A photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit

Through the internal product transformation filtering algorithm and the inner and outer nesting optimization algorithm, the power of hybrid energy storage units is divided, which solves the problem of insufficient filtering effect and control accuracy in the existing technology, and effectively cuts the power fluctuations of the photovoltaic power generation system Smooth output of peak valley filling and DC bus power.

CN118868204BActive Publication Date: 2024-11-29STATE GRID GANSU ELECTRIC POWER CORP +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202411336598.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-25
Publication Date
2024-11-29
Estimated Expiration
2044-09-25

AI Technical Summary

Technical Problem

The filtering effect in the existing hybrid energy storage power control technology is insufficient, and the power control accuracy and frequency division processing effect are poor, which fails to effectively improve the constant output of the photovoltaic power generation system.

Method used

The power of the hybrid energy storage unit is divided by the internal product transformation filtering algorithm. The carrier function transformation, structural element processing and the 1-D threshold criterion reconstruction of the internal product transformation filtering algorithm are combined with the inner and outer layer embedding. The optimization algorithm optimizes internal parameters, separates the power low-speed change signal and high-speed change signal, and sends it to the battery and supercapacitor for control respectively.

Benefits of technology

The filtering effect and power control accuracy are improved, the power frequency division processing is enhanced, and the effective peak-cutting and valley filling of power fluctuations in the photovoltaic power generation system is achieved, ensuring the stable output of DC bus power.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118868204B_ABST
    Figure CN118868204B_ABST
Patent Text Reader

Abstract

The present invention discloses a photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit, which relates to the technical field of hybrid energy storage power control, and includes the following steps: outputting the power of the hybrid energy storage unit; using an inner product transformation filtering algorithm to perform power frequency division processing on the power of the hybrid energy storage unit to obtain a power low-speed change signal and a power high-speed change signal; sending the power low-speed change signal and the power high-speed change signal to a battery controller and a supercapacitor controller respectively to realize power control. The present application performs power frequency division processing on the power of the hybrid energy storage unit by using an inner product transformation filtering algorithm, wherein a structural element is selected to process the inner product transformation sub-zone, thereby improving the filtering effect, and thus improving the power control accuracy, and using an inner and outer nested optimization algorithm to optimize the internal parameters of the inner product transformation 1-D threshold criterion, thereby improving the power frequency division processing effect.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of hybrid energy storage power control, and in particular to a photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit. Background Art

[0002] Photovoltaic power generation systems are constrained by environmental factors, the power generation process is significantly volatile, the means of regulation are relatively limited, and the photovoltaic output power is full of variables and difficult to maintain constant. In order to solve this problem, hybrid energy storage units are generally used to coordinate the operation and control of photovoltaic power generation systems.

[0003] In the prior art, Chinese patent CN117879007A discloses a hybrid energy storage power allocation method based on variational modal decomposition and Savitzky-Golay filtering, which uses the VMD algorithm to decompose the photovoltaic output power signal, and determines the optimal number of decomposition layers by the maximum center frequency difference of different decomposition layers; evaluates the similarity between each modal component and the original photovoltaic output power signal by kernel density estimation and Bhattacharyya distance, which is used to screen the grid-connected component and the energy storage component; then extracts the stable power in the energy storage component by Savitzky-Golay, and connects it to the grid, while taking into account that the power fluctuation cannot exceed the limit; performs spectrum analysis on the remaining fluctuating power in the energy storage component, and the high-frequency power is compensated by the supercapacitor, and the low-frequency power is compensated by the energy storage battery.

[0004] The above-mentioned prior art extracts the steady power in the energy storage component through Savitzky-Golay filtering, and its filtering effect needs to be improved, and thus the power control accuracy needs to be improved; at the same time, the above-mentioned prior art does not study the internal parameter optimization of the filtering algorithm, and the power frequency division processing effect is poor. Summary of the invention

[0005] The present application provides a photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit, which is used to solve the problems in the existing hybrid energy storage power control technology that the filtering effect needs to be improved, the power control accuracy needs to be improved, and the power division processing effect is poor.

[0006] On the one hand, the present application provides a photovoltaic power generation coordinated operation control method including a hybrid energy storage unit, comprising the following steps:

[0007] Step S1, outputting the power of the hybrid energy storage unit.

[0008] Step S2, using an inner product transformation filtering algorithm to perform power frequency division processing on the power of the hybrid energy storage unit to obtain a power low-speed change signal and a power high-speed change signal.

