Shield door opening structure system and construction method thereof

Through counter-process construction, including pouring end walls, waist beams and embedded steel rings, and setting up vertical and oblique braces, the problems of long construction cycle and poor strength reliability of shield door opening structures are solved, and construction efficiency is improved and safety is achieved enhancement of sexuality.

CN118911700AActive Publication Date: 2024-11-08CHINA RAILWAY TUNNEL GROUP CO LTD +1

Patent Information

Application Number
CN202411007773.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-11-08
Estimated Expiration
2044-07-25

AI Technical Summary

Technical Problem

The existing shield door opening structure has a long construction cycle and poor structural strength reliability, resulting in slow construction progress and safety risks.

Method used

The reverse construction method is adopted, including pouring the end wall, waist beam and embedded steel ring after the foundation pit enclosure structure is completed, and vertical and oblique braces are set on both sides of the end wall, and finally pouring the concrete base to form a stable door opening structure. , ensure sealing and strength.

Benefits of technology

Significantly save construction period, reduce costs, improve construction efficiency, and enhance the stability and safety of the door opening structure, avoiding the problem of reducing strength reliability due to material selection and design parameters.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118911700A_ABST
    Figure CN118911700A_ABST
Patent Text Reader

Abstract

The invention discloses a shield door opening structure system and a construction method thereof. The problems that an existing shield tunnel portal is long in construction period and poor in structural strength reliability are solved. The end wall is arranged at the position corresponding to the free face of the foundation pit support structure, the waist beams and the end wall are stressed in an intersecting mode, the waist beams are arranged in the horizontal direction, the embedded steel ring is embedded into the position corresponding to the end wall and is concentric with a door opening, and the portal seal is fixedly connected with the embedded steel ring. The vertical supports are symmetrically arranged on the two sides of the end wall along the vertical center line of the end wall and fixedly connected with the free face of the end wall, the inclined supports are supported between the vertical supports and a foundation pit bottom plate, and the concrete base is arranged between the tunnel portal seal and the foundation pit bottom plate and used for wrapping and supporting the bottom of the tunnel portal seal. Compared with the construction of a full-coverage type secondary lining structure of a conventional shield launching foundation pit, the construction of the shield door opening structure can greatly shorten the construction period, reduce the construction cost and improve the construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of shield tunnels, and in particular to a shield portal structure system and an application method thereof. Background Art

[0002] As a key component in shield tunnel construction, the structural design and function of the shield portal have a vital impact on the safety, stability and subsequent operation effect of tunnel construction.

[0003] The shield portal is the entrance and exit of tunnel construction. Its structural stability and sealing are directly related to the safety of tunnel construction. The structure of the shield portal mainly includes the main structure of the portal, the sealing device and other parts. The main structure of the portal is usually a cast-in-place reinforced concrete structure with sufficient strength and rigidity to withstand the water and soil pressure inside and outside the tunnel and various loads during the construction process. The portal has various forms, including end wall type, wing wall type, column type portal, etc. The specific selection needs to be determined according to factors such as geological conditions, tunnel section size and construction requirements. The sealing device of the shield portal is mainly composed of a curtain rubber plate, a circular ring plate, a fan-shaped flap and corresponding connecting bolts and washers. These components cooperate with each other to form a reliable sealing system to prevent groundwater and sediment from infiltrating into the tunnel.

[0004] The existing shield portal structure is generally constructed using the sequential construction process, that is, after the foundation pit is excavated to the designed elevation, the foundation pit is lined with a fully covered secondary lining structure, and the shield portal is constructed. Since the entire foundation pit fully covered secondary lining structure has a large amount of work and a long construction period, the shield portal construction period is delayed, which in turn affects the start of the shield, resulting in slow overall construction progress and low efficiency; at the same time, the strength of the portal structure is affected by many factors such as material selection, design parameters, and construction technology, and the existing portal structure is mainly a cast-in-place portal ring beam. If there is an error in any link, the strength reliability of the portal ring beam will be reduced, which makes the start of the shield machine a safety risk.

