42, two clamping plates 44 and other components are moved downward by the third driving device, the first bidirectional screw rod 16, multiple first arms 11, multiple first sliders 12, multiple second arms 14, multiple second sliders 15, multiple third arms 18 and multiple fourth arms 19, so that the two second rectangular tubes 45 can be located on both sides of the precast beam. Then, the second driving device, two second bidirectional screw rods 421, two sprocket wheels 422, chains 423, two first nut seats 425 and two second nut seats 426 are used to move the two clamping plates 44 and the two second rectangular tubes 45 inward, thereby clamping the precast beam and lifting the clamped precast beam.
[0081] The fourth step is transportation. The four mobile vehicles 31 are used to move the clamped precast beam to the placement position, and then the transport vehicle is driven to the bottom of the clamped precast beam and the clamped precast beam is moved downward. Then the two conveyor belts 53 are contacted with the two ends of the carriage of the transport vehicle and continue to move downward, so that the clamped precast beam rotates, and then the clamped precast beam is corrected. The two first driving devices, two first bevel gears 442, two second bevel gears 453, two second rollers 443, multiple first rollers 441, multiple third rollers 451 and two fourth rollers 452 are used to move the clamped precast beam to the top of the carriage of the transport vehicle, and then the clamped precast beam is placed on the carriage of the transport vehicle, and the clamping of the precast beam is released, and then the transport vehicle is used to transport the precast beam to the required position.
[0082] Although this specification is described according to implementation modes, not every implementation mode includes only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. An efficient positioning beam hanging device for a prefabricated beam yard, characterized in that: The utility model comprises a top plate (2), two A-shaped frames (3) are symmetrically mounted on the lower end of the top plate (2), two moving vehicles (31) are symmetrically mounted on the lower ends of the two A-shaped frames (3), a first shaft (22) is mounted in the middle of the lower end of the top plate (2), the outer end of the first shaft (22) is rotatably connected to a function plate (1), and the function plate (1) is attached to the lower end of the top plate (2), the function plate (1) is located between the two A-shaped frames (3), a lifting member is mounted on the lower end of the function plate (1), a driving member is arranged at the lower end of the lifting member, two clamping plates (44) are symmetrically mounted on the lower side of the driving member, a guide member is arranged at the outer end of the driving member, and the guide member is located outside the two clamping plates (44); A second rectangular tube (45) is installed at the inner end of the lower part of the two clamping plates (44), and a second bevel gear (453) is arranged on the upper side of the two second rectangular tubes (45). The inside of the two second rectangular tubes (45) is rotatably connected to a fourth roller (452), and the fourth roller (452) extends out of the second rectangular tube (45) toward the inner side. The shafts of the two fourth rollers (452) respectively pass through the two second rectangular tubes (45) and are respectively connected to the two second bevel gears (453). The two clamping plates (44) The inner ends of the two second rollers (443) are rotatably connected to the second roller (443), and the second roller (443) is located on the upper side of the second rectangular cylinder (45); the inner ends of the two second rollers (443) are provided with a first bevel gear (442), and the lower right end of the first bevel gear (442) and the upper left end of the second bevel gear (453) are meshed with each other; the outer ends of the two clamping plates (44) are provided with a first driving device, and the output shafts of the two first driving devices respectively penetrate the two clamping plates (44) and are respectively connected to the two second rollers (443); The driving member comprises a first rectangular tube (4), the first rectangular tube (4) being movably mounted on the lower end of the lifting member, and the first rectangular tube (4) being arranged in a transverse manner, and the left and right ends of the first rectangular tube (4) being connected to each other and being provided with a mounting box (42), and the mounting box (42) being located on the upper side of the clamping plate (44); The guide member comprises a straight tube (41), the straight tube (41) being rotatably connected to the middle part of the front end of the first rectangular tube (4), and the straight tube (41) passes through the first rectangular tube (4), the straight tube (41) is located inside the chain (423), the front and rear ends of the straight tube (41) are both threadedly connected to the threaded rod (49), and the threaded rod (49) extends into the straight tube (41), the two threaded rods (49) are both installed with a limit box (51) at the outer ends, and the limit box (51) is located between the two installation boxes (42), and two telescopic rods (46) are symmetrically installed between the limit box (51) and the first rectangular tube (4), and the two telescopic rods (46) are located on the left and right sides of the straight tube (41); The two limit boxes (51) are both in contact with the straight plate (5) at their outer ends, and the upper ends of the straight plates (5) are hinged to the upper ends of the limit boxes (51). The lower ends of the two straight plates (5) are both provided with inclined plates (54), and the straight plates (5) are located outside the clamping plate (44). The two inclined plates (54) are in a V-shaped structure with a width at the bottom and a narrowness at the top. The outer end surfaces of the two inclined plates (54) are both recessed inward to form a through groove (55), and the through groove (55) penetrates the inclined plates (54). A conveyor belt (53) is movably installed in the through groove (55), and the conveyor belt (53) extends out of the inclined plate (54) toward the inside. The inner wall of the conveyor belt (53) symmetrically meshes with two rollers (56), and the two rollers (56) are both rotatably connected in the through groove (55).
