Water pipe heat preservation and anti-freezing construction method for low-temperature area

By combining PPR pipes with galvanized steel pipes in low-temperature areas, and using liquid foaming agent to form an insulation layer, the problem of freezing and cracking of water pipes is solved, effective anti-freezing and insulation effects are achieved, and maintenance costs and frequency are reduced.

CN118912268APending Publication Date: 2024-11-08WATER RESOURCES RES INST OF SHANDONG PROVINCE
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411006211.6
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-25
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

In low-temperature areas, the stones on the mountainous areas are difficult to deal with, and the road surfaces are difficult to deal with in winter, resulting in the problem of freezing and cracking of water pipes.

Method used

Use PPR tubes and galvanized steel tubes to form an insulation layer using liquid foaming agent. The foaming agent is injected through a pressure pump and the fixing ring is pushed to form a uniform insulation layer to isolate the external low temperature and prevent the water pipe from freezing and cracking, and at the same time, it does not need to be on the road surface. Excavate the water pipe laying path.

Benefits of technology

Effectively prevent water pipes from freezing and cracking, reduce maintenance and replacement frequency, improve system stability, significantly improve the insulation performance of the pipeline, reduce heat loss, and reduce long-term maintenance costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118912268A_ABST
    Figure CN118912268A_ABST
Patent Text Reader

Abstract

The invention provides a water pipe heat preservation anti-freezing construction method for a low-temperature area, and relates to the technical field of water pipe anti-freezing laying. The water pipe heat preservation anti-freezing construction method for the low-temperature area comprises the following steps of S1, material preparation, S2, pipeline cutting, S3, pipeline laying, S4, liquid foaming agent injection, S5, pipeline connection, S6, branch pipeline connection, S7, curve laying, S8, home-entry connection, S9, home-entry curve laying, S10, home-entry diversion laying and S11, end sealing. The PPR pipe is good in temperature resistance and pressure resistance, the galvanized steel pipe is arranged on the outer side of the PPR pipe in a sleeving mode so that external damage can be prevented, the foaming agent can expand after filling, a uniform heat preservation layer is formed, external low temperature is effectively isolated, heat loss is reduced, the heat preservation performance of the pipeline can be remarkably improved through the heat preservation layer, and the water temperature lowering speed in the pipeline is reduced. Therefore, the PPR pipe is effectively prevented from frost cracking in a low-temperature environment, a water pipe laying path does not need to be dug on the road surface, and meanwhile the anti-freezing capacity and the heat preservation capacity of the PPR pipe can be guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of water pipe antifreeze laying, in particular to a water pipe thermal insulation and antifreeze construction method for low-temperature areas. Background Art

[0002] Water sources in mountainous areas usually include groundwater and surface water. When developing water sources, protecting them from pollution is the key to ensuring water supply safety. This includes establishing water source protection areas, restricting surrounding activities, and regularly monitoring water quality. The supply of tap water in mountainous areas is a complex system project that requires comprehensive consideration of natural conditions, technical feasibility, and socio-economic factors. Through scientific planning and management, it is necessary to ensure that residents have access to a safe and stable supply of tap water. Tap water pipes need to be laid during the tap water transportation process.

[0003] In the current process of laying water pipes in mountainous areas, it is necessary to bury the water pipes at a depth of about one meter underground. Since the ground stones in mountainous areas are difficult to handle and the road surface is even more difficult to handle in winter, construction cannot be carried out, resulting in freezing and cracking of the water pipes. Therefore, technical personnel in this field provide a water pipe insulation and antifreeze construction method for low temperature areas to solve the problems raised in the above background technology. Summary of the invention

[0004] 1. Technical issues to be solved

[0005] In view of the deficiencies in the prior art, the present invention provides a water pipe insulation and antifreeze construction method for low-temperature areas, which solves the problem of water pipes freezing and cracking due to the difficulty in handling ground stones in mountainous areas and the even greater difficulty in handling the road surface in winter, which makes construction impossible.