[0005] The information disclosed in this background technology section is only used to deepen the understanding of the background technology of the present disclosure, and should not be regarded as acknowledging or suggesting in any form that the information constitutes the prior art known to those skilled in the art. Summary of the invention

[0006] In view of at least one of the above technical problems, the present disclosure provides a shield tunnel portal structure system and a construction method thereof, aiming to solve the problems of long construction period and poor structural strength reliability of existing shield tunnel portals.

[0007] According to one aspect of the present disclosure, a shield portal structure system is provided, which includes an end wall arranged at a position corresponding to the free surface of a foundation pit retaining structure, at least one waist beam intersecting with the end wall and receiving force and arranged in a horizontal direction, an embedded steel ring embedded in the corresponding position of the end wall and concentric with the portal, a portal seal fixedly connected to the embedded steel ring, vertical supports symmetrically arranged on both sides of the end wall along the vertical center line of the end wall and fixedly connected to the free surface of the end wall, a plurality of oblique supports supported between the vertical supports and a foundation pit bottom plate, and a concrete base arranged between the portal seal and the foundation pit bottom plate for covering and supporting the bottom of the portal seal.

[0008] In some embodiments of the present disclosure, the free surface of the foundation pit retaining structure for corresponding combination with the end wall is provided with a concave-convex texture.

[0009] In some embodiments of the present disclosure, the internal reinforcement of the end wall includes anchor reinforcement embedded in the end wall.

[0010] In some embodiments of the present disclosure, the end wall is a square structure, whose width and height are respectively 1 to 4 m larger than the shield diameter, and the thickness of the end wall structure is 0.8 to 2 m; the length of the waist beam is not less than the corresponding width of the end wall.

[0011] In some embodiments of the present disclosure, the top end surface of the vertical support is not lower than the plane corresponding to the narrowest part of the door opening excavation edge and the end wall edge in the horizontal direction.

[0012] In some embodiments of the present disclosure, the angle between the diagonal brace and the foundation pit bottom plate is 40° to 50°.

[0013] According to another aspect of the present disclosure, a method for constructing a shield portal structure system is provided, comprising the following steps: (1) Cast the end wall and waist beam by reverse method synchronously with the excavation of foundation pit, and bury the embedded steel ring and embedded steel plate at the corresponding position of the end wall and / or waist beam; before the construction of the end wall and waist beam, the corresponding free surface of the foundation pit retaining structure shall be roughened, and then high-pressure washing shall be carried out and the interface agent shall be applied; (2) bolting the tunnel door seal including the steel ring, the curtain rubber plate, the sealing brush, and the folding plate in blocks at the embedded steel ring, and welding and fixing the tunnel door seal to the embedded steel ring after the tunnel door seal forms a ring; (3) Vertical braces are fixedly installed at the corresponding embedded steel plates on both sides of the end wall, and corresponding diagonal braces are fixedly installed between the vertical braces and the bottom plate of the foundation pit; (4) After the tunnel door seal is installed and measured and verified, a concrete base is poured at the bottom of the tunnel door seal, and the concrete base densely fills the corresponding space between the bottom surface of the tunnel door seal and the bottom plate of the foundation pit.

[0014] In some embodiments of the present disclosure, in the step (1), the upper waist beam, the middle waist beam, the upper end wall between the upper waist beam and the middle waist beam, the lower waist beam, and the lower end wall between the middle waist beam and the lower waist beam are cast in sequence; and the corresponding internal reinforcement steel bars are tied in sequence from bottom to top in each casting section.

[0015] In some embodiments of the present disclosure, in step (3), the vertical supports are welded to the embedded steel plates, and before welding, the gap between the vertical supports and the end wall is filled with steel plates or iron sheets.

