Automatic welding equipment and welding method for steel mesh for construction

Through the design of automated welding equipment, automatic placement and resistance spot welding of steel bars are achieved using hydraulic cylinders and limiting components, which solves the efficiency and quality problems of steel bar mesh welding in the prior art, and improves the accuracy and efficiency of welding.

CN118808848BActive Publication Date: 2024-12-13ANHUI JIUQIANJIU NEW MATERIALS CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411297210.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-18
Publication Date
2024-12-13
Estimated Expiration
2044-09-18

AI Technical Summary

Technical Problem

The existing steel mesh welding technology requires manual operation, resulting in cumbersome feeding of horizontal steel bars, and the longitudinal steel bars are prone to leakage and angular deviation, affecting welding efficiency and quality.

Method used

Design an automated welding equipment, using horizontal and longitudinal loading plates, hydraulic cylinders, limiting components and welding mechanisms, to realize the automatic placement of multiple steel bars and resistive spot welding, ensuring the accuracy and high efficiency of welding.

Benefits of technology

Automatic placement and rapid welding of multiple steel bars is realized, which avoids offset problems in manual operations, improves welding efficiency and quality, and ensures the accurate welding and circulating welding process of the steel bar mesh.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118808848B_ABST
    Figure CN118808848B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of steel mesh processing, and provides an automated welding device and welding method for steel mesh for construction, comprising a base, a pair of side plates arranged transversely fixedly mounted on the base, a plurality of conveying wheels mounted on the top side walls of the pair of side plates facing each other, a plurality of transverse loading plates for transverse conveying placed between the plurality of pairs of conveying wheels, a plurality of transverse steel bar grooves spaced apart on the transverse loading plates, a plurality of pairs of longitudinal limit assemblies spaced apart on the transverse loading plates in the longitudinal direction, and welding holes spaced apart at the bottom of the plurality of transverse steel bar grooves. The present invention also discloses a welding method for automated welding equipment, which can automatically complete the placement process of a plurality of transverse steel bars and a plurality of longitudinal steel bars without offset, adopts resistance spot welding to quickly weld, has high welding quality, and can realize cycle welding and automated material unloading process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of steel mesh processing, and in particular to an automatic welding device and a welding method for a steel mesh for construction. Background Art

[0002] The steel mesh is made of longitudinal steel bars and transverse steel bars arranged at a certain interval and at right angles to each other, with all intersections welded together. Currently, most steel meshes are welded by steel mesh welding machines. Before welding, the existing steel mesh machines need to feed several transverse steel bars into the feeding end of the steel mesh welding machine through a transverse steel bar feeding device, and on the other hand, the longitudinal steel bars need to be fed one by one onto the transverse steel bars through a longitudinal steel bar feeding device, and then the longitudinal steel bars and the transverse steel bars are welded together through the welding device on the steel mesh welding machine, and finally formed into a steel mesh and then output.

[0003] This welding method requires manual feeding of multiple transverse steel bars into the corresponding transverse steel bar feeding device, which is rather troublesome. In addition, the longitudinal steel bar feeding device uses a circulating belt to feed the steel bars one by one, which is prone to leakage. When the longitudinal steel bars fall on the transverse steel bars, the angle is easily offset, which affects the welding effect. Feeding the steel bars one by one affects the overall welding efficiency. Summary of the invention

[0004] In view of the above problems, the present invention provides an automated welding device and welding method for a steel mesh for construction. The device can automatically complete the placement process of multiple transverse steel bars and multiple longitudinal steel bars without deviation, adopts resistance spot welding to quickly weld, has high welding quality, and can realize cyclic welding and automated material cutting process.

[0005] To solve the above problems, the technical solution adopted by the present invention is:

[0006] An automated welding device for building steel mesh comprises a base, a pair of transversely arranged side plates are fixedly mounted on the base, a plurality of conveying wheels are mounted on the top side walls of the pair of side plates facing each other, a plurality of transverse loading plates for transverse conveying are placed between the pairs of conveying wheels, a plurality of transverse steel bar grooves are arranged at intervals on the transverse loading plates, a plurality of pairs of longitudinal limit assemblies are arranged at intervals on the transverse loading plates in the longitudinal direction, welding holes are arranged at intervals on the bottoms of the plurality of transverse steel bar grooves, longitudinal loading platforms flush with the top surfaces of the transverse loading plates are fixedly mounted on both sides of the middle top of the pair of side plates, a transverse material box that can move longitudinally through the transverse loading plates is mounted on the rear longitudinal loading platform, and the The bottom of the transverse material box is provided with a transverse material discharge channel that contacts the top surface of the longitudinal loading platform, a pair of side panels are installed with mounting frames on the top, a liftable longitudinal loading plate is installed on the top of the mounting frame, a plurality of longitudinal steel bar openings are arranged at intervals on the longitudinal loading plate, an opening and closing assembly that can synchronously open the plurality of longitudinal steel bar openings is installed on the bottom of the longitudinal loading plate, a pair of transverse material loading platforms flush with the top surface of the longitudinal loading plate are fixedly installed on the top of the mounting frame, a longitudinal material box that can move laterally through the longitudinal loading plate is installed on the transverse loading platform, the bottom of the longitudinal material box is connected to the longitudinal material discharge channel, and a welding mechanism that cooperates with the welding hole is installed on the left side of the mounting frame and the corresponding position of the side panel.

