A safety management system for infrastructure construction sites
By conducting pre-collecting and simulated construction drills on the infrastructure construction site, dividing the building areas and evaluating the emergency equipment layout parameters, the problem of insufficient rationality of emergency equipment layout in the existing technology has been solved, and the value of equipment layout and the health of construction personnel has been improved. Safety.
Patent Information
- Application Number
- CN202410774355.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-17
- Publication Date
- 2025-02-07
- Estimated Expiration
- 2044-06-17
AI Technical Summary
There are few analysis of the layout of emergency equipment at the construction site in the existing technology, which makes it difficult to ensure the rationality of emergency equipment layout, and insufficient monitoring safety and the convenience of construction personnel use, thereby reducing the value of emergency equipment layout and increasing construction personnel. health risks.
The three-dimensional model is obtained through the pre-acquisition module of the infrastructure construction site and simulated construction drills, divide the internal and external building areas, and conduct emergency equipment layout evaluation based on the safety level set, generate emergency equipment layout parameters for internal and external building sub-regions to ensure equipment Rationality and monitoring security of layout.
It improves the rationality and value of emergency equipment layout, ensures the health and safety of construction personnel, and reduces the difficulty of using emergency equipment and the occurrence of construction accidents.
Smart Images

Figure CN118798528B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of infrastructure construction, and in particular to an infrastructure construction site safety management system. Background Art
[0002] In the rapidly developing modern society, infrastructure construction is an important means to promote economic growth and improve people's livelihood. However, infrastructure projects often have the characteristics of large investment, long cycle, complex technology and high labor intensity. Construction site safety management has become a key factor in ensuring project quality and construction efficiency. Safety management of infrastructure construction sites can not only protect the lives of workers, but also effectively reduce economic losses and enhance corporate image. Therefore, it is extremely necessary to carry out safety management of infrastructure construction sites.
[0003] Prior art, such as the invention application patent with announcement number: CN116934099A discloses a safety management system for infrastructure construction sites. The invention includes a safety management platform, which is connected to a site traffic safety monitoring unit, a traffic environment analysis monitoring unit, a construction equipment analysis monitoring unit, and an equipment operation safety risk unit. The site traffic safety monitoring unit performs traffic safety monitoring on the infrastructure construction site and monitors traffic around the construction area in the infrastructure construction site. The traffic environment analysis monitoring unit performs traffic environment analysis monitoring on the safety supervision area. The construction equipment analysis monitoring unit analyzes the real-time construction equipment in the safety supervision area, performs real-time safety monitoring on the safety supervision area through the analysis of real-time construction completion volume, monitors common features and makes targeted rectifications, and after the rectification is completed, the equipment operation safety risk unit performs operation safety risk analysis on the construction equipment in the safety supervision area. The invention avoids hidden dangers in the traffic locations around the construction area in the infrastructure construction site. Improve the safety of traffic in the safety supervision area, and avoid the abnormal traffic environment causing pedestrians or vehicles in the traffic area to be unable to effectively receive instructions, causing unnecessary safety accidents. The invention improves the safety of real-time completed buildings in the safety supervision area, minimizes the impact of building abnormalities, and ensures the safety performance of the safety supervision area. It ensures the equipment operation efficiency in the safety supervision area and avoids equipment operation abnormalities or equipment monitoring abnormalities, which will reduce the safety efficiency of the safety supervision area.
[0004] In view of the above scheme, it is found that: there is little analysis on the layout of emergency equipment at construction sites in the existing technology. The number of emergency equipment deployed to a certain extent reflects the demand for emergency equipment at the construction site, and the layout location of the emergency equipment is closely related to the convenience of use and construction for construction workers. At the same time, when analyzing the health status of construction workers, most of the health status thresholds of construction workers are compared. Due to the different number of emergency equipment in the area where the construction workers are located and the interference around the layout location, there is a certain impact on the health status threshold of construction workers. The existing technology ignores these aspects. On the one hand, it is difficult to ensure the rationality of the layout of emergency equipment at the construction site, and thus it is difficult to ensure the subsequent monitoring safety of the emergency equipment and the convenience of use for construction workers, reducing the value of the deployment of emergency equipment. On the other hand, when the emergency equipment is difficult to use in time, it is difficult to ensure the health of construction workers, resulting in casualties. Summary of the invention
[0005] The purpose of the present invention is to provide a infrastructure construction site safety management system that solves the problems existing in the background technology.
