Construction method for anti-deviation reinforced cushion layer of precast pile in soft soil area
By combining the reinforced concrete cushion layer and angle steel fixtures on prefabricated piles in soft soil areas, the problem of inclination and deviation of prefabricated piles in soft soil areas is solved, and higher engineering safety and progress control are achieved. Reduced construction costs.
Patent Information
- Application Number
- CN202411219508.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-02
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-09-02
AI Technical Summary
In construction in soft soil areas, prefabricated piles are prone to deviate, tilt or break due to uneven soil pressure, which affects the safety and progress of the project.
Reinforced concrete cushion is connected to prefabricated piles, and an integral structure is formed through angle steel fixtures and high-strength bolts. The anti-side and anti-tilt support of the pile top is added, and a gap is reserved in the cushion for subsequent pouring of cast-in-place concrete to ensure that the piles and Stable connection of the cushion.
Effectively prevent inclined damage caused by uneven soil pressure of the pile body, improve project safety and progress, and the reinforced cushion layer and connectors can be reused, reducing construction costs.
Smart Images

Figure CN118911184A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of precast pile anti-deviation, and in particular to a construction method of a precast pile anti-deviation reinforced cushion layer in a soft soil area. Background Art
[0002] The main types of precast piles are solid square piles, hollow square piles, and pipe piles. Precast piles are prefabricated in factories and can be transported to the site for construction, which can greatly shorten the construction period. Because precast piles are made in factories, their quality is guaranteed, the pile body is high in strength, the bearing capacity is strong, and they are economical. However, during construction in soft soil areas, piles are generally driven first, and then the basement is excavated. Since soft soil areas are mostly silty soils in a plastic state, improper excavation sequence or construction disturbance can easily cause bending damage to the pile body. In view of this, the present application utilizes a prefabricated reinforced cushion layer to be connected and fixed to the top of the precast pile in advance to prevent the concrete pipe pile from having top deviation, tilting, or broken piles.
[0003] Therefore, the applicant, based on many years of rich experience in design, development and actual production in the relevant industry, has conducted research and improvements on the existing structures and deficiencies, and provided a construction method for precast pile anti-deviation reinforced cushion layer in soft soil areas, in order to achieve a more practical purpose. Summary of the invention
[0004] 1. Technical issues to be solved
[0005] In view of the deficiencies in the prior art, the present invention provides a construction method for a precast pile anti-deflection reinforced cushion layer in soft soil areas, which solves the problems of top deviation, tilt or broken piles of concrete pipe piles.
[0006] (II) Technical solution
[0007] To achieve the above purpose, the present invention is implemented through the following technical solutions: a construction method of a precast pile anti-deviation reinforced cushion layer in a soft soil area, comprising a precast pile anti-deviation reinforced cushion layer in a soft soil area, wherein the reinforced cushion layer comprises a reinforced concrete cushion layer and a precast pile; an angle steel fixing piece is arranged on the reinforced concrete cushion layer, and an angle steel fixing bolt is arranged on the angle steel fixing piece; a pile top steel cover plate is arranged on the precast pile, and the precast pile and the pile top steel cover plate are connected by high-strength bolts;
[0008] The reinforced concrete cushion layer and the precast pile are connected together by angle steel fixings, pile top steel cover plates, angle steel fixing bolts and high-strength bolts to form a whole;
[0009] The specific operations are as follows:
[0010] S1: The reinforced concrete cushion is a rectangular precast concrete cushion with a single-layer bidirectional steel mesh inside. The reserved hole in the middle of the reinforced concrete cushion is slightly larger than the sum of the diameter (or side length) of the precast pile and the height of the angle steel fixing piece. Two angle steel fixing bolts are reserved on each side of the orthogonal positions around the reinforced concrete cushion, and the angle steel fixing bolts are embedded in the reinforced concrete cushion through embedded plates;
[0011] S2: The angle steel fixing piece is welded into an L shape by equilateral angle steel. When the angle steel fixing piece is connected to the reinforced concrete cushion layer, the position of the angle steel fixing piece is adjusted through the oblong hole on the angle steel fixing piece to ensure that the four angle steel fixing pieces hold the precast pile tightly without shaking;
[0012] S3: Four bolt holes are reserved at the top of the precast pile. The steel cover plate at the top of the pile adopts a circular cover plate. Four holes are reserved at the positions corresponding to the bolt holes at the top of the pile. The circular steel cover plate at the top of the pile is connected and fixed to the top of the precast pile by four connected high-strength bolts. The size of the steel cover plate at the top of the pile should ensure that it can completely press the vertical angle steel section of the angle steel fixing piece. The high-strength bolts connected on the steel cover plate at the top of the pile are tightened so that the steel cover plate at the top of the pile applies a pre-pressure to the angle steel fixing piece. The pre-pressure is transmitted to the reinforced concrete cushion layer through the angle steel fixing piece, so that the reinforced concrete cushion layer is in close contact with the soil. The soil body provides support force to the reinforced concrete cushion layer to prevent the precast pile from tilting.