[0016] One or more technical solutions provided in the embodiments of the present application have at least the following technical effects or advantages: Compared with the construction of the fully covered secondary lining structure of the conventional shield starting pit, the shield portal structure only needs to construct the end wall waist beam on the portal surface before the shield can be assembled in the well, and the reverse construction method is adopted, which can greatly save the construction period and reduce the construction cost. In addition, the installation of the portal seal and the construction of the vertical brace, diagonal brace and concrete base can be carried out simultaneously with the assembly of the shield machine, thereby further saving the construction period and improving the construction efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 This is a schematic diagram of the structure of a shield portal structure system in one embodiment of the present application.

[0018] Figure 2 This is a schematic diagram of the structure of the embedded steel plate in one embodiment of the present application.

[0019] Figure 3 It is a schematic diagram of the door opening structure in the foundation pit in one embodiment of the present application.

[0020] In the above figures, 1 is the foundation pit retaining wall, 2 is the end wall, 21 is the upper end wall, 22 is the lower end wall, 31 is the upper waist beam, 32 is the middle waist beam, 33 is the lower waist beam, 4 is the tunnel door seal, 5 is the vertical support, 6 is the diagonal support, 7 is the concrete base, 8 is the embedded steel plate, and 81 is the fixed reinforcement. DETAILED DESCRIPTION

[0021] In the description of the present application, it should be understood that the terms "up", "down", "front", "back", "left", "right", "top", "bottom", "inside", "outside", "vertical", "horizontal", "clockwise", "counterclockwise", etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0022] In order to better understand the technical solution of the present application, the above technical solution will be described in detail below in conjunction with the accompanying drawings and specific implementation methods.

[0023] In order to solve the technical problems of the long construction period and relatively low structural strength reliability of the existing shield portal structure, this example discloses a shield portal structure system, taking the open excavation foundation pit construction as an example, see Figure 1 It includes end walls, waist beams, portal seals 4, vertical braces 5, diagonal braces 6 and a concrete base 7.

[0024] Considering that the construction of the existing door opening structure is generally carried out after the completion of the foundation pit retaining structure along with the foundation pit full-coverage type secondary lining structure, this will delay the construction period of the door opening structure and hinder the construction progress of the overall project. For this reason, in this embodiment, after the construction of the foundation pit retaining structure, i.e., the foundation pit retaining wall 1, is completed, the end wall is cast and constructed at the wall facing the shield door opening of the foundation pit retaining wall. The end wall is made of reinforced concrete, and its structural width and height are 1m to 4m larger than the shield diameter, and the structural thickness is 0.8m to 2m, and the structural form is square. Therefore, the stability of the foundation pit wall where the door opening is located can be ensured by the end wall, so as to avoid the door opening structure being disturbed during the initial excavation and causing safety accidents. Since the end wall is constructed after the completion of the foundation pit retaining structure, in order to ensure that the end wall can reliably play a stabilizing effect, it is necessary to ensure the reliable combination of the end wall and the foundation pit retaining structure. For this reason, in this embodiment, the foundation pit retaining structure, i.e., the free surface of the foundation pit retaining wall, is provided with a concave-convex texture, thereby increasing the bonding strength between the end wall and the foundation pit retaining wall through the concave-convex texture to ensure the bonding effect of the two. In addition, in this embodiment, an interface layer is provided between the free surface of the foundation pit retaining wall and the end wall, and the interface layer is formed after the interface agent solidifies to increase the bonding strength between the foundation pit retaining wall and the end wall. In order to further improve the bonding effect between the foundation pit retaining wall and the end wall, in this example, a number of anchor bars are planted in the foundation pit retaining wall, each anchor bar is connected and fixed to the inner bar of the end wall, and the anchor bar is inserted into the pit wall to a certain depth and reliably anchored at the foundation pit pit wall, thereby avoiding the foundation pit retaining wall and the end wall from being affected by the sequential pouring of the two and the overall force.