[0006] In order to solve the above technical problems, the present invention adopts the following technical solutions: The present invention provides a infrastructure construction site safety management system, including: an infrastructure construction site pre-collection module, which is used to pre-collect the infrastructure construction site, obtain a three-dimensional model of the infrastructure construction site, and perform simulated construction drills on the infrastructure construction site.
[0007] The infrastructure area safety level division module is used to divide the infrastructure construction site into internal building areas and external building areas, and to divide the internal building area to obtain a number of internal building sub-areas, and to divide the external building area to obtain a number of external building sub-areas, and to obtain the simulated construction drill parameters of each internal building sub-area and the simulated construction drill parameters of each external building sub-area, and then generate a set of internal building sub-area safety levels and a set of external building sub-area safety levels.
[0008] The equipment deployment assessment module is used to deploy emergency equipment to the internal building area and the external building area in turn according to the internal building sub-area safety level set and the external building sub-area safety level set.
[0009] The equipment monitoring module is used to monitor the emergency equipment in the internal building area and the external building area, and generate the internal building sub-area risk set and the external building sub-area risk set.
[0010] The early warning processing terminal is used to locate internal risk personnel and external risk personnel according to the internal building sub-area risk set and the external building sub-area risk set, and to issue early warning prompts to the internal risk personnel and the external risk personnel.
[0011] The display terminal is used to display the internal building sub-area risk set and the external building sub-area risk set.
[0012] The beneficial effects of the present invention are: 1. The present invention pre-collects the infrastructure construction site in the infrastructure construction pre-collection module and conducts simulation exercises, laying a foundation for the subsequent analysis of the safety level division of the infrastructure area.
[0013] 2. The present invention divides the infrastructure construction site into internal building areas and external building areas in the infrastructure area safety level division module, obtains the simulated construction drill parameters of each internal building sub-area and the simulated construction drill parameters of each external building sub-area, generates an internal building sub-area safety level set and an external building sub-area safety level set, and provides support for the subsequent deployment of emergency equipment in the internal building areas and the external building areas.
[0014] 3. In the equipment layout evaluation module, the present invention first evaluates the appropriate emergency equipment layout parameters of each internal building sub-area, and then analyzes each suitable layout sub-area of each internal building sub-area, which makes up for the deficiency of neglecting this aspect in the prior art, and ensures the rationality of the layout of emergency equipment at the construction site, thereby ensuring the subsequent monitoring safety of the emergency equipment and the convenience of use for construction personnel, and improving the value of the emergency equipment layout.
[0015] 4. The present invention performs emergency equipment monitoring on the internal building area and the external building area in the equipment monitoring module, and generates an internal building sub-area risk set and an external building sub-area risk set taking into account the number of emergency equipment in the area where the construction personnel are located and the interference around the layout location.
[0016] 5. The present invention uses the health status index of each worker currently in construction and the adjusted health status threshold in the early warning processing terminal to judge the risk workers currently in construction, thereby overcoming the defect of neglecting this aspect in the prior art. When emergency equipment is difficult to use in time, the health of construction workers is protected and casualties are avoided. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0018] Figure 1 It is a schematic diagram of the system structure connection of the present invention. DETAILED DESCRIPTION
[0019] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0020] Reference Figure 1 As shown, the present invention provides a infrastructure construction site safety management system, including: an infrastructure construction site pre-collection module, an infrastructure area safety level classification module, an equipment layout evaluation module, an equipment monitoring module, an early warning processing terminal and a display terminal.
[0021] The infrastructure construction site pre-collection module is used to pre-collect the infrastructure construction site, obtain a three-dimensional model of the infrastructure construction site, and perform simulated construction drills on the infrastructure construction site.
[0022] The present invention pre-collects information on the infrastructure construction site in the infrastructure construction pre-collection module and conducts simulation drills, laying a foundation for subsequent analysis of the safety level division of the infrastructure area.