[0013] S4: After the precast pile anti-deviation reinforcement device is in place, the gaps between the reinforced cushions of each precast pile are connected as a whole with a cast-in-place concrete cushion. After the cushion is connected as a whole and the strength reaches the design requirements, the high-strength bolts connected to the top of the precast pile, the steel cover plate on the top of the pile, the angle steel fixing bolts and the angle steel fixings are successively removed and recycled. After removal, the hole in the middle of the precast reinforced cushion is immediately poured with cast-in-place concrete to connect the cushion and the pile as a whole.
[0014] Preferably, the reinforced concrete cushion layer is a prefabricated reinforced concrete component with a single-layer bidirectional steel mesh inside. It is rectangular in shape, and the size of the rectangle is the pile spacing minus the width of the post-casting area, which is 300 mm wide. A hole is reserved in the middle of the reinforced concrete cushion layer. The size of the reserved hole is the sum of the diameter (or side length) of the prefabricated pile and the height of the steel fixing part. The adjustable gap is 50 mm.
[0015] Preferably, the angle steel fixing piece is made into an L-shaped component by welding equilateral angle steels, the flat side of the L-shaped angle steel fixing piece is fixed to the reinforced concrete cushion layer by bolts, and the flat side of the L-shaped fixing piece has an oblong hole on its angle steel limb.
[0016] Preferably, the pile top steel cover plate adopts a circular steel cover plate, and the circular steel cover plate has four bolt holes reserved at orthogonal positions. The diameter of the circular pile top steel cover plate is the sum of the prefabricated pile diameter (or side length) and the height of the steel fixing part.
[0017] Preferably, the pile top steel cover plate is connected to the top of the precast pile by high-strength bolts, and the pile top steel cover plate is compressed and connected to the angle steel fixing piece by the tightening force of the high-strength bolts, and the angle steel fixing piece compresses the reinforced concrete cushion layer to provide reliable anti-lateral and anti-tilt support for the precast pile.
[0018] (III) Beneficial effects
[0019] The present invention provides a construction method for a prefabricated pile anti-deviation reinforced cushion in a soft soil area. It has the following beneficial effects: effectively preventing the pile body from tilting and damaging due to uneven soil pressure, which affects the safety and progress of the project. The column top reinforced steel cover plate and the angle steel fixing parts are all connected by bolts. The pile top steel cover plate and the angle steel fixing parts can be removed by simply removing the bolts. The subsequent removal is convenient and quick. The angle steel connector, pile top cover plate and bolts can be reused, which reduces costs.
