Deep ramming treatment method for large-thickness collapsible loess

By setting the main and secondary tamping points in the loess, combined with multiple tamping and humidity-enhancing treatment, the problems of insufficient depth and insufficient construction experience in the existing technology are solved, and the depth of the loess foundation is realized Stable treatment significantly reduces wettability and reduces construction costs.

CN118911109AInactive Publication Date: 2024-11-08WUHAN SURVEYING GEOTECHN RES INST OF MCC
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202411170601.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-26
Publication Date
2024-11-08
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

The existing technology does not have enough depth and lacks construction experience when dealing with deep wet loess, resulting in high construction costs and long construction periods, which cannot meet the deep treatment needs of modern buildings.

Method used

The deep tamping treatment method of large-thick wet-sinking loess is adopted. By setting the main tamping point and the secondary tamping point in the loess, combining multiple tamping operations and humidity-enhancing treatment, the tamping energy configuration and construction sequence are optimized, and the tamping interval is controlled. Time ensures that the processing depth can reach 10m or more.

Benefits of technology

It significantly weakens or eliminates the foundation wettability of the depth of about 10m, improves the treatment depth and construction efficiency, reduces construction costs, and provides new foundation treatment solutions for Class A and Class B buildings.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911109A_ABST
    Figure CN118911109A_ABST
Patent Text Reader

Abstract

The invention provides a deep ramming treatment method for large-thickness collapsible loess. The method comprises the following steps: calculating the tamping energy of each point and the falling distance of a tamping hammer according to the formula by adjusting the spacing of tamping points, optimally configuring a main tamping point and an auxiliary tamping point and according to the effective depth required to be reinforced, tamping the main tamping point firstly and then tamping the auxiliary tamping point according to the calculated tamping energy of each tamping point and the falling distance of the tamping hammer. The loess treatment depth can reach 10 m or above, the collapsibility of new loess foundations with the depth of about 10 m can be remarkably weakened and eliminated, the problems that domestic large-thickness collapsible loess foundations are insufficient in tamping treatment depth and insufficient in design and construction experience are solved, new possibilities are provided for current first and second building foundation form selection, and extremely high practicability is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of building foundation treatment in loess areas, in particular to a deep tamping treatment method for large-thickness collapsible loess. Background Art

[0002] As a special Quaternary sediment, loess is very harmful to engineering construction due to its loose structure, large porosity, and easy collapse when exposed to water. In order to reduce the collapse and improve the performance of the project, foundation treatment is often required during construction.

[0003] Dynamic compaction has always been the preferred treatment solution for Class C and D industrial and civil buildings in loess regions due to its low cost and convenience. For Class B buildings, because their actual collapsible treatment depth is mostly below 6.5m, the depth of the existing dynamic compaction treatment process does not meet the residual wet limit calculation requirements of the current specifications. Therefore, the existing treatment methods for Class A and Class B buildings generally use other composite foundations or pile foundation solutions such as compaction piles and rammed expansion piles. Compared with dynamic compaction, these treatment methods are more troublesome to construct, have a long construction period, and high construction costs, which invisibly increases the construction cost. In recent years, with the continuous emergence of medium and high-rise buildings (structures), dynamic compaction has become a loess treatment solution that is easily accepted by builders, achieving deep treatment, and meeting modern construction needs has become a new requirement of the industry. Summary of the invention

[0004] In view of the defects of the prior art, the present invention provides a method for tamping treatment of deep collapsible new loess, the loess treatment depth of which can reach 10m or more, which can solve the problems of difficulty in tamping treatment of deep collapsible loess and insufficient experience in design and construction of ultra-deep tamping treatment in China, and also provides new possibilities for the selection of current Class A and Class B building foundation forms.

