Shield launching construction method for shallow earthing section of mountain high slope

Through the reinforcement of the foot of the hillside and the segmented design of the shield launch shaft, the problem of landslides caused by shield machine excavation was solved, construction safety was improved, and the shield tunnel was realized in the shallow soil-covered section of the high mountain slope. stable construction.

CN118774850APending Publication Date: 2024-10-15CHINA WATER RESOURCES PEARL RIVER PLANNING SURVERYING & DESIGNING
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411006378.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-10-15

AI Technical Summary

Technical Problem

When shield tunneling is carried out on a shallow soil-covered section of a high mountain slope, landslides are likely to occur during the excavation process of the shield tunneling machine, causing safety hazards and economic losses. It is difficult for existing technology to effectively solve this problem.

Method used

By reinforcing the foot of the hillside, setting up concrete pressure plates and plain concrete layers, and dividing the shield starting shaft into a foundation pit section and a grading section, placing shield machines and trolleys respectively, using layered excavation and spraying Anchor support and other technologies can reduce soil disturbance and increase resistance.

Benefits of technology

It effectively reduces the disturbance of the upper slope foot caused by the shield machine excavation, improves the safety of tunnel construction, prevents landslides, and ensures the safety of the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118774850A_ABST
    Figure CN118774850A_ABST
Patent Text Reader

Abstract

The invention provides a shield launching construction method for a shallow earthing section of a mountain high slope, and relates to the technical field of shield tunnel construction. The construction method comprises the following steps that a site at the slope toe of the mountain high slope is leveled, the end of a shield launching well is reinforced, and the slope toe is backfilled with a plain concrete layer; a first intercepting ditch is arranged on the periphery of the shield launching well to prevent surface water from flowing into the launching well, and shield launching well foundation pit section fender posts, top beams and concrete inner supports are constructed to form a supporting system; soil excavation is conducted on the foundation pit section and the slope section of the shield launching well; performing concrete pouring construction on the structural side wall and the structural bottom plate of the shield launching well; and the shield tunneling machine and the rear matched trolley are placed on the foundation pit section and the sloping section of the shield launching well through the shield hoisting platform correspondingly, the counter-force frame is installed, and launching construction is conducted after debugging of the shield tunneling machine is completed. According to the method, back pressure stacking treatment is conducted on the high-slope shallow soil covering section tunnel upward slope, and the influence of water and soil pressure of the tunnel face in the shield tunneling machine starting stage on the slope toe is effectively reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of shield tunnel construction, in particular to a shield initial construction method for a shallow covered soil section of a mountain high slope. Background Art

[0002] Compared with urban subway tunnels, mountain tunnels constructed using the shield method often do not require a deeper foundation pit as the shield starting working shaft. The shield starting shaft is usually set up at the foot of the hillside. The thickness of the upper cover of the shield tunnel changes from shallow to thick. When the upper cover of the shield tunnel is shallow, the water and soil pressure during the shield machine's excavation process affects the surrounding soil. The upper cover of the tunnel at the foot of the hillside is often shallow, so shield construction at the shallow cover section of the high slope of the mountain can easily cause landslides, resulting in casualties and economic losses. Summary of the invention

[0003] The purpose of the present invention is to provide a shield construction method for a shallow overburden section of a high slope of a mountain, so as to alleviate the technical problem of low safety performance of shield construction in the prior art.

[0004] In order to solve the above technical solution, the technical solution provided by the present invention is:

[0005] The shield construction method for the shallow soil covering section of a high slope of a mountain provided by the present invention comprises the following steps:

[0006] Site reinforcement treatment for shallow soil covering section of high mountain slope:

[0007] Determine the construction area, repair the slope of the mountain around the construction area, and backfill the soil generated by the slope repair to the construction area to form a construction platform; reinforce the end of the shield starting shaft on the construction platform, install a concrete pressure plate at the end of the shield starting shaft, and backfill a plain concrete layer on the top of the concrete pressure plate;

[0008] Construction of support system for shield launching shaft:

[0009] The shield starting shaft includes a foundation pit section and a slope section, wherein the slope section is located on a side of the foundation pit section away from the concrete pressure plate; a concrete inner support and a plurality of retaining piles are arranged in the foundation pit section, wherein the plurality of retaining piles are arranged around the outer periphery of the concrete inner support; the top of the retaining piles and the soil around the concrete inner support are excavated, and the inferior concrete on the top of the retaining piles is chiseled out to the required elevation of the bottom surface of the designed crown beam; the crown beam and the concrete inner support beam are reinforced and the formwork is installed; the crown beam and the concrete inner support are cast and formed at one time;

[0010] Soil excavation of the foundation pit section and the slope section:

[0011] Based on the boundary line between the foundation pit section and the slope section, excavation is carried out towards both ends, and excavation is carried out in layers from top to bottom; the foundation pit section is provided with inter-pile spraying protection, and the slope section is provided with side slope support, until the foundation pit section and the slope section reach the designed elevation, and the bottom of the slope section extends along the direction of the tunnel and is connected with the bottom of the foundation pit section; the slope surface of the slope section is provided with spraying anchor support, and is divided into two levels of slope, and a horseway is provided in the middle;

[0012] Shield launching shaft structure construction:

[0013] A concrete cushion is provided at the bottom of the slope of the slope section and the bottom of the foundation pit section, and a starting shaft structural bottom plate is formed by pouring in layers on the upper slope of the concrete cushion, and two side walls are provided above the starting shaft structural bottom plate; a starting tunnel door is reserved at the end of the shield starting shaft, and the starting tunnel door is located between the two side walls;

[0014] Installation of shield machine and its supporting trolley in the well:

[0015] The shield machine and the supporting trolley behind the shield machine are respectively placed in the foundation pit section and the slope section through the shield hoisting platform, and a reaction frame is installed at the tail of the shield machine; the shield machine starts to construct the tunnel.

[0016] Furthermore, the construction of the support system for the shield launch shaft also includes:

[0017] A first intercepting ditch is arranged in the shield starting shaft, and the first intercepting ditch extends along the direction of the tunnel.

[0018] Furthermore, the soil excavation of the foundation pit section and the slope section also includes:

[0019] A water retaining ridge is arranged on the top of the slope of the slope reduction section.

[0020] Furthermore, the end reinforcement treatment of the shield starting shaft on the construction platform includes the following steps:

[0021] High-pressure rotary jetting piles are arranged in the tunnel direction of the end of the shield starting shaft, and cement soil mixing piles are arranged on the other two sides of the end of the shield starting shaft.

[0022] Furthermore, the length of the high-pressure jet grouting pile is greater than the length of the shield machine.

[0023] Furthermore, a second intercepting ditch is arranged on the top of the plain concrete layer, and the second intercepting ditch extends in a horizontal direction, and the horizontal direction is perpendicular to the axial direction of the tunnel.

[0024] Furthermore, the thickness of the plain concrete layer is L, the diameter of the tunnel is D, and L≥0.5D.

[0025] Furthermore, the shield hoisting platform and the foundation pit section are spaced apart in a horizontal direction, and the horizontal direction is perpendicular to the axial direction of the tunnel.

[0026] Furthermore, the shield lifting platform is made of concrete casting.

[0027] Furthermore, while the foundation pit section is being excavated, spraying protection is carried out between piles, and while the slope section is being excavated, slope support is carried out. The excavation of the foundation pit section follows the principle of layered excavation, from top to bottom, and supporting before excavating. The excavation of the slope section follows the principle of layered excavation, from top to bottom, and supporting as excavation progresses.

[0028] Based on the above technical solutions, the technical effects that can be achieved by the present invention are analyzed as follows:

[0029] The shield construction method for the shallow covering section of a high slope of a mountain provided by the present invention faces the problem that the covering soil on the upper part of the tunnel at the foot of the slope is relatively shallow and cannot meet the requirements for shield construction. By reinforcing the soil at the foot of the slope, a concrete pressure plate is arranged at the end of the shield starting shaft, the shield starting shaft is divided into a foundation pit section and a slope section, the shield machine and the supporting trolley behind the shield machine are respectively placed in different positions, and then the shield construction is carried out. This can reduce the disturbance of the soil at the upper foot of the slope by the shield machine during the excavation stage. At the same time, backfilling a plain concrete layer on the concrete pressure plate can increase the horizontal resistance, prevent landslides caused by the shallow covering soil at the initial stage of the shield, and ensure the safety of the tunnel construction process. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0031] Figure 1 A schematic plan view of a shield machine launching shaft in a shield launching construction method for a shallow overburden section on a high slope of a mountain provided by an embodiment of the present invention;