[0020] (1) The main function of the reinforced concrete cushion is to add an enlarged pile cap on the top of the precast pile. When the precast pile has a tendency to tilt, the reinforced cushion on the side of the tilting direction can transmit the tilting force to the soil at the bottom, that is, the tilting effect is resisted and resolved by the pressure of the soil, so as to achieve the purpose of preventing the precast pile from tilting;
[0021] (2) A single layer of bidirectional steel bars is arranged in the reinforced cushion layer; space is left in the middle of the reinforced cushion layer for the pile and angle steel, and a certain gap is left for installation; the angle steel and the reinforced cushion layer are connected by pre-buried bolts, and oblong holes are used at the connection between the angle steel and the bolts to facilitate adjustment; the prefabricated pile is tightened when the angle steel and the reinforced cushion layer are fixed; the pile top reinforcement cover plate is used to clamp the angle steel to prevent the cushion layer from lifting; the pile top reinforcement cover plate is connected to the pile top with high-strength bolts; the high-strength bolts are used to apply a pre-pressure to the reinforced cushion layer to ensure the stability of the pile head.
[0022] (3) High-strength bolts are used, which have sufficient tensile strength and shear strength. The bolts are tightened without loosening and the angle steel is compressed. The top of the pile is fixed to the reinforced cushion layer through bolt connectors and a circular steel cover plate, so that the pile, the reinforced cushion layer and the soil form a whole. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 : Top view of precast pile anti-deflection reinforced cushion
[0024] Figure 2 :Sectional view of the connection between the reinforced cushion and the precast pile (AA section view)
[0025] 1. Reinforced concrete cushion, 2. Precast piles, 3. Angle steel fixings, 4. Angle steel fixing bolts, 5. Steel cover plate on top of pile, 6. High-strength bolts. DETAILED DESCRIPTION
[0026] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0027] See also Figure 1-Figure 2 The present invention provides a technical solution: a construction method of a precast pile anti-deviation reinforced cushion layer in a soft soil area, comprising a precast pile anti-deviation reinforced cushion layer in a soft soil area, wherein the reinforced cushion layer comprises a reinforced concrete cushion layer 1 and a precast pile 2; an angle steel fixing piece 3 is arranged on the reinforced concrete cushion layer 1, and an angle steel fixing bolt 4 is arranged on the angle steel fixing piece 3; a pile top steel cover plate 5 is arranged on the precast pile 2, and the precast pile 2 and the pile top steel cover plate 5 are connected by high-strength bolts 6;
[0028] The reinforced concrete cushion layer 1 and the precast pile 2 are connected together by angle steel fixings 3, pile top steel cover plates 5, angle steel fixing bolts 4 and high-strength bolts 6 to form a whole;
[0029] The specific operations are as follows:
[0030] S1: The reinforced concrete cushion layer 1 is a rectangular precast concrete cushion layer with a single-layer bidirectional steel mesh inside. The reserved hole in the middle of the reinforced concrete cushion layer 1 is slightly larger than the sum of the diameter or side length of the precast pile 2 and the height of the angle steel fixing piece 3. Two angle steel fixing bolts 4 are reserved at orthogonal positions around the reinforced concrete cushion layer 1 on each side. The angle steel fixing bolts 4 are pre-embedded in the reinforced concrete cushion layer 1 through an embedded plate;
[0031] S2: The angle steel fixing piece 3 is welded into an L shape by using equilateral angle steel. When the angle steel fixing piece 3 is connected to the reinforced concrete cushion layer 1, the position of the angle steel fixing piece 3 is adjusted through the oblong hole on the angle steel fixing piece 3 to ensure that the four angle steel fixing pieces 3 hold the precast pile 2 tightly without shaking;
[0032] S3: Four bolt holes are reserved on the top of the precast pile 2. The pile top steel cover plate 5 adopts a circular cover plate. Four holes are reserved at the positions corresponding to the pile top bolt holes of the pile top steel cover plate 5. The circular pile top steel cover plate 5 is connected and fixed to the top of the precast pile 2 by four connected high-strength bolts 6. The size of the pile top steel cover plate 5 should ensure that the vertical angle steel section of the angle steel fixing piece 3 is completely pressed. The high-strength bolts 6 connected on the pile top steel cover plate 5 are tightened so that the pile top steel cover plate 5 applies a pre-pressure to the angle steel fixing piece 3. The pre-pressure is transmitted to the reinforced concrete cushion layer 1 through the angle steel fixing piece 3, so that the reinforced concrete cushion layer 1 is in close contact with the soil. The soil body provides support force to the reinforced concrete cushion layer 1 to prevent the precast pile 2 from tilting.
