Field experiment device and method for mechanical property of new and old bridge splicing and widening joint

By designing a field experimental device for mechanical properties of new and old bridges, and using the old bridge structure as a loading platform, efficient experimental data acquisition is achieved, solving the problems of incomplete load experiments and high model experiment costs in the existing technology, and realizing the Low-cost and efficient experimental methods.

CN118913745APending Publication Date: 2024-11-08TIANYUAN CONSTR GROUP +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411030611.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-30
Publication Date
2024-11-08

AI Technical Summary

Technical Problem

In the prior art, the on-site load experiment of wide joints of new and old bridges cannot be loaded to the limit load, resulting in incomplete experimental results, and the on-site experiment cost and long periods of model models are high.

Method used

A field experimental device for mechanical properties of wide-splitting joints of new and old bridges was designed, including old bridge cover beams, old bridge box beams, new bridge flange plates, loading mechanisms and adjustable top pressure mechanisms, using the old bridge structure as a loading platform , vertical downward loading is achieved through hydraulic jacks, reducing experimental costs and time.

Benefits of technology

Destructive experiments were realized, complete experimental data was obtained, materials and time were saved, experimental costs were reduced, and experimental conditions were not limited by experimental conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118913745A_ABST
    Figure CN118913745A_ABST
Patent Text Reader

Abstract

The invention provides a new and old bridge widening joint mechanical property field experiment device and method.The new and old bridge widening joint mechanical property field experiment device comprises an old bridge cover beam, an old bridge box beam, a new bridge flange plate, a loading mechanism and a first adjustable jacking mechanism, and the old bridge box beam is horizontally distributed between the old bridge cover beam and an old bridge straining beam in the front-back direction; first adjustable supporting mechanisms are arranged on the lower portions of the two ends of an old bridge box girder respectively, a supporting frame is fixedly arranged on the upper portion of an old bridge straining beam, the bottom of a new bridge flange plate is fixedly arranged on the upper portion of the supporting frame, the new bridge flange plate is located on the right side of the old bridge box girder, and a splicing and widening joint is reserved between the old bridge box girder and the new bridge flange plate. The loading mechanism is used for vertically and downwards loading an old bridge box girder or a new bridge flange plate, and the first adjustable jacking mechanism is used for jacking and fixing the right side of the upper portion of the new bridge flange plate. The experimental device can be used for carrying out destructive experiments, the completeness of experimental data is realized, and meanwhile, the experimental device can be used for carrying out experiments by utilizing a part of structures of an old bridge, so that the experimental research cost can be greatly reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of widening new and old bridges, and specifically to a field experimental device and method for mechanical properties of widening joints of new and old bridges. Background Art

[0002] In the process of widening and reconstruction of bridge projects, the longitudinal connection between the new and old bridges is an inevitable problem. Since the new and old bridges may have differences in span, structural form, service life and load, the stress at the joint position is relatively complex, which is prone to large deformation, resulting in structural damage at the joint and shortening the service life.

[0003] In order to verify the reliability of the joint structure of the new and old bridges, it is usually necessary to conduct on-site mechanical performance tests on the joints of the new and old bridges. At present, the on-site mechanical performance test method is to conduct on-site load tests at the joints of the new and old bridges, or on-site scale model tests. Due to the limitations of experimental conditions and usage requirements, on-site load tests are difficult to load and cannot be loaded to the ultimate load, resulting in incomplete experimental results; on-site scale model tests require component production, and use pile load loading methods for mechanical performance tests, which have high experimental costs and long experimental times. Summary of the invention

[0004] The purpose of the invention is to provide a field test device and method for the mechanical properties of the widened joints of new and old bridges, so as to solve the problem that the on-site load test cannot be loaded to the limit and complete test data cannot be obtained; at the same time, it solves the problem of high cost and long test cycle of on-site proportional model tests.

