Landfill engineering soil or backfill soil containing graphene oxide and use method
By using graphene oxide waste slag in landfill engineering soil or backfill soil, the problems of soil stiffness improvement and environmental friendliness are solved, and the dynamic shear modulus and earthquake resistance and shock absorption capacity of the soil are improved, and the existing solutions are solved. Inadequate soil stiffness improvement and environmental friendliness in technology.
Patent Information
- Application Number
- CN202410863468.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-29
- Publication Date
- 2024-11-08
AI Technical Summary
The prior art is difficult to find a soil improvement additive that can not only improve soil stiffness but also be environmentally friendly, especially in reducing earthquake damage and preventing structural deformation. The waste rubber may release heavy metals and organic pollution during the decomposition process. Things.
Graphene oxide waste slag is used as a component of landfill engineering soil or backfill soil. By uniformly mixing and layered backfill, the dynamic shear modulus and elastic stiffness of the soil are improved, and the earthquake resistance and shock absorption capacity is enhanced.
Effectively improve the dynamic characteristics of soft soil foundation soil, improve the earthquake resistance and shock absorption capacity of the soil, reduce structural damage, and achieve environmentally friendly engineering soil improvement due to the environmental protection and low cost of graphene oxide.
Smart Images

Figure CN118911160A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of landfill engineering soil or backfill soil, and specifically to a landfill engineering soil or backfill soil containing graphene oxide and a method for using the same. Background Art
[0002] What kind of additives can be used in reality to improve the dynamic performance of soil engineering is also a problem. Otsubo et al. found that earthquakes caused the floating of sewage pipes and manholes on artificial islands, which was caused by the liquefaction of backfill soil. They tested recycled materials such as broken glass, broken concrete, mixtures of tire debris and sand, and cement-mixed liquefied spray as backfill materials, and conducted vibration tests. The authors suggested using recycled broken glass as backfill materials. However, because the mechanical behavior of tire-soil mixtures is unknown, tires are not recommended. However, in recent years, the application research of waste tires as backfill materials in civil engineering has progressed rapidly. This revolutionary use method not only solves environmental problems, but also brings new technologies and methods to the field of engineering materials. For example, Liu et al. studied the compression performance of waste tire-sand mixtures, used cyclic triaxial experiments to study the dynamic characteristics under different ratios, and found that a 10% ratio is suitable for seismic isolation of low-rise buildings. The hollow cylinder experiment was used to study the influence of various factors on the dynamic performance of sand-rubber mixtures, and found that rubber content and confining pressure were the main factors. The characteristics of stratified and uniform mixtures were studied through triaxial tests, and it was found that stratified mixtures have better dynamic performance. Placing tire fragments and gravel under the foundation was found to be effective in preventing earthquake damage and finding the best ratio. Elyas et al. used a mixture of rubber and sand as a seismic isolation material and found that it could reduce the acceleration response of the building, but increasing the thickness would lead to settlement. This would limit the promotion of rubber as an earthquake-resistant material, and waste rubber may release heavy metals and organic pollutants during decomposition, posing risks to the environment and human health. Therefore, it is necessary to find soil improvement additives that can simultaneously improve stiffness and be environmentally friendly.
[0003] Graphene is regarded as a future material with revolutionary potential due to its extremely high strength, excellent electrical and thermal conductivity, excellent mechanical properties, good transparency, chemical stability and barrier properties. These characteristics make it have broad application prospects in many fields such as aviation, electronics, energy, and medical care. It is possible to create new technological innovations and change the use and application of existing materials in multiple industries. Due to its unique physical properties and broad application prospects, it has received widespread attention and research. However, in the process of graphene extraction, a large amount of waste will be generated. The generation of these wastes mainly comes from the high energy consumption required in the preparation process of graphene. The materials used are often high-purity graphite, and many by-products are generated in the preparation process. These by-products include organic waste and inorganic waste. For waste residues with some graphene content, they can be used for backfill engineering.