[0005] In order to achieve the above technical purpose, the present invention provides a deep tamping treatment method for collapsible loess with large thickness, characterized in that: the method is applicable to new loess with natural water content ω satisfying 10%≤ω<20% and natural porosity ratio e>0.9, and the treatment depth is applicable to 7.5-15m, and the specific steps are as follows:

[0006] S1. Clean and level the collapsible loess construction site, mark the positions of the main tamping points and the secondary tamping points; the main tamping points are distributed in a square, the secondary tamping points are arranged between the main tamping points by the insertion method, and the spacing between adjacent tamping points is 3.5 to 4.5 times the diameter of the tamping hammer;

[0007] S2. The crane and the supporting rammer are in place, and the rammer weight W is 65 to 95T;

[0008] S3. Perform multiple tamping operations on the flattened collapsible loess construction site in step S1, first tamping the main tamping point, then tamping the secondary tamping point, the single-point tamping energy E is combined with the effective reinforcement depth, calculated according to the following formula ①, and the single-point tamping drop distance H, i.e. the distance from the bottom of the hammer to the tamping surface, is calculated according to the following formula ②:

[0009] E=β0*10(D / K) 2 ①

[0010] Where: E-single point impact energy, KN.m; D-effective reinforcement depth, m;

[0011] K-correction coefficient, 0.4 for new loess;

[0012] β0-deep correction coefficient for treatment depth of thick collapsible loess; the main point tamping is 2.0, and the auxiliary point tamping is 1.5;

[0013] H= E / W ②

[0014] In the above formula: E-ramming energy, KN.m; H-fall distance, m;

[0015] W-ramming hammer weight, KN;

[0016] S4. After the last round of tamping of the auxiliary tamping point is completed, it is pushed flat and tamped 1 to 2 times with a low-energy full tamping force of 2000KN.m to 3000KN.m. The drop distance H is calculated according to the above formula ②;

[0017] S5. Take samples to test the porosity ratio and collapsibility coefficient indicators, and use the collapsibility coefficient to determine whether the collapsibility of the foundation at different depths in the treatment area has been weakened or eliminated.

[0018] A preferred technical solution of the present invention is: when the natural water content ω in the collapsible loess to be treated is less than 10%, a humidification treatment should be performed before the tamping treatment so that the water content ω in the collapsible loess to be treated satisfies 10%≤ω<20%.

[0019] A better technical solution of the present invention: in the step S1, the main tamping points of two adjacent rows and two adjacent columns are staggered, the auxiliary tamping points of two adjacent rows and two adjacent columns are also staggered, and all the main tamping points and auxiliary tamping points are cross-distributed to form a square, the actual distance between two adjacent tamping points is 4 times the hammer diameter, and the hammer diameter D of the tamping hammer is 2.5m.

[0020] A better technical solution of the present invention: in the S3 step, four strong tamping operations are performed, wherein the main tamping points are tamped twice, and the auxiliary tamping points are tamped twice, the main tamping point of the second time is located at the center of the square formed by the main tamping points of the first time, the auxiliary tamping point of the third time is located at the center of the side line of the square formed by the main tamping points of the first time, and the auxiliary tamping point of the fourth time is located at the center of the side line of the square formed by the tamping points of the first time, and is arranged vertically; each tamping operation is performed in sequence, and the interval between two adjacent tamping operations is 3 days.

[0021] A more preferred technical solution of the present invention: in the S3 step, the effective reinforcement depth is 7.5 to 15 m, wherein when the effective reinforcement depth is 10 m, the tamping energy of the main tamping point is 16000 KN.m, and the tamping energy of the auxiliary point is 9000 KN.m.

[0022] A preferred technical solution of the present invention is as follows: in the step S3, tamping is stopped when the average tamping amount of the last two tamping hits of each main tamping point is s≤250mm, and tamping is stopped when the average tamping amount of the last two tamping hits of each auxiliary tamping point is s≤200mm.

[0023] A preferred technical solution of the present invention: in the S5 step, sampling and testing are carried out by exploratory well sampling, the spacing of the exploratory wells is 1m to 1.5m, and the depth of the exploratory wells is in the range of 7.5 to 15m; when the loess foundation collapsibility coefficient δZS≤0.015, it means that the collapsibility of the foundation soil in this depth section is basically eliminated or weakened; δZS>0.015 means that the collapsibility of the foundation soil in this depth section has not been weakened or eliminated, and further processing is required.