[0033] S4: After the anti-deviation reinforcement device of the precast pile 2 is in place, the gaps between the reinforced cushions of each precast pile are connected as a whole with a cast-in-place concrete cushion. After the cushion is connected as a whole and its strength reaches the design requirements, the high-strength bolts 6, the pile top steel cover plate 5, the angle steel fixing bolts 4 and the angle steel fixings 3 connected to the top of the precast pile are successively removed and recycled. After removal, the hole in the middle of the precast reinforced cushion is immediately poured with cast-in-place concrete to connect the cushion and the pile as a whole.
[0034] The reinforced concrete cushion layer 1 is a reinforced concrete prefabricated component with a single-layer bidirectional steel mesh inside. Its shape is a rectangle. The size of the rectangle is the pile spacing minus the width of the post-casting area, which is 300mm wide. A hole is reserved in the middle of the reinforced concrete cushion layer 1. The size of the reserved hole is the sum of the diameter or side length of the prefabricated pile 2 and the height of the steel fixing part 3. The adjustable gap is 50mm.
[0035] The angle steel fixing member 3 is made into an L-shaped member by welding equilateral angle steels. The flat side of the L-shaped angle steel fixing member is fixed to the reinforced concrete cushion layer 1 by bolts. The flat side of the L-shaped fixing member has an oblong hole on its angle steel limb.
[0036] The pile top steel cover plate 5 is a circular steel cover plate with four bolt holes reserved at orthogonal positions. The diameter of the circular pile top steel cover plate 5 is the sum of the diameter or side length of the prefabricated pile 2 and the height of the steel fixing part 3.
[0037] The pile top steel cover plate 5 is connected to the top of the precast pile 2 by high-strength bolts. The pile top steel cover plate 5 is tightly connected to the angle steel fixing piece 3 by the fastening force of the high-strength bolts 6. The angle steel fixing piece 3 presses the reinforced concrete cushion layer 1 to provide reliable anti-lateral and anti-tilt support for the precast pile.
[0038] Example, see Figure 1 The reinforced concrete cushion layer 1 is a rectangular precast concrete cushion layer with a single-layer bidirectional steel mesh inside. The reserved hole in the middle of the reinforced concrete cushion layer 1 is slightly larger than the diameter of the precast pile 2 or the side length and the height of the angle steel fixing piece 3. Two angle steel fixing bolts 4 are reserved on each side of the orthogonal positions around the reinforced concrete cushion layer 1. The angle steel fixing bolts 4 are embedded in the reinforced concrete cushion layer 1 through embedded plates; the angle steel fixing piece 3 is welded into an L shape by equilateral angle steel. When the angle steel fixing piece 3 is connected to the reinforced concrete cushion layer 1, the position of the angle steel fixing piece 3 is adjusted through the oblong hole on the angle steel fixing piece 3 to ensure that the four angle steel fixing pieces 3 tighten the precast pile 2 without shaking.
[0039] Reference Figure 2, four bolt holes are reserved at the top of the precast pile 2, and a circular cover plate is used for the pile top steel cover plate 5. Four holes are reserved at the positions corresponding to the pile top bolt holes of the pile top steel cover plate 5. The circular pile top steel cover plate 5 is connected and fixed to the top of the precast pile 2 by four connected high-strength bolts 6. The size of the pile top steel cover plate 5 should ensure that it can completely press the vertical angle steel section of the angle steel fixing piece 3. The high-strength bolts 6 connected on the pile top steel cover plate 5 are tightened, so that the pile top steel cover plate 5 applies a pre-pressure to the angle steel fixing piece 3, and the pre-pressure is transmitted to the reinforced concrete cushion layer 1 through the angle steel fixing piece 3, so that the reinforced concrete cushion layer 1 can be reinforced. The concrete cushion layer 1 is in close contact with the soil, and the soil provides supporting force for the reinforced concrete cushion layer 1 to prevent the precast pile 2 from tilting; after the anti-deviation reinforcement device of the precast pile 2 is in place, the gaps between the reinforced cushion layers of each precast pile are connected as a whole with a cast-in-place concrete cushion layer. After the cushion layers are connected as a whole and the strength reaches the design requirements, the high-strength bolts 6 connected to the top of the precast pile, the pile top steel cover plate 5, the angle steel fixing bolts 4 and the angle steel fixing parts 3 are successively dismantled and recycled. After dismantling, the hole in the middle of the precast reinforced cushion layer is immediately poured with cast-in-place concrete to connect the cushion layer and the pile as a whole.