2. The high-efficiency positioning beam hanging device for prefabricated beam yard according to claim 1 is characterized in that: The two second rectangular tubes (45) are equidistantly connected to a plurality of third rollers (451) in rotation, and the third rollers (451) are located behind the fourth rollers (452). The plurality of third rollers (451) extend out of the second rectangular tube (45) toward the inside. The two clamping plates (44) are equidistantly connected to a plurality of first rollers (441) in rotation toward the inside, and the first rollers (441) are located behind the second rollers (443). The plurality of first rollers (441) are located on the upper side of the second rectangular tube (45).
3. The high-efficiency positioning beam hanging device for prefabricated beam yard according to claim 1 is characterized in that: The two installation boxes (42) are both rotatably connected to the second bidirectional screw rod (421), and the second bidirectional screw rod (421) is arranged along the length direction of the installation box (42), and the rear outer ends of the two second bidirectional screw rods (421) are both threadedly connected to the first nut seat (425), and the two first nut seats (425) are respectively slidably connected in the two installation boxes (42), and the first nut seat (425) extends out of the lower side of the installation box (42) and is connected to the clamping plate (44) located at the rear side; The front outer ends of the two second bidirectional screws (421) are both threadedly connected to the second nut seats (426), and the two second nut seats (426) are respectively slidably connected in the two installation boxes (42), and the second nut seats (426) extend out of the lower side of the installation box (42) and are connected to the clamping plate (44) located on the front side. A sprocket (422) is installed in the middle of the outer ends of the two second bidirectional screws (421), and the sprocket (422) is located between the first nut seat (425) and the second nut seat (426). The two sprockets (422) are connected by a chain (423), and the chain (423) passes through the first rectangular tube (4). A second driving device is arranged at the rear end of one of the installation boxes (42), and the output shaft of the second driving device is connected to a second bidirectional screw (421).
4. The high-efficiency positioning beam hanging device for prefabricated beam yard according to claim 3 is characterized in that: The two straight plates (5) are symmetrically slidably connected to the two functional blocks (57) at their inner ends, and the functional blocks (57) are located in the limit box (51). The two limit boxes (51) are symmetrically installed with two telescopic devices at their inner ends, and the telescopic devices are located between the straight tube (41) and the telescopic rod (46). The movable parts of the telescopic devices pass through the limit box (51) and are movably connected to the functional blocks (57), and the telescopic devices are located outside the first rectangular tube (4).
5. The high-efficiency positioning beam hanging device for prefabricated beam yard according to claim 3 is characterized in that: A solar panel (47) is installed at the middle of the outer ends of the two installation boxes (42), a battery storage device is arranged at the lower ends of the two solar panels (47), and the two battery storage devices are electrically connected to the two solar panels (47) respectively, a positioning tracker (48) is installed at the lower ends of the two battery storage devices, and the two positioning trackers (48) are electrically connected to the two battery storage devices respectively, and two light boxes (21) are symmetrically installed at the upper end of the top plate (2), and the two light boxes (21) are arranged opposite to each other, and the two light boxes (21) are electrically connected to the two battery storage devices respectively.