[0032] Figure 2 A schematic elevation diagram of a slope-lowering section in a shield tunneling initial construction method for a shallow overburden section of a mountain high slope provided by an embodiment of the present invention;

[0033] Figure 3 A schematic elevation diagram of a foundation pit section in a shield tunneling initial construction method for a shallow overburden section on a mountain high slope provided by an embodiment of the present invention;

[0034] Figure 4A schematic diagram of the vertical reinforcement of the end of the shield starting shaft in the shield starting construction method for the shallow overburden section of a mountain high slope provided by an embodiment of the present invention;

[0035] Figure 5 A schematic diagram of the tunnel at the end of the shield starting shaft in the shield starting construction method for a shallow covering section on a high slope of a mountain provided by an embodiment of the present invention.

[0036] icon:

[0037] 1-mountain slope; 11-mountain slope foot; 12-cement soil mixing pile; 13-high-pressure rotary jet pile; 14-concrete pressure plate; 15-plain concrete layer; 151-second intercepting ditch;

[0038] 21-foundation pit section; 213-concrete internal support; 211-guard piles; 212-cap beam; 215-launch shaft structure bottom plate; 214-side wall; 216-launch tunnel door;

[0039] 22-slope section; 223-slope surface; 224-horse path; 221-first ditch; 222-water retaining ridge;

[0040] 3- Shield machine;

[0041] 4- The supporting trolley behind the shield machine;

[0042] 5-Reaction frame;

[0043] 6- Tunnel. DETAILED DESCRIPTION

[0044] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0045] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0046] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0047] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the product of the invention is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0048] In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0049] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0050] Some embodiments of the present invention are described in detail below in conjunction with the accompanying drawings. In the absence of conflict, the following embodiments and features in the embodiments can be combined with each other.

[0051] Compared with the urban subway tunnel 6, the construction of the mountain tunnel 6 by the shield method often does not require a deeper foundation pit as the shield starting working shaft. The shield starting shaft is usually set at the foot of the hillside. The thickness of the upper soil cover of the shield tunnel 6 changes from shallow to thick. When the upper soil cover of the shield tunnel 6 is shallow, the water and soil pressure during the excavation process of the shield machine 3 has a greater impact on the surrounding soil. The upper soil cover of the tunnel 6 at the foot of the hillside is often shallow, so the initial construction of the shield in the shallow soil cover section of the high slope of the mountain is likely to cause landslides, thereby causing casualties and economic losses. Therefore, when the shield is started in the shallow soil cover section of the high slope of the mountain, how to deal with the shallow soil cover on the upper part of the tunnel 6 at the foot of the hillside to prevent the shield machine 3 from affecting it during the excavation process and causing safety accidents has become a key problem that needs to be solved urgently by technicians in this field.

[0052] In view of this, see Figures 1 to 5The shield construction method for the shallow covering section of a high slope of a mountain provided by the embodiment of the present invention comprises the following steps:

[0053] S100: Site reinforcement treatment of shallow covered section of high mountain slope: determine the construction area, repair the slope of the mountain foot 11 around the construction area, and backfill the soil generated by the slope repair to the construction area to form a construction platform; reinforce the end of the shield starting shaft on the construction platform, install a concrete pressure plate 14 at the end of the shield starting shaft, and backfill a plain concrete layer 15 on the top of the concrete pressure plate 14.

[0054] Specifically, see Figure 1 According to the actual terrain environment on site, the foot of the mountain slope 11 around the construction area is repaired, and the earthwork generated by the slope repair is backfilled into the ground of the construction area to form a construction platform. The end of the shield starting shaft is reinforced on the construction platform. Then, the end concrete pressure plate 14 of the shield starting shaft is constructed. When the strength of the concrete pressure plate 14 reaches more than 75%, a plain concrete layer 15 is backfilled on the pressure plate.

[0055] This step is to reinforce the shallow soil covering site on the high slope of the mountain. A concrete pressure plate 14 is set at the end of the shield starting shaft, and then the shield starting construction is carried out. This can reduce the disturbance of the soil at the upper slope foot by the shield machine 3 during the excavation stage. At the same time, a plain concrete layer 15 is backfilled on the concrete pressure plate 14 to increase the horizontal resistance and prevent landslides caused by the shallow soil covering during the shield starting stage. The safety of the tunnel 6 during the construction process is guaranteed.

