An energy consumption monitoring and evaluation system for photovoltaic field collector lines
By introducing a multi-point data monitoring and analysis system into the photovoltaic field collecting line design, the problem of insufficient energy consumption calculation of the collecting line is solved, the accuracy and reliability of energy consumption analysis are achieved, and design adjustment is supported.
Patent Information
- Application Number
- CN202411313491.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-20
- Publication Date
- 2024-12-17
- Estimated Expiration
- 2044-09-20
AI Technical Summary
The existing technology lacks energy consumption calculation methods in the design of photovoltaic field collecting lines, which leads to the inability to accurately determine the problem during design, affecting the accuracy and reliability of system operation.
Design a system including server, information collection unit, information supervision unit, missing analysis unit and energy consumption accounting unit. By monitoring, verifying and analyzing data from the front, mid-end and back-end, we ensure the accuracy of energy consumption analysis results. and reliability.
Through front-end information deviation supervision and evaluation, mid-range transmission risk verification and back-end energy consumption intelligent calculation, we ensure the authenticity and availability of data, provide accurate energy consumption analysis of collector lines, and support timely adjustment of design plans.
Smart Images

Figure CN118837617B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of line energy consumption monitoring, and in particular to an energy consumption monitoring and evaluation system for a photovoltaic field collector line. Background Art
[0002] The collector line is an important component of the power system. It is mainly responsible for collecting the electric energy generated by each power generation unit or power generation equipment and transmitting it to the booster station or switch station. This process is particularly critical in photovoltaic power generation systems and wind power generation systems. The role and characteristics of the collector line are different. In the photovoltaic power generation system, the collector line is a DC and AC transmission line that combines the electric energy output by each photovoltaic module string to the inverter through the combiner box and collects it to the power generation bus through the inverter output end. This process involves transmitting the electric energy output by the local booster transformer to the power generation bus to ensure the effective transmission and utilization of electric energy.
[0003] However, the current design institutes are still in the early stages of understanding the parameters of the collector line and the loss of the collector line. When designing, they often fail to take into account the unfavorable conditions such as the large capacity of the collector line and the energy consumption and voltage drop loss caused by the long distance. There is a lack of relevant calculation and research methods for the loss calculation of the collector line. Designers cannot fully grasp the parameters of the collector line and cannot accurately determine the problem when the system operates abnormally. In addition, there is a lack of data verification and identification process in the loss calculation of the collector line, and it is impossible to supervise and analyze the validity and accuracy of the data from the front end, middle end and back end, thereby reducing the accuracy and reliability of subsequent analysis results.
[0004] In view of the above technical defects, a solution is now proposed. Summary of the invention
[0005] The purpose of the present invention is to provide an energy consumption monitoring and evaluation system for a photovoltaic field collector line to solve the above-mentioned technical defects. The present invention analyzes from three points: the front end, the middle end, and the back end. On the one hand, it helps to track and verify the data, and on the other hand, it helps to ensure the accuracy and reliability of the energy consumption analysis results, so as to understand whether the current photovoltaic field collector line design scheme meets the requirements so as to make timely changes.
[0006] The object of the present invention can be achieved by the following technical solutions: an energy consumption monitoring and evaluation system for a photovoltaic field collector line, comprising a server, an information collection unit, an information supervision unit, a missing analysis unit, an energy consumption accounting unit, and a display management unit;
[0007] After receiving the supervision instruction, the information collection unit immediately collects and stores the monitoring data and transmission risk information of the photovoltaic field energy consumption collection equipment. The information supervision unit is used to retrieve the monitoring data, and perform information deviation supervision evaluation analysis on the monitoring data, compare and analyze the obtained information deviation value and interference risk value, and obtain normal signals and abnormal signals;
[0008] The missing analysis unit is used to respond to the normal signal and retrieve the transmission risk information, and at the same time perform information transmission verification feedback evaluation analysis on the transmission risk information, compare and analyze the obtained actual character string with the verification character string to obtain the standard signal and the missing signal;
[0009] The energy consumption accounting unit is used to respond to standard signals and perform intelligent energy consumption calculation, evaluation, processing and analysis at the same time, to judge and process the energy consumption of each section of the collection line or the energy consumption of each collection line, and to send the obtained feedback signal to the display management unit, and to verify, match, supervise and analyze the table of imported original data, and to send the obtained qualified signals and unqualified signals to the display management unit.