[0006] (II) Technical solution

[0007] To achieve the above objectives, the present invention is implemented through the following technical solutions: A water pipe insulation and antifreeze construction method for low temperature areas, comprising the following steps:

[0008] S1. Material preparation, DN40 PPR pipe, DN40 PPR elbow connecting pipe, DN40 PPR straight connecting pipe fittings, DN40 PPR multi-way connecting pipe fittings, DN20 PPR pipe, DN20 PPR elbow connecting pipe, DN20 PPR straight connecting pipe fittings, DN20 PPR multi-way connecting pipe fittings, PPR three-way connecting pipe fittings, DN80 galvanized steel pipe, DM80 galvanized steel threaded elbow connecting pipe, DM80 galvanized steel threaded straight connecting pipe fittings, DN80 galvanized steel pipe multi-way connecting pipe fittings, galvanized steel pipe three-way connecting pipe fittings, liquid foaming agent, fixing ring, pressure pump, hose, galvanized pipe fitting fixings, cutting tools, sealant and cleaning agent;

[0009] S2. Pipe cutting: Use cutting tools to accurately cut DN40 PPR pipes, DN20 PPR pipes and DN80 galvanized steel pipes according to design drawings and actual needs, ensuring that the cutting surface is smooth and free of burrs;

[0010] S3. Pipeline laying: connect the N40 PPR pipe to the output end of the water supply station. After passing through the courtyard wall of the water supply station, place a DN80 galvanized steel pipe on the outside of the N40 PPR pipe, support it with galvanized pipe fixtures, fix one end to the wall, and then fix it between the galvanized pipe fixtures;

[0011] S4. Inject liquid foaming agent, put one end of the hose between the outside of the DN40 PPR pipe and the DN80 galvanized steel pipe, pull the DN40 PPR pipe to the center of the DN80 galvanized steel pipe, and then start the pressure pump to transport the liquid foaming agent to the outside of the DN40 PPR pipe and the DN80 galvanized steel pipe, while pumping outwards, stop injecting when it is 1 meter, insert the fixing ring between the DN80 galvanized steel pipe outside the DN40 PPR pipe, use the steel pipe to push the fixing ring inwards, and after it fits with the liquid foaming agent, insert the hose again into one side of the fixing ring between the DN80 galvanized steel pipe outside the DN40 PPR pipe, and inject the liquid foaming agent again until it is full;

[0012] S5. Connect the pipelines. Install galvanized pipe fixtures at the location where the pipelines are not laid. Cut and grind the other DN40 PPR pipe and the end of the DN80 galvanized steel pipe. First, put a DN40 straight-through connection pipe fitting on the fixed DN40 PPR pipe end and seal it with sealant. Connect the other DN40 PPR pipe end to the DN80 straight-through connection pipe fitting and seal it with sealant. Then use a cutting tool to cut and grind the other end. Install the DN80 galvanized steel threaded straight-through connection pipe fitting on the fixed DN80 galvanized steel pipe and seal it with sealant. Then connect the other DN80 galvanized steel pipe to the end of the DN80 straight-through connection pipe fitting and seal it with sealant. Seal it, and then fix it between the galvanized pipe fixings, insert the hose between the outside of the DN40 PPR pipe and the DN80 galvanized steel pipe again, pull the DN40 PPR pipe to the center of the DN80 galvanized steel pipe, and then start the pressure pump to transport the liquid foaming agent to the outside of the DN40 PPR pipe and the DN80 galvanized steel pipe, while injecting and pumping outward, stop injecting when pumping 1 meter, insert the fixing ring between the DN80 galvanized steel pipe outside the DN40 PPR pipe, use the steel pipe to push the fixing ring inward, and after it fits with the liquid foaming agent, insert the hose again into one side of the fixing ring between the DN80 galvanized steel pipe outside the DN40 PPR pipe, and inject the liquid foaming agent again until it is full;