[0009] Step S3, sending the power low-speed change signal and the power high-speed change signal to the battery controller and the supercapacitor controller respectively to realize power control.

[0010] Step S2 includes:

[0011] Step S21, selecting a carrier function of an inner product transformation filtering algorithm, performing signal transformation on the power of the hybrid energy storage unit, and obtaining a series of inner product transformation sub-bands.

[0012] Step S22, selecting a structure element to perform XOR followed by IOR and IOR followed by XOR processing on the inner product transformation sub-band to obtain an inner product transformation coefficient.

[0013] Step S23, reconstructing the inner product transformation coefficients by using the inner product transformation 1-D threshold criterion based on the Birgé-Massart strategy to obtain the power low-speed change signal, and the difference between the power of the hybrid energy storage unit and the power low-speed change signal is the power high-speed change signal.

[0014] In step S23, before reconstructing the inner product transform coefficients, an inner and outer nested optimization algorithm is used to optimize the internal parameters of the inner product transform 1-D threshold criterion.

[0015] In a possible implementation, step S21 includes:

[0016] A composite function composed of a mother function and a scale function is selected as the carrier function, the number of deconstruction layers is set, and signal transformation is performed on the power of the hybrid energy storage unit to obtain a series of inner product transformation sub-bands.

[0017] In a possible implementation, step S22 includes:

[0018] Select a structural element, and perform XOR followed by XOR and XOR followed by XOR on the inner product transformation sub-bands to obtain a first inner product transformation sub-band and a second inner product transformation sub-band.

[0019] The inner product transform sub-region is subjected to coupling processing of the first inner product transform sub-region and the second inner product transform sub-region to obtain the inner product transform coefficient.

[0020] In a possible implementation, in step S22, if the inner product transform coefficient does not meet the system requirements, a larger range of structural elements is selected, and the inner product transform coefficient is coupled with the first inner product transform sub-band and the second inner product transform sub-band until the obtained inner product transform coefficient meets the system requirements.

[0021] In a possible implementation, in step S23, the process of determining the threshold value by the inner product transform 1-D threshold criterion includes:

[0022] Determine the number of transformation levels , retain more than the number of transformation layers All coefficients of the components of .

[0023] For layer, , retaining the largest value coefficients, among which, Determined by the following formula:

[0024]

[0025] In the formula, the first empirical coefficient and the second empirical coefficient is a constant, , is the number of transformation layers The corresponding first-layer inner product transform coefficients.

[0026] In a possible implementation, in step S23, before reconstructing the inner product transform coefficients, an inner and outer nested optimization algorithm is used to optimize the number of transformation layers of the inner product transform 1-D threshold criterion. , the first empirical coefficient and the second empirical coefficient Optimize, wherein the outer optimization algorithm is used to optimize the number of transformation layers and the second empirical coefficient , the inner optimization algorithm is used to optimize the first empirical coefficient .

[0027] In a possible implementation, in step S23, the number of transformation layers of the inner product transformation 1-D threshold criterion is , the first empirical coefficient and the second empirical coefficient Optimizations include:

[0028] First, the outer layer optimization algorithm is used to optimize the number of transformation layers. and the second empirical coefficient , initially configure the element set and randomize the element level, calculate the fitness value of each individual in the outer optimization algorithm, and then enter the inner optimization algorithm stage.

[0029] In the inner optimization algorithm stage, the parameters and elements are initially assigned values, the element adaptability values ​​in the inner optimization algorithm are calculated, the speed and position of the elements in the inner optimization algorithm are adjusted, the element adaptability values ​​are calculated again, the optimal position of the single element and the optimal position of the global element are updated, and if the end condition of the inner optimization algorithm is met, the first empirical coefficient is output. If the optimal value does not meet the end condition of the inner optimization algorithm, the speed and position of the elements in the inner optimization algorithm will continue to be adjusted until the end condition of the inner optimization algorithm is met.

[0030] In getting the first empirical coefficient After the optimal value is obtained, return to the outer optimization algorithm and change the current optimal number of transformation layers , the first empirical coefficient and the second empirical coefficient Save, adjust the individual positions of the element set in the outer optimization algorithm, obtain a new element set, repeat the inner optimization algorithm stage, and output a new first empirical coefficient Optimal value, calculate the fitness value of each individual in the new element set, and update the current optimal number of transformation layers , the first empirical coefficient and the second empirical coefficient , if the end condition of the outer optimization algorithm is met, the current optimal number of transformation layers is output , the first empirical coefficient and the second empirical coefficient , if the end condition of the outer optimization algorithm is not met, the individual positions of the element set in the outer optimization algorithm continue to be adjusted until the end condition of the outer optimization algorithm is met.