[0010] Preferably, the information deviation supervision evaluation and analysis process of the information supervision unit is as follows:
[0011] Set the monitoring cycle and set it as the time threshold to obtain the monitoring data of the collector line energy consumption collection equipment in the photovoltaic field within the time threshold. The monitoring data includes information deviation value and interference risk value. The information deviation value and interference risk value are compared and analyzed with the preset information deviation value threshold and preset interference risk value threshold stored in the internal input:
[0012] If the information deviation value is less than the preset information deviation value threshold, and the interference risk value is less than the preset interference risk value threshold, a normal signal is generated;
[0013] If the information deviation value is less than the preset information deviation value threshold, and the interference risk value is less than the preset interference risk value threshold, an abnormal signal is generated.
[0014] Preferably, the information deviation value indicates the number of deviations between the monitoring and collection time of the energy consumption collection device and the preset monitoring and collection time; the interference risk value indicates the product value obtained by multiplying the external interference value and the self-interference value after data normalization processing, the external interference value indicates the duration of the overlap corresponding to the corresponding value of the environmental parameter exceeding the preset threshold, the environmental parameters include temperature and humidity, and the self-interference value indicates the historical abnormal frequency of the energy consumption collection device itself, and the historical abnormalities include failures and high loads.
[0015] Preferably, the information transmission verification feedback evaluation analysis process of the missing analysis unit is as follows:
[0016] The energy consumption data of each section of the collector line in the photovoltaic field within the time threshold is obtained, and the energy consumption data of each section of the collector line is set as the original data; the transmission period of the original data within the time threshold is obtained, and the transmission period of the original data is set as the analysis period; the transmission risk information of the original data within the analysis period is obtained, and the transmission risk information represents the transmission obstacle value, and the transmission obstacle value is compared and analyzed with the preset transmission obstacle value threshold value entered and stored internally; if the transmission obstacle value is less than the preset transmission obstacle value threshold value, a stabilization instruction is generated; when the stabilization instruction is generated, the number of transmission bytes of the original data within the analysis period is obtained, and the text characters of the transmission bytes are extracted, and the character string composed of the text character extraction of the transmission byte number is set as the verification character string;
[0017] The number of bytes transmitted after the original data transmission in the analysis period is obtained, and text characters are extracted from the number of bytes transmitted after the original data transmission. The string composed of the text characters extracted from the number of bytes transmitted after the original data transmission is set as the actual string, and the actual string is compared and analyzed with the verification string one by one:
[0018] If the actual string corresponds to the verification string one by one, a standard signal is generated;
[0019] If the actual string does not correspond to the verification string one-to-one, a loss signal is generated;
[0020] The transmission obstruction value indicates the overlap duration between the duration corresponding to the packet loss rate of the transmission network exceeding the preset packet loss rate threshold and the transmission freeze duration.