[0013] S6. Branch pipeline connection, build galvanized pipe fittings at the location where the pipeline needs to be branched, connect the DN40 multi-way connecting pipe fitting to the DN40 PPR pipe end, seal it with sealant, and then put the DN80 galvanized steel pipe multi-way connecting pipe fitting on the DN80 galvanized steel pipe end outside the DN40 multi-way connecting pipe fitting. After sealing with sealant, insert the end of the hose between the DN40 multi-way connecting pipe fitting and the DN80 galvanized steel pipe multi-way connecting pipe fitting, and pump it outward while injecting, leaving a position for the fixing ring for injection, and then put the fixing ring on the outside of the DN40 PPR multi-way connecting pipe fitting. After filling, connect the pipeline according to the above S5 steps;

[0014] S7. Laying the curved road, build galvanized pipe fixtures at the corners, connect the DN40 PPR elbow connecting pipe at the DN40 PPR pipe position, seal it with sealant, then sleeve the DN80 galvanized steel pipe elbow connecting pipe on the end of the DN80 galvanized steel pipe outside the DN40 PPR elbow connecting pipe, seal it with sealant, insert the hose between the outside of the DN40 PPR elbow connecting pipe and the DN80 galvanized steel pipe elbow connecting pipe, lift the end of the DN40 PPR elbow connecting pipe so that the DN40 PPR elbow connecting pipe is located at the center of the DN80 galvanized steel pipe elbow connecting pipe, then insert the hose between the DN40 PPR elbow connecting pipe and the DN80 galvanized steel pipe elbow connecting pipe, pump outward while injecting, reserve the position of the fixing ring for injection, then sleeve the fixing ring on the outside of the DN40 PPR elbow connecting pipe until it is full;

[0015] S8. Household connection: Build galvanized pipe fixtures at the household location, connect the PPR three-way connection fitting to the end of the D40 PPR pipe, seal it with sealant, and then put a DN40 PPR straight connection fitting on the output end of the fixed DN40 PPR pipe in a straight position, seal it with sealant, and then put a DN80 galvanized steel threaded straight connection fitting on it, seal it with sealant, make a hole on the wall at the vertical position of the pipeline, fix the DN20 PPR pipe on the other output end of the PPR three-way connection fitting, seal it with sealant, and pass it through the hole in the wall;

[0016] S9. Lay the entrance bend, build galvanized pipe fixtures at the corner, connect the DN20 PPR elbow connecting pipe to the DN20 PPR pipe position, use sealant to seal, then connect the DN20 PPR pipe to the end of the DN20 PPR elbow connecting pipe, and use sealant to seal;

[0017] S10. For household diversion, install galvanized pipe fixtures at the location where diversion is required, fix the DN20 PPR multi-way connecting pipe fittings on the end of the DN20 PPR pipe, and use sealant to seal it. The output ends of the DN20 PPR multi-way connecting pipe fittings are all fixed with DN20 PPR pipes, and sealed with sealant;

[0018] S11. End sealing: insert end seals into the ends of the DN40 PPR pipe, the DN20 PPR pipe and the DN80 galvanized steel pipe for sealing.

[0019] Preferably, the nominal diameter of the input end of the PPR three-way connecting pipe fitting is 40, and the nominal diameters of the two output ends are 40 and 20 respectively.

[0020] (III) Beneficial effects

[0021] The present invention provides a water pipe insulation and antifreeze construction method for low-temperature areas. It has the following beneficial effects:

[0022] 1. In the present invention, PPR pipes are often used in hot and cold water pipe systems because of their good temperature resistance and pressure resistance. The galvanized steel pipe is sheathed on the outside to prevent external damage. The foaming agent will expand after filling to form a uniform insulation layer, which effectively isolates the low temperature from the outside and reduces the loss of heat. This insulation layer can significantly improve the thermal insulation performance of the pipeline and reduce the speed at which the water temperature in the pipeline drops, thereby effectively preventing the PPR pipe from freezing and cracking in a low temperature environment. There is no need to dig out a water pipe laying path on the road surface, and at the same time, the antifreeze and thermal insulation capabilities of the PPR pipe can be guaranteed.