[0023] The infrastructure area safety level division module is used to divide the infrastructure construction site into an internal building area and an external building area, and divide the internal building area to obtain a number of internal building sub-areas, divide the external building area to obtain a number of external building sub-areas, and obtain the simulated construction drill parameters of each internal building sub-area and the simulated construction drill parameters of each external building sub-area, thereby generating a set of internal building sub-area safety levels and a set of external building sub-area safety levels.
[0024] In a specific embodiment of the present invention, the simulated construction drill parameters include the number of personnel, temperature fluctuation graph, humidity fluctuation graph, dust fluctuation graph, height, average wind speed, and the number of equipment passing through.
[0025] It should be noted that the number of equipment passing through includes but is not limited to the number of vehicles passing through and the number of construction tools passing through.
[0026] In a specific embodiment of the present invention, the internal building sub-area security level set and the external building sub-area security level set are generated by a specific generation method: based on the simulated construction drill parameters of each internal building sub-area, simulated construction characteristic parameters of each internal building sub-area are obtained through processing; based on the simulated construction drill parameters of each external building sub-area, simulated construction characteristic parameters of each external building sub-area are obtained through similar processing.
[0027] The simulated construction characteristic parameters of each internal building sub-area are imported into the safety level evaluation model, and the safety level of each internal building sub-area is obtained by output. The safety level of each external building sub-area is obtained by similar processing. The specific safety level evaluation model is: i =m,α i ∈α′ m , where ε i is the safety level of the i-th internal building sub-area, α i is the simulated construction characteristic parameter of the i-th internal building sub-area, α′ m is the simulated construction characteristic parameter interval corresponding to the mth security level stored in the web database, i is the number of each internal building sub-area, i=1,2,...,n, n is an arbitrary integer greater than 2, m is the number of each security level, m=1,2,...,l, l is an arbitrary integer greater than 2.
[0028] Based on the security level of each internal building sub-area, generate the internal building sub-area security level set A = {ε 1 ,ε 2 ,ε 3 ,,,ε n}, where ε 1 , ε 2 , ε 3 , ε n They are the safety levels of the first inner building sub-area, the second inner building sub-area, the third inner building sub-area and the nth inner building sub-area respectively.
[0029] Based on the safety level η of each external building sub-area p , p is the number of each external building sub-area, p = 1, 2, ..., q, q is any integer greater than 2, and generates a set of external building sub-area security levels B = {η 1 ,η 2 ,η 3 ,,,η q}, where η 1 , η 2 , η 3 , η q They are the safety levels of the first external building sub-area, the second external building sub-area, the third external building sub-area and the qth external building sub-area respectively.
[0030] In a specific embodiment of the present invention, the simulated construction characteristic parameters of each internal building sub-area are specifically analyzed in the following manner: based on the number of personnel in the simulated construction drill parameters of each internal building sub-area, combined with the spatial volume of each internal building sub-area, the personnel distribution density of each internal building sub-area is calculated.
[0031] It should be noted that the calculation obtains the population distribution density of each internal building sub-area, and the specific calculation formula is: divide the number of people in each internal building sub-area by the space volume to obtain the population distribution density of each internal building sub-area.
[0032] Based on the temperature fluctuation graph, humidity fluctuation graph, dust fluctuation graph, wind speed average Q in the simulated construction drill parameters of each internal building sub-area i , and the environmental safety characteristic values of each internal building sub-area are obtained through numerical processing.
[0033] It should be noted that the environmental safety characteristic value of each internal building sub-area is specifically analyzed by: obtaining the temperature fluctuation value W based on the temperature fluctuation map, humidity fluctuation map and dust fluctuation map of each internal building sub-area i ″、Temperature mean W i , humidity fluctuation value S i ″、Humidity mean S i , dust content average F i , and calculated by the formula Calculate the environmental safety characteristic value of each internal building sub-area, where e is a natural constant, Where W i ′、S i ′、F i ′, Q i ′ respectively represent the suitable construction temperature, suitable construction humidity, suitable construction dust content, and suitable construction wind speed stored in the web database.
[0034] In a specific embodiment, the temperature fluctuation value is obtained based on the temperature fluctuation diagram of each internal building sub-area, and the specific method is: construct Y based on the temperature mean WI of each internal building sub-area i = WI, and obtain each wave point of the temperature fluctuation diagram of each internal building sub-area, and obtain the characteristic distance T between each wave point of the temperature fluctuation diagram of each internal building sub-area and the straight line ih , and then evaluate the temperature fluctuation value of each internal building sub-area h is the number of each wave point, h=1, 2, ..., g, and g is any integer greater than 2.