[0031] In a possible implementation, in step S23, a signal-to-noise ratio evaluation index and a waveform similarity evaluation index are further selected to form an adaptability function for evaluating the performance of the inner and outer nested optimization algorithm.

[0032] A photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit in the present application has the following advantages:

[0033] The power of the hybrid energy storage unit is divided into power frequencies by adopting the inner product transform filtering algorithm, wherein the structural elements are selected to perform XOR followed by XOR and XOR followed by XOR processing on the inner product transform sub-bands, thereby improving the filtering effect and thus improving the power control accuracy. The inner and outer layer nested optimization algorithm is used to optimize the internal parameters of the inner product transform 1-D threshold criterion, thereby improving the power frequency division processing effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] In order to more clearly illustrate the embodiments of the present application or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0035] Figure 1A schematic flow chart of a photovoltaic power generation coordinated operation control method including a hybrid energy storage unit provided in an embodiment of the present application;

[0036] Figure 2 A schematic diagram of the process of step S2 provided in an embodiment of the present application;

[0037] Figure 3 A schematic diagram of a power low-speed change signal and a power high-speed change signal provided in an embodiment of the present application;

[0038] Figure 4 A schematic diagram of power output of a photovoltaic power generation system provided in an embodiment of the present application;

[0039] Figure 5 A schematic diagram of the DC bus power after being smoothed provided in an embodiment of the present application;

[0040] Figure 6 A schematic diagram of a battery output power curve and a supercapacitor output power curve provided in an embodiment of the present application. DETAILED DESCRIPTION

[0041] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0042] like Figure 1 and Figure 2 As shown, the embodiment of the present application provides a photovoltaic power generation coordinated operation control method including a hybrid energy storage unit, comprising the following steps:

[0043] Step S1, outputting the power of the hybrid energy storage unit.

[0044] Step S2, using an inner product transformation filtering algorithm to perform power frequency division processing on the power of the hybrid energy storage unit to obtain a power low-speed change signal and a power high-speed change signal.

[0045] Step S3, sending the power low-speed change signal and the power high-speed change signal to the battery controller and the supercapacitor controller respectively to realize power control.

[0046] Step S2 includes:

[0047] Step S21, selecting a carrier function of an inner product transformation filtering algorithm, performing signal transformation on the power of the hybrid energy storage unit, and obtaining a series of inner product transformation sub-bands.

[0048] Step S22, selecting a structure element to perform XOR followed by IOR and IOR followed by XOR processing on the inner product transformation sub-band to obtain an inner product transformation coefficient.

[0049] Step S23, reconstructing the inner product transformation coefficients by using the inner product transformation 1-D threshold criterion based on the Birgé-Massart strategy to obtain the power low-speed change signal, and the difference between the power of the hybrid energy storage unit and the power low-speed change signal is the power high-speed change signal.

[0050] In step S23, before reconstructing the inner product transform coefficients, an inner and outer nested optimization algorithm is used to optimize the internal parameters of the inner product transform 1-D threshold criterion.

[0051] Specifically, in step S1, the steady target power is set to , the power output of the photovoltaic power generation system is , then the hybrid energy storage unit power As shown below:

[0052]

[0053] Hybrid energy storage unit power Equal to the steady target power Power output of photovoltaic power generation system The difference.

[0054] In step S2, the inner product transformation filtering algorithm is used to filter the power of the hybrid energy storage unit. Perform power frequency division processing and mix the energy storage unit power After being processed by the inner product transform filtering algorithm, the power slow change signal is obtained. , hybrid energy storage unit power With power slow change signal The difference is the power high-speed change signal .

[0055] In step S3, the power slow change signal Sent to the battery controller, the power high-speed change signal The power is sent to the supercapacitor controller, so that the battery and supercapacitor can perform power smoothing work respectively.

[0056] Exemplarily, step S21 includes:

[0057] A composite function composed of a mother function and a scale function is selected as the carrier function, the number of deconstruction layers is set, and signal transformation is performed on the power of the hybrid energy storage unit to obtain a series of inner product transformation sub-bands.

[0058] Specifically, in this embodiment, the generating function and scale function As shown below:

[0059]

[0060]

[0061] in, Indicates the signal sampling point.