[0005] The technical solution adopted by the invention to solve its technical problems is: a field experimental device for the mechanical properties of the widened joint of the new and old bridges, including an old bridge cover beam, an old bridge box beam, a new bridge flange plate, a loading mechanism, and a first adjustable top pressure mechanism. Two old bridge piers distributed left and right are arranged at the bottom of the old bridge cover beam, an old bridge tie beam located below the old bridge cover beam is arranged between the two old bridge piers, the old bridge box beam is horizontally distributed between the old bridge cover beam and the old bridge tie beam along the front-back direction, and a first adjustable top pressure mechanism is arranged at the lower part of both ends of the old bridge box beam. Adjust the support mechanism, a support frame is fixedly set on the upper part of the old bridge tie beam, the bottom of the new bridge flange plate is fixedly set on the upper part of the support frame and the new bridge flange plate is located on the right side of the old bridge box beam, the upper plane of the old bridge box beam and the upper plane of the new bridge flange plate are in the same horizontal plane and a widened joint is reserved between the old bridge box beam and the new bridge flange plate, the loading mechanism is used to realize vertical downward loading to the old bridge box beam or the new bridge flange plate, and the first adjustable top pressure mechanism is used to realize the top pressure fixation of the upper right side of the new bridge flange plate.

[0006] Preferably, the first adjustable pressing mechanism includes two first threaded jacks.

[0007] Furthermore, the first adjustable support mechanism includes a support pier and two second threaded jacks. The support pier is fixedly arranged on the ground, and the two second threaded jacks are arranged on the upper part of the support pier.

[0008] Furthermore, the loading mechanism is a hydraulic jack.

[0009] A method for testing the mechanical properties of a widened joint between a new and an old bridge, a device for testing the mechanical properties of a widened joint between a new and an old bridge, and the method further comprising the following steps:

[0010] S1. At the construction site, a span node supporting pier of an old bridge is selected according to the demand, and the supporting pier includes the old bridge cap beam, the old bridge tie beam and the old bridge pier;

[0011] S2. Cast two supporting piers on both sides of the selected span node supporting bridge pier according to the experimental requirements. After the supporting piers are solidified and formed, two second threaded jacks are set on the supporting piers and the fixed ends of the second threaded jacks are fixedly set on the supporting piers. The supporting frame is fixedly set at the corresponding position of the tie beam of the old bridge. When the second threaded jacks are used to support the box girder of the old bridge and the supporting frame is used to support the flange plate of the new bridge, it is necessary to ensure that the width of the widened joint between the box girder of the old bridge and the flange plate of the new bridge is equal to the designed width of the widened joint between the old and new bridges.

[0012] S3. According to the design requirements of the width of the new and old bridges, the corresponding span of the old bridge is dismantled. During the dismantling process, the two dismantled box girders of the old bridge are transported to the implementation site, and one of the box girders of the old bridge is installed using lifting equipment. When installing the box girder of the old bridge, ensure that the two second threaded jacks on the supporting piers realize the end support of the box girder of the old bridge;

[0013] S4. Prefabricate the new bridge flange plate of the unit segment according to the design requirements of the new bridge, and fix the prepared new bridge flange plate to the upper part of the support frame. After the new bridge flange plate is installed and fixed, adjust the corresponding second threaded jack so that the upper plane of the old bridge box girder and the upper plane of the new bridge flange plate are in the same horizontal plane;

[0014] S5. After adjusting the horizontal height of the box girder of the old bridge, the box girder of the old bridge and the flange plate of the new bridge are spliced ​​and the bridge deck is paved. The construction requirements of splicing and bridge deck paving are consistent with the design and construction requirements of widening the new and old bridges. Specifically, a steel plate is set on the upper part of the box girder of the old bridge and the flange plate of the new bridge, and the steel plate spans directly above the widening joint between the two. After the steel plate is laid, a number of first strain gauges are set in the horizontal middle and left and right ends of the steel plate. After the first strain gauge is set, a steel mesh is laid on the upper part of the steel plate. The steel mesh spans the entire width range of the box girder of the old bridge and the flange plate of the new bridge. After the steel mesh is laid, the steel mesh is set with the first strain gauges corresponding to the upper and lower parts of the first strain gauge. Two strain gauges, after the second strain gauge is set, UHPC concrete is poured in the upper and lower overlapping areas of the steel mesh and the steel plate, and ordinary concrete is poured in the remaining covering position of the steel mesh. After the UHPC concrete and the ordinary concrete are both solidified and formed, a third strain gauge is set on the upper part of the UHPC concrete, and a fourth strain gauge is set on the upper part of the ordinary concrete. After the third and fourth strain gauges are set, a waterproof layer is laid on the upper part of the UHPC concrete and the ordinary concrete. After the waterproof layer is laid, a fifth strain gauge is set on the upper part of the waterproof layer. After the fifth strain gauge is set, an asphalt layer is laid on the upper part of the waterproof layer. The above strain gauges are all electrically connected to the static data acquisition instrument;