[0023] 2. In the present invention, adding an insulation layer to the outside of the PPR pipe can prevent condensation from forming on the surface of the PPR pipe, reducing corrosion and mildew problems caused by condensation. Since the foaming agent insulation layer can protect the PPR pipe from temperature and environmental factors, the maintenance and replacement frequency of the PPR pipe can be reduced, thereby reducing long-term maintenance costs.

[0024] 3. In the present invention, the thermal insulation layer formed by the foaming agent has a certain elasticity, which can adapt to the slight movement and vibration of the PPR pipe and improve the overall stability of the system. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a structural schematic diagram of the household connection of the present invention.

[0026] Among them, 1. DN40 PPR pipe; 2. DN80 galvanized steel pipe; 3. liquid foaming agent; 4. fixing ring; 5. wall; 6. DN20 PPR pipe; 7. PPR three-way connecting pipe fittings. DETAILED DESCRIPTION

[0027] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0028] Embodiment 1:

[0029] like Figure 1 As shown, an embodiment of the present invention provides a water pipe insulation and antifreeze construction method for low temperature areas, comprising the following steps:

[0030] S1. Material preparation, DN40 PPR pipe 1, DN40 PPR elbow connecting pipe, DN40 PPR straight connecting pipe fittings, DN40 PPR multi-way connecting pipe fittings, DN20 PPR pipe 6, DN20 PPR elbow connecting pipe, DN20 PPR straight connecting pipe fittings, DN20 PPR multi-way connecting pipe fittings, PPR three-way connecting pipe fittings, DN80 galvanized steel pipe 2, DM80 galvanized steel threaded elbow connecting pipe, DM80 galvanized steel threaded straight connecting pipe fittings, DN80 galvanized steel pipe multi-way connecting pipe fittings, galvanized steel pipe three-way connecting pipe fittings, liquid foaming agent 3, fixing ring 4, pressure pump, hose, galvanized pipe fitting fixings, cutting tools, sealant and cleaning agent;

[0031] S2. Pipe cutting: Use cutting tools to accurately cut the DN40 PPR pipe 1, DN20 PPR pipe 6 and DN80 galvanized steel pipe 2 according to the design drawings and actual needs, ensuring that the cutting surface is flat and free of burrs;

[0032] S3. Pipeline laying: connect the N40 PPR pipe 1 to the output end of the water supply station, pass through the courtyard wall of the water supply station, and then put the DN80 galvanized steel pipe 2 on the outside of the N40 PPR pipe 1, support it with galvanized pipe fixings, and then fix one end to the wall 5, and then fix it between the galvanized pipe fixings;

[0033] S4. Inject liquid foaming agent, put one end of the hose into the space between the outer side of the DN40 PPR pipe 1 and the DN80 galvanized steel pipe 2, pull the DN40 PPR pipe 1 to the center of the DN80 galvanized steel pipe 2, and then start the pressure pump to transport the liquid foaming agent 3 to the space between the outer side of the DN40 PPR pipe 1 and the DN80 galvanized steel pipe 2, while pumping outwards while injecting, stop injecting when the pumping reaches 1 meter, insert the fixing ring 4 into the space between the DN80 galvanized steel pipe 2 on the outer side of the DN40 PPR pipe 1, use the steel pipe to push the fixing ring 4 inwards, and after it fits with the liquid foaming agent 3, insert the hose into one side of the fixing ring 4 between the DN80 galvanized steel pipe 2 on the outer side of the DN40 PPR pipe 1 again, and inject the liquid foaming agent 3 again until it is full;