[0062] In this embodiment, the number of structural layers is set to 4 according to the signal length, and the hybrid energy storage unit power is transformed into a signal to obtain a series of inner product transformation sub-bands. .

[0063] Exemplarily, step S22 includes:

[0064] Select a structural element, and perform XOR followed by XOR and XOR followed by XOR on the inner product transformation sub-bands to obtain a first inner product transformation sub-band and a second inner product transformation sub-band.

[0065] The inner product transform sub-region is subjected to coupling processing of the first inner product transform sub-region and the second inner product transform sub-region to obtain the inner product transform coefficient.

[0066] Specifically, in this embodiment, a structural element of an appropriate size is selected. , for all inner product transformation sub-zones Perform XOR and then IOR processing, as shown below , get the first inner product transformation sub-zone ; For all inner product transformation sub-zones Perform the same or followed by XOR processing, as shown below , get the second inner product transformation sub-zone .

[0067] Inner product transformation sub-zone Perform the first inner product transformation sub-zone and the second inner product transform sub-zone The coupling process is shown in the following formula:

[0068]

[0069] in, Represents the first generation inner product transform coefficients.

[0070] Exemplarily, in step S22, if the inner product transform coefficient does not meet the system requirements, a larger range of structural elements is selected, and the inner product transform coefficient is coupled with the first inner product transform sub-band and the second inner product transform sub-band until the obtained inner product transform coefficient meets the system requirements.

[0071] Specifically, if the first generation inner product transformation coefficient If the system requirements are not met, a larger range of structural elements is selected , for the first generation inner product transformation coefficient The coupling process of the first inner product transform sub-zone and the second inner product transform sub-zone is performed, and the process is repeated until the inner product transform coefficient is obtained. Meet the system requirements, as shown in the following formula:

[0072]

[0073] in, Indicates Substitute the inner product transformation coefficients.

[0074] Exemplarily, in step S23, the process of determining the threshold value by the inner product transform 1-D threshold criterion includes:

[0075] Determine the number of transformation levels , retain more than the number of transformation layers All coefficients of the components of .

[0076] For layer, , retaining the largest value coefficients, among which, Determined by the following formula:

[0077]

[0078] In the formula, the first empirical coefficient and the second empirical coefficient is a constant, , is the number of transformation layers The corresponding first layer inner product transformation coefficient and the second empirical coefficient Usually 3 is chosen.

[0079] Exemplarily, in step S23, before reconstructing the inner product transform coefficients, an inner and outer nested optimization algorithm is used to optimize the number of transformation layers of the inner product transform 1-D threshold criterion. , the first empirical coefficient and the second empirical coefficient Optimize, wherein the outer optimization algorithm is used to optimize the number of transformation layers and the second empirical coefficient , the inner optimization algorithm is used to optimize the first empirical coefficient .

[0080] Exemplarily, in step S23, the number of transformation layers of the inner product transformation 1-D threshold criterion is , the first empirical coefficient and the second empirical coefficient Optimizations include:

[0081] First, the outer layer optimization algorithm is used to optimize the number of transformation layers. and the second empirical coefficient , initially configure the element set and randomize the element level, calculate the fitness value of each individual in the outer optimization algorithm, and then enter the inner optimization algorithm stage.

[0082] In the inner optimization algorithm stage, the parameters and elements are initially assigned values, the element adaptability values ​​in the inner optimization algorithm are calculated, the speed and position of the elements in the inner optimization algorithm are adjusted, the element adaptability values ​​are calculated again, and the optimal position of a single element is updated. and the optimal position of global elements , if the inner optimization algorithm termination condition is met, the first empirical coefficient is output If the optimal value does not meet the end condition of the inner optimization algorithm, the speed and position of the elements in the inner optimization algorithm will continue to be adjusted until the end condition of the inner optimization algorithm is met.

[0083] In getting the first empirical coefficient After the optimal value is obtained, return to the outer optimization algorithm and change the current optimal number of transformation layers , the first empirical coefficient and the second empirical coefficient Save, adjust the individual positions of the element set in the outer optimization algorithm, obtain a new element set, repeat the inner optimization algorithm stage, and output a new first empirical coefficient Optimal value, calculate the fitness value of each individual in the new element set, and update the current optimal number of transformation layers , the first empirical coefficient and the second empirical coefficient , if the end condition of the outer optimization algorithm is met, the current optimal number of transformation layers is output , the first empirical coefficient and the second empirical coefficient , if the end condition of the outer optimization algorithm is not met, the individual positions of the element set in the outer optimization algorithm continue to be adjusted until the end condition of the outer optimization algorithm is met.