[0025] Considering the limited area of ​​the end wall, in order to ensure that the foundation pit retaining structure will not be retracted and improve the foundation pit support effect, in this embodiment, waist beams are respectively set at the top, middle and bottom of the end wall. The length of the waist beam is longer than the corresponding length of the end wall, and it is ensured that the two ends of the waist beam extend a certain length from both sides of the end wall, thereby improving the load strength of the end wall through the waist beam to ensure the support effect of the foundation pit. In some other embodiments, according to the foundation pit structure and the end wall load calculation, the waist beam is selectively set at different positions. Similarly, when the waist beam is cast, the corresponding position of the foundation pit retaining wall facing the empty surface is also provided with a concave and convex texture for enhancing the bonding strength, and an interface layer is provided at the junction of the two. In addition, in order to further improve the bonding strength of the two, an anchor bar fixed to the inner reinforcement of the waist beam is added and anchored at the corresponding pit wall of the foundation pit. Thus, through the cooperation of the waist beam and the end wall, reliable support for the foundation pit retaining wall where the shield portal is located is achieved to prevent the foundation pit wall from retracting.

[0026] Among them, it is considered that the subsequent door opening needs to be equipped with a door seal when it is actually used, so as to prevent external soil and water from entering the working pit from the gap between the door opening and the shield machine or the pipe segment and affecting the construction safety. To this end, in this embodiment, when constructing the end wall and the corresponding waist beam, a pre-embedded steel ring matching the door seal is pre-embedded in the end wall. The diameter of the pre-embedded steel ring matches the diameter of the door seal, so that the two can be arranged in a superimposed manner, and it is ensured that the center of the pre-embedded steel ring coincides with the center of the shield door opening when it is pre-embedded, so as to avoid interference between the shield machine and it during excavation and affect the excavation and door opening structure. Among them, in order to ensure the bonding strength between the pre-embedded steel ring and the end wall, in this embodiment, an annular groove is provided on the circumferential side of the pre-embedded steel ring body, and the corresponding end of the end wall steel bar located outside the pre-embedded steel ring body is in the annular groove, thereby causing position interference between the two, thereby preventing the pre-embedded steel ring from being separated from the end wall, and ensuring the pre-embedded strength of the pre-embedded steel ring. In some other embodiments, in order to further improve the reliability of the connection between the embedded steel ring and the end wall, the inner reinforcement of the end wall is fixed to the embedded steel ring by welding.

[0027] In this example, the tunnel door seal is in block form and consists of components such as a steel ring, a curtain rubber ring, a sealing brush, and a folding pressure plate. When installing the tunnel door seal, each block is fixed to the embedded steel ring buried in the end wall in turn. Since the embedded steel ring is firmly and reliably fixed to the end wall, the stability of the tunnel door seal connection can be guaranteed.

[0028] However, in order to improve the reliability of the door opening structure, in this embodiment, see Figure 1, vertical supports 5 are also provided on both sides of the end wall, which are arranged perpendicular to the foundation pit bottom plate, and the bottom surface is coplanar with the foundation pit bottom plate. In this example, the end wall is a square structure as a whole, so the structure of the end wall at the widest part of the door opening is relatively weak in the horizontal direction. After the shield machine passes through the door opening, it is difficult to ensure the structural strength of the door opening. Therefore, in this example, support is provided by vertical supports 5 on both sides of the end wall. The vertical supports on both sides are symmetrically arranged about the vertical center line of the end wall, and the top surface of the vertical support 5 is not lower than the plane corresponding to the narrowest part of the door opening excavation edge and the end wall edge in the horizontal direction. Therefore, the vertical supports can provide strong support for the weak structure of the end wall, so that the door opening structure always maintains reliable structural strength.