[0007] Preferably, sprockets are fixedly mounted at the ends of the wheel axles of the plurality of conveying wheels, chains are sleeved between the plurality of sprockets on one side, the chains are used to drive a row of sprockets to rotate synchronously, and the front and rear sides of the transverse loading plate are placed on the plurality of conveying wheels.

[0008] Preferably, the longitudinal limit assembly includes a plurality of pairs of limit grooves, and the plurality of pairs of limit grooves are arranged between adjacent transverse steel bar grooves of the transverse loading plate. A limit plate is provided in the limit groove, and a connecting rod extending from the limit groove is fixed to the bottom of the limit plate, and an extended end of the connecting rod is fixedly connected to a stop plate, and a plurality of welding holes corresponding to the welding holes on the transverse loading plate are provided on the stop plate, and a plurality of matching magnetic sheets are embedded on the top surface of the stop plate and the bottom surface of the transverse loading plate, and a first cylinder for rising against the stop plate is installed in the middle of the base.

[0009] Preferably, a longitudinal hydraulic cylinder capable of driving the longitudinal movement of the transverse material discharge channel is installed at the end of the longitudinal material loading platform on the rear side, and a transverse hydraulic cylinder capable of driving the transverse movement of the longitudinal material discharge channel is installed at the end of the transverse material loading platform on the right side.

[0010] Preferably, the opening and closing assembly includes a baffle slidably installed at the bottom of the longitudinal loading plate, the baffle is provided with a plurality of discharge ports spaced apart in the longitudinal direction, the plurality of discharge ports correspond one-to-one to a plurality of longitudinal steel bar ports, and a second cylinder is installed at the end of the longitudinal loading plate that can drive the baffle to move laterally.

[0011] Preferably, the welding mechanism includes a pair of third cylinders fixedly mounted on the mounting frame and the side plate, the opposite ends of the pair of third cylinders are fixedly mounted with longitudinally arranged pressure plates, the opposite sides of the pair of pressure plates are fixedly connected with a plurality of anti-pillars, the bottoms of the upper plurality of anti-pillars are fixed with upper electrodes, the tops of the lower plurality of anti-pillars are fixed with lower electrodes, and the lower anti-pillars and lower electrodes are adapted to the plurality of longitudinal welding holes.

[0012] Preferably, a pair of liftable transverse guide rails are installed between the left and right ends of a pair of side panels, a pair of transverse conveyor belts are installed on opposite sides of the bottom of a pair of side panels, upward hydraulic cylinders are installed at the bottom of the left and right ends of the base, the telescopic ends of the upward hydraulic cylinders are fixedly connected to the corresponding transverse guide rails, the transverse guide rails are raised to the highest point and flush with the conveying wheels, and a transversely arranged fourth cylinder is fixedly installed between the right ends of the pair of side panels, and the fourth cylinder is used to push the transverse loading plate onto the conveying wheel.

[0013] Preferably, a suspension arm is installed above the left end of a pair of side panels, an electromagnetic suction plate is installed at the end of the suspension arm, a plurality of abutment rods corresponding to the limiting grooves are fixed to the bottom of the electromagnetic suction plate, and the electromagnetic suction plate is used to magnetically absorb the welded steel mesh.

[0014] Preferably, a downward hydraulic cylinder capable of driving the longitudinal loading plate to move up and down is installed on the top of the mounting frame.

[0015] The present invention also provides an automated welding method for a steel mesh for construction, comprising the following specific steps:

[0016] S1. The transverse loading plate is smoothly transported to the bottom of the longitudinal loading plate by multiple pairs of conveying wheels, and the transverse material box is pushed to move by the longitudinal hydraulic cylinder, so that the transverse material discharge channel passes through the transverse loading plate, and the steel bars stacked transversely inside automatically fall into the multiple transverse steel bar grooves. The transverse hydraulic cylinder is synchronously started to drive the longitudinal material box to move transversely, and the steel bars in the longitudinal material discharge channel automatically fall into the multiple longitudinal steel bar openings on the longitudinal loading plate;

