Method for repairing tubular pile at fixed wharf
By using crane knocking devices and high-pressure freshwater cleaning technology at the fixed dock, PHC pipe piles are repaired, combined with the sequential structural repair method, the problems of easy damage and low repair efficiency in the prior art pipe pile repair are solved, and high efficiency is achieved. Safe pile foundation and structural restoration effects.
Patent Information
- Application Number
- CN202411097994.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-11-08
AI Technical Summary
In the prior art, the repair method of pipe piles for fixed docks mainly relies on chisel removal, which can easily cause secondary damage and poor grouting effect, and lack of sequence of structural repair, resulting in low repair efficiency and flatness.
The lifting and knocking device of the crane is used to remove impurities and press grout to repair PHC pipe piles. The cracks and concrete damage are repaired in a specific order during structural repair. High-pressure fresh water cleaning and polymer cement mortar are used for filling and repair, avoiding the risk of direct chiseling and Repair at will.
It improves the safety and construction efficiency of repairs, reduces pollution to the underwater environment, ensures the accuracy of repairs and material savings, and forms an efficient and targeted repair process.
Smart Images

Figure CN118911126A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of pipe pile repair and supplementation, and in particular to a pipe pile repair method at a fixed wharf. Background Art
[0002] In the existing technology, it is necessary to upgrade and transform the environmental protection facilities of fixed docks to meet the new requirements. In this process, it is generally necessary to add drainage ditches and production sewage collection pools. In this process, there must be repairs to the existing pile foundations and structures, such as damage to pipe piles and damage to structures. However, in the existing technology, the repair of pipe pile damage is mainly done by chiseling. In this process, the tools are relatively sharp and can easily cause secondary damage to the pipe piles. As for structural repair, most of them are mainly repaired directly as a whole, without any requirements for the relevant order, resulting in poor grouting effect and poor surface flatness. Summary of the invention
[0003] The technical problem to be solved by the present invention is to provide a pile foundation and structure repair method at a fixed wharf to solve the above technical problem.
[0004] In order to solve the above technical problems, the technical solutions provided by the present invention are as follows: A method for repairing pile foundations and structures at fixed docks, including pile foundation repair and structure repair. Specifically, the pile foundation repair is to use a crane to hoist a hammering device to act on the PHC pipe piles constituting the pile foundation to remove impurities until the hard part or the steel bar is exposed, and then assemble and position the sleeve to the outer periphery of the PHC pipe pile to be repaired, and grouting is completed in batches and continuously by pressure grouting, and the repair is completed by maintenance; The structural repair is mainly to repair the reinforced concrete structure at the approach bridge structure and the fixed pier, including repair of cracks and concrete damage; In the repair of the cracks, the vertical joints are pressure grouted in a top-to-bottom order, while the horizontal joints are pressure grouted in a one-end-to-other order, and the pressure of the pressure grouting is 0.2-0.8MPa.
[0005] Furthermore, after removing the impurities, the method further includes flushing the surface of the PHC pile to be repaired with pressurized water.
[0006] Furthermore, the flushing is completed by a construction vessel, and after flushing, the sleeve is suspended in the air to complete its installation.
[0007] Furthermore, the damaged part of the PHC pile to be repaired is mainly located in the underwater section or within 2 m under the mud, or close to the pile top and within 1 m from the pile top.
[0008] Furthermore, in the repair of the crack, when the crack width is less than or equal to 0.3 mm, it is necessary to chisel a groove and then press the sealing material into the groove once or several times. The chiseled groove is specifically a U-shaped groove.
[0009] Furthermore, in the concrete damage repair, the damaged part is first cleaned by high-pressure fresh water with a pressure of not less than 20 MPa, and then filled and repaired by spraying concrete or polymer cement mortar.
[0010] Furthermore, the hammering device is mainly used to hammer the cracks of the PHC piles and the marine organisms, loose concrete and other loose attachments around the cracks until the hard parts are exposed.