[0035] In another specific embodiment, the temperature fluctuation value obtained based on the temperature fluctuation diagram of each internal building sub-area can also be achieved in the following way: each wave point of the temperature fluctuation diagram of each internal building sub-area is obtained, and a straight line is formed by adjacent wave points, and the slope of the straight line of adjacent wave points is obtained to obtain each slope of the temperature fluctuation diagram of each internal building sub-area, and the slope fluctuation value of the temperature fluctuation diagram of each internal building sub-area is used as the temperature fluctuation value of each internal building sub-area.
[0036] The wave points mentioned above are specifically wave crest points or wave trough points.
[0037] Based on the height in the simulated construction drill parameters of each internal building sub-area, the risk factor corresponding to each internal building sub-area is obtained by multiplying it with the risk factor corresponding to the unit height stored in the web database.
[0038] The population distribution density, environmental safety characteristic values and risk factors of each internal building sub-area are imported into the simulated construction characteristic parameter model, and the simulated construction characteristic parameters of each internal building sub-area are output.
[0039] Based on the simulated construction drill parameters of each external building sub-area, the simulated construction characteristic parameters of each external building sub-area are obtained through similar processing.
[0040] In a specific embodiment of the present invention, the simulation construction characteristic parameter model is specifically: Where M i , H i 、F i are the personnel distribution density, environmental safety characteristic value, and risk factor of the i-th internal building sub-area, respectively.
[0041] The present invention divides the infrastructure construction site into internal building areas and external building areas in the infrastructure area safety level division module, obtains simulated construction drill parameters of each internal building sub-area and simulated construction drill parameters of each external building sub-area, generates an internal building sub-area safety level set and an external building sub-area safety level set, and provides support for the subsequent deployment of emergency equipment in the internal building areas and the external building areas.
[0042] The equipment deployment assessment module is used to deploy emergency equipment in the internal building area and the external building area in sequence according to the internal building sub-area safety level set and the external building sub-area safety level set.
[0043] In a specific embodiment of the present invention, the emergency equipment deployment in the internal building area and the external building area is carried out, and the specific deployment process is: extracting the safety level of each internal building sub-area from the internal building sub-area safety level set, and obtaining the emergency equipment parameters corresponding to each safety level from the web database, and screening the appropriate emergency equipment parameters for each internal building sub-area.
[0044] It should be noted that the emergency equipment parameters include a required number of emergency equipment combinations, and the first aid equipment combination includes a first aid kit, a first aid bed, and first aid medicines.
[0045] Based on the appropriate emergency equipment layout parameters of each internal building sub-area, the unit layout volume of each internal building sub-area is constructed.
[0046] It should be noted that the volumes of the equipment in a group of emergency equipment combinations are integrated to obtain the unit layout volume of each internal building sub-area.
[0047] The bottom surface of each internal building sub-area is divided into regions according to the unit layout volume to obtain each sub-area of each internal building sub-area, and each suitable layout sub-area of each internal building sub-area is screened.
[0048] Through similar processing, suitable emergency equipment layout parameters for each external building sub-area and each suitable layout sub-area are obtained.
[0049] Emergency equipment is deployed in the internal building area according to the appropriate emergency equipment deployment parameters of each internal building sub-area and each suitable deployment sub-area, and emergency equipment is deployed in the external building area according to the appropriate emergency equipment deployment parameters of each external building sub-area and each suitable deployment sub-area.
[0050] In a specific embodiment of the present invention, the specific analysis method for screening the suitable layout sub-areas of each internal building sub-area is as follows: extracting the number of personnel and the number of equipment passing through from the simulated construction drill parameters of each internal building sub-area, and locating the number of personnel involved and the number of equipment passing through each sub-area corresponding to each internal building sub-area.
[0051] It should be noted that, based on the simulated construction drills conducted at the infrastructure construction site, the number of people involved and the number of equipment passing through each internal building sub-area corresponding to each sub-area were located.
[0052] Based on the installation points of the monitoring equipment reserved in each internal building sub-area, the monitoring volume of each sub-area of each internal building sub-area is obtained.