[0034] S5. Connect the pipelines. Install galvanized pipe fixtures at the location where the pipelines are not laid. Cut and grind the ends of the other DN40 PPR pipe 1 and the DN80 galvanized steel pipe 2. First, put a DN40 straight-through connecting pipe fitting on the fixed end of the DN40 PPR pipe 1 and seal it with sealant. Connect the end of the other DN40 PPR pipe 1 to the DN80 straight-through connecting pipe fitting and seal it with sealant. Then use a cutting tool to cut and grind the other end flat. Install the DN80 galvanized steel threaded straight-through connecting pipe fitting on the fixed DN80 galvanized steel pipe 2 and seal it with sealant. Then connect the other DN80 galvanized steel pipe 2 to the end of the DN80 straight-through connecting pipe fitting and seal it with sealant. Fix the galvanized pipe fittings between them, insert the hose again between the outside of the DN40 PPR pipe 1 and the DN80 galvanized steel pipe 2, pull the DN40 PPR pipe 1 to the center of the DN80 galvanized steel pipe 2, and then start the pressure pump to transport the liquid foaming agent 3 to the outside of the DN40 PPR pipe 1 and the DN80 galvanized steel pipe 2, while pumping outwards, stop injecting at the 1-meter position, insert the fixing ring 4 between the DN80 galvanized steel pipe 2 on the outside of the DN40 PPR pipe 1, use the steel pipe to push the fixing ring 4 inwards, and after it fits with the liquid foaming agent 3, insert the hose again on one side of the fixing ring 4 between the DN80 galvanized steel pipe 2 on the outside of the DN40 PPR pipe 1, and inject the liquid foaming agent 3 again until it is full;

[0035] S6. Branch pipeline connection, build galvanized pipe fittings at the location where the pipeline needs to be branched, connect the DN40 multi-way connecting pipe fitting to the end of the DN40 PPR pipe 1, seal it with sealant, and then put the DN80 galvanized steel pipe multi-way connecting pipe fitting on the end of the DN80 galvanized steel pipe 2 outside the DN40 multi-way connecting pipe fitting. After sealing with sealant, insert the end of the hose between the DN40 multi-way connecting pipe fitting and the DN80 galvanized steel pipe multi-way connecting pipe fitting, and pump it outward while injecting, leaving a position for the fixing ring 4 for injection, and then put the fixing ring 4 on the outside of the DN40 PPR multi-way connecting pipe fitting. After filling, connect the pipeline according to the above S5 steps;

[0036] S7. Laying the curved road, build the galvanized pipe fixture at the corner position, connect the DN40 PPR elbow connecting pipe at the DN40 PPR pipe 1 position, use sealant to seal, then set the DN80 galvanized steel pipe elbow connecting pipe sleeve on the end of the DN80 galvanized steel pipe 2 outside the DN40 PPR elbow connecting pipe, use sealant to seal, insert the hose between the outside of the DN40 PPR elbow connecting pipe and the DN80 galvanized steel pipe elbow connecting pipe, lift the end of the DN40 PPR elbow connecting pipe so that the DN40 PPR elbow connecting pipe is located at the center of the DN80 galvanized steel pipe elbow connecting pipe, then insert the hose between the DN40 PPR elbow connecting pipe and the DN80 galvanized steel pipe elbow connecting pipe, and pump outward while injecting, reserve the position of the fixing ring 4 for injection, and then set the fixing ring sleeve on the outside of the DN40 PPR elbow connecting pipe until it is full;

[0037] S8. Household connection: Build a galvanized pipe fixture at the household location, connect the PPR three-way connection pipe fitting 7 to the end of the D40 PPR pipe 1, seal it with sealant, and then put a DN40 PPR straight connection pipe fitting on the output end of the fixed DN40 PPR pipe 1 in a straight position, seal it with sealant, and then put a DN80 galvanized steel threaded straight connection pipe fitting, seal it with sealant, make a hole on the wall 5 at the vertical position of the pipeline, fix the DN20 PPR pipe 6 on the other output end of the PPR three-way connection pipe fitting, seal it with sealant, and pass it through the hole in the wall;

[0038] S9. Lay the entrance bend, build galvanized pipe fixtures at the corner, connect the DN20 PPR elbow connecting pipe to the DN20 PPR pipe position, use sealant to seal, then connect the DN20 PPR pipe to the end of the DN20 PPR elbow connecting pipe, and use sealant to seal;