[0011] Furthermore, the striking device includes a motor connected to the lifting device and a motor support located under the motor. The outer periphery of the motor support extends to form a plurality of linkage mechanisms, and each of the linkage mechanisms is provided with a striking mechanism.
[0012] Furthermore, the linkage mechanism includes a synchronous wheel located on the motor support, and the synchronous wheel is synchronously assembled with a rotating rod sleeved on the striking mechanism through a synchronous belt to achieve synchronous linkage.
[0013] Furthermore, the knocking mechanism includes a screw rod connected to the end of the rotating rod, a screw rod sleeve is provided on the screw rod, and the support arms on both sides of the screw rod are connected to a positioning seat, and a plurality of knocking blocks are provided on the positioning seat.
[0014] The present invention has the following beneficial effects: In the present invention, the use of a hammering device is safer than direct chiseling, will not cause excessive pollution to the underwater environment, and avoids secondary damage to the pipe piles. Then, subsequent flushing and pouring, etc., have higher construction efficiency.
[0015] In the present invention, a specific sequence is used in structural repair to avoid the problem of poor repair efficiency caused by random repair. The repair efficiency is higher and the accuracy is also high, forming a targeted repair process that saves repair materials. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 A flow chart of a pile foundation and structure repair method at a fixed dock provided by the present invention; Figure 2 This is one of the structural schematic diagrams of the striking device provided by the present invention; Figure 3 The second structural schematic diagram of the striking device provided by the present invention; Figure 4 A schematic diagram of the structure of the driving mechanism provided by the present invention; Figure 5A schematic diagram of the structure of the locking head provided by the present invention; In the figure: 6. Motor support; 61. Motor; 62. Electric push rod; 63. Locking head; 64. Synchronous wheel; 65. Locking groove; 66. Driven wheel; 67. Rotating rod; 68. Synchronous belt; 7. Beating mechanism; 71. T-type slide groove; 72. Screw rod; 73. Screw rod sleeve; 74. T-type slide block; 75. Support arm; 76. Positioning seat; 77. Beating block; 78. Fixing cylinder. DETAILED DESCRIPTION
[0017] The present invention is described in detail below in conjunction with the various embodiments shown in the accompanying drawings, but it should be noted that these embodiments are not limitations of the present invention, and any equivalent transformations or substitutions in functions, methods, or structures made by ordinary technicians in the field based on these embodiments are all within the scope of protection of the present invention.
[0018] See attached Figure 1-5 As shown, the pile foundation and structure repair method at the fixed dock in this embodiment is applied to a certain project, and its main construction content is: when carrying out the renovation and maintenance of a certain level of fish port, it is necessary to upgrade and transform the environmental protection facilities at the fixed dock to add a 197m collection ditch and 2 production sewage collection areas with a volume of 30m³. Two sets of domestic sewage collection equipment are added. The dock has 9 additional sewage collection tanks, 3 with a volume of 50m³, 6 with a volume of 12m³, and three sets of domestic sewage collection equipment. 40 PHC pipe piles are repaired for hydraulic structures, 8 additional φ800 cast-in-place piles, 3212m² of fixed dock superstructures are repaired, 6 pole piers, 4 steel poles, and 2 steel approach bridges are repaired for the mooring facilities structure of the floating dock. 5 shore approach bridges and 9 pontoons are repaired. It also includes rubber fenders, bollard repairs, 1 dredging, and 1 shipwreck salvage.
[0019] The following is an introduction to pile foundation repair and structural repair respectively.
[0020] The first step, in this embodiment, is to specifically introduce the pile foundation repair construction as follows: In this embodiment, the pile foundation repair mainly focuses on the repair construction of PHC pipe piles and the construction of cast-in-place piles that need to be added later.
[0021] Pipe pile repair construction The prestressed pipe piles on site were cracked and their durability did not meet the design requirements. The piles with defects in the pile body needed to be repaired. About 40 pipe piles needed to be repaired at the site approach bridge and the lower part of the wharf. Two different methods were used for repair according to the different degrees of damage to the pile body.