[0053] Based on the number of people involved in each sub-area corresponding to each internal building sub-area R if , the number of equipment involved SL if and monitoring volume Vif , after numerical processing, the layout characteristic parameters of each sub-area of each internal building sub-area are obtained.
[0054] It should be noted that the specific analysis method of the layout characteristic parameters of each sub-area of each internal building sub-area is as follows: f is the number of each sub-area, f=1, 2, ..., t, and t is any integer greater than 2.
[0055] It should be noted that the mobility of personnel, the mobility of vehicles and the convenience of subsequent monitoring all affect the choice of the deployment area of emergency equipment. If the mobility of personnel in a deployment area is higher, the mobility of vehicles is higher, and the convenience of monitoring is lower, it will affect the construction work of personnel, the passage of vehicles and normal monitoring, which is not conducive to subsequent construction and monitoring.
[0056] The sub-areas of each internal building sub-area are arranged in order from top to bottom according to the layout characteristic parameters, and the suitable layout sub-areas are selected based on the emergency equipment parameters of each internal building sub-area to obtain the suitable layout sub-areas of each internal building sub-area.
[0057] It should be noted that the specific method for selecting suitable sub-areas for layout based on the emergency equipment parameters of each internal building sub-area is as follows: based on the sub-areas of the sorted internal building sub-areas, in order from top to bottom, the sub-areas corresponding to the number of demand groups of each internal building sub-area are selected from the sorted sub-areas of the internal building sub-areas in turn, as the suitable sub-areas for layout of each internal building sub-area.
[0058] The present invention first evaluates the suitable emergency equipment parameters of each internal building sub-area in the equipment layout evaluation module, and then analyzes each suitable layout sub-area of each internal building sub-area, which makes up for the deficiency of neglecting this aspect in the prior art, and ensures the rationality of the layout of emergency equipment at the construction site, thereby ensuring the subsequent monitoring safety of the emergency equipment and the convenience of use for construction personnel, and improving the value of the emergency equipment layout.
[0059] The equipment monitoring module is used to monitor the emergency equipment in the internal building area and the external building area, and generate an internal building sub-area risk set and an external building sub-area risk set.
[0060] In a specific embodiment of the present invention, the specific method for generating the internal building sub-area risk set and the external building sub-area risk set is: based on the video of emergency equipment monitoring of the internal building area and the external building area, the use frequency CI of the emergency equipment corresponding to each suitable sub-area of each internal building sub-area is obtained. if , the volume of the obstacle areaVI if, after data processing, the constraint characteristic values of each building sub-area corresponding to each suitable layout sub-area are obtained.
[0061] It should be noted that each building sub-area corresponds to a constraint characteristic value of each suitable layout sub-area, and the specific analysis method is as follows: Where CI′ is the estimated usage frequency of a group of emergency equipment combinations, VI i ' f The volume of each building sub-area corresponding to each suitable sub-area layout.
[0062] It is necessary to add that the frequency of use of emergency equipment in the deployment area and the volume of the obstacle area affect the adequacy, ease of use and ease of replenishment of emergency equipment in the deployment area. By using the constraint characteristic values of each building sub-area corresponding to each suitable deployment sub-area, risky deployment sub-areas are screened, and important attention is paid to construction personnel in subsequent risky deployment sub-areas to prevent accidents and protect the health of construction personnel.
[0063] Through the risk judgment model, the risk layout sub-areas corresponding to each building sub-area are obtained, and the risk layout sub-areas are numbered as 1, 2, ..., j, ..., k, and then the internal building sub-area risk set C = {u1i, u2i, u3i,,,uki} is generated based on this, where u1 i 、u2 i 、u3 i ,uk i They are respectively represented as the first risk layout sub-area, the second risk layout sub-area, the third risk layout sub-area, and the kth risk layout sub-area corresponding to the i-th building sub-area.
[0064] It should be noted that the risk judgment model is specifically: Output the risk value θ of each building sub-area corresponding to each layout sub-area if , and record each layout sub-area with a risk value of 1 as each risk layout sub-area, and obtain each risk layout sub-area corresponding to each building sub-area, where σ′ is the preset constraint feature threshold.