[0021] Preferably, the energy consumption intelligent calculation, evaluation, processing and analysis steps of the energy consumption accounting unit are as follows:
[0022] Step 1: Establish a database of structures and electrical parameters of various types of cables and overhead lines, uniquely identify each conductor model and transformer capacity, write algorithm formulas for various energy consumption, and edit and import raw data;
[0023] Obtain the table for importing the original data, and conduct verification, matching, supervision and analysis on the table for importing the original data to determine whether the original data import is qualified. If a qualified signal is obtained, proceed to step 2; if an unqualified signal is obtained, feedback and adjustment are given;
[0024] Step 2: Use different line types to design conductors of different models in the existing software, and design them one by one according to the transformer capacity and conductor model identification in the electrical parameter database. After completion, the conductor model, length, and the starting and ending points of the connection are automatically exported into a table;
[0025] Step 3: After inputting the set threshold parameters, the series connection of each collector line can be automatically completed, and the energy consumption of each collector line or each collector line can be calculated;
[0026] Step 4: The energy consumption of each section of the collector line or each collection line is judged and processed. If the energy consumption of each section of the collector line or each collection line exceeds the preset threshold, a feedback signal is generated. If the energy consumption of each section of the collector line or each collection line exceeds the preset threshold, no signal is generated.
[0027] Preferably, the verification matching supervision analysis process of the energy consumption accounting unit is as follows:
[0028] The number of data format errors and sorting difference values in the process of converting the original data during the analysis period are obtained. The sorting risk value refers to the number of differences between the sorting order of enterprise project data and the preset sorting order. The number of data format errors and sorting difference values are discriminantly analyzed respectively:
[0029] If the number of data format errors is zero, an accurate signal is generated;
[0030] If the number of data format errors is not zero, a deviation signal is generated;
[0031] If the sort difference value is zero, a corresponding signal is generated;
[0032] If the sorting difference value is not zero, a non-corresponding signal is generated, and the accurate signal, deviation signal, corresponding signal, and non-corresponding signal are interactively analyzed:
[0033] If an accurate signal and a corresponding signal are generated, a qualified signal is obtained;
[0034] If an accurate signal and a non-corresponding signal or a deviation signal and a non-corresponding signal or a non-corresponding signal and a non-corresponding signal are generated, an unqualified signal is obtained.
[0035] The beneficial effects of the present invention are as follows:
[0036] (1) The present invention ensures the accuracy and reliability of the energy consumption analysis results by analyzing from the front end, the middle end and the back end, so as to understand whether the current photovoltaic field area collection line design scheme meets the needs, so as to make timely changes, that is, to conduct information deviation supervision and evaluation analysis on the monitoring data from the perspective of the front end, so as to determine whether the collected information is normal and valid, so as to repair and correct the collected data according to the information feedback, so as to ensure the authenticity and validity of the data;
[0037] (2) The present invention conducts information transmission verification feedback evaluation analysis on the transmission risk information at the middle end by means of information feedback, so as to further track the information and verify the identification information, so as to manage and supplement the transmitted original data according to the information feedback situation, so as to ensure the availability of the original data, and to conduct verification matching supervision analysis from the perspective of data conversion at the back end in a progressive manner, so as to ensure the pass rate of data conversion, so as to analyze the energy consumption of each section of the collector line or each collector line, so as to provide data support for the subsequent adjustment of the collector line in the photovoltaic field. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] The present invention will be further described below in conjunction with the accompanying drawings;
[0039] Figure 1 It is a flowchart of the system of the present invention;
[0040] Figure 2 It is an analysis diagram of Example 1 of the present invention. DETAILED DESCRIPTION
[0041] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0042] Embodiment 1:
[0043] See also Figure 1 to Figure 2 As shown, the present invention is an energy consumption monitoring and evaluation system for a photovoltaic field collector line, comprising a server, an information collection unit, an information supervision unit, a missing analysis unit, an energy consumption accounting unit and a display management unit, wherein the server is connected to the information collection unit in a one-way communication manner, the information collection unit is connected to the information supervision unit and the missing analysis unit in a one-way communication manner, the information supervision unit is connected to the missing analysis unit and the display management unit in a one-way communication manner, the missing analysis unit is connected to the energy consumption accounting unit and the display management unit in a one-way communication manner, and the energy consumption accounting unit is connected to the display management unit in a one-way communication manner;
[0044] When the server generates a supervision instruction, it sends the supervision instruction to the information collection unit. After receiving the supervision instruction, the information collection unit immediately collects and stores the monitoring data and transmission risk information of the photovoltaic field energy consumption collection equipment. The information supervision unit is used to retrieve the monitoring data and perform information deviation supervision evaluation and analysis on the monitoring data to determine whether the collected information is normal and valid, so as to repair and correct the collected data according to the information feedback to ensure the authenticity and validity of the data. The specific information deviation supervision evaluation and analysis process is as follows:
[0045] Set the monitoring cycle and set it as the time threshold to obtain the monitoring data of the collector line energy consumption collection equipment in the photovoltaic field within the time threshold. The monitoring data includes information deviation value and interference risk value. The information deviation value and interference risk value are compared and analyzed with the preset information deviation value threshold and preset interference risk value threshold stored in the internal input:
[0046] If the information deviation value is less than the preset information deviation value threshold, and the interference risk value is less than the preset interference risk value threshold, a normal signal is generated;
[0047] If the information deviation value is less than the preset information deviation value threshold, and the interference risk value is less than the preset interference risk value threshold, an abnormal signal is generated, and the normal signal and the abnormal signal are sent to the display management unit. After receiving the normal signal and the abnormal signal, the display management unit immediately displays the preset warning text corresponding to the normal signal and the abnormal signal, so as to manage the energy consumption collection equipment according to the information feedback, and at the same time repair and correct the collected data to ensure the authenticity and validity of the data;
[0048] In the embodiment of the present invention, the information deviation value indicates the number of deviations between the monitoring and collection time of the energy consumption collection device and the preset monitoring and collection time. It should be noted that the information deviation value is an influencing parameter reflecting the accuracy of the data;
[0049] In the embodiment of the present invention, the interference risk value represents the product value obtained by multiplying the external interference value and the self-interference value after data normalization processing. The external interference value represents the duration of the overlap corresponding to the value of the environmental parameter exceeding the preset threshold value. The environmental parameters include temperature, humidity, etc. The self-interference value represents the historical abnormal frequency of the energy consumption collection device itself. The historical abnormalities include failures, high loads, etc. It should be noted that information risk analysis is performed from both internal and external points to ensure the validity and authenticity of the data;
[0050] When a normal signal is generated, the missing analysis unit is used to respond to the normal signal and retrieve the transmission risk information, and at the same time perform information transmission verification feedback evaluation analysis on the transmission risk information, so as to further track the information and verify the identification information, so as to manage and supplement the transmitted original data according to the information feedback to ensure the availability of the original data. The specific information transmission verification feedback evaluation analysis process is as follows:
[0051] The energy consumption data of each section of the collector line in the photovoltaic field within the time threshold is obtained, and the energy consumption data of each section of the collector line is set as the original data; the transmission period of the original data within the time threshold is obtained, and the transmission period of the original data is set as the analysis period; the transmission risk information of the original data within the analysis period is obtained, and the transmission risk information represents the transmission obstacle value, and the transmission obstacle value is compared and analyzed with the preset transmission obstacle value threshold value entered and stored internally; if the transmission obstacle value is less than the preset transmission obstacle value threshold value, a stabilization instruction is generated; when the stabilization instruction is generated, the number of transmission bytes of the original data within the analysis period is obtained, and the text characters of the transmission bytes are extracted, and the character string composed of the text character extraction of the transmission byte number is set as the verification character string;
[0052] The number of bytes transmitted after the original data transmission in the analysis period is obtained, and text characters are extracted from the number of bytes transmitted after the original data transmission. The string composed of the text characters extracted from the number of bytes transmitted after the original data transmission is set as the actual string, and the actual string is compared and analyzed with the verification string one by one:
[0053] If the actual string corresponds to the verification string one by one, a standard signal is generated;
[0054] If the actual character string does not correspond to the verification character string one by one, a loss signal is generated, and the standard signal and the loss signal are sent to the display management unit. After receiving the standard signal and the loss signal, the display management unit immediately displays the preset warning text corresponding to the standard signal and the loss signal, so as to manage and supplement the transmitted original data according to the information feedback to ensure the authenticity and validity of the data;
[0055] In the embodiment of the present invention, the transmission obstacle value indicates the overlap duration between the duration corresponding to the packet loss rate of the transmission network exceeding the preset packet loss rate threshold and the transmission freeze duration. It should be noted that the transmission obstacle value is an influencing parameter reflecting the state of the transmission network;
[0056] In the embodiment of the present invention, the energy consumption data includes but is not limited to active power loss, reactive power loss, and charging power.