[0022] (1) For pile foundations with cracks or defects in the underwater section or within a depth of about 2m below the mud, adopt the following measures: a. Use a hammering device to knock off the surface marine organisms, loose concrete and other loose attachments from the damaged parts until the hard parts are exposed; b. Rinse the concrete surface to be repaired with high-pressure fresh water at a pressure of not less than 20MPa; c. Locate and splice the steel sleeve at the damaged part of the pile foundation, and then check the installation conditions of the steel sleeve, such as its sealing, firmness, and smoothness of the joints; d. Pressure injection of high-strength grouting material into the cavity between the steel sleeve and the pile; (2) For pile foundations with cracks or defects within 1m from the top of the pile, adopt the following measures: a. Use a hammering device to knock off the surface marine organisms, loose concrete and other loose attachments at the damaged part until the hard part is exposed; b. Rinse the concrete surface to be repaired with high-pressure fresh water at a pressure of not less than 20MPa; c. Drill holes and plant the steel bars after finding out the arrangement of the main bars of the upper components; d. Locate and splice the steel sleeve at the damaged part of the pile foundation, and then check the installation conditions of the steel sleeve, such as its sealing, firmness, and smoothness of the joints; e. Pressure-inject high-strength grouting material into the cavity between the steel sleeve and the pile; When repairing PHC pipe piles, a construction boat is used to carry out the construction, the pile body is manually flushed, and after the reinforcement is planted with an electric drill, a crane is used to lift the steel sleeve on the shore or on the upper part of the structure. After the steel sleeve is installed, pressure grouting is carried out. The grouting construction is carried out in batches and continuously.
[0023] f. Pressure grouting is carried out from the grouting pipe prefabricated and installed at the bottom of the steel sleeve. The water and air in the sleeve are discharged through the air holes at the top of the steel sleeve to ensure that the steel sleeve is filled. The grouting operation must be carried out continuously, and the pressure and speed of the grouting should be maintained. When it is necessary to pause, the pause time should be short, and grouting should be carried out again within the operable time. If the operable time is exceeded, the grouting pipeline and machine must be cleaned, and no human disturbance should occur during the consolidation process. If a fault occurs during the grouting process and the grouting is interrupted, the steel sleeve must be removed immediately, the grouting materials must be cleaned, and the installation and grouting operations must be carried out again.
[0024] g. During the grouting process, samples are taken from the material in the grouting pump and the material overflowing from the overflow port according to the on-site conditions, test samples are made and maintained, and compressive strength index performance tests are carried out.
[0025] After the grouting is completed, the overflow port is temporarily sealed to extend the consolidation time of the material as much as possible and ensure the quality of the consolidated body.
[0026] As is known to all, when underwater pipe piles are damaged, especially PHC pipe piles, their own strength will be reduced, and slight knocking will have little effect on them. However, if they are chiseled out, greater force will be used to directly act on the damaged part. Once the strength of the concrete in the damaged part is greatly weakened, it is easy to cause it to break directly, causing secondary damage. The knocking device in this embodiment performs repeated slight knocking within the set force range, thereby achieving better effect.
[0027] See attached Figure 2-5 As shown, in this embodiment, in order to achieve better knocking, it includes a motor 6 connected to the lifting device, and the motor 61 at this time acts toward its motor support 6. In this embodiment, a structure such as a hanging hole that matches the hanging distance can be set at the end of the motor 61, or at the position where the motor support 6 extends. In order to synchronously drive multiple structures, the outer periphery of the motor support 61 is extended to form a plurality of linkage mechanisms, and each of the linkage mechanisms is provided with a knocking mechanism.
[0028] Furthermore, the linkage mechanism includes a synchronous wheel 64 located on the motor support 6, and the synchronous wheel 64 is synchronously assembled with a rotating rod 67 sleeved on the knocking mechanism 7 through a synchronous belt to achieve synchronous linkage.