[0017] S2, start the first cylinder to drive the stop plate to rise, then drive the multiple pairs of limit plates to extend out of the limit slots through multiple connecting rods, drive the longitudinal loading plate to descend to a position close to the transverse loading plate through the downward hydraulic cylinder, start the second cylinder to push the baffle, so that the multiple discharge ports correspond to the multiple longitudinal steel bar ports one by one, and the longitudinal steel bars fall between the multiple pairs of longitudinal limit plates, so that the multiple transverse steel bars and the multiple longitudinal steel bars are equidistantly placed crosswise;

[0018] S3, the cross-placed steel bars continue to move to the left through the transverse loading plate, a pair of third cylinders are intermittently started, multiple longitudinal upper electrodes touch the top of the intersection, multiple longitudinal lower electrodes pass through the welding holes and touch the bottom of the intersection, the electrodes are energized, the steel bars at the intersection are heated and melted, and then the pressure plate is used to pressurize the steel bars at the intersection to weld them together, and the intermittent movement and intermittent welding can complete the welding process of the steel mesh;

[0019] S4, the welded steel mesh continues to move to a pair of horizontal guide rails at the left end, and the electromagnetic suction plate is driven down by the crane arm to magnetically suck the steel mesh for unloading;

[0020] S5. After unloading, the transverse loading plate is lowered and placed on a pair of conveyor belts, transported to the right end, and then raised to be parallel to the conveyor wheel through a pair of transverse guide rails at the right end. The fourth cylinder can be started to push the transverse loading plate onto the conveyor wheel again to realize the cyclic welding process.

[0021] The beneficial effects of the present invention are:

[0022] 1. By installing the transverse loading plate, longitudinal loading platform, transverse material box, longitudinal loading plate, transverse loading platform, longitudinal material box and other components, the transverse material box is pushed to move by the longitudinal hydraulic cylinder, so that the transverse unloading channel is against the transverse loading plate, and the steel bars stacked horizontally inside automatically fall into the multiple transverse steel bar grooves. The transverse hydraulic cylinder is started synchronously to drive the longitudinal material box to move horizontally, and the steel bars in the longitudinal unloading channel are automatically dropped into the multiple longitudinal steel bar openings on the longitudinal loading plate, and the pre-placement process of multiple transverse steel bars and multiple longitudinal steel bars can be completed synchronously.

[0023] 2. By installing the longitudinal limit assembly and the downward hydraulic cylinder, start the first cylinder to drive the stop plate to rise, and then drive multiple pairs of limit plates to extend out of the limit slot through multiple connecting rods, and drive the longitudinal loading plate to descend to the position close to the transverse loading plate through the downward hydraulic cylinder, and start the second cylinder to push the baffle, so that the multiple discharge ports correspond to the multiple longitudinal steel bar ports one by one, and the longitudinal steel bars fall between the multiple pairs of longitudinal limit plates, so that multiple transverse steel bars and multiple longitudinal steel bars are equidistantly placed crosswise, and the placement process of the entire steel mesh is completed quickly without offset, thereby ensuring the accuracy of welding.

[0024] 3. By installing multiple pairs of conveying wheels and welding mechanisms, the chain can synchronously drive multiple sprockets to rotate, and then synchronously drive multiple pairs of conveying wheels to rotate, and the cross-placed steel bars continue to move to the left through the transverse loading plate. A pair of third cylinders are intermittently started, and multiple longitudinal upper electrodes touch the top of the intersection, and multiple longitudinal lower electrodes pass through the welding holes to touch the bottom of the intersection. The electrodes are energized, and the steel bars at the intersection are heated and melted, and then the pressure plate is used to pressurize the steel bars at the intersection to weld them together. The welding process of the steel mesh can be completed by intermittent movement and intermittent welding. The welding process is quickly completed in the form of resistance spot welding, and the welding is accurate and efficient.

[0025] 4. By installing the boom and the electromagnetic suction plate, the welded steel mesh continues to move to a pair of horizontal guide rails at the left end. The electromagnetic suction plate is driven down by the boom. Multiple push rods first push multiple pairs of limit plates back into the limit grooves, so that the bottom surface of the electromagnetic suction plate contacts the steel mesh, and the steel mesh can be magnetically sucked for unloading.

[0026] 5. By installing two pairs of transverse guide rails and conveyor belts, the transverse loading plate after unloading is lowered by the upward hydraulic cylinder and placed on a pair of conveyor belts, transported to the right end, and then raised to a position parallel to the conveyor wheel through a pair of transverse guide rails at the right end. Starting the fourth cylinder can push the transverse loading plate onto the conveyor wheel again to realize the cyclic welding process. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a structural schematic diagram of the present invention;

[0028] Figure 2 A schematic diagram of a middle cross-sectional view of a pair of side panels proposed by the present invention;

[0029] Figure 3 A cross-sectional schematic diagram of a transverse loading plate proposed by the present invention;

[0030] Figure 4 A top view of the transverse loading plate proposed by the present invention;

[0031] Figure 5 A schematic top view of the baffle proposed by the present invention;

[0032] Figure 6 This is a schematic top view of the pressing plate proposed by the present invention.