[0056] In an optional scheme of an embodiment of the present invention, the end reinforcement treatment of the shield starting shaft on the construction platform includes the following steps: high-pressure rotary jet piles 13 are set in the direction of the end tunnel 6 of the shield starting shaft, and cement soil mixing piles 12 are set on the other two sides of the end of the shield starting shaft.

[0057] Specifically, the end tunnel 6 direction of the shield starting shaft is reinforced with high-pressure rotary jet piles 13, and the other two sides of the end of the shield starting shaft are reinforced with cement soil mixing piles 12.

[0058] By using high-pressure rotary jet piles 13 to reinforce the soil at the foot of the slope, setting a concrete pressure plate at the end of the shield starting shaft, and then carrying out the shield starting construction, the disturbance of the soil at the upper foot of the slope by the shield machine 3 during the excavation stage can be reduced. At the same time, backfilling the plain concrete layer 15 on the concrete pressure plate 14 can increase the horizontal resistance and prevent landslides caused by shallow cover during the shield starting stage. The safety of the tunnel 6 during the construction process is guaranteed.

[0059] In an optional solution of the embodiment of the present invention, the length of the high-pressure jet grouting pile 13 is greater than the length of the shield machine 3 .

[0060] Specifically, the reinforcement length of the high-pressure jet grouting pile 13 is at least 2 meters greater than the length of the shield machine 3 .

[0061] The length of the high-pressure jet grouting pile 13 is greater than the length of the shield machine 3 to ensure the reinforcement strength.

[0062] In an optional solution of the embodiment of the present invention, a second intercepting ditch 151 is provided on the top of the plain concrete layer 15 , and the second intercepting ditch 151 extends in a horizontal direction, which is perpendicular to the axial direction of the tunnel 6 .

[0063] Specifically, the second intercepting ditch 151 is located on a side of the plain concrete layer 15 close to the mountain slope foot 11 .

[0064] A second intercepting ditch 151 is provided on the top of the plain concrete layer 15 to prevent water from flowing into the shield starting shaft.

[0065] In an optional solution of the embodiment of the present invention, the thickness of the plain concrete layer 15 is L, the diameter of the tunnel 6 is D, and L≥0.5D.

[0066] Specifically, when the strength of the concrete platen 14 reaches 75% or more, a plain concrete layer 15 is backfilled on the concrete platen 14 , the thickness of the backfilled plain concrete layer 15 is not less than 0.5 times the diameter of the tunnel 6 , and a second intercepting ditch 151 is provided on the upper part.

[0067] The thickness of the plain concrete layer 15 is greater than or equal to 0.5 times the diameter of the tunnel 6, so as to ensure the strength of the plain concrete layer 15 and thus improve the stability of the foot of the slope.

[0068] S200: See Figure 1 and Figure 3 , Construction of the support system of the shield starting shaft: The shield starting shaft includes a foundation pit section 21 and a slope section 22, and the slope section 22 is located on the side of the foundation pit section 21 away from the concrete pressure plate 14; a concrete inner support 213 and a plurality of retaining piles 211 are arranged in the foundation pit section 21, and the plurality of retaining piles 211 are arranged around the outer periphery of the concrete inner support 213; the top of the retaining pile 211 and the soil around the concrete inner support 213 are excavated, and the inferior concrete on the top of the retaining pile 211 is chiseled out to the required elevation of the bottom surface of the designed crown beam 212; the crown beam 212 and the concrete inner support 213 are reinforced and the formwork is installed; the crown beam 212 and the concrete inner support 213 are cast and formed at one time.

[0069] Specifically, the shield starting shaft is divided into a foundation pit section 21 and a slope section 22. First, the first water cut ditch 221 is set in the shield starting shaft. Then, the foundation pit retaining piles 211 are constructed around the foundation pit section 21. After the foundation pit retaining piles 211 reach the design strength requirements, the soil around the pile tops and the concrete inner supports 213 is excavated, and the inferior concrete on the pile tops is chiseled out to the designed bottom elevation of the crown beam 212; then, the crown beam 212 and the concrete inner support 213 are reinforced and the formwork is installed according to the design documents and construction drawings; finally, the crown beam 212 and the concrete inner support 213 are cast and formed at one time, completing the support system of the shield starting shaft divided into the foundation pit section 21 retaining piles 211 and the concrete inner support 213; the slope surface 223 support design of the slope section 22 adopts the sprayed anchor support form, which is divided into two slopes with a horseway 224 in the middle; and a water retaining ridge 222 is set on the top of the slope.