[0029] Specifically, the striking mechanism 7 includes a screw rod 72 connected to the end of the rotating rod 67 , a screw rod sleeve 73 is provided on the screw rod 72 , and support arms 75 on both sides of the screw rod 72 are connected to a positioning seat 76 , and a plurality of striking blocks 77 are provided on the positioning seat 76 .
[0030] In this embodiment, the working structure of the striking device is as follows: First, a click is set on the motor support 6, and then an electric push rod 62 is embedded on the output shaft of the motor 61, and the piston rod of the electric push rod 62 is fixedly connected with a locking head 63, and a synchronous wheel 64 is rotatably connected at the center of the bottom of the inner cavity of the motor support 6, and a locking groove 65 used in conjunction with the locking head 63 is provided at the center of the top of the synchronous wheel 64. The electric push rod 62 plays a role in regulating the clamping stroke between the locking head 63 and the locking groove 65, and the synchronous wheel 64 is transmission-connected with a driven wheel 66 on all sides away from the motor support 6, and the top of the driven wheel 66 is fixedly connected with a rotating rod 67 that rotates with the fixed cylinder 78, and the transmission cooperation of the synchronous wheel 64 and the four groups of driven wheels 66 drives the four groups of rotating rods 67 to rotate synchronously. In this embodiment, in the entire knocking mechanism 7, the screw rod and other components are assembled in the fixed cylinder.
[0031] The top of the rotating rod 67 is fixedly connected with a screw 72 composed of forward and reverse screw rods that rotate with the fixed tube 78, and the upper and lower sides of the forward and reverse screw rods are threadedly connected with screw sleeves 73, and the outer side of the screw sleeve 73 is fixedly connected with a T-shaped slider 74 that slides with the T-shaped slot 71. The inner side of the screw sleeve 73 is hinged with a support arm 75, and the side of the support arm 75 away from the screw sleeve 73 is hinged with a positioning seat 76, and the inner side of the positioning seat 76 is rotatably connected with a striking block 77. The four groups of rotating rods 67 drive the striking blocks 77 on the four groups of positioning seats 76 to perform four-way striking on the concrete pipe piles to be repaired through the four groups of forward and reverse screw rods 72, screw sleeves 73 and support arms 75. When performing relevant control, the synchronous wheel 64 and the driven wheel 66 are both connected to the synchronous belt 68, which is beneficial for the synchronous wheel 64 to drive the four groups of driven wheels 66 to rotate synchronously, and the four sides of the synchronous wheel 64 are rotatably connected to the first tensioning wheel (not shown in the figure) that cooperates with the synchronous belt 68 for transmission, which plays a role of tensioning and limiting transmission for the synchronous belt 68, thereby improving the stability of the synchronous wheel 64 during the rotation of the four groups of driven wheels 66 driven by the synchronous belt 68, so as to prevent the synchronous belt 68 from slipping and idling on the four groups of driven wheels 66, and a vertical groove used in conjunction with the support arm 75 and the positioning seat 76 is opened on the opposite side of the fixed cylinder 78, which provides space support for the support arm 75 and the positioning seat 76, and is beneficial for adjusting the height of the outer periphery during the knocking.
[0032] In this embodiment, the striking block is a geometric solid with a larger cross-section, such as a cube or a cylinder. The geometric solid is in surface contact with the PHC pile and has no sharp structure, thereby ensuring the safety of striking to the greatest extent.
[0033] 2. Cast-in-place pile construction 2.1 The casing is buried using the pile center point at the center of the circle method. The casing pit is excavated for the cast-in-place pile on the shore and the casing is buried. The cast-in-place pile on the water adopts the approach bridge or dock structure, and the long casing is buried in conjunction with the built water platform. The casing is made of 6mm steel plate, and the inner diameter of the casing used is Φ600. The allowable deviation between the center line of the casing and the center line of the pile position is ≤20mm, and the casing should be buried vertically. After the casing is placed, the pile position should be checked in time. If the error is greater than the specification requirements, it should be re-arranged.