[0033] In the figure: 1 side plate, 2 fourth cylinder, 3 horizontal loading platform, 4 horizontal hydraulic cylinder, 5 longitudinal material box, 6 second cylinder, 7 mounting frame, 8 downward hydraulic cylinder, 9 longitudinal loading plate, 10 pressure plate, 11 support column, 12 horizontal loading plate, 13 support plate, 14 conveying wheel, 15 first cylinder, 16 conveying belt, 17 base, 18 electromagnetic suction plate, 19 boom, 20 support rod, 21 horizontal guide rail, 22 upward hydraulic cylinder, 23 longitudinal loading platform, 24 sprocket, 25 chain, 26 horizontal material box, 27 longitudinal hydraulic cylinder, 28 horizontal unloading channel, 29 longitudinal steel bar mouth, 30 baffle, 31 horizontal steel bar groove, 32 limit groove, 33 limit plate, 34 welding hole, 35 connecting rod, 36 magnetic sheet, 37 discharge port, 38 longitudinal unloading channel, 39 third cylinder. DETAILED DESCRIPTION

[0034] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific embodiments of the present invention are described in detail below in conjunction with the accompanying drawings. In the following description, many specific details are set forth to facilitate a full understanding of the present invention. However, the present invention can be implemented in many other ways different from those described herein, and those skilled in the art can make similar improvements without violating the connotation of the present invention, so the present invention is not limited by the specific implementation disclosed below.

[0035] It should be noted that when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only and do not represent the only implementation method.

[0036] Reference Figure 1-6 , an automated welding device for a steel mesh for construction, comprising a base 17, a pair of side plates 1 arranged transversely are fixedly mounted on the base 17, a plurality of conveying wheels 14 are mounted on the top side walls facing each other of the pair of side plates 1, a plurality of transverse loading plates 12 for transverse conveyance are placed between the plurality of pairs of conveying wheels 14, sprocket wheels 24 are fixedly mounted at the ends of the wheel axles of the plurality of conveying wheels 14, a chain 25 is sleeved between the plurality of sprocket wheels 24 on one side, the chain 25 is used to drive a row of sprocket wheels 24 to rotate synchronously, the front and rear sides of the transverse loading plates 12 are placed on the plurality of conveying wheels 14, the chain 25 can synchronously drive the plurality of sprocket wheels 24 to rotate, and then synchronously drive the plurality of pairs of conveying wheels 14 to rotate, and smoothly convey the transverse loading plates 12 laterally.

[0037] A plurality of transverse steel bar grooves 31 are arranged at intervals on the transverse loading plate 12, and longitudinal loading platforms 23 flush with the top surface of the transverse loading plate 12 are fixedly installed on both sides of the middle top of a pair of side plates 1, and a transverse material box 26 that can move longitudinally through the transverse loading plate 12 is installed on the rear longitudinal loading platform 23, and a transverse unloading channel 28 that abuts against the top surface of the longitudinal loading platform 23 is provided at the bottom of the transverse material box 26, and a longitudinal hydraulic cylinder 27 that can drive the transverse unloading channel 28 to move longitudinally is installed at the end of the rear longitudinal loading platform 23, and the transverse material box 26 is pushed to move by the longitudinal hydraulic cylinder 27, so that the transverse unloading channel 28 abuts against the transverse loading plate 12, and the steel bars stacked horizontally inside automatically fall into the plurality of transverse steel bar grooves 31.

[0038] The transverse loading plate 12 is provided with a plurality of pairs of longitudinal limit assemblies at intervals in the longitudinal direction, and the longitudinal limit assemblies include a plurality of pairs of limit grooves 32, and the plurality of pairs of limit grooves 32 are arranged between adjacent transverse steel bar grooves 31 of the transverse loading plate 12, and a limit plate 33 is arranged in the limit groove 32, and a connecting rod 35 extending from the limit groove 32 is fixed to the bottom of the limit plate 33, and an extended end of the connecting rod 35 is fixedly connected to the abutment plate 13, and a plurality of welding holes 34 corresponding to the welding holes 34 on the transverse loading plate 12 are provided on the abutment plate 13. 4. The top surface of the abutment plate 13 and the bottom surface of the transverse loading plate 12 are both embedded with a plurality of matching magnetic sheets 36. The middle part of the base 17 is provided with a first cylinder 15 for rising against the abutment plate 13. The abutment plate 13 is raised by starting the first cylinder 15, and then the plurality of pairs of limit plates 33 are driven to extend out of the limit grooves 32 through the plurality of connecting rods 35. The plurality of pairs of magnetic sheets 36 are magnetically attracted to each other, and then the plurality of pairs of limit plates 33 are kept in an extended state during the welding process, and the crossover will not be offset, thereby ensuring the accuracy of welding.