[0065] After similar analysis and processing, a risk set of external building sub-areas is generated.
[0066] The present invention performs emergency equipment monitoring on internal building areas and external building areas in the equipment monitoring module, and generates an internal building sub-area risk set and an external building sub-area risk set, taking into account the number of emergency equipment in the area where construction workers are located and the interference around the layout location.
[0067] The early warning processing terminal is used to locate internal risk personnel and external risk personnel according to the internal building sub-area risk set and the external building sub-area risk set, and to issue early warning prompts to the internal risk personnel and the external risk personnel.
[0068] In a specific embodiment of the present invention, the specific analysis method for locating internal risk personnel and external risk personnel is as follows: obtain the current construction sub-areas of the infrastructure construction site and the construction personnel in each sub-area, and based on the internal construction sub-area risk set, obtain the risk-affected areas and the corresponding construction personnel in the current construction sub-areas of the infrastructure construction site.
[0069] It should be noted that the risk affected areas of each current construction building sub-area of the infrastructure construction site are specifically: the surrounding sub-areas of each risk layout sub-area of each current construction building sub-area of the infrastructure construction site, and they are summarized to obtain the risk affected areas of each current construction building sub-area of the infrastructure construction site.
[0070] Obtain the health status index K of each construction worker in each risk affected area of each current construction sub-area of the infrastructure construction site ixb , x is the number of each risk affected area, x=1,2,...,y, y is any integer greater than 2, b is the number of each construction worker, b=1,2,...,d, d is any integer greater than 2, and the health status assessment model is used to obtain the risk construction workers in each risk affected area of each current construction sub-area of the infrastructure construction site, and the internal risk workers are summarized and the external risk workers are obtained through similar processing.
[0071] It should be noted that when carrying out infrastructure construction, construction workers usually wear technology bracelets, head-mounted helmets, safety vests or safety glasses to check their health status, so that timely warnings can be issued when the construction workers have physical abnormalities. The existing technology is relatively mature and will not be elaborated here.
[0072] It should also be noted that each construction worker with a health safety value of -1 is recorded as a risky construction worker, and the risky construction workers in each risk-affected area of each current construction sub-area of the infrastructure construction site are obtained.
[0073] In a specific embodiment of the present invention, the health status evaluation model is specifically:
[0074]
[0075] Where ξ ixb is the health safety value of the bth construction worker in the xth risk affected area of the current i-th construction sub-area of the infrastructure construction site, σix is the constraint characteristic value of the risk layout sub-area belonging to the x-th risk affected area of the current ith construction sub-area of the infrastructure construction site, K′ is the preset health status index threshold, and τ is the health status index reduction value corresponding to the preset unit constraint characteristic increase value.
[0076] The present invention judges the risky workers of the current construction according to the health status index of each worker currently under construction in combination with the adjusted health status threshold in the early warning processing terminal, thereby overcoming the defect of neglecting this aspect in the prior art. When emergency equipment is difficult to use in time, the health of the construction workers is protected and casualties are avoided.
[0077] The display terminal is used to display the internal building sub-area risk set and the external building sub-area risk set.
[0078] It should be noted that the present invention also includes a web database for storing simulated construction characteristic parameter intervals corresponding to each safety level, emergency equipment parameters and the volume of each equipment, suitable construction temperature, suitable construction humidity, suitable construction dust content, suitable construction wind speed, and risk factors corresponding to unit height.
[0079] It should also be noted that the infrastructure construction site pre-collection module is connected to the infrastructure area safety level division module, the infrastructure area safety level division module is connected to the equipment deployment assessment module, the equipment deployment assessment module is connected to the equipment monitoring module, the equipment monitoring module is respectively connected to the early warning processing terminal and the display terminal, and the web database is respectively connected to the infrastructure area safety level division module and the equipment deployment assessment module.
[0080] The above contents are merely examples and explanations of the concept of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the concept of the invention or exceed the scope defined by the present invention, they shall all fall within the protection scope of the present invention.