[0070] The shield starting shaft is divided into a support system of foundation pit section 21 retaining piles 211 and concrete inner supports 213, which improves the support strength and enhances the safety of construction.

[0071] In an optional solution of the embodiment of the present invention, the construction of the support system of the shield starting shaft also includes the following steps: a first intercepting ditch 221 is set in the shield starting shaft, and the first intercepting ditch 221 extends along the direction of the tunnel 6.

[0072] Specifically, two first water intercepting ditches 221 are provided, and the two first water intercepting ditches 221 are respectively located on two slope surfaces 223 of the slope reduction section 22 .

[0073] The first water ditch 221 is used for drainage to prevent water from flowing into the shield starting shaft.

[0074] S300: Excavation of the soil of the foundation pit section 21 and the slope section 22: Excavation is carried out towards both ends based on the boundary line of the foundation pit section 21 and the slope section 22, and excavation is carried out in layers from top to bottom; the foundation pit section 21 is provided with inter-pile spraying protection, and the slope section 22 is provided with slope support, until the foundation pit section 21 and the slope section 22 reach the designed elevation, and the bottom of the slope section 22 extends along the direction of the tunnel 6 and is connected with the bottom of the foundation pit section 21; the slope surface 223 of the slope section 22 is provided with sprayed anchor support, and is divided into two slopes, and a horseway 224 is provided in the middle.

[0075] Specifically, the excavation of the shield starting shaft is divided into two parts: the foundation pit section 21 and the slope section 22. The excavation is carried out in layers from top to bottom, and the excavation direction is from the boundary line between the foundation pit section 21 and the slope section 22 to both ends. While the foundation pit section 21 is being excavated, spraying is carried out between piles, and while the slope section 22 is being excavated, slope support is carried out until the excavation reaches the designed elevation.

[0076] In an optional solution of the embodiment of the present invention, the soil excavation of the foundation pit section 21 and the slope section 22 further includes the following steps: a water retaining ridge 222 is provided at the top of the slope surface 223 of the slope section 22 .

[0077] Specifically, see Figure 2 The water retaining ridge 222 is located on the inner side of the first water intercepting ditch 221 to further prevent water from flowing into the shield starting shaft.

[0078] In the optional scheme of the embodiment of the present invention, while the foundation pit section 21 is being excavated, spraying protection is carried out between piles, and while the slope section 22 is being excavated, slope support is carried out. The excavation of the foundation pit section 21 follows the principle of layered excavation, from top to bottom, and supporting before excavating, and the excavation of the slope section 22 follows the principle of layered excavation, from top to bottom, and supporting as excavation proceeds.

[0079] S400: See Figure 4 and Figure 5 , shield starting shaft structure construction: a concrete cushion layer is set at the bottom of the slope section 22 and the bottom of the foundation pit section 21, and the inclined surface of the concrete cushion layer is layeredly poured to form a starting shaft structure bottom plate 215, and two side walls 214 are set above the starting shaft structure bottom plate 215; a starting tunnel door 216 is reserved at the end of the shield starting shaft, and the starting tunnel door 216 is located between the two side walls 214.

[0080] Specifically, after the excavation of the shield starting shaft is completed and the trench is tested and qualified, a 10 cm concrete cushion layer is constructed at the bottom, and then the concrete of the starting shaft structure bottom plate 215 is poured in layers on the inclined surface. After the concrete strength of the starting shaft structure bottom plate 215 reaches 75%, the side wall 214 concrete is poured, and a starting tunnel gate 216 is reserved at the end of the starting shaft.

[0081] S500: See Figure 4 , the shield machine 3 and the supporting trolley 4 behind the shield machine are installed in the well: the shield machine 3 and the supporting trolley 4 behind the shield machine are placed in the foundation pit section 21 and the slope section 22 respectively through the shield lifting platform, and a reaction frame 5 is installed at the tail of the shield machine 3; the shield machine 3 starts to construct the tunnel 6.