[0040] The application adopts a reinforced concrete cushion layer, which is mainly used to add an enlarged pile cap on the top of the precast pile. When the precast pile has a tendency to tilt, the reinforced cushion layer on the tilting direction can transmit the tilting force to the soil at its bottom, that is, the tilting effect is resisted and resolved by the pressure of the soil, so as to achieve the purpose of preventing the precast pile from tilting;
[0041] A single-layer bidirectional steel bar is arranged in the reinforced cushion layer; a space for the pile and angle steel is left in the middle of the reinforced cushion layer, and a certain gap is left for installation; the angle steel and the reinforced cushion layer are connected by pre-buried bolts, and oblong holes are used at the connection between the angle steel and the bolts to facilitate adjustment; the prefabricated pile is tightened when the angle steel and the reinforced cushion layer are fixed; the pile top reinforcement cover plate is used to clamp the angle steel to prevent the cushion layer from lifting; the pile top reinforcement cover plate and the pile top are connected by high-strength bolts; the high-strength bolts are used to apply a pre-pressure to the reinforced cushion layer to ensure the stability of the pile head;
[0042] Bolts are high-strength bolts with sufficient tensile and shear strength. The bolts are tightened without loosening and the angle steel is compressed. The top of the pile is fixed to the reinforced cushion by bolt connectors and a circular steel cover plate, so that the pile, the reinforced cushion and the soil form a whole;
[0043] To sum up, in order to effectively prevent the pile body from tilting and damaging due to uneven soil pressure, which would affect the safety and progress of the project, the column top reinforcement steel cover plate and angle steel fixings are connected by bolts. Only the bolts need to be removed to remove the pile top steel cover plate and angle steel fixings. The subsequent dismantling is convenient and quick. The angle steel connectors, pile top cover plate and bolts can be reused to reduce costs.
[0044] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0045] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A construction method for a prefabricated pile anti-deflection reinforced cushion in soft soil areas. Features: The invention comprises a reinforced cushion layer for preventing the precast pile from deflecting in a soft soil area, wherein the reinforced cushion layer comprises a reinforced concrete cushion layer (1) and a precast pile (2); an angle steel fixing piece (3) is arranged on the reinforced concrete cushion layer (1), and an angle steel fixing bolt (4) is arranged on the angle steel fixing piece (3); a pile top steel cover plate (5) is arranged on the precast pile (2), and the precast pile (2) and the pile top steel cover plate (5) are connected by high-strength bolts (6); The reinforced concrete cushion layer (1) and the prefabricated pile (2) are connected together through angle steel fixing pieces (3), pile top steel cover plates (5), angle steel fixing bolts (4) and high-strength bolts (6) to form a whole; The specific operations are as follows: S1: The reinforced concrete cushion layer (1) is a rectangular precast concrete cushion layer with a single-layer bidirectional steel mesh inside. The reserved opening in the middle of the reinforced concrete cushion layer (1) is slightly larger than the sum of the diameter (or side length) of the precast pile (2) and the height of the angle steel fixing member (3). Two angle steel fixing bolts (4) are reserved at orthogonal positions on each side of the reinforced concrete cushion layer (1). The angle steel fixing bolts (4) are pre-buried in the reinforced concrete cushion layer (1) through an embedded plate. S2: The angle steel fixing piece (3) is welded into an L shape by using equilateral angle steel. When the angle steel fixing piece (3) is connected to the reinforced concrete cushion layer (1), the position of the angle steel fixing piece (3) is adjusted through the oblong hole on the angle steel fixing piece (3) to ensure that the four angle steel fixing pieces (3) hold the prefabricated pile (2) tightly without