[0039] S10. For household diversion, install galvanized pipe fixtures at the location where diversion is required, fix the DN20 PPR multi-way connecting pipe fittings on the end of the DN20 PPR pipe, and use sealant to seal it. The output ends of the DN20 PPR multi-way connecting pipe fittings are all fixed with DN20 PPR pipes, and sealed with sealant;

[0040] S11. End sealing: insert end seals into the ends of the DN40 PPR pipe, the DN20 PPR pipe and the DN80 galvanized steel pipe for sealing.

[0041] The nominal diameter of the input end of the PPR tee connecting pipe fitting is 40, and the nominal diameters of the two output ends are 40 and 20 respectively, which is convenient for connecting to the DN20 PPR pipe into the house. After the connection into the house, the connection position is protected.

[0042] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A water pipe insulation and antifreeze construction method for low temperature areas, characterized by: The following steps are involved: S1. Material preparation, DN40 PPR pipe, DN40 PPR elbow connecting pipe, DN40 PPR straight connecting pipe fittings, DN40 PPR multi-way connecting pipe fittings, DN20 PPR pipe, DN20 PPR elbow connecting pipe, DN20 PPR straight connecting pipe fittings, DN20 PPR multi-way connecting pipe fittings, PPR three-way connecting pipe fittings, DN80 galvanized steel pipe, DM80 galvanized steel threaded elbow connecting pipe, DM80 galvanized steel threaded straight connecting pipe fittings, DN80 galvanized steel pipe multi-way connecting pipe fittings, galvanized steel pipe three-way connecting pipe fittings, liquid foaming agent, fixing ring, pressure pump, hose, galvanized pipe fitting fixings, cutting tools, sealant and cleaning agent; S2. Pipe cutting: Use cutting tools to accurately cut DN40 PPR pipes, DN20 PPR pipes and DN80 galvanized steel pipes according to design drawings and actual needs, ensuring that the cutting surface is smooth and free of burrs; S3. Pipeline laying: connect the N40 PPR pipe to the output end of the water supply station. After passing through the courtyard wall of the water supply station, place a DN80 galvanized steel pipe on the outside of the N40 PPR pipe, support it with galvanized pipe fixtures, fix one end to the wall, and then fix it between the galvanized pipe fixtures; S4. Inject liquid foaming agent, put one end of the hose between the outside of the DN40 PPR pipe and the DN80 galvanized steel pipe, pull the DN40 PPR pipe to the center of the DN80 galvanized steel pipe, and then start the pressure pump to transport the liquid foaming agent to the outside of the DN40 PPR pipe and the DN80 galvanized steel pipe, while pumping outwards, stop injecting when it is 1 meter, insert the fixing ring between the DN80 galvanized steel pipe outside the DN40 PPR pipe, use the steel pipe to push the fixing ring inwards, and after it fits with the liquid foaming agent, insert the hose again into one side of the fixing ring between the DN80 galvanized steel pipe outside the DN40 PPR pipe, and inject the liquid foaming agent again until it is full; S5. Connect the pipelines. Install galvanized pipe fixtures at the location where the pipelines are not laid. Cut and grind the other DN40 PPR pipe and the end of the DN80 galvanized steel pipe. First, put a DN40 straight-through connection pipe fitting on the fixed DN40 PPR pipe end and seal it with sealant. Connect the other DN40 PPR pipe end to the DN80 straight-through connection pipe fitting and seal it with sealant. Then use a cutting tool to cut and grind the other end. Install the DN80 galvanized steel threaded straight-through connection pipe fitting on the fixed DN80 galvanized steel pipe and seal it with sealant. Then connect the other DN80 galvanized steel pipe to the end of the DN80 straight-through connection pipe fitting and seal it with sealant. Seal it, and then fix it between the galvanized pipe fixings, insert the hose between the outside of the DN40 PPR pipe and the DN80 galvanized steel pipe again, pull the DN40 PPR pipe to the center of