[0057] Embodiment 2:
[0058] After the standard signal is generated, the energy consumption accounting unit is used to respond to the standard signal and perform intelligent energy consumption calculation, evaluation, processing and analysis to understand whether the current design scheme meets the requirements so as to make timely changes. The specific steps of intelligent energy consumption calculation, evaluation, processing and analysis are as follows:
[0059] Step 1: Establish a database of structures and electrical parameters of various types of cables and overhead lines, uniquely identify each conductor model and transformer capacity, write algorithm formulas for various energy consumption, and edit and import raw data;
[0060] Obtain the table for importing the original data, and conduct verification, matching, supervision and analysis on the table for importing the original data to determine whether the original data import is qualified. If a qualified signal is obtained, proceed to step 2; if an unqualified signal is obtained, feedback and adjustment are given;
[0061] Step 2: Use different line types to design conductors of different models in the existing software, and design them one by one according to the transformer capacity and conductor model identification in the electrical parameter database. After completion, the conductor model, length, and the starting and ending points of the connection are automatically exported into a table;
[0062] In the embodiment of the present invention, electrical parameters include but are not limited to: voltage, current, power;
[0063] In the embodiment of the present invention, the existing software includes but is not limited to: CAD, Geometry Sketchpad;
[0064] Step 3: After inputting the set threshold parameters, the series connection of each collector line can be automatically completed, and the energy consumption of each collector line or each collector line can be calculated;
[0065] Step 4: The energy consumption of each section of the collector line or each collector line is judged and processed. If the energy consumption of each section of the collector line or each collector line exceeds the preset threshold, a feedback signal is generated. If the energy consumption of each section of the collector line or each collector line exceeds the preset threshold, no signal is generated, and the feedback signal is sent to the display management unit. After receiving the feedback signal, the display management unit immediately displays the preset warning text corresponding to the feedback signal to understand whether the current design scheme meets the requirements so as to make timely changes;
[0066] The specific verification, matching, supervision and analysis process is as follows:
[0067] The number of data format errors and sorting difference values in the process of converting the original data during the analysis period are obtained. The sorting risk value refers to the number of differences between the sorting order of enterprise project data and the preset sorting order. The number of data format errors and sorting difference values are discriminantly analyzed respectively:
[0068] If the number of data format errors is zero, an accurate signal is generated;
[0069] If the number of data format errors is not zero, a deviation signal is generated;
[0070] If the sort difference value is zero, a corresponding signal is generated;
[0071] If the sorting difference value is not zero, a non-corresponding signal is generated, and the accurate signal, deviation signal, corresponding signal, and non-corresponding signal are interactively analyzed:
[0072] If an accurate signal and a corresponding signal are generated, a qualified signal is obtained;
[0073] If an accurate signal and a non-corresponding signal, or a deviation signal and a non-corresponding signal, or a non-corresponding signal and a non-corresponding signal are generated, an unqualified signal is obtained, and the qualified signal and the unqualified signal are sent to the display management unit. After receiving the qualified signal and the unqualified signal, the display management unit immediately displays the preset warning text corresponding to the qualified signal and the unqualified signal, so as to ensure the accuracy and reliability of the energy consumption analysis result;
[0074] In summary, the present invention ensures the accuracy and reliability of the energy consumption analysis results by analyzing from three points: the front end, the middle end, and the back end, so as to understand whether the current photovoltaic field collector line design scheme meets the needs, so as to make timely changes, that is, to perform information deviation supervision and evaluation analysis on the monitoring data from the front end perspective to determine whether the collected information is normal and valid, so as to repair and correct the collected data according to the information feedback to ensure the authenticity and validity of the data, and to perform information transmission verification feedback evaluation analysis on the transmission risk information at the middle end through information feedback, so as to further track the information and verify the identification information, so as to manage and supplement the transmitted original data according to the information feedback to ensure the availability of the original data, and to perform verification and matching supervision analysis from the data conversion perspective of the back end in a progressive manner to ensure the pass rate of data conversion, so as to analyze the energy consumption of each section of the collector line or the energy consumption of each collector line, so as to provide data support for subsequent adjustments to the photovoltaic field collector line.