[0029] In order to enable the vertical brace to provide effective support, in this embodiment, when the end wall is constructed, a steel plate is pre-buried at the support position corresponding to the vertical brace. Figure 2 A plurality of fixing ribs 81 are provided on one side of the embedded steel plate 8, so that the embedded steel plate can be firmly combined with the end wall through the staggered fixing ribs 81. In this example, the vertical support is made of steel, so that the fixed connection between the vertical support and the embedded steel plate at the end wall ensures that the load can be effectively transferred to the vertical support when the foundation pit wall is deformed.

[0030] See also Figure 1 In this example, several diagonal braces 6 are arranged between the vertical brace 5 and the foundation pit bottom plate. One end of the diagonal brace is supported at the vertical brace, and the other end is supported at the foundation pit bottom plate. In this example, the diagonal brace 6 is also made of steel, so the same material setting facilitates the fixed connection between the diagonal brace and the vertical brace and ensures the connection strength. In addition, a pre-buried steel plate 8 is also embedded in the foundation pit bottom plate to fix the diagonal brace to prevent the diagonal brace and the foundation pit bottom plate from sliding relative to each other and affecting the support effect. Therefore, after the pit wall corresponding to the door opening of the foundation pit is deformed, the load can be transferred to the foundation pit bottom plate through the vertical brace and the diagonal brace to release, thereby ensuring the structural safety of the shield door opening. In this embodiment, the angle between the diagonal brace 6 and the foundation pit bottom plate is 45 degrees, thereby achieving an excellent support effect. In some other embodiments, the angle between the diagonal brace 6 and the foundation pit bottom plate is other angle values ​​between 40° and 50°. Therefore, the connection strength between the diagonal brace and the end wall is enhanced by the vertical brace, thereby avoiding stress concentration and affecting the structural strength of the end wall.

[0031] In addition, since the portal seal has a certain thickness, it will protrude from the end wall when it is fixed on the free surface of the end wall. In order to avoid its adverse effect on the structural strength of the shield portal, in this embodiment, a concrete base is cast between the portal seal and the foundation pit floor, thereby covering the bottom of the portal seal, and utilizing the strength of the concrete and the adhesion between the concrete base and the portal seal to achieve the effect of increasing rigidity and anti-seepage.

[0032] In some other embodiments, the shield portal structure system is used for opening the slope pit and the starting pit of the mining portal.

[0033] This example also discloses a method for constructing a shield portal structure system, see Figure 3 , which specifically includes the following steps: (1) The end walls and waist beams are cast using the reverse method simultaneously with the excavation of the foundation pit.

[0034] In order to save construction time, in this embodiment, the end wall and the corresponding waist beam are constructed by reverse construction method, which is carried out simultaneously with the foundation pit excavation. Figure 1 , and cast the upper waist beam 31, the middle waist beam 32, the upper end wall 21 between the upper waist beam 31 and the middle waist beam 32, the lower waist beam 33, and the lower end wall 22 between the middle waist beam 32 and the lower waist beam 33 in sequence.

[0035] Specifically, in this embodiment, in order to increase the bonding strength between the end wall and waist beam and the foundation pit retaining structure, the bonding parts of the end wall and waist beam corresponding to the foundation pit retaining wall are roughened to form concave and convex patterns, exposing the fresh concrete surface, increasing the contact area between the concrete body of the end wall and waist beam and the foundation pit retaining wall, and thus strengthening the connection quality between the new and old concrete bodies. After the foundation pit retaining wall is roughened, the roughened surface is rinsed with high-pressure water to ensure that there is no dust, soil and other attachments on the base surface. After the base surface is dry, an interface agent is applied between the contact surface of the end wall and the foundation pit retaining structure to form an interface layer to stabilize the connection between the end wall and waist beam and the foundation pit retaining wall. Among them, in each casting section, the corresponding internal reinforcement steel bars are tied and the positioning bars are installed from bottom to top, respectively, to improve the overall stability and reliability of the reinforcement. In this case, after the foundation pit retaining wall is roughened and before high-pressure washing, anchor bars are implanted at the foundation pit wall, and the anchor bars are fixedly connected to the inner bars of the end wall and / or waist beam during steel bar binding, thereby further improving the bonding strength between the end wall and the foundation pit retaining wall. Before the end wall and waist beam are cast, embedded steel rings and embedded steel plates are buried at the corresponding positions of the end wall to provide reliable fixed points for the subsequent door sealing and vertical support settings. During the casting operation, concrete is cast in layers with a height of 300mm to 500mm per layer.