[0039] A mounting frame 7 is installed on the top of a pair of side plates 1, and a liftable longitudinal loading plate 9 is installed on the top of the mounting frame 7. A downward hydraulic cylinder 8 that can drive the longitudinal loading plate 9 to move up and down is installed on the top of the mounting frame 7. A plurality of longitudinal steel bar openings 29 are arranged at intervals on the longitudinal loading plate 9, and an opening and closing assembly that can synchronously open the plurality of longitudinal steel bar openings 29 is installed at the bottom of the longitudinal loading plate 9. A pair of transverse loading platforms 3 flush with the top surface of the longitudinal loading plate 9 are fixedly installed on the top of the mounting frame 7, and a longitudinal material box 5 that can move transversely through the longitudinal loading plate 9 is installed on the transverse loading platform 3. A longitudinal unloading channel 38 is docked at the bottom of the longitudinal material box 5, and a transverse hydraulic cylinder 4 that can drive the longitudinal unloading channel 38 to move transversely is installed at the end of the right transverse loading platform 3. The transverse hydraulic cylinder 4 is started to drive the longitudinal material box 5 to move transversely, and the steel bars in the longitudinal unloading channel 38 automatically fall into the plurality of longitudinal steel bar openings 29 on the longitudinal loading plate 9.

[0040] Specifically, the opening and closing assembly includes a baffle 30 slidably installed at the bottom of the longitudinal loading plate 9. The baffle 30 is provided with a plurality of discharge ports 37 at intervals in the longitudinal direction. The plurality of discharge ports 37 correspond one-to-one to the plurality of longitudinal steel bar ports 29. A second cylinder 6 that can drive the baffle 30 to move laterally is installed at the end of the longitudinal loading plate 9. When the second cylinder 6 is started, the baffle 30 is pushed, so that the plurality of discharge ports 37 correspond one-to-one to the plurality of longitudinal steel bar ports 29 and are in an open state. When the discharge ports 37 and the longitudinal steel bar ports 29 are misaligned, they are in a closed state.

[0041] A welding mechanism that cooperates with the welding hole 34 is installed on the left side of the mounting frame 7 and the corresponding position of the side plate 1. The welding mechanism includes a pair of third cylinders 39 fixedly installed on the mounting frame 7 and the side plate 1. The opposite ends of the pair of third cylinders 39 are fixedly installed with longitudinally arranged pressing plates 10. The opposite sides of the pair of pressing plates 10 are fixedly connected with multiple anti-pillars 11. The bottoms of the multiple anti-pillars 11 above are fixed with upper electrodes, and the tops of the multiple anti-pillars 11 below are fixed with lower electrodes. The bottoms of the multiple transverse steel bar grooves 31 are spaced apart with welding holes 34. The lower anti-pillars 11 and the lower electrodes are adapted to the multiple longitudinal welding holes 34. The pair of third cylinders 39 are started intermittently, and the multiple longitudinal upper electrodes touch the top of the intersection, and the multiple longitudinal lower electrodes pass through the welding holes 34 to touch the bottom of the intersection. The electrodes are energized, and the steel bars at the intersection are heated and melted, and then the pressing plate 10 is used to pressurize the steel bars at the intersection to weld them together. The welding process of the steel mesh can be completed by intermittent movement and intermittent welding, and the welding process can be quickly completed in the form of resistance spot welding.

[0042] Furthermore, a pair of liftable transverse guide rails 21 are installed between the left and right ends of a pair of side panels 1, a pair of transverse conveyor belts 16 are installed on the opposite sides of the bottom of the pair of side panels 1, and an upward hydraulic cylinder 22 is installed at the bottom of the left and right ends of the base 17. The telescopic ends of the upward hydraulic cylinder 22 are fixedly connected to the corresponding transverse guide rails 21. The transverse guide rails 21 are raised to the highest point and are flush with the conveying wheel 14. A transversely arranged fourth cylinder 2 is fixedly installed between the right ends of the pair of side panels 1. The fourth cylinder 2 is used to push the transverse loading plate 12 onto the conveying wheel 14. The transverse loading plate 12 after unloading is lowered by the upward hydraulic cylinder 22 and placed on a pair of conveyor belts 16, and transported to the right end. Then, it is raised to a position parallel to the conveying wheel 14 through a pair of transverse guide rails 21 at the right end. Starting the fourth cylinder 2 can push the transverse loading plate 12 onto the conveying wheel 14 again, thereby realizing a cyclic welding process.

[0043] In addition, a hanging arm 19 is installed above the left end of a pair of side panels 1, and an electromagnetic suction plate 18 is installed at the end of the hanging arm 19. A plurality of abutment rods 20 corresponding to the limit grooves 32 are fixed to the bottom of the electromagnetic suction plate 18. The electromagnetic suction plate 18 is used to magnetically absorb the welded steel mesh. The welded steel mesh continues to move to a pair of transverse guide rails 21 at the left end, and the electromagnetic suction plate 18 is driven to descend by the hanging arm 19. The plurality of abutment rods 20 first push the plurality of pairs of limit plates 33 back into the limit grooves 32, so that the bottom surface of the electromagnetic suction plate 18 contacts the steel mesh, and the steel mesh can be magnetically absorbed for the unloading process.