the DN80 galvanized steel pipe, and then start the pressure pump to transport the liquid foaming agent to the outside of the DN40 PPR pipe and the DN80 galvanized steel pipe, while injecting and pumping outward, stop injecting when pumping 1 meter, insert the fixing ring between the DN80 galvanized steel pipe outside the DN40 PPR pipe, use the steel pipe to push the fixing ring inward, and after it fits with the liquid foaming agent, insert the hose again into one side of the fixing ring between the DN80 galvanized steel pipe outside the DN40 PPR pipe, and inject the liquid foaming agent again until it is full; S6. Branch pipeline connection, build galvanized pipe fittings at the location where the pipeline needs to be branched, connect the DN40 multi-way connecting pipe fitting to the DN40 PPR pipe end, seal it with sealant, and then put the DN80 galvanized steel pipe multi-way connecting pipe fitting on the DN80 galvanized steel pipe end outside the DN40 multi-way connecting pipe fitting. After sealing with sealant, insert the end of the hose between the DN40 multi-way connecting pipe fitting and the DN80 galvanized steel pipe multi-way connecting pipe fitting, and pump it outward while injecting, leaving a position for the fixing ring for injection, and then put the fixing ring on the outside of the DN40 PPR multi-way connecting pipe fitting. After filling, connect the pipeline according to the above S5 steps; S7. Laying the curved road, build galvanized pipe fixtures at the corners, connect the DN40 PPR elbow connecting pipe at the DN40 PPR pipe position, seal it with sealant, then sleeve the DN80 galvanized steel pipe elbow connecting pipe on the end of the DN80 galvanized steel pipe outside the DN40 PPR elbow connecting pipe, seal it with sealant, insert the hose between the outside of the DN40 PPR elbow connecting pipe and the DN80 galvanized steel pipe elbow connecting pipe, lift the end of the DN40 PPR elbow connecting pipe so that the DN40 PPR elbow connecting pipe is located at the center of the DN80 galvanized steel pipe elbow connecting pipe, then insert the hose between the DN40 PPR elbow connecting pipe and the DN80 galvanized steel pipe elbow connecting pipe, pump outward while injecting, reserve the position of the fixing ring for injection, then sleeve the fixing ring on the outside of the DN40 PPR elbow connecting pipe until it is full; S8. Household connection: Build galvanized pipe fixtures at the household location, connect the PPR three-way connection fitting to the end of the D40 PPR pipe, seal it with sealant, and then put a DN40 PPR straight connection fitting on the output end of the fixed DN40 PPR pipe in a straight position, seal it with sealant, and then put a DN80 galvanized steel threaded straight connection fitting on it, seal it with sealant, make a hole on the wall at the vertical position of the pipeline, fix the DN20 PPR pipe on the other output end of the PPR three-way connection fitting, seal it with sealant, and pass it through the hole in the wall; S9. Lay the entrance bend, build galvanized pipe fixtures at the corner, connect the DN20 PPR elbow connecting pipe to the DN20 PPR pipe position, use sealant to seal, then connect the DN20 PPR pipe to the end of the DN20 PPR elbow connecting pipe, and use sealant to seal; S10. For household diversion, install galvanized pipe fixtures at the location where diversion is required, fix the DN20 PPR multi-way connecting pipe fittings on the end of the DN20 PPR pipe, and use sealant to seal it. The output ends of the DN20 PPR multi-way connecting pipe fittings are all fixed with DN20 PPR pipes, and sealed with sealant; S11. End sealing: insert end seals into the ends of the DN40 PPR pipe, the DN20 PPR pipe and the DN80 galvanized steel pipe for sealing.

2. A water pipe insulation and antifreeze construction method for low temperature areas according to claim 1, characterized in that: The nominal diameter of the input end of the PPR tee connecting pipe is 40, and the nominal diameters of the two output ends are 40 and 20 respectively.