[0036] Therefore, the shield portal structure can be constructed simultaneously with the foundation pit excavation through the reverse construction method, and there is no need to set up a scaffolding support system from the bottom of the foundation pit upwards. Compared with the conventional full-coverage secondary lining structure construction followed by the forward construction method for shield portal construction, it can save 30 to 70 days of construction time and reduce project investment by approximately RMB 5 to 8.9 million.

[0037] In some other embodiments, during the excavation of the foundation pit, anchor rods or anchor cables are installed on other side walls of the foundation pit as auxiliary reinforcement measures to enhance the stability of the foundation pit structure.

[0038] (2) Bolt the portal seal blocks in sequence at the embedded steel ring, and weld the portal seal to the embedded steel ring after the portal seal forms a ring.

[0039] After the end wall and waist beam are constructed, the door seal is installed. In this embodiment, the door seal is in the form of blocks, and each block is installed in turn. The blocks are connected by bolts and finally installed into a ring. When the door seal is installed, each block is connected to the embedded steel ring at the end wall by a Losa hybrid connection. After the door seal forms a ring, the door seal and the embedded steel ring are welded and fixed to ensure the strength and reliability of the connection between the two.

[0040] (3) Vertical braces are fixedly installed at the corresponding embedded steel plates on both sides of the end wall, and corresponding diagonal braces are fixedly installed between the vertical braces and the bottom plate of the foundation pit.

[0041] In this embodiment, the installation of the portal seal is carried out simultaneously with the installation of the vertical support to shorten the construction period, and the installation of the portal seal, the vertical support and the diagonal support are carried out simultaneously with the assembly of the shield machine, thereby achieving the purpose of further saving the construction period. In this embodiment, the vertical support adopts I-shaped steel, which is welded and fixed with the embedded steel plate at the end wall, wherein the contact surface between the steel structure and the embedded steel plate is fully welded. In addition, before welding, the gap between the vertical support and the end wall is filled with steel plate or iron sheet until it is dense, thereby ensuring reliable and uniform transmission of stress. After the vertical support is firmly set, the diagonal support is set between the vertical support and the embedded steel plate of the foundation pit bottom plate, and the diagonal support is set at an angle of 45 degrees to the ground, and the two side ends of the diagonal support are respectively fixed with the vertical support and the embedded steel plate at the foundation pit bottom plate by full welding, thereby realizing the effective transmission of the foundation pit stress through the end wall, the vertical support and the diagonal support to the foundation pit bottom plate.

[0042] (4) After the portal seal is installed and measured and verified, a concrete base is poured at the bottom of the portal seal, and the concrete base densely fills the corresponding space between the bottom surface of the portal seal and the bottom plate of the foundation pit.

[0043] The concrete base is in the form of cast-in-place concrete, which is used to completely wrap the bottom portal seal, and the strength of the concrete body and its adhesion to the portal seal are used to achieve support rigidity and anti-seepage effect. In this embodiment, the concrete base is plain concrete. Specifically, before pouring the concrete base, the contact base surface between the foundation pit bottom plate, the end wall and the portal seal steel ring and the concrete base is first cleaned, and the debris or rust on the base surface is removed, and then the support and installation of the formwork are carried out. After the concrete is poured and cured, the density of the concrete pouring is checked. In this example, an ultrasonic detector is used to check the pouring density, and the pouring cavity is filled in time.

[0044] Although some preferred embodiments of the present application have been described, those skilled in the art may make additional changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present application.

[0045] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the inventive concept. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.

