A tower crane standard section installation control method and system

By evaluating the installation accuracy of the tower crane standard section in real time and adjusting the installation time according to the accuracy, the accuracy error and safety hazards during the installation process of the tower crane standard section are solved, and an efficient and safe installation process is achieved.

CN118771224BActive Publication Date: 2025-03-18ZHANGJIAGANG ZHONGLIAN CONSTRUCT MASCH CO LTD
2 Cites 0 Cited by

Patent Information

Application Number
CN202411164836.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-23
Publication Date
2025-03-18
Estimated Expiration
2044-08-23

AI Technical Summary

Technical Problem

During the installation process of the tower crane standard section, due to the accumulation of accuracy errors and errors, frequent inspection and debugging are required, which consumes a lot of manpower and financial resources, and there are safety hazards for high-altitude maintenance.

Method used

By determining the standard installation parameters of the first standard section based on the installation data and environmental data of the second standard section, the installation accuracy is evaluated in real time, and when the installation accuracy exceeds the threshold, the installation time is adjusted and the instructions are sent to the user terminal to realize the control of the installation process.

Benefits of technology

Real-time evaluation and control of installation accuracy is realized, installation time is saved, risks is reduced, and tower crane safety and installation efficiency are improved.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

An embodiment of the present specification provides a tower crane standard section installation control method and system, the method comprising determining the installation accuracy of the first standard section based on the installation data and installation environment data of the second standard section and the standard installation parameters of the first standard section, the second standard section having been installed before the first standard section; in response to the installation accuracy of the first standard section being greater than a first threshold, determining an installation time adjustment instruction and sending it to a user terminal; obtaining time parameters based on the user terminal, and determining the installation time of the first standard section based on the time parameters.