[0084] Specifically, in this embodiment, the outer optimization algorithm adopts the gray wolf optimization algorithm, and the inner optimization algorithm adopts the particle swarm optimization algorithm. In other possible embodiments, the outer optimization algorithm and the inner optimization algorithm may also adopt other optimization algorithms as long as they can form an inner and outer nested optimization algorithm.

[0085] Exemplarily, in step S23, a signal-to-noise ratio evaluation index and a waveform similarity evaluation index are further selected to form an adaptability function for evaluating the performance of the inner and outer nested optimization algorithm.

[0086] Specifically, the signal-to-noise ratio evaluation index As shown below:

[0087]

[0088] in, is the denoised signal, For a "pure" signal.

[0089] Waveform similarity evaluation index As shown below:

[0090]

[0091] in, is the original signal.

[0092] From the signal-to-noise ratio evaluation index Similarity evaluation index with waveform From the definition of The larger the value, the better the filtering effect; The smaller the value, the more similar the processed signal is to the original signal. Take the inverse and compare it with the waveform similarity evaluation index Add together to form the fitness function As shown below:

[0093]

[0094] Fitness function Used to evaluate the performance of inner and outer nested optimization algorithms.

[0095] In a possible embodiment, a photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit of the present application is simulated and verified, and the parameters of the photovoltaic cells under standard test conditions are selected as follows: the number of photovoltaic arrays in parallel N p =28, the number of photovoltaic panels in series N s =14, the maximum point power of a single photovoltaic panel P max =120.7W. Figure 3 The figure shows the power low-speed change signal and the power high-speed change signal output by the simulation result of a photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit of the present application, which are Figure 3It can be seen that the photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit in the present application can effectively and accurately separate the power low-speed change signal and the power high-speed change signal from the power of the hybrid energy storage unit, reduce the battery operating frequency, and perform accurate power distribution. Figure 4 and Figure 5 The following are schematic diagrams of the photovoltaic power generation system power output and the DC bus power after smoothing. Figure 4 and Figure 5 It can be seen that the photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit in the present application can effectively reduce the peak and fill the valley of power fluctuations to ensure the stability of the DC bus power. Figure 6 The output power curve of the battery and the output power curve of the supercapacitor are shown in Figure 1. Figure 6 It can be seen that the photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit in the present application effectively reduces the operating frequency of the battery, and achieves the purpose of power leveling of different frequency bands undertaken by the battery and the supercapacitor respectively. In summary, the photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit in the present application is applied to the power allocation and coordinated control of the photovoltaic hybrid energy storage system of supercapacitors and batteries, and has effectiveness and stability.

[0096] The embodiment of the present application performs power division processing on the power of the hybrid energy storage unit by adopting an inner product transform filtering algorithm, wherein a structural element is selected to perform XOR followed by XOR and XOR followed by XOR processing on the inner product transform sub-bands, thereby improving the filtering effect and further improving the power control accuracy, and adopting an inner and outer layer nested optimization algorithm to optimize the internal parameters of the inner product transform 1-D threshold criterion, thereby improving the power division processing effect.

[0097] Although the preferred embodiments of the present application have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present application.

[0098] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.