[0024] A more preferred technical solution of the present invention: in the step S4, when the humidification treatment is not performed, the tamping energy E is 3000 KN.m; after the humidification treatment is performed, the tamping energy E is 2000 KN.m.

[0025] The preferred technical solution of the present invention: The specific process of the humidification treatment is as follows: humidification holes are arranged in the collapsible loess area to be treated, the humidification holes are arranged in an equilateral triangle, with a spacing of 1.5m, a hole diameter of 150mm, a humidification depth of 8.5 to 11.5m, and an interval of at least 3 days after water injection. When the moisture content meets the requirements through sampling and monitoring, the dynamic compaction treatment is started.

[0026] The present invention adopts the setting of main and auxiliary tamping point systems, the optimal configuration of tamping energy, the operation of multiple tamping sequences, and the reasonable control of intermittent time, so that the loess treatment depth can reach 10m or more, which can significantly reduce and eliminate the collapsible property of new loess foundations about 10m deep, making up for the problems of insufficient tamping treatment depth of large-thickness collapsible loess foundations and insufficient design and construction experience in China, and also provides new possibilities for the selection of modern A and B building foundation forms, and has extremely strong practicality. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of the arrangement of tamping points;

[0028] Figure 2 This is a schematic diagram of the full tamping point arrangement;

[0029] Figure 3 It is a schematic diagram of the humidification hole setting. DETAILED DESCRIPTION

[0030] The present invention will be further described below in conjunction with the accompanying drawings and embodiments. Figures 1 to 3 The drawings are all of embodiments, which are drawn in a simplified manner and are only used for the purpose of clearly and concisely illustrating the embodiments of the present invention. The technical solutions shown in the following drawings are specific solutions of the embodiments of the present invention and are not intended to limit the scope of the invention claimed for protection. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0031] Embodiment For a thick layer of collapsible loess site in Lanzhou, the natural average water content ω is close to 10%, the porosity ratio e>0.9, and dynamic compaction treatment is carried out in two ways: natural and humidification.

[0032] Implementation 1: Directly process according to natural conditions. The specific steps are as follows:

[0033] S1. Clean and level the construction site of collapsible loess, design the tamping energy plan according to the depth requirements of collapsible treatment, and mark the positions of the main tamping points and auxiliary tamping points: the main tamping points are arranged in a square, and the auxiliary tamping points are arranged by the insertion method, with a tamping point spacing of 10m; Figure 1 As shown;

[0034] S2. The crane and the supporting rammer are in place, and the rammer weight W is 65 to 95T;

[0035] S3. Perform multiple tamping operations on the flattened collapsible loess layer construction site in step S1, first perform tamping twice on the main tamping point, and then perform tamping twice on the secondary tamping point; according to the needs of the construction site, the effective reinforcement depth is 10m, the single-point tamping energy E is combined with the effective reinforcement depth, and is calculated according to the following formula ①, and the single-point tamping drop distance H, that is, the distance from the bottom of the hammer to the starting surface of the tamping, is calculated according to the following formula ②:

[0036] E=β0*10(D / K) 2 ①

[0037] Where: E-single point impact energy, KN.m; D-effective reinforcement depth, m;

[0038] K-correction coefficient, 0.4 for new loess;

[0039] β0-deep correction coefficient for treatment depth of thick collapsible loess; the main point tamping is 2.0, and the auxiliary point tamping is 1.5;

[0040] E=WH

[0041] H= E / W ②

[0042] In the above formula: E – impact energy, KN.m;

[0043] W-ramming hammer weight, KN; H-drop distance, m;