[0044] The present invention also provides an automated welding method for a steel mesh for construction, comprising the following specific steps:

[0045] S1, the transverse loading plate 12 is smoothly transported to the bottom of the longitudinal loading plate 9 by multiple pairs of conveying wheels 14, and the transverse material box 26 is pushed to move by the longitudinal hydraulic cylinder 27, so that the transverse material discharge channel 28 is pushed against the transverse loading plate 12, and the steel bars stacked horizontally inside automatically fall into the multiple transverse steel bar grooves 31, and the transverse hydraulic cylinder 4 is synchronously started to drive the longitudinal material box 5 to move horizontally, so that the steel bars in the longitudinal material discharge channel 38 automatically fall into the multiple longitudinal steel bar openings 29 on the longitudinal loading plate 9;

[0046] S2, start the first cylinder 15 to drive the stop plate 13 to rise, and then drive the multiple pairs of limit plates 33 to extend out of the limit slots 32 through the multiple connecting rods 35, and drive the longitudinal loading plate 9 to descend to a position close to the transverse loading plate 12 through the downward hydraulic cylinder 8, and start the second cylinder 6 to push the baffle 30, so that the multiple discharge ports 37 correspond to the multiple longitudinal steel bar ports 29 one by one, and the longitudinal steel bars fall between the multiple pairs of limit plates 33 in the longitudinal direction, so that the multiple transverse steel bars and the multiple longitudinal steel bars are equidistantly placed crosswise;

[0047] S3, the cross-placed steel bars continue to move to the left through the transverse loading plate 12, and a pair of third cylinders 39 are intermittently started, and multiple longitudinal upper electrodes abut against the top of the intersection, and multiple longitudinal lower electrodes pass through the welding holes 34 to abut against the bottom of the intersection. The electrodes are energized, and the steel bars at the intersection are heated and melted, and then the pressure plate 10 is used to pressurize the steel bars at the intersection to weld them together. The intermittent movement and intermittent welding can complete the welding process of the steel mesh;

[0048] S4, the welded steel mesh continues to move to the pair of transverse guide rails 21 at the left end, and the electromagnetic suction plate 18 is driven down by the suspension arm 19 to magnetically suck the steel mesh for unloading;

[0049] S5. After unloading, the transverse loading plate 12 is lowered and placed on a pair of conveyor belts 16, transported to the right end, and then raised to be parallel to the conveyor wheel 14 through a pair of transverse guide rails 21 at the right end. The fourth cylinder 2 is started to push the transverse loading plate 12 onto the conveyor wheel 14 again to realize the cyclic welding process.

[0050] Working principle: The transverse loading plate 12 is smoothly transported to the bottom of the longitudinal loading plate 9 through multiple pairs of conveying wheels 14, and the transverse material box 26 is pushed to move by the longitudinal hydraulic cylinder 27, so that the transverse unloading channel 28 is against the transverse loading plate 12, and the steel bars stacked horizontally inside automatically fall into the multiple transverse steel bar grooves 31. The transverse hydraulic cylinder 4 is started synchronously to drive the longitudinal material box 5 to move horizontally, and the steel bars in the longitudinal unloading channel 38 automatically fall into the multiple longitudinal steel bar openings 29 on the longitudinal loading plate 9, and the pre-placement process of multiple transverse steel bars and multiple longitudinal steel bars is completed synchronously.

[0051] Start the first cylinder 15 to drive the stop plate 13 to rise, and then drive the multiple pairs of limit plates 33 to extend out of the limit slots 32 through the multiple connecting rods 35. The multiple pairs of magnetic plates 36 are magnetically attracted to each other, so that the multiple pairs of limit plates 33 are kept in the extended state during the welding process. The longitudinal loading plate 9 is driven down to a position close to the transverse loading plate 12 by the downward hydraulic cylinder 8, and the second cylinder 6 is started to push the baffle 30, so that the multiple discharge ports 37 correspond to the multiple longitudinal steel bar ports 29 one by one, and the longitudinal steel bars fall between the multiple pairs of longitudinal limit plates 33, so that the multiple transverse steel bars and the multiple longitudinal steel bars are equidistantly placed crosswise, and the placement process of the entire steel mesh is completed quickly without offset.