6. The high-efficiency positioning beam hanging device for prefabricated beam yard according to claim 3 is characterized by: The lifting member comprises a rectangular frame (13), the rectangular frame (13) being arranged between the function plate (1) and the first rectangular tube (4), and the rectangular frame (13) being arranged in a transverse manner, a first bidirectional screw (16) being rotatably connected in the rectangular frame (13), a third driving device being installed at the right end of the rectangular frame (13), and an output shaft of the third driving device being connected to the first bidirectional screw (16), a plurality of first sliders (12) being equidistantly threadedly connected at the left outer end of the first bidirectional screw (16), and the first slider (12) being slidably connected in the rectangular frame (13), a plurality of second sliders (15) being equidistantly threadedly connected at the right outer end of the first bidirectional screw (16), and the second sliders (15) being slidably connected in the rectangular frame (13); A first support arm (11) is movably mounted on the upper ends of a plurality of the first slide blocks (12), and the other ends of a plurality of the first support arms (11) are movably arranged at the lower end of the function board (1); a second support arm (14) is movably mounted on the upper ends of a plurality of the second slide blocks (15), and the other ends of a plurality of the second support arms (14) are movably arranged at the lower end of the function board (1), and the first support arm (11) and the second support arm (14) are in a V-shaped structure arranged wide at the top and narrow at the bottom; a fourth support arm (19) is movably mounted on the lower ends of a plurality of the first slide blocks (12), and the other ends of a plurality of the fourth support arms (19) are movably arranged at the upper end of the first rectangular tube (4); a third support arm (18) is movably mounted on the lower ends of a plurality of the second slide blocks (15), and the other ends of a plurality of the third support arms (18) are movably arranged at the upper end of the first rectangular tube (4), and the third support arm (18) and the fourth support arm (19) are in a V-shaped structure arranged narrow at the top and wide at the bottom.
7. A method for efficiently positioning and hanging beams in a precast beam yard, using the efficient positioning and hanging beam device of any one of claims 1 to 6, characterized in that: The following steps are involved: The first step is pre-processing. During the box girder production process in the prefabricated beam yard, two anti-metal RFID identification chips with basic digital information such as the bridge name are embedded in the box girder, and an electronic fence is set up in the beam storage area; The second step is visual positioning, inputting the corresponding prefabricated beam information on the APP or other terminals, and using the electronic fence to allow the corresponding positioning tracker (48) to receive the information, and allowing the corresponding four mobile vehicles (31) to move, and then using the positioning tracker (48) to capture the information on the anti-metal RFID identification chip, and then starting the corresponding two light boxes (21), so that the light boxes (21) emit flashes, and realize visual and efficient positioning beam locating operations; The third step is to suspend the lifting beam. The first rectangular tube (4), two installation boxes (42), two clamping plates (44) and other components are moved downward by means of the third driving device, the first bidirectional screw rod (16), a plurality of first supporting arms (11), a plurality of first sliding blocks (12), a plurality of second supporting arms (14), a plurality of second sliding blocks (15), a plurality of third supporting arms (18) and a plurality of fourth supporting arms (19), so that the two second rectangular tubes (45) are located on both sides of the prefabricated beam. Then, the second driving device, two second bidirectional screw rods (421), two sprocket wheels (422), a chain (423), two first nut seats (425) and two second nut seats (426) are used to move the two clamping plates (44) and the two second rectangular tubes (45) inwardly, thereby clamping the prefabricated beam and lifting the clamped prefabricated beam. The fourth step is transportation. The four moving vehicles (31) are used to move the clamped precast beam to the placement position. The transport vehicle is then driven to the bottom of the clamped precast beam and the clamped precast beam is moved downward. The two conveyor belts (53) are then brought into contact with the two ends of the carriage of the transport vehicle and continue to move downward, so that the clamped precast beam is rotated, and the clamped precast beam is corrected. The two first driving devices, two first bevel gears (442), two second bevel gears (453), two second rollers (443), a plurality of first rollers (441), a plurality of third rollers (451) and two fourth rollers (452) are used to move the clamped precast beam to the top of the carriage of the transport vehicle. The clamped precast beam is then placed on the carriage of the transport vehicle, and the clamping of the precast beam is released. The precast beam is then transported to the required position by the transport vehicle.
Citation Information
Patent Citations
Portal frame device for mechanical automatic machining
CN112265907A
Lifting device for mounting precast beam plate
CN118458582A
Prefabricated pipe positioning and mounting construction equipment
CN118561147A