[0075] The threshold is set to facilitate comparison. The size of the threshold depends on the amount of sample data and the number of bases set by technicians in this field for each group of sample data; as long as it does not affect the proportional relationship between the parameter and the quantized value.
[0076] The above formulas are obtained by collecting a large amount of data for software simulation and selecting a formula that is close to the actual value. The coefficients in the formula are set by technical personnel in this field according to actual conditions. The above is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited to this. Any technical personnel familiar with the technical field within the technical scope disclosed by the present invention, according to the technical solution and the inventive concept of the present invention, make equivalent replacement or change, which should be covered within the protection scope of the present invention.
Claims
1. An energy consumption monitoring and evaluation system for a photovoltaic field collector line, characterized in that: It includes a server, an information collection unit, an information supervision unit, a missing analysis unit, an energy consumption accounting unit and a display management unit; After receiving the supervision instruction, the information collection unit immediately collects and stores the monitoring data and transmission risk information of the photovoltaic field energy consumption collection equipment. The information supervision unit is used to retrieve the monitoring data, and perform information deviation supervision evaluation analysis on the monitoring data, compare and analyze the obtained information deviation value and interference risk value, and obtain normal signals and abnormal signals; The missing analysis unit is used to respond to the normal signal and retrieve the transmission risk information, and at the same time perform information transmission verification feedback evaluation analysis on the transmission risk information, compare and analyze the obtained actual character string with the verification character string to obtain the standard signal and the missing signal; The energy consumption accounting unit is used to respond to the standard signal, and at the same time perform intelligent energy consumption calculation, evaluation, processing and analysis, distinguish and process the energy consumption of each section of the collector line or each collector line, send the obtained feedback signal to the display management unit, and verify and match the table of imported original data, and send the obtained qualified signal and unqualified signal to the display management unit; The information deviation supervision assessment and analysis process of the information supervision unit is as follows: Set the monitoring cycle and set it as the time threshold to obtain the monitoring data of the collector line energy consumption collection equipment in the photovoltaic field within the time threshold. The monitoring data includes information deviation value and interference risk value. The information deviation value and interference risk value are compared and analyzed with the preset information deviation value threshold and preset interference risk value threshold stored in the internal input: If the information deviation value is less than the preset information deviation value threshold, and the interference risk value is less than the preset interference risk value threshold, a normal signal is generated; If the information deviation value is greater than or equal to the preset information deviation value threshold, or the interference risk value is greater than or equal to the preset interference risk value threshold, an abnormal signal is generated; The information deviation value indicates the number of deviations between the monitoring and collection time of the energy consumption collection device and the preset monitoring and collection time; the interference risk value indicates the product value obtained by multiplying the external interference value and the self-interference value after data normalization processing, the external interference value indicates the duration of the overlap corresponding to the value of the environmental parameter exceeding the preset threshold, the environmental parameters include temperature and humidity, and the self-interference value indicates the historical abnormal frequency of the energy consumption collection device itself, and the historical abnormalities include faults and high loads; The information transmission verification feedback evaluation analysis process of the missing analysis unit is as follows: The energy consumption data of each section of the collector line in the photovoltaic field within the time threshold is obtained, and the energy consumption data of each section of the collector line is set as the original data; the transmission period of the original data within the time threshold is obtained, and the transmission period of the original data is set as the analysis period; the transmission