[0044] The calculated tamping energy of the main tamping point is 16000kN.m, with a drop distance of 25m; the tamping energy of the auxiliary tamping point is 9000kN.m, with a drop distance of 14m; the tamping energy of the first main point tamping is 16000kN.m, with a drop distance of 25m, and the average tamping amount of the last two hits does not exceed 250mm; the second tamping point is located at the center of the square formed by the first tamping points, and the tamping energy is 16000kN.m, with a drop distance of 25m, and the average tamping amount of the last two hits does not exceed 250mm; the auxiliary tamping point of the third time is located at the center of the side line of the square formed by the first tamping points, and the tamping energy is 9000kN.m, with a drop distance of 14m, and the average tamping amount of the last two hits does not exceed 200mm; the auxiliary tamping point of the fourth time is located at the center of the side line of the square formed by the first tamping points, and the tamping energy is 9000kN.m, with a drop distance of 14m, and the average tamping amount of the last two hits does not exceed 200mm. According to the tamping energy plan, each tamping point is given 10 strikes, and the interval between two adjacent tamping times is 3 days.

[0045] S4. After two main tamping and two auxiliary tamping, use 3000KN.m tamping energy, 5m drop distance, and low tamping energy for one full tamping, 2 hits per point, as follows: Figure 2 As shown;

[0046] S5. After full tamping and leveling, take samples from the exploration well to determine the porosity ratio and collapsibility index. The sampling interval is 1.0m. The collapsibility coefficient is used to determine whether the collapsibility of the foundation in the depth section of the treatment area is weakened or eliminated.

[0047] Embodiment 1 The foundation treatment depth was tested and evaluated according to the collapsibility coefficient δZS≤0.015. The results showed that under natural conditions, the main tamping energy of 16000 KN.m can effectively reduce and eliminate the collapsibility of 10m loess foundation.

[0048] Implementation 2: tamping the loess under humidification conditions. The specific steps are as follows:

[0049] S1. Perform humidification treatment first according to the determined plane treatment range, and the humidification holes are arranged in an equilateral triangle, such as Figure 3 As shown, the spacing is 1.5m, the hole diameter is 150mm, and the humidification depth is 10.0m; water is injected into the hole according to the estimated water volume, and the intermittent time is based on the stability standard of the average wetting volume of the last day being less than 1mm / d;

[0050] S2. According to the requirements of the depth of collapsible treatment, the tamping energy scheme is designed as follows. Specifically, the scheme in Example 1 is the same. The main point tamping is arranged in a square, and the auxiliary point tamping is arranged by the insertion point method. The spacing between the tamping points is 10m; the first main point tamping, the tamping energy is 16000kN.m, the drop distance is 25m, and the average tamping amount of the last two hits does not exceed 250mm; the second tamping point is located at the center of the square formed by the first tamping point, and the tamping energy is 16000kN.m, the drop distance is 25m, and the average tamping amount of the last two hits does not exceed 2 50mm; the third auxiliary tamping point is located in the center of the square edge formed by the first tamping point and is arranged horizontally. The tamping energy is 9000kN.m, the drop distance is 14m, and the average tamping amount of the last two hits does not exceed 200mm; the fourth auxiliary tamping point is located in the center of the square edge formed by the first tamping point and is arranged vertically. The tamping energy is 9000kN.m, the drop distance is 14m, and the average tamping amount of the last two hits does not exceed 200mm; each main tamping point has 10 hits, each auxiliary tamping point has 8 hits, and the interval between two adjacent tampings is 3 days;

[0051] S3. After two main tamping and two auxiliary tamping, use 2000KN.m tamping energy, 5m drop distance, and then tamping once more with low tamping energy, 2 hits per point;

[0052] S4. After full tamping and leveling, take samples from the exploration well to determine the porosity ratio and collapsibility coefficient. The sampling interval is 1.0m. The collapsibility coefficient is used to determine whether the collapsibility of the foundation in the depth section of the treatment area is weakened or eliminated.

[0053] The foundation treatment depth was tested and evaluated according to the collapsibility coefficient δZS≤0.015. The results showed that the main tamping energy of 16000KN.m can effectively weaken and eliminate the collapsibility of 10-13m loess foundation. Compared with the method without humidification treatment, its effective reinforcement depth is greater.