[0034] 2.2 Hole forming construction (1) This process is the most critical process in the entire bored pile construction. The drilling rig is in place and leveled. The pulley at the head of the drilling rig tower, the center of the turntable and the pile position should be on a vertical line. The drilling rig body must be firm to ensure that it does not move or tilt during the construction process. It must be operated at full load before drilling.
[0035] (2) During the drilling process, the circulation ditch of the mud pool should be dredged frequently, and the mud pool should be cleaned regularly and the waste slurry should be transported out in time.
[0036] (3) The key points of this process are: pay close attention to the stability of the pile frame during drilling, whether the casing and soil are sinking, be careful when connecting and removing the drill rod, and carefully check the tight connection of the drill rod joint each time.
[0037] 2.3 Hole cleaning (1) Bored pile hole cleaning adopts secondary slurry replacement and hole cleaning (2) First hole cleaning: After the hole is drilled, slightly raise the drill rod and use it to clean the hole for the first time. Because the first hole cleaning is done with the drill rod, the time and method are strictly controlled in order to remove the sediment generated during the drilling process.
[0038] (3) Second hole cleaning: After the first hole cleaning, the drill rod is pulled out, the hole depth is measured, and the steel cage and concrete conduit are placed in time. The slurry is pressed into the concrete conduit for the second hole cleaning. The purpose is to remove the sediment generated when the steel cage and concrete conduit are placed. After the hole cleaning, the slurry density in the hole is 1.15-1.25, and the sediment at the bottom of the hole meets the design and specification requirements.
[0039] (4) After the second hole cleaning is completed, a dedicated person will measure the hole depth and bottom sediment. Various mud testing tools are available. If the mud in the hole does not meet the design and specification requirements, the hole should be cleaned again until it is qualified.
[0040] The key requirements of this process are: the key to hole cleaning lies in the first cleaning, which should be carried out when drilling to 1 to 2 meters from the designed bottom of the pile foundation. Lifting the drill rod up and down during hole cleaning is conducive to crushing larger mud blocks, so that smaller mud blocks can flow out of the hole with the mud. Therefore, the successful completion of the first cleaning work can better ensure that the bottom sedimentation meets the design requirements.
[0041] 2.4 Steel Cage Production (1) The steel cage is manufactured in sections according to the 9-meter-long fixed-length steel bars, and a certain overlap length is reserved. The overlap length should meet the design and specification requirements.
[0042] (2) A steel cage production shed is set up at the construction site, and a special steel cage production rack is processed.
[0043] (3) To control the thickness of the protective layer, a positioning block is set every 3 meters on the main reinforcement of the steel cage, and 4 are arranged symmetrically around the steel cage. Slag should be removed in time during the welding process.
[0044] (4) The main reinforcement connection of the steel cage shall be carried out in accordance with the design requirements. The distance between the joints of two adjacent main reinforcements (center distance) shall be ≥ 35d, and the number of joints on the same section shall not exceed 50%.
[0045] (5) The key points of this process are: the steel cage must be made on the platform, and the diameter of the steel cage must meet the design and specification requirements; the cage body must not be deformed during transportation; the cage body must be straight when it is made; the reserved steel bars at the overlap position of the upper and lower sections of the steel cage must meet the design and specification requirements.
[0046] 2.5 Steel Cage Placement (1) The steel cage is hoisted by drilling rig and the hole welding of the steel cage adopts vertical centering method. The upper cage is perpendicular to the lower cage and should be located in the center of the hole so that the central axis of the upper and lower cages coincide. Then, it is hoisted to the designed depth in the hole and fixed by crane.
[0047] (2) The steel cage must not be forced down the cage. When lowering the cage, it should be slowly rotated and lowered. Care should be taken to lower it vertically and in the center to avoid collision with the soil wall. The suspension rods should be firm to prevent the steel cage from falling. The length of the suspension rods should be calculated based on the actual measured elevation to ensure that the cage top elevation is correct.