[0004] Graphene oxide is derived from natural and widely distributed graphite. It is not easy to separate from the soil, and it is difficult to decompose and release harmful substances such as heavy metals and organic pollutants, so it has less impact on the environment. As an industrial waste, graphene oxide is low-cost, and a small amount of addition can cause significant parameter changes. In addition, graphene oxide is currently one of the few substances that can simultaneously increase soil stiffness and damping ratio, which can effectively improve the dynamic performance of soil, thereby reducing structural damage, showing its great potential in foundation improvement and backfill applications.
[0005] Application Contents
[0006] The purpose of the present application is to provide a landfill engineering soil or backfill soil containing graphene oxide and a method of use, which can effectively improve the dynamic characteristics of soft soil foundation soil, increase the dynamic shear modulus of the soil, and enhance the elastic stiffness of the soil, so that it can recover faster when subjected to an earthquake. At the same time, it also enhances the soil's ability to effectively absorb vibration energy and reduce the amplitude of seismic shock absorption.
[0007] To achieve the above-mentioned purpose, the present application provides the following technical solution: a landfill engineering soil or backfill soil containing graphene oxide, including graphene oxide waste residue, wherein the graphene oxide waste residue is a waste residue containing graphene in the by-product generated in the preparation process of graphene, and the weight of the graphene oxide waste residue in the landfill engineering soil or backfill soil containing graphene oxide exceeds 1% of the total weight of the landfill engineering soil or backfill soil containing graphene oxide.
[0008] Preferably, the graphene oxide waste residue is contacted with other components of the landfill engineering soil or backfill soil containing graphene oxide by uniform mixing.
[0009] A method for using landfill engineering soil or backfill soil containing graphene oxide, using the landfill engineering soil or backfill soil containing graphene oxide as described above, comprising the following steps:
[0010] Step 1: Prepare an appropriate amount of landfill soil or backfill soil containing graphene oxide and select appropriate compaction machinery;
[0011] Step 2: Level the site, divide the work area, fill the pit in different areas and construction sections, remove garbage, silt and other debris on the surface of the foundation pit, and keep the foundation pit flat and clean;
[0012] Step 3: Compact the site. Use the compaction machine selected in step 1 to compact the original soil at the base until the compaction coefficient of the original soil reaches 0.93. Check the depth and horizontal elevation of the foundation pit and lay thickness marks.
[0013] Step 4: Layered backfilling and compaction. The landfill engineering soil or backfill soil containing graphene oxide and medium-coarse sand are backfilled in alternating layers. The foundation pit is divided into horizontal layers from low to high, and the soil is filled upward layer by layer. After each layer of backfill soil is filled and compacted, the compaction coefficient and bearing capacity of each layer of backfill soil are tested to see if they meet the design requirements. If they meet the design requirements, the next layer is constructed, otherwise it is re-rolled.
[0014] Step 5: Filling test: after step 4 is completed, some samples are taken out for testing. The samples include each layer of soil sample backfilled and compacted in step 4;
[0015] Step 6: Adjust steps 1 to 4 based on the results of the fill test in step 5.
[0016] Preferably, the thickness of each layer is consistent during the layered backfilling in step 4.
[0017] Preferably, the thickness of each layer during layered backfilling in step 4 does not exceed 100 cm. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Figure 1 A conceptual diagram of a manhole and surrounding backfill soil in an embodiment of the present invention;
[0019] Figure 2 A conceptual diagram of a manhole in an embodiment of the present invention;
[0020] Figure 3 is the displacement response of the manhole in the x direction in the embodiment of the present invention;
[0021] Figure 4 is the displacement response of the manhole in the y direction in the embodiment of the present invention;
[0022] Figure 5 is the displacement response of the manhole in the z direction in the embodiment of the present invention;
[0023] Figure 6 It is the total displacement response of the manhole in the embodiment of the present invention.
[0024] Note: The data points for displacement response are Figure 1 The triangular area shown is the connection between the tunnel or pipeline and the working shaft (manhole). Once a large deformation occurs, it will cause rupture, affecting the large-scale drinking water shortage of urban residents.