[0054] The inventor of this application used a strong compaction treatment method for the sample strong compaction area of ​​the excavation area of ​​a thick layer of collapsible loess site project in Lanzhou. According to the "Technical Specifications for Building Foundation Treatment" (JGJ79-2012), the effective reinforcement depth of the strong compaction method should be calculated from the initial tamping surface. Through on-site soil sampling and indoor test detection of the project test strong compaction area, the results show that:

[0055] In the test tamping area of ​​the excavation area, the effective reinforcement depth of 8000KN.m tamping energy is 5m, and the collapsibility is basically eliminated within the effective reinforcement depth; the effective reinforcement depth of 12000KN.m tamping energy is 7m, and the collapsibility is basically eliminated within the effective reinforcement depth; the effective reinforcement depth of 1600KN.m tamping energy is 10m, and the collapsibility is basically eliminated within the effective reinforcement depth. In the test ramming area of ​​the water injection area, after water is injected, the moisture content ω satisfies 10%≤ω<20%. Judging from the perspective of eliminating collapsibility, the reinforcement depths of the three sampling holes in the 1600KN.m ramming energy test ramming area are 10m, 12m, and 13m respectively; the reinforcement depths of the three sampling holes in the 800KN.m ramming energy test ramming area are 8m, 8m, and 7m respectively; the reinforcement depths of the three sampling holes in the 1200KN.m ramming energy test ramming area are 8m, 10m, and 11m respectively.

[0056] Through the above experiments, it can be seen that in the process of treating collapsible loess, in addition to the requirements for impact energy, there are also certain requirements for water content. When the water content is controlled at 10%≤ω<20%, the treatment effect is better than that when the water content is less than 10%. With the same impact energy, the reinforcement depth is greater.

[0057] The above is only one embodiment of the present invention, and its description is relatively specific and detailed, but it cannot be understood as limiting the scope of the present invention. It should be pointed out that for ordinary technicians in this field, several modifications and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the present invention shall be based on the attached claims.

Claims

1. A deep tamping treatment method for thick collapsible loess, characterized by: The method is applicable to new loess with a natural water content ω satisfying 10%≤ω<20% and a natural porosity ratio e>0.9, and the treatment depth is applicable to 7.5-15m, and the specific steps are as follows: S1. Clean and level the collapsible loess construction site, mark the positions of the main tamping points and the secondary tamping points; the main tamping points are distributed in a square, the secondary tamping points are arranged between the main tamping points by the insertion method, and the spacing between adjacent tamping points is 3.5 to 4.5 times the diameter of the tamping hammer; S2. The crane and the supporting rammer are in place, and the rammer weight W is 65 to 95T; S3. Perform multiple tamping operations on the flattened collapsible loess construction site in step S1, first tamping the main tamping point, then tamping the secondary tamping point, the single-point tamping energy E is combined with the effective reinforcement depth, calculated according to the following formula ①, and the single-point tamping drop distance H, i.e. the distance from the bottom of the hammer to the tamping surface, is calculated according to the following formula ②: E=β0*10(D / K) 2 ① Where: E-single point impact energy, KN.m; D-effective reinforcement depth, m; K-correction coefficient, 0.4 for new loess; β0-deep correction coefficient for treatment depth of thick collapsible loess; the main point tamping is 2.0, and the auxiliary point tamping is 1.5; H= E / W ② In the above formula: E-ramming energy, KN.m; H-fall distance, m; W-ramming hammer weight, KN; S4. After the last round of tamping of the auxiliary tamping point is completed, it is pushed flat and tamped 1 to 2 times with a low-energy full tamping force of 2000KN.m to 3000KN.m. The drop distance H is calculated according to the above formula ②; S5. Take samples to test the porosity ratio and collapsibility coefficient indicators, and use the collapsibility coefficient to determine whether the collapsibility of the foundation at different depths in the treatment area has been weakened or eliminated.