Claims

1. A shield portal structure system, characterized in that: It includes an end wall arranged at a position corresponding to the free surface of the foundation pit retaining structure, at least one waist beam intersecting with the end wall and receiving force and arranged in the horizontal direction, an embedded steel ring embedded in the corresponding position of the end wall and concentric with the doorway, a door seal fixedly connected to the embedded steel ring, vertical supports symmetrically arranged on both sides of the end wall along the vertical center line of the end wall and fixedly connected to the free surface of the end wall, a plurality of oblique supports supported between the vertical supports and the foundation pit bottom plate, and a concrete base arranged between the door seal and the foundation pit bottom plate for covering and supporting the bottom of the door seal.

2. The shield portal structure system according to claim 1, characterized in that: The free surface of the foundation pit retaining structure used for corresponding combination with the end wall is provided with a concave-convex texture.

3. The shield portal structure system according to claim 1, characterized in that: The internal reinforcement of the end wall includes anchor reinforcement embedded in the end wall.

4. The shield portal structure system according to claim 1, characterized in that: The end wall is a square structure, and its width and height are respectively 1 to 4 m larger than the diameter of the shield, and the thickness of the end wall structure is 0.8 to 2 m; the length of the waist beam is not less than the corresponding width of the end wall.

5. The shield portal structure system according to claim 1, characterized in that: The top end surface of the vertical support is not lower than the plane corresponding to the narrowest part of the door opening excavation edge and the end wall edge in the horizontal direction.

6. The shield portal structure system according to claim 1, characterized in that: The angle between the diagonal brace and the foundation pit bottom plate is 40° to 50°.

7. A method for constructing a shield portal structure system, characterized in that: The steps include: (1) Cast the end wall and waist beam by reverse method synchronously with the excavation of foundation pit, and bury the embedded steel ring and embedded steel plate at the corresponding position of the end wall and / or waist beam; before the construction of the end wall and waist beam, the corresponding free surface of the foundation pit retaining structure shall be roughened, and then high-pressure washing shall be carried out and the interface agent shall be applied; (2) bolting the tunnel door seal including the steel ring, the curtain rubber plate, the sealing brush, and the folding plate in blocks at the embedded steel ring, and welding and fixing the tunnel door seal to the embedded steel ring after the tunnel door seal forms a ring; (3) Vertical braces are fixedly installed at the corresponding embedded steel plates on both sides of the end wall, and corresponding diagonal braces are fixedly installed between the vertical braces and the bottom plate of the foundation pit; (4) After the tunnel door seal is installed and measured and verified, a concrete base is poured at the bottom of the tunnel door seal, and the concrete base densely fills the corresponding space between the bottom surface of the tunnel door seal and the bottom plate of the foundation pit.

8. The method for constructing a shield portal structure system according to claim 7, characterized in that: In the step (1), the upper waist beam, the middle waist beam, the upper end wall between the upper waist beam and the middle waist beam, the lower waist beam, and the lower end wall between the middle waist beam and the lower waist beam are cast in sequence; and the corresponding internal reinforcement steel bars are tied in sequence from bottom to top in each casting section.

9. The method for constructing a shield portal structure system according to claim 7, characterized in that: In the step (3), the vertical brace is welded to the embedded steel plates, and before welding, a steel plate or iron sheet is used to fill the gap between the vertical brace and the end wall.

Citation Information

Patent Citations

  • Construction device and construction method for shield tunneling machine starting

    CN106837362A

  • Sealing structure of square mud gate of dredger

    CN108130932A

  • Starting end tunnel portal sealing device and method when shield tunneling machine starts to downwards transverse existing shield tunnel immediately

    CN109736832A

  • Tunnel portal sealing device for launching and receiving of shield tunneling machine and construction method

    CN113137252A

  • Shield launching construction tunnel portal sealing device and method

    CN114382503A

Cited By

  • Construction method of auxiliary structure for receiving of suspended wall foundation pit shield tunneling machine

    CN122190765A