[0025] Compared with the prior art, the beneficial effects of this application are:
[0026] 1. The landfill engineering soil or backfill soil containing graphene oxide of the present invention uses graphene oxide waste residue as engineering soil or backfill soil by landfilling, places it on the compacted soil of the roadbed, and places it around a series of surface structures such as manholes, so as to reduce the deformation and displacement of the structure under the action of earthquake, realize an engineering comprehensive utilization method, do not generate secondary pollution, have a fast treatment speed, low cost, and reduce the construction cost;
[0027] 2. The present invention utilizes the high specific surface area and excellent adsorption of graphene oxide itself, thereby generating an adsorption superposition effect and intercalation effect between the graphene oxide and the soil body, thereby increasing the cohesion of the entire foundation soil and making it more fluffy. In terms of dynamic performance, it exhibits higher dynamic shear stiffness and a damping ratio that is more suitable for shock absorption and anti-disturbance. Compared with the prior art, the technology of the present invention can not only improve the bearing capacity, but also improve the ability to resist shock and disturbance at the same time. DETAILED DESCRIPTION
[0028] The following will be combined with the drawings in the embodiments of the present application to clearly and completely describe the technical solutions in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.
[0029] Example 1
[0030] A landfill engineering soil or backfill soil containing graphene oxide, comprising graphene oxide waste residue, wherein the graphene oxide waste residue is waste residue containing graphene in a byproduct generated in a graphene preparation process, the weight of the graphene oxide waste residue in the landfill engineering soil or backfill soil containing graphene oxide is 0.5% of the total weight of the landfill engineering soil or backfill soil containing graphene oxide, and the contact mode of the graphene oxide waste residue and other components of the landfill engineering soil or backfill soil containing graphene oxide is uniform mixing.
[0031] The preparation and use methods thereof include:
[0032] Step 1: Prepare an appropriate amount of graphene oxide waste residue and soil, use a mixer or other suitable equipment to mix the graphene waste residue with the soil to ensure that the graphene is evenly distributed, sieve the mixed soil to remove large stones, garbage and silt, ensure that the particles are uniform, and select appropriate compaction machinery;
[0033] Step 2: Level the site, divide the work area, fill the pit in different areas and construction sections, remove garbage, silt and other debris on the surface of the foundation pit, and keep the foundation pit flat and clean;
[0034] Step 3: Compact the site. Use the compaction machine selected in step 1 to compact the original soil at the base until the compaction coefficient of the original soil reaches 0.93. Check the depth and horizontal elevation of the foundation pit and lay thickness marks.
[0035] Step 4: backfill and compact in layers. The landfill engineering soil or backfill soil containing graphene oxide and medium-coarse sand are backfilled in layers in an alternating manner. The thickness of each layer is consistent and does not exceed 100 cm. The foundation pit is divided into horizontal layers from low to high, and is filled upward layer by layer. After each layer of backfill soil is filled and compacted, the compaction coefficient and bearing capacity of each layer of backfill soil are tested to see if they meet the design requirements. If they meet the design requirements, the next layer is constructed, otherwise it is re-rolled;
[0036] Step 5: Filling test: after step 4 is completed, some samples are taken out for testing. The samples include each layer of soil sample backfilled and compacted in step 4;
[0037] Step 6: Adjust steps 1 to 4 based on the results of the fill test in step 5.
[0038] Example 2
[0039] The difference between this embodiment and embodiment 1 is that the weight of graphene oxide waste residue in the landfill engineering soil or backfill soil containing graphene oxide is 1% of the total weight of the landfill engineering soil or backfill soil containing graphene oxide.
[0040] Example 3
[0041] The difference between this embodiment and embodiment 1 is that the weight of graphene oxide waste residue in the landfill engineering soil or backfill soil containing graphene oxide is 1.5% of the total weight of the landfill engineering soil or backfill soil containing graphene oxide.