Claims

1. A photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit, It is characterized in that The following steps are involved: Step S1, outputting the power of the hybrid energy storage unit; Step S2, using an inner product transformation filtering algorithm to perform power frequency division processing on the power of the hybrid energy storage unit to obtain a power low-speed change signal and a power high-speed change signal; Step S3, sending the power low-speed change signal and the power high-speed change signal to the battery controller and the supercapacitor controller respectively to realize power control; Step S2 includes: Step S21, selecting a carrier function of an inner product transformation filtering algorithm, performing signal transformation on the power of the hybrid energy storage unit, and obtaining a series of inner product transformation sub-bands; Step S22, selecting a structural element to perform XOR followed by IOR and IOR followed by XOR processing on the inner product transformation sub-band to obtain an inner product transformation coefficient; The XOR followed by the same OR is as follows , the same or followed by different or is as follows ,in, represents the inner product transform sub-zone, Represents a structural element, represents the first inner product transform sub-region, represents the second inner product transform sub-region; Step S23, reconstructing the inner product transformation coefficients by using the inner product transformation 1-D threshold criterion based on the Birgé-Massart strategy to obtain the power low-speed change signal, and the difference between the power of the hybrid energy storage unit and the power low-speed change signal is the power high-speed change signal; In step S23, before reconstructing the inner product transform coefficients, an inner and outer nested optimization algorithm is used to optimize the internal parameters of the inner product transform 1-D threshold criterion; In step S23, the process of determining the threshold value by the inner product transform 1-D threshold criterion includes: Determine the number of transformation layers , retain more than the number of transformation layers All coefficients of the components of ; For layer, , retaining the largest value coefficients, among which, Determined by the following formula: In the formula, the first empirical coefficient and the second empirical coefficient is a constant, , is the number of transformation layers The corresponding first-layer inner product transformation coefficient; In step S23, before reconstructing the inner product transform coefficients, an inner and outer nested optimization algorithm is used to optimize the number of transformation layers of the inner product transform 1-D threshold criterion. , the first empirical coefficient and the second empirical coefficient Optimize, wherein the outer optimization algorithm is used to optimize the number of transformation layers and the second empirical coefficient , the inner optimization algorithm is used to optimize the first empirical coefficient ; In step S23, the inner and outer nested optimization algorithm is used to transform the number of transformation layers of the inner product transformation 1-D threshold criterion. , the first empirical coefficient and the second empirical coefficient Optimizations include: First, the outer layer optimization algorithm is used to optimize the number of transformation layers. and the second empirical coefficient , initially configure the element set and randomize the element level, calculate the fitness value of each individual in the outer optimization algorithm, and then enter the inner optimization algorithm stage; In the inner optimization algorithm stage, the parameters and elements are initially assigned values, the element adaptability values ​​in the inner optimization algorithm are calculated, the speed and position of the elements in the inner optimization algorithm are adjusted, the element adaptability values ​​are calculated again, the optimal position of the single element and the optimal position of the global element are updated, and if the end condition of the inner optimization algorithm is met, the first empirical coefficient is output. If the optimal value does not meet the end condition of the inner optimization algorithm, the speed and position of the elements in the inner optimization algorithm will continue to be adjusted until the end condition of the inner optimization algorithm is met; In getting the first empirical coefficient After the optimal value is obtained, return to the outer optimization algorithm and change the current optimal number of transformation layers , the first empirical coefficient and the second empirical coefficient Save, adjust the individual positions of the element set in the outer optimization algorithm, obtain a new element set, repeat the inner optimization algorithm stage, and output a new first empirical coefficient Optimal value, calculate the fitness value of each individual in the new element set, and update the current optimal number of transformation layers , the first empirical coefficient and the second empirical coefficient , if the end condition of the outer optimization algorithm is met, the current optimal number of transformation layers is output , the first empirical coefficient and the second empirical coefficient , if the end condition of the outer optimization algorithm is not met, the individual positions of the element set in the outer optimization algorithm continue to be adjusted until the end condition of the outer optimization algorithm is met.

2. A photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit according to claim 1, It is characterized in that Step S21 includes: A composite function composed of a mother function and a scale function is selected as the carrier function, the number of deconstruction layers is set, and signal transformation is performed on the power of the hybrid energy storage unit to obtain a series of inner product transformation sub-bands.

3. A photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit according to claim 1, It is characterized in that Step S22 includes: Selecting a structural element, performing an XOR followed by an IOR and an IOR followed by an XOR process on the inner product transformation sub-region, respectively, to obtain a first inner product transformation sub-region and a second inner product transformation sub-region; The inner product transform sub-region is subjected to coupling processing of the first inner product transform sub-region and the second inner product transform sub-region to obtain the inner product transform coefficient.

4. A photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit according to claim 3, It is characterized in that In step S22, if the inner product transform coefficient does not meet the system requirements, a larger range of structural elements is selected, and the inner product transform coefficient is coupled with the first inner product transform sub-band and the second inner product transform sub-band until the obtained inner product transform coefficient meets the system requirements.

5. A photovoltaic power generation coordinated operation control method containing a hybrid energy storage unit according to claim 1, It is characterized in that In step S23, a signal-to-noise ratio evaluation index and a waveform similarity evaluation index are further selected to form an adaptability function for evaluating the performance of the inner and outer nested optimization algorithm.

Citation Information

Patent Citations

  • Hybrid energy storage power distribution method based on variational mode decomposition and Savitzky-Golay filtering

    CN117879007A

  • Self-adaptive wavelet threshold image de-noising algorithm and device

    CN105913393A

  • Power distribution method and device of hybrid energy storage device, medium and equipment

    CN114977237A