[0082] Specifically, the shield machine 3 and the rear supporting trolley 4 of the shield machine are respectively placed in the foundation pit section 21 and the slope section 22 of the shield starting shaft through the shield lifting platform, and the reaction frame 5 is installed at the tail of the shield machine 3. After the debugging is completed, the shield machine 3 is started to construct the shield tunnel 6.

[0083] In an optional solution of the embodiment of the present invention, the shield hoisting platform and the foundation pit section 21 are arranged at intervals in the horizontal direction, and the horizontal direction is perpendicular to the axial direction of the tunnel 6; the shield hoisting platform is made of concrete casting.

[0084] Specifically, the shield machine 3 and the rear supporting trolley 4 of the shield machine are respectively placed in the shield starting shaft foundation pit section 21 and the slope section 22 through the shield lifting platform. The shield lifting platform is arranged on one side of the shield starting shaft foundation pit section 21 and is cast by concrete. The bearing capacity of the shield lifting platform must meet the design requirements.

[0085] The shield construction method for the shallow soil covering section of the high slope of the mountain faces the problem that the soil covering the upper part of the tunnel 6 at the foot of the slope is too shallow to meet the requirements of the shield construction. By reinforcing the soil at the foot of the slope, a concrete pressure plate 14 is set at the end of the shield starting shaft, the shield starting shaft is divided into a foundation pit section 21 and a slope section 22, and the shield machine 3 and the supporting trolley 4 behind the shield machine are placed in different positions, and then the shield construction is carried out. This can reduce the disturbance of the soil at the upper foot of the slope by the shield machine 3 during the excavation stage. At the same time, a plain concrete layer 15 is backfilled on the concrete pressure plate 14 to increase the horizontal resistance, prevent landslides caused by the shallow soil covering at the initial stage of the shield, and ensure the safety of the tunnel 6 during the construction process.

[0086] The following is a brief description of the steps of the shield construction method for the shallow overburden section of the high slope of the mountain:

[0087] The present embodiment provides a shield construction method for a shallow covered section of a high mountain slope. First, the site at the foot of the mountain slope 1 is leveled, the end of the shield starting shaft is reinforced, and a plain concrete layer 15 is backfilled at the foot of the slope. Then, a first intercepting ditch 221 is set around the shield starting shaft to prevent surface water from flowing into the shield starting shaft. The shield starting shaft foundation pit section 21 retaining piles 211, crown beams 212 and concrete inner supports 213 are constructed to form a support system, and then the shield starting shaft foundation pit section 21 and the slope section 22 are excavated. The shield starting shaft structure side walls 214 and the starting shaft structure bottom plate 215 are cast, and finally the shield machine 3 and the shield machine rear supporting trolley 4 are placed in the shield starting shaft foundation pit section 21 and the slope section 22 respectively, the reaction frame 5 is installed, the shield machine 3 is debugged, and the shield tunnel 6 is started for construction. This embodiment effectively reduces the influence of the water and soil pressure of the heading face of the shield machine 3 in the starting stage on the slope foot by performing back pressure loading treatment on the back slope of the high slope and shallow covering section of the tunnel 6, so that the safety of the tunnel 6 during the construction process is guaranteed.