Claims
1. A construction site safety management system, characterized in that: include: The infrastructure construction site pre-collection module is used to pre-collect the infrastructure construction site, obtain the three-dimensional model of the infrastructure construction site, and conduct simulated construction drills on the infrastructure construction site; The infrastructure area safety level division module is used to divide the infrastructure construction site into an internal building area and an external building area, and divide the internal building area to obtain a number of internal building sub-areas, divide the external building area to obtain a number of external building sub-areas, and obtain the simulated construction drill parameters of each internal building sub-area and the simulated construction drill parameters of each external building sub-area, thereby generating a set of internal building sub-area safety levels and a set of external building sub-area safety levels; The simulated construction drill parameters include the number of personnel, temperature fluctuation graph, humidity fluctuation graph, dust fluctuation graph, height, average wind speed, and number of equipment passing; The specific generation method of the internal building sub-area security level set and the external building sub-area security level set is as follows: based on the simulated construction drill parameters of each internal building sub-area, the simulated construction characteristic parameters of each internal building sub-area are obtained through processing; based on the simulated construction drill parameters of each external building sub-area, the simulated construction characteristic parameters of each external building sub-area are obtained through similar processing; The simulated construction characteristic parameters of each internal building sub-area are imported into the safety level evaluation model, and the safety level of each internal building sub-area is obtained by output. The safety level of each external building sub-area is obtained by similar processing. The specific safety level evaluation model is: i =m,α i ∈α′ m , where ε i is the safety level of the i-th internal building sub-area, α i is the simulated construction characteristic parameter of the i-th internal building sub-area, α′ m is the simulated construction characteristic parameter interval corresponding to the mth security level stored in the web database, i is the number of each internal building sub-area, i=1,2,...,n, n is any integer greater than 2, m is the number of each security level, m=1,2,...,l, l is any integer greater than 2; Based on the security level of each internal building sub-area, generate the internal building sub-area security level set A = {ε1,ε2,ε3,,,ε n }, where ε1, ε2, ε3, ε n The safety levels of the first inner building sub-area, the second inner building sub-area, the third inner building sub-area and the nth inner building sub-area respectively; Based on the safety level η of each external building sub-area p , p is the number of each external building sub-area, p = 1, 2, ..., q, q is any integer greater than 2, and generates a set of external building sub-area security levels B = {η1, η2, η3,,, η q }, where eta1, eta2, eta3, eta q The safety levels of the first external building sub-area, the second external building sub-area, the third external building sub-area and the qth external building sub-area respectively; The simulated construction characteristic parameters of each internal building sub-area are specifically analyzed in the following manner: based on the number of personnel in the simulated construction drill parameters of each internal building sub-area, combined with the spatial volume of each internal building sub-area, the personnel distribution density of each internal building sub-area is calculated; Based on the temperature fluctuation graph, humidity fluctuation graph, dust fluctuation graph, and wind speed average value in the simulated construction drill parameters of each internal building sub-area, the environmental safety characteristic value of each internal building sub-area is obtained through numerical processing; Based on the height in the simulated construction drill parameters of each internal building sub-area, multiply it by the risk factor corresponding to the unit height stored in the web database to obtain the risk factor corresponding to each internal building sub-area; Importing the population distribution density, environmental safety characteristic values and risk factors of each internal building sub-area into the simulated construction characteristic parameter model, and outputting the simulated construction characteristic parameters of each internal building sub-area; Based on the simulated construction drill parameters of each external building sub-area, the simulated construction characteristic parameters of each external building sub-area are obtained through similar processing; The simulation construction characteristic parameter model is specifically as follows: Where M i , H i 、F i are the personnel distribution density, environmental safety characteristic value, and risk factor of the i-th internal building sub-area respectively; An equipment deployment assessment module is used to deploy emergency equipment in the internal building area and the external building area in turn according to the internal building sub-area safety level set and the external building sub-area safety level set; The specific process of deploying emergency equipment in the internal building area and the external building area is as follows: extracting the safety level of each internal building sub-area from the safety level set of the internal building sub-area, obtaining the emergency equipment parameters corresponding to each safety level from the web database, and screening the appropriate emergency equipment parameters for each internal building sub-area; Based on the appropriate emergency equipment layout parameters of each internal building sub-area, the unit layout volume of each internal building sub-area