[0052] The chain 25 can synchronously drive multiple sprockets 24 to rotate, and then synchronously drive multiple pairs of conveying wheels 14 to rotate, and the cross-placed steel bars continue to move to the left through the transverse loading plate 12. A pair of third cylinders 39 are intermittently started, and multiple longitudinal upper electrodes abut the top of the intersection, and multiple longitudinal lower electrodes pass through the welding hole 34 through the abutment column 11 to abut the bottom of the intersection. The positioning is accurate, the electrodes are energized, the steel bars at the intersection are heated and melted, and then the pressure is applied by the pressing plate 10 to weld the steel bars at the intersection together. The welding process of the steel mesh can be completed by intermittent movement and intermittent welding.

[0053] The welded steel mesh continues to move to a pair of transverse guide rails 21 at the left end, and the electromagnetic suction plate 18 is driven down by the boom 19. The multiple push rods 20 first push the multiple pairs of limit plates 33 back into the limit grooves 32, so that the bottom surface of the electromagnetic suction plate 18 contacts the steel mesh, and the steel mesh can be magnetically sucked for the unloading process.

[0054] After unloading, the transverse loading plate 12 is lowered by the upward hydraulic cylinder 22 and placed on a pair of conveyor belts 16, transported to the right end, and then raised to a position parallel to the conveyor wheel 14 through a pair of transverse guide rails 21 at the right end. The fourth cylinder 2 is started to push the transverse loading plate 12 onto the conveyor wheel 14 again to realize the cyclic welding process.

[0055] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. An automated welding device for a steel mesh for construction, comprising a base (17), characterized in that: A pair of transversely arranged side plates (1) are fixedly mounted on the base (17); a plurality of conveying wheels (14) are mounted on the top side walls of the pair of side plates (1) facing each other; a plurality of transverse loading plates (12) capable of transverse conveyance are placed between the pairs of conveying wheels (14); a plurality of transverse steel bar grooves (31) are arranged at intervals on the transverse loading plates (12); a plurality of pairs of longitudinal limit assemblies are arranged at intervals on the transverse loading plates (12); welding holes (34) are arranged at intervals at the bottom of the plurality of transverse steel bar grooves (31); longitudinal loading platforms (23) flush with the top surfaces of the transverse loading plates (12) are fixedly mounted on both sides of the middle top of the pair of side plates (1); a transverse material box (26) capable of longitudinally moving through the transverse loading plates (12) is mounted on the rear side of the longitudinal loading platform (23); a bottom of the transverse material box (26) is provided with a resistance A transverse material discharge channel (28) is provided on the top surface of the longitudinal material loading platform (23); a mounting frame (7) is installed on the top of a pair of the side panels (1); a longitudinal loading plate (9) that can be raised and lowered is installed on the top of the mounting frame (7); a plurality of longitudinal steel bar openings (29) are provided on the longitudinal loading plate (9) at intervals; an opening and closing assembly that can synchronously open the plurality of longitudinal steel bar openings (29) is installed on the bottom of the longitudinal loading plate (9); a pair of transverse material loading platforms (3) that are flush with the top surface of the longitudinal loading plate (9) are fixedly installed on the top of the mounting frame (7); a longitudinal material box (5) that can be laterally moved through the longitudinal loading plate (9) is installed on the transverse material loading platform (3); a longitudinal material discharge channel (38) is connected to the bottom of the longitudinal material box (5); a welding mechanism that cooperates with the welding hole (34) is installed on the left side of the mounting frame (7) and at the corresponding position of the side panel (1); The longitudinal limiting assembly comprises a plurality of pairs of limiting grooves (32), the plurality of pairs of limiting grooves (32) being arranged between adjacent transverse steel bar grooves (31) of the transverse loading plate (12), a limiting plate (33) being arranged in the limiting grooves (32), a connecting rod (35) extending out of the limiting groove (32) being fixed at the bottom of the limiting plate (33), an extending end of the connecting rod (35) being fixedly connected to a support plate (13), a plurality of welding holes (34) corresponding to the welding holes (34) on the transverse loading plate (12) being arranged on the support plate (13), a plurality of matching magnetic sheets (36) being embedded on the top surface of the support plate (13) and the bottom surface of the transverse loading plate (12), a first cylinder (15) for rising against the support plate (13) being installed in the middle of the base (17), The opening and closing assembly comprises a baffle (30) slidably mounted in the bottom of the longitudinal loading plate (9), the baffle (30) being provided with a plurality of discharge ports (37) at intervals in the longitudinal direction, the plurality of discharge ports (37) corresponding one-to-one to a plurality of longitudinal steel bar ports (29), and a second cylinder (6) being mounted at the end of the longitudinal loading plate (9) for driving the baffle (30) to move transversely. The welding mechanism comprises a pair of third cylinders (39) fixedly mounted on the mounting frame (7) and the side plate (1), the opposite ends of the pair of third cylinders (39) are fixedly mounted with longitudinally arranged pressing plates (10), the opposite sides of the pair of pressing plates (10) are fixedly connected with a plurality of supporting columns (11), the bottoms of the upper plurality of supporting columns (11) are fixed with upper electrodes, the tops of the lower plurality of supporting columns (11) are fixed with lower electrodes, and the lower supporting columns (11) and the lower electrodes are adapted to the plurality of longitudinal welding holes (34), A pair of liftable transverse guide rails (21) are installed between the left and right ends of the pair of side panels (1); a pair of transverse conveyor belts (16) are installed on opposite sides of the bottom of the pair of side panels (1); an upward hydraulic cylinder (22) is installed at the bottom of the left and right ends of the base (17); the telescopic end of the upward hydraulic cylinder (22) is fixedly connected to the corresponding transverse guide rail (21); the transverse guide rail (21) is raised to the highest point and is flush with the conveying wheel (14); a transversely arranged fourth cylinder (2) is fixedly installed between the right ends of the pair of side panels (1); the fourth cylinder (2) is used to push the transverse loading plate (12) onto the conveying wheel (14); A suspension arm (19) is installed above the left ends of the pair of side plates (1), an electromagnetic suction plate (18) is installed at the end of the suspension arm (19), a plurality of stop rods (20) corresponding to the limit grooves (32) are fixed to the bottom of the electromagnetic suction plate (18), and the electromagnetic suction plate (18) is used to magnetically attract the welded steel mesh.