[0048] 2.6 Underwater concrete construction (1) This process uses the conduit method to pour underwater concrete. The design strength grade of the pile foundation concrete is C30 concrete, and commercial concrete is used in the construction. The slump should be controlled at 200±20mm.
[0049] (2) During the concrete pouring process, the depth of the conduit buried in the concrete should be maintained at 3 to 10 meters, generally controlled at 4 to 6 meters, and the minimum buried depth should not be less than 2 meters.
[0050] (3) Accurately calculate the theoretical initial pouring volume to ensure that the bottom of the conduit is buried more than 2m below the concrete surface after the first bucket enters the hole; to ensure the quality of underwater concrete pouring, the conduit should be tested for water tightness before use, and the removal of the conduit must be based on the actual measured data to prevent the conduit from being pulled out and causing broken piles.
[0051] The second step, in this embodiment, is to repair the structure, which is specifically described as follows: In this project, mainly because the beams and panels of the project approach bridge, the beams and panels of the fixed pier, the ship-mooring components, the horizontal braces and the anti-collision piers and other reinforced concrete structures have different damages and need to be repaired. In this embodiment, five repair methods are divided according to the different degrees of structural damage. At this time, since all operations are on water and are affected by the tide level, it is planned to use a combination of construction boats and hanging baskets for manual repair during construction.
[0052] The five specific repair methods are introduced as follows: (1) Measure S1 - Crack repair (width ≤ 0.3 mm) For concrete components with surface cracks with a width of no more than 0.3m in the test report, repair them according to the following steps and requirements: a. A U-shaped groove with a depth of not less than 30mm and a width of not less than 20mm is chiseled along the crack direction; b. Remove loose layers, floating dust, oil stains and other loose attachments in the tank; c. Accurately weigh and mix the sealing material, then press it into the U-shaped groove once or in batches and make it slightly higher than the groove surface, and then smooth and trim it.
[0053] (2) Measure S2 - Crack repair (width > 0.3 mm) For concrete components with cracks with a width greater than 0.3mm on the surface in the test report, repair them according to the following steps and requirements: a. Remove loose objects on the surface of concrete cracks and foreign objects in the cracks; b. Grouting nozzles are buried at the ends of the cracks, at the intersections and on both sides of the cracks. The spacing between the grouting nozzles is 500mm. The method of burying the grouting nozzles is in accordance with the provisions of Article B.2.1 of Appendix B of the Technical Specifications for Repair and Reinforcement of Port Hydraulic Structures: c. Accurately weigh and prepare the sealing material, then press it into the crack once or in batches and make it slightly higher than the groove surface, smooth it and trim it, then pressurize the air to test the connectivity and sealing effect of the grouting nozzle; d. Prepare grouting materials and use them according to the curing time and grouting speed of the grouting liquid; e. Pressure grouting is performed on vertical joints from top to bottom and horizontal joints from one end to the other end, with a grouting pressure of 0.2-0.8MPa; f. After the slurry solidifies, remove the grouting nozzle and trim the concrete surface; g. Paste three layers of carbon fiber cloth in sequence to the damaged area; h. Spray 20mm thick M15 cement mortar to protect the carbon fiber cloth.
[0054] (3) Measure S3 - Concrete damage (no exposed reinforcement) For components with concrete damage but no exposed reinforcement in the test report, repair them according to the following steps and requirements: a. Chisel away the loose concrete at the damaged part until the hard part is exposed, and use high-pressure fresh water with a pressure of not less than 20MPa to clean the dust, loose objects and other loose attachments on the concrete surface; b. Accurately weigh and prepare the concrete interface bonding material, and apply it to the concrete surface to be repaired according to the specified amount; c. According to the on-site construction conditions, use shotcrete or polymer cement mortar to fill and repair to restore the original cross-section of the component.