is constructed; Divide the bottom surface of each internal building sub-area into regions according to the unit layout volume to obtain each sub-area of each internal building sub-area, and select each suitable layout sub-area of each internal building sub-area; After similar processing, the appropriate emergency equipment layout parameters and appropriate layout sub-areas of each external building sub-area are obtained; Deploy emergency equipment in the internal building area according to the appropriate emergency equipment deployment parameters of each internal building sub-area and each appropriate deployment sub-area, and deploy emergency equipment in the external building area according to the appropriate emergency equipment deployment parameters of each external building sub-area and each appropriate deployment sub-area; The specific analysis method for screening the suitable sub-areas for layout of each internal building sub-area is as follows: extracting the number of personnel and the number of equipment passing from the simulated construction drill parameters of each internal building sub-area, and locating the number of personnel involved and the number of equipment passing corresponding to each sub-area of each internal building sub-area; Based on the installation points of monitoring equipment reserved for each internal building sub-area, obtaining the monitoring volume of each sub-area of each internal building sub-area; Based on the number of personnel involved, the number of equipment passing and the monitoring volume of each sub-area corresponding to each internal building sub-area, the layout characteristic parameters of each sub-area of each internal building sub-area are obtained through numerical processing; Arrange the sub-areas of each internal building sub-area in order from top to bottom according to the layout characteristic parameters, and select suitable layout sub-areas based on the emergency equipment parameters of each internal building sub-area to obtain suitable layout sub-areas of each internal building sub-area; An equipment monitoring module is used to monitor emergency equipment in the internal building area and the external building area, and generate an internal building sub-area risk set and an external building sub-area risk set; The specific method of generating the risk set of the internal building sub-area and the risk set of the external building sub-area is as follows: based on the video of emergency equipment monitoring of the internal building area and the external building area, the frequency of use of emergency equipment corresponding to each suitable sub-area of each internal building sub-area and the volume of the obstacle area are obtained, and the constraint characteristic value corresponding to each suitable sub-area of each building sub-area is obtained through data processing; Through the risk judgment model, the risk layout sub-areas corresponding to each building sub-area are obtained, and the risk layout sub-areas are numbered as 1, 2, ..., j, ..., k, and then the internal building sub-area risk set C = {u1 i ,u2 i ,u3 i ,,,uk i }, where u1 i 、u2 i 、u3 i ,uk i They are respectively represented as the first risk layout sub-area, the second risk layout sub-area, the third risk layout sub-area, and the kth risk layout sub-area corresponding to the i-th building sub-area; After similar analysis and processing, a risk set of external building sub-areas is generated; The early warning processing terminal is used to locate each internal risk person and each external risk person according to the internal building sub-area risk set and the external building sub-area risk set, and issue early warning prompts to each internal risk person and each external risk person; The display terminal is used to display the internal building sub-area risk set and the external building sub-area risk set.
2. A construction site safety management system according to claim 1, characterized in that: The specific analysis method for locating internal and external risk personnel is as follows: Obtain the current construction sub-areas of the infrastructure construction site and the construction personnel in each sub-area, and based on the internal construction sub-area risk set, obtain the risk affected areas of the current construction sub-areas of the infrastructure construction site and their corresponding construction personnel; Obtain the health status index K of each construction worker in each risk affected area of each current construction sub-area of the infrastructure construction site ixb , x is the number of each risk affected area, x=1,2,...,y, y is any integer greater than 2, b is the number of each construction worker, b=1,2,...,d, d is any integer greater than 2, and the health status assessment model is used to obtain the risk construction workers in each risk affected area of each current construction sub-area of the infrastructure construction site, and the internal risk workers are summarized and the external risk workers are obtained through similar processing.
3. A construction site safety management system according to claim 2, characterized in that: The health status evaluation model is specifically as follows: Where ξ ixb is the health safety value of the bth construction worker in the xth risk affected area of the current i-th construction sub-area of the infrastructure construction site, σ ix is the constraint characteristic value of the risk layout sub-area belonging to the x-th risk affected area of the current ith construction sub-area of the infrastructure construction site, K′ is the preset health status index threshold, and τ is the health status index reduction value corresponding to the preset unit constraint characteristic increase value.
Citation Information
Patent Citations
Infrastructure construction site safety management system
CN116934099A
Building construction site emergency and rescue management system and method based on BIM (Building Information Modeling)
CN108876082A
Building construction operation informatization management platform based on big data analysis
CN114819488A