2. The deep tamping treatment method for thick collapsible loess according to claim 1 is characterized by: When the natural water content ω of the collapsible loess to be treated is <10%, humidification treatment should be carried out before tamping treatment to make the water content ω of the collapsible loess to be treated meet 10%≤ω<20%.

3. A deep tamping treatment method for thick collapsible loess according to claim 1 or 2, characterized in that: In step S1, the main tamping points of two adjacent rows and two adjacent columns are arranged alternately, the auxiliary tamping points of two adjacent rows and two adjacent columns are also arranged alternately, and all the main tamping points and auxiliary tamping points are cross-distributed to form a square, the actual distance between two adjacent tamping points is 4 times the hammer diameter, and the hammer diameter D of the tamping hammer is 2.5m.

4. A deep tamping treatment method for thick collapsible loess according to claim 1 or 2, characterized in that: In the step S3, four strong tamping operations are performed, wherein the main tamping points are tamped twice, and the auxiliary tamping points are tamped twice, the main tamping point of the second time is located at the center of the square formed by the main tamping points of the first time, the auxiliary tamping point of the third time is located at the center of the side line of the square formed by the main tamping points of the first time, and the auxiliary tamping point of the fourth time is located at the center of the side line of the square formed by the tamping points of the first time. Each tamping operation is performed in sequence, and the interval between two adjacent tamping operations is 3 days.

5. A deep tamping treatment method for thick collapsible loess according to claim 1 or 2, characterized in that: In the step S3, the effective reinforcement depth is 7.5 to 15 m, wherein when the effective reinforcement depth is 10 m, the tamping energy of the main tamping point is 16000 KN.m, and the tamping energy of the auxiliary point is 9000 KN.m.

6. A deep tamping treatment method for thick collapsible loess according to claim 1 or 2, characterized in that: In the step S3, tamping is stopped when the average tamping depth of the last two tamping hits of each main tamping point is s≤250mm, and tamping is stopped when the average tamping depth of the last two tamping hits of each auxiliary tamping point is s≤200mm.

7. A deep tamping treatment method for thick collapsible loess according to claim 1 or 2, characterized in that: In the step S5, sampling and testing are carried out by using exploration well sampling, the spacing between the exploration wells is 1m to 1.5m, and the depth of the exploration wells is in the range of 7.5 to 15m. When the loess foundation collapsibility coefficient δZS≤0.015, it means that the collapsibility of the foundation soil in this depth section is basically eliminated or weakened; δZS>0.015 means that the collapsibility of the foundation soil in this depth section has not been weakened or eliminated, and further processing is required.

8. The deep tamping treatment method for thick collapsible loess according to claim 2 is characterized by: In the step S4, when the humidification treatment is not performed, the tamping energy E is 3000 KN.m; after the humidification treatment is performed, the tamping energy E is 2000 KN.m.

9. The deep tamping treatment method for thick collapsible loess according to claim 2 is characterized in that: The specific process of the humidification treatment is as follows: humidification holes are arranged in the collapsible loess area to be treated. The humidification holes are arranged in an equilateral triangle, with a spacing of 1.5m, a hole diameter of 150mm, a humidification depth of 8.5 to 11.5m, and an interval of at least 3 days after water injection. When the moisture content meets the requirements through sampling and monitoring, the dynamic compaction treatment is started.

Citation Information

Patent Citations

  • Technology of large-energy dynamic-compaction-treated foundation

    CN106032667A

  • Construction method for treating costal backfill ultrathick gravel soil foundation by 25000 KN.m dynamic compaction

    CN108252291A

  • Construction method for performing humidification and ultra-high energy level treatment on collapsible loess foundation with height of 25m or more

    CN108374403A

  • Novel forced compaction method capable of achieving 15,000-kilonewton-meter tamping energy

    CN109235415A

  • Construction method for treating coastal backfill super-thick gravel soil foundation

    CN117536192A