[0042] Example 4
[0043] The difference between this embodiment and embodiment 1 is that the weight of graphene oxide waste residue in the landfill engineering soil or backfill soil containing graphene oxide is 6% of the total weight of the landfill engineering soil or backfill soil containing graphene oxide.
[0044] Comparative Example 1
[0045] The difference between this comparative example and Example 1 is that the landfill engineering soil or backfill soil does not contain graphene oxide waste residue.
[0046] The initial shear modulus under the reference stress of the embodiments and comparative examples of the present application and the shear stress test results corresponding to 0.7 times the initial shear modulus are as follows:
[0047]
[0048] Other test results of Example 3 of the present application are as follows:
[0049]
[0050]
[0051] The present invention can be applied to the reinforcement of foundation soil near a shield tunnel-working shaft structure. By filling the gap between the shield tunnel and the working shaft with foundation soil reshaped with graphene oxide or reshaping the foundation soil in a certain range around the tunnel and the working shaft using the method of the present invention, the shield tunnel and the working shaft can be effectively absorbing energy and reducing shock.
[0052] The above embodiments are merely illustrative of the principles and effects of the present invention, and are not intended to limit the present invention. In practice, the confining pressure and the amount of graphene oxide incorporated can be freely controlled according to a similar ratio, and anyone familiar with the technology can modify or change the above embodiments without violating the spirit and scope of the present invention. Therefore, all equivalent modifications or changes made by those with ordinary knowledge in the technical field without departing from the spirit and technical ideas disclosed by the present invention should still be covered by the claims of the present invention.
Claims
1. A landfill soil or backfill soil containing graphene oxide, characterized in that: The invention relates to graphene oxide waste residue, wherein the graphene oxide waste residue is waste residue containing graphene in byproducts generated in the process of preparing graphene, and the weight of the graphene oxide waste residue in the landfill engineering soil or backfill soil containing graphene oxide exceeds 1% of the total weight of the landfill engineering soil or backfill soil containing graphene oxide.
2. The landfill soil or backfill soil containing graphene oxide according to claim 1, characterized in that: The contact mode between the graphene oxide waste residue and other components of the landfill engineering soil or backfill soil containing graphene oxide is uniform mixing.
3. A method for using landfill engineering soil or backfill soil containing graphene oxide, using the landfill engineering soil or backfill soil containing graphene oxide as claimed in claim 1 or 2, characterized in that: The following steps are involved: Step 1: Prepare an appropriate amount of landfill soil or backfill soil containing graphene oxide and select appropriate compaction machinery; Step 2: Level the site, divide the work area, fill the pit in different areas and construction sections, remove garbage, silt and other debris on the surface of the foundation pit, and keep the foundation pit flat and clean; Step 3: Compact the site. Use the compaction machine selected in step 1 to compact the original soil at the base until the compaction coefficient of the original soil reaches 0.
93. Check the depth and horizontal elevation of the foundation pit and lay thickness marks. Step 4: Layered backfilling and compaction. The landfill engineering soil or backfill soil containing graphene oxide and medium-coarse sand are backfilled in alternating layers. The foundation pit is divided into horizontal layers from low to high, and the soil is filled upward layer by layer. After each layer of backfill soil is filled and compacted, the compaction coefficient and bearing capacity of each layer of backfill soil are tested to see if they meet the design requirements. If they meet the design requirements, the next layer is constructed, otherwise it is re-rolled. Step 5: Filling test: after step 4 is completed, some samples are taken out for testing. The samples include each layer of soil sample backfilled and compacted in step 4; Step 6: Adjust steps 1 to 4 based on the results of the fill test in step 5.
4. The method for using landfill engineering soil or backfill soil containing graphene oxide according to claim 3, characterized in that: When backfilling in layers in step 4, the thickness of each layer is consistent.
5. The method for using landfill engineering soil or backfill soil containing graphene oxide according to claim 4, characterized in that: When backfilling in layers in step 4, the thickness of each layer shall not exceed 100 cm.