shaking; S3: Four bolt holes are reserved at the top of the precast pile (2). The pile top steel cover plate (5) adopts a circular cover plate. Four holes are reserved at the positions of the pile top steel cover plate (5) corresponding to the pile top bolt holes. The circular pile top steel cover plate (5) is connected and fixed to the top of the precast pile (2) by four connected high-strength bolts (6). The size of the pile top steel cover plate (5) should ensure that the vertical angle steel section of the angle steel fixing piece (3) is completely pressed. The connected high-strength bolts (6) on the pile top steel cover plate (5) are tightened so that the pile top steel cover plate (5) applies a pre-pressure to the angle steel fixing piece (3). The pre-pressure is transmitted to the reinforced concrete cushion layer (1) through the angle steel fixing piece (3), so that the reinforced concrete cushion layer (1) is in close contact with the soil. The soil provides a supporting force to the reinforced concrete cushion layer (1) to prevent the precast pile (2) from tilting. S4: After the precast pile (2) anti-deviation reinforcement device is in place, the gaps between the reinforced cushion layers of each precast pile are connected as a whole using a cast-in-place concrete cushion layer. After the cushion layers are connected as a whole and their strength reaches the design requirements, the high-strength bolts (6) connected to the top of the precast pile, the pile top steel cover plate (5), the angle steel fixing bolts (4) and the angle steel fixing parts (3) are successively removed and recycled. After removal, the hole in the middle of the precast reinforced cushion layer is immediately poured with cast-in-place concrete to connect the cushion layer and the pile as a whole.
2. The construction method of the precast pile anti-deviation reinforced cushion layer in soft soil area according to claim 1, Features: The reinforced concrete cushion layer (1) is a reinforced concrete prefabricated component, with a single-layer bidirectional steel mesh inside, and is rectangular in shape. The size of the rectangle is the width of the post-casting area minus the width of the post-casting area of 300 mm. A hole is reserved in the middle of the reinforced concrete cushion layer (1). The size of the reserved hole is the sum of the diameter (or side length) of the prefabricated pile (2) and the height of the steel fixing piece (3). The adjustable gap is 50 mm.
3. The construction method of the precast pile anti-deviation reinforced cushion layer in soft soil area according to claim 1, Features: The angle steel fixing piece (3) is made into an L-shaped component by welding equilateral angle steels. The flat side of the L-shaped angle steel fixing piece is connected and fixed to the reinforced concrete cushion layer (1) by bolts. The flat side of the L-shaped fixing piece is provided with an oblong hole on the angle steel limb.
4. The construction method of the precast pile anti-deviation reinforced cushion layer in soft soil area according to claim 1, Features: The pile top steel cover plate (5) is a circular steel cover plate, and four bolt holes are reserved at orthogonal positions on the circular steel cover plate. The diameter of the circular pile top steel cover plate (5) is the sum of the diameter (or side length) of the prefabricated pile (2) and the height of the steel fixing member (3).
5. The construction method of the precast pile anti-deviation reinforced cushion layer in soft soil area according to claim 1, Features: The pile top steel cover plate (5) is connected to the top of the precast pile (2) by high-strength bolts. The pile top steel cover plate (5) is pressed and connected to the angle steel fixing piece (3) by the tightening force of the high-strength bolts (6). The angle steel fixing piece (3) presses the reinforced concrete cushion layer (1) to provide reliable anti-lateral and anti-tilt support for the precast pile.
Citation Information
Patent Citations
Anti-tilting method for concrete prestressed pipe pile
CN107288128A
Reinforced connecting structure between pile and pile cap
CN203514315U
Foundation structure, pile head structure of steel-pipe pile, and construction method for foundation structure
JP2018062812A