risk information of the original data within the analysis period is obtained, and the transmission risk information represents the transmission obstacle value, and the transmission obstacle value is compared and analyzed with the preset transmission obstacle value threshold value entered and stored internally; if the transmission obstacle value is less than the preset transmission obstacle value threshold value, a stabilization instruction is generated; when the stabilization instruction is generated, the number of transmission bytes of the original data within the analysis period is obtained, and the text characters of the transmission bytes are extracted, and the character string composed of the text character extraction of the transmission bytes is set as the verification character string; The number of bytes transmitted after the original data transmission in the analysis period is obtained, and text characters are extracted from the number of bytes transmitted after the original data transmission. The string composed of the text characters extracted from the number of bytes transmitted after the original data transmission is set as the actual string, and the actual string is compared and analyzed with the verification string one by one: If the actual string corresponds to the verification string one by one, a standard signal is generated; If the actual string does not correspond to the verification string one-to-one, a loss signal is generated; The transmission obstruction value indicates the overlap between the duration of the transmission network packet loss rate exceeding the preset packet loss rate threshold and the transmission freeze duration; The energy consumption intelligent calculation, evaluation, processing and analysis steps of the energy consumption accounting unit are as follows: Step 1: Establish a database of structures and electrical parameters of various types of cables and overhead lines, uniquely identify each conductor model and transformer capacity, write algorithm formulas for various energy consumption, and edit and import raw data; Obtain the table for importing the original data, and conduct verification, matching, supervision and analysis on the table for importing the original data to determine whether the original data import is qualified. If a qualified signal is obtained, proceed to step 2; if an unqualified signal is obtained, feedback and adjustment are given; Step 2: Use different line types to design conductors of different models in the existing software, and design them one by one according to the transformer capacity and conductor model identification in the electrical parameter database. After completion, the conductor model, length, and the starting and ending points of the connection are automatically exported into a table; Step 3: After inputting the set threshold parameters, the series connection of each collector line can be automatically completed, and the energy consumption of each collector line or each collector line can be calculated; Step 4: The energy consumption of each section of the collector line or each collector line is judged and processed. If the energy consumption of each section of the collector line or each collector line exceeds the preset threshold, a feedback signal is generated. If the energy consumption of each section of the collector line and each collector line does not exceed the preset threshold, no signal is generated. The verification matching supervision analysis process of the energy consumption accounting unit is as follows: The number of data format errors and sorting difference values in the process of converting the original data during the analysis period are obtained. The sorting risk value refers to the number of differences between the sorting order of enterprise project data and the preset sorting order. The number of data format errors and sorting difference values are discriminantly analyzed respectively: If the number of data format errors is zero, an accurate signal is generated; If the number of data format errors is not zero, a deviation signal is generated; If the sort difference value is zero, a corresponding signal is generated; If the sorting difference value is not zero, a non-corresponding signal is generated, and the accurate signal, deviation signal, corresponding signal, and non-corresponding signal are interactively analyzed: If an accurate signal and a corresponding signal are generated, a qualified signal is obtained; If an accurate signal and a non-corresponding signal or a deviation signal and a non-corresponding signal or a deviation signal and a corresponding signal are generated, an unqualified signal is obtained.
Citation Information
Patent Citations
Method for calculating maximum load loss hours of current collection line of photovoltaic power station
CN115455649A
Regional photovoltaic energy storage charging system based on distributed power generation
CN118249388A
Wind power plant current collection line monitoring system
CN210604844U
Regulation method and regulation device for converter of wind turbine generator in wind power plant
WO2021184702A1