[0088] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A shield construction method for a shallow overburden section on a high slope of a mountain, characterized in that: The following steps are involved: Site reinforcement treatment for shallow soil covering section of high mountain slope: Determine a construction area, repair the slope of the mountain foot (11) around the construction area, and backfill the earthwork generated by the repair to the construction area to form a construction platform; reinforce the end of the shield starting shaft on the construction platform, install a concrete pressure plate (14) at the end of the shield starting shaft, and backfill a plain concrete layer (15) on the top of the concrete pressure plate (14); Construction of support system for shield launching shaft: The shield starting shaft comprises a foundation pit section (21) and a slope section (22), wherein the slope section (22) is located at a side of the foundation pit section (21) away from the concrete pressure plate (14); a concrete inner support (213) and a plurality of retaining piles (211) are arranged in the foundation pit section (21), wherein the plurality of retaining piles (211) are arranged around the outer periphery of the concrete inner support (213); the top of the retaining pile (211) and the soil around the concrete inner support (213) are excavated, and the inferior concrete at the top of the retaining pile (211) is chiseled out to the required elevation of the bottom surface of the designed crown beam (212); the crown beam (212) and the concrete inner support (213) are reinforced and the formwork is installed; the crown beam (212) and the concrete inner support (213) are cast and formed at one time; Soil excavation of the foundation pit section (21) and the slope section (22): Based on the boundary line between the foundation pit section (21) and the slope section (22), excavation is carried out towards both ends, and excavation is carried out in layers from top to bottom; the foundation pit section (21) is provided with inter-pile spraying protection, and the slope section (22) is provided with side slope support, until the foundation pit section (21) and the slope section (22) reach the designed elevation, and the bottom of the slope section (22) extends along the direction of the tunnel (6) and is connected with the bottom of the foundation pit section (21); the slope surface (223) of the slope section (22) is provided with spraying anchor support, and is divided into two levels of slope, and a horseway (224) is provided in the middle; Shield launching shaft structure construction: A concrete cushion layer is provided at the bottom of the slope of the slope section (22) and the bottom of the foundation pit section (21), and a starting shaft structural bottom plate (215) is formed by pouring in layers on the upper slope of the concrete cushion layer, and two side walls (214) are provided above the starting shaft structural bottom plate (215); a starting tunnel door (216) is reserved at the end of the shield starting shaft, and the starting tunnel door (216) is located between the two side walls (214); The shield machine (3) and the supporting trolley (4) behind the shield machine are installed in the well: The shield machine (3) and the shield machine rear supporting trolley (4) are respectively placed in the foundation pit section (21) and the slope section (22) through a shield hoisting platform, and a reaction frame (5) is installed at the tail of the shield machine (3); the shield machine (3) starts to construct the tunnel (6).

2. The shield construction method for the shallow soil covering section of a high slope of a mountain according to claim 1 is characterized in that: The support system construction of the shield launch shaft also includes: A first intercepting ditch (221) is arranged in the shield starting shaft, and the first intercepting ditch (221) extends in the direction of the tunnel (6).

3. The shield construction method for the shallow soil covering section of a high slope of a mountain according to claim 1 is characterized in that: The soil excavation of the foundation pit section (21) and the slope section (22) further includes: A water retaining ridge (222) is provided at the top of the slope surface (223) of the slope reduction section (22).

4. The shield construction method for the shallow soil covering section of a high slope of a mountain according to claim 1 is characterized in that: The end reinforcement treatment of the shield starting shaft on the construction platform includes the following steps: High-pressure jet grouting piles (13) are arranged in the direction of the end tunnel (6) of the shield starting shaft, and cement soil mixing piles (12) are arranged on the other two sides of the end of the shield starting shaft.

5. The shield construction method for the shallow soil covering section of a high slope of a mountain according to claim 4 is characterized in that: The length of the high-pressure jet grouting pile (13) is greater than the length of the shield machine (3).

6. The shield construction method for the shallow soil covering section of a high slope of a mountain according to claim 1 is characterized in that: A second intercepting ditch (151) is arranged on the top of the plain concrete layer (15), and the second intercepting ditch (151) extends in a horizontal direction, wherein the horizontal direction is perpendicular to the axial direction of the tunnel (6).

7. The shield construction method for the shallow soil covering section of a high slope of a mountain according to claim 1 is characterized in that: The thickness of the plain concrete layer (15) is L, the diameter of the tunnel (6) is D, and L≥0.5D.

8. The shield construction method for the shallow soil covering section of a high slope of a mountain according to claim 1 is characterized in that: The shield hoisting platform and the foundation pit section (21) are arranged at intervals in a horizontal direction, and the horizontal direction is perpendicular to the axial direction of the tunnel (6).

9. The shield construction method for the shallow soil covering section of a high slope of a mountain according to claim 1, characterized in that: The shield hoisting platform is made of concrete pouring.

10. The shield construction method for the shallow soil covering section of a high slope of a mountain according to claim 1, characterized in that: The foundation pit section (21) is excavated while spraying and protecting the piles, and the slope section (22) is excavated while supporting the slope. The foundation pit section (21) is excavated in accordance with the principle of layered excavation, from top to bottom, and supporting before excavation, and the slope section (22) is excavated in accordance with the principle of layered excavation, from top to bottom, and supporting as excavation progresses.