[0055] (4) Measure S4 - Concrete damage (exposed reinforcement) For components with serious damage and exposed reinforcement in the inspection report, repair them according to the following steps and requirements; a. Chisel away the concrete protective layer where rust expansion cracks appear. For the concrete where the steel bars have been corroded, chisel to 2-3cm behind the main bars, and chisel along the direction of the steel bars to 5cm from the rust-free area: b. Remove rust from the steel bar surface to St2 level, and clean the steel bar and concrete surface with high pressure fresh water: c. When the loss of steel bar section is greater than 10%, additional steel bars should be welded, and the total area of welded steel bars should not be less than 1.1 times the original design quantity; d. Accurately weigh and prepare the concrete interface bonding material, and apply it to the concrete surface to be repaired according to the specified amount; e. According to the on-site construction conditions, use vertical formwork poured concrete, sprayed concrete or polymer cement mortar for filling and repair to restore the original cross-section of the component.
[0056] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.
[0057] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A method for repairing pile foundations and structures at fixed docks, characterized in that: It includes pile foundation repair and structural repair. Specifically, the pile foundation repair is to use a crane to hoist a hammering device to act on the PHC piles that constitute the pile foundation to remove impurities until the hard part or the steel bar is exposed, and then assemble and position the sleeve to the outer periphery of the PHC pile to be repaired, and complete the grouting in batches and continuously by pressure grouting, and complete the repair through maintenance; The structural repair is mainly to repair the reinforced concrete structure at the approach bridge structure and the fixed pier, including repair of cracks and concrete damage; In the repair of the cracks, the vertical joints are pressure grouted in a top-to-bottom order, while the horizontal joints are pressure grouted in a one-end-to-other order, and the pressure of the pressure grouting is 0.2-0.8MPa.
2. The method for repairing pile foundation and structure at a fixed wharf according to claim 1, characterized in that: After the impurities are removed, the process further includes flushing the surface of the PHC pile to be repaired with pressurized water.
3. The method for repairing pile foundation and structure at a fixed wharf according to claim 2, characterized in that: The flushing is completed by a construction vessel, and after flushing, the sleeve is suspended in the air to complete its installation.
4. The method for repairing pile foundation and structure at a fixed wharf according to claim 1, characterized in that: The damaged part of the PHC pile to be repaired is mainly located in the underwater section or within 2m under the mud, or close to the pile top and within 1m away from the pile top.
5. The method for repairing pile foundation and structure at a fixed wharf according to claim 1, characterized in that: In the repair of the crack, when the crack width is less than or equal to 0.3 mm, it is necessary to chisel a groove and then press the sealing material into the groove once or several times. The chiseled groove is specifically a U-shaped groove.
6. The method for repairing pile foundation and structure at a fixed wharf according to claim 1, characterized in that: In the concrete damage repair, the damaged part is first cleaned by high-pressure fresh water with a pressure of not less than 20 MPa, and then filled and repaired by spraying concrete or polymer cement mortar.
7. The method for repairing pile foundation and structure at a fixed wharf according to claim 1, characterized in that: The hammering device is mainly used to hammer the cracks of the PHC piles and the marine organisms, loose concrete and other loose attachments around the cracks until the hard parts are exposed.
8. The method for repairing pile foundation and structure at a fixed wharf according to claim 1, characterized in that: The striking device comprises a motor connected to the lifting device and a motor support located under the motor. The outer periphery of the motor support extends to form a plurality of linkage mechanisms, and each linkage mechanism is provided with a striking mechanism.
9. The method for repairing pile foundation and structure at a fixed wharf according to claim 8, characterized in that: The linkage mechanism comprises a synchronous wheel located on the motor support, and the synchronous wheel is synchronously assembled with a rotating rod sleeved on the striking mechanism through a synchronous belt to achieve synchronous linkage.
10. The method for repairing pile foundation and structure at a fixed wharf according to claim 9, characterized in that: The knocking mechanism comprises a screw rod connected to the end of the rotating rod, a screw rod sleeve is arranged on the screw rod, the supporting arms on both sides of the screw rod are connected to a positioning seat, and a plurality of knocking blocks are arranged on the positioning seat.