2. The automatic welding equipment for steel mesh for construction according to claim 1, characterized in that: Sprockets (24) are fixedly mounted at the ends of the wheel shafts of the plurality of conveying wheels (14), a chain (25) is sleeved between the plurality of sprockets (24) on one side, the chain (25) is used to drive a row of sprockets (24) to rotate synchronously, and the front and rear sides of the transverse loading plate (12) are placed on the plurality of conveying wheels (14).

3. The automatic welding equipment for building steel mesh according to claim 2, characterized in that: A longitudinal hydraulic cylinder (27) capable of driving the transverse material discharge channel (28) to move longitudinally is installed at the end of the longitudinal material loading platform (23) on the rear side, and a transverse hydraulic cylinder (4) capable of driving the longitudinal material discharge channel (38) to move transversely is installed at the end of the transverse material loading platform (3) on the right side.

4. The automatic welding equipment for building steel mesh according to claim 3, characterized in that: A descending hydraulic cylinder (8) capable of driving the longitudinal loading plate (9) to move up and down is installed on the top of the mounting frame (7).

5. A welding method based on the automated welding equipment for building steel mesh according to claim 4, characterized in that: The specific steps include: S1, the transverse loading plate (12) is smoothly transported to the bottom of the longitudinal loading plate (9) by multiple pairs of conveying wheels (14), and the transverse material box (26) is pushed to move by the longitudinal hydraulic cylinder (27), so that the transverse material discharge channel (28) contacts the transverse loading plate (12), and the steel bars stacked transversely inside automatically fall into the multiple transverse steel bar grooves (31), and the transverse hydraulic cylinder (4) is synchronously started to drive the longitudinal material box (5) to move transversely, so that the steel bars in the longitudinal material discharge channel (38) automatically fall into the multiple longitudinal steel bar openings (29) on the longitudinal loading plate (9); S2, start the first cylinder (15) to drive the stop plate (13) to rise, then drive the multiple pairs of limit plates (33) to extend out of the limit slots (32) through the multiple connecting rods (35), drive the longitudinal loading plate (9) to descend to a position adjacent to the transverse loading plate (12) through the downward hydraulic cylinder (8), start the second cylinder (6) to push the baffle (30), so that the multiple discharge ports (37) correspond to the multiple longitudinal steel bar ports (29) one by one, and the longitudinal steel bars fall between the multiple pairs of longitudinal limit plates (33), so that the multiple transverse steel bars and the multiple longitudinal steel bars are equidistantly placed crosswise; S3, the cross-placed steel bars continue to move to the left through the transverse loading plate (12), a pair of third cylinders (39) are intermittently started, a plurality of longitudinal upper electrodes abut against the top of the intersection, a plurality of longitudinal lower electrodes pass through the welding holes (34) and abut against the bottom of the intersection, the electrodes are energized, the steel bars at the intersection are heated and melted, and then pressure is applied through the pressing plate (10) to weld the steel bars at the intersection together, and the welding process of the steel mesh can be completed by intermittent movement and intermittent welding; S4, the welded steel mesh continues to move to the pair of transverse guide rails (21) at the left end, and the electromagnetic suction plate (18) is driven down by the suspension arm (19) to magnetically suck the steel mesh to start the unloading process; S5. After unloading, the transverse loading plate (12) is lowered and placed on a pair of conveyor belts (16), transported to the right end, and then raised to be parallel to the conveyor wheel (14) through a pair of transverse guide rails (21) at the right end. The fourth cylinder (2) is started to push the transverse loading plate (12) onto the conveyor wheel (14) again, thereby realizing a cyclic welding process.