[0015] S6. Use the old bridge cap beam to press the two first threaded jacks onto the asphalt layer on the left side of the upper part of the new bridge flange plate;

[0016] S7. Displacement meters are set at the lower part of the upper flange adjacent to the flange plate of the old bridge box girder and the new bridge and at the lower part of the flange plate of the new bridge, and the displacement meters are located on both sides of the widened joint. Displacement meters are set at both ends, mid-span and lower part of 1 / 4 span of the old bridge box girder, and the displacement meters are electrically connected to the static data acquisition instrument;

[0017] S8, performing experimental load loading;

[0018] The hydraulic jack is arranged on the upper part of the asphalt layer of the box girder of the old bridge, and the hydraulic jack can realize vertical downward loading on the box girder of the old bridge by using the support of the cap beam of the old bridge;

[0019] The hydraulic jack is used to conduct graded loading experiments on the box girder of the old bridge. Specifically, the loading load can be controlled according to the downward deflection of the box girder of the old bridge to control the design load and overload. The loading process is: load to the control load in sequence of 20%, 30%, and 50%, and then continue to load until the box girder or the splicing part of the old bridge is damaged. During the loading process, the static data acquisition instrument collects and records the relevant data after each loading;

[0020] After the above loading experiment is finished, when the old bridge box girder is not damaged but only the splicing part is damaged, all the original splicing materials are cleaned up, and then the above steps S5-S7 are repeated to complete the re-splicing and paving of the splicing part; when the old bridge box girder is damaged but the splicing part is not damaged, the old bridge box girder is transported away by hoisting equipment and the splicing materials on the flange plate of the new bridge are cleaned up, and then an old bridge box girder is reinstalled. After the old bridge box girder is installed, then the above steps S5-S7 are repeated to complete the re-splicing and paving of the splicing part;

[0021] After the re-splicing and paving are completed, the hydraulic jack is set on the asphalt layer on the upper part of the flange plate of the new bridge. Then, the flange plate of the new bridge is loaded according to the above loading process until the box girder or splicing part of the old bridge is damaged. During the loading process, the static data acquisition instrument collects and records the relevant data after each loading.

[0022] Preferably, a high-definition camera is arranged near the displacement meter, and the high-definition camera is used to record the change process of the displacement meter reading at all times.

[0023] Preferably, grids are drawn on the surface of the flange plates of the new bridge and the surface of the box girders of the old bridge on both sides of the widened joint.

[0024] The beneficial effects of the invention are:

[0025] (1) Only the flange plate of the new bridge in unit segment needs to be prefabricated as the test module, and there is no need to make a component model of the same scale, thus avoiding the need to pour a large amount of concrete and saving materials.

[0026] (2) The foundation and substructure of the existing old bridge are used as the loading platform, and the original cap beam is used as the reaction frame to avoid stacking, reduce experimental costs, and shorten experimental time.

[0027] (3) This experimental method is not limited by experimental conditions and usage requirements, and destructive experiments can be performed to ensure the integrity of the experimental data. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] In order to more clearly illustrate the embodiments of the invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some preferred embodiments of the invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0029] Figure 1 It is a schematic diagram of the overall structure of the invention;

[0030] Figure 2 This is the main view of the splicing of the box girder of the old bridge and the flange plate of the new bridge;

[0031] Figure 3 This is a schematic diagram of the distribution of displacement meters under the box girder of the old bridge;

[0032] Figure 4 Schematic diagram of strain gauge distribution on the steel plate;

[0033] Figure 5 Schematic diagram of strain gauge distribution on the steel mesh;

[0034] Figure 6 Schematic diagram of the distribution of strain gauges on the upper surface of ordinary concrete and UHPC concrete;

[0035] Figure 7 Schematic diagram of strain gauge distribution on the upper surface of the waterproof layer;

[0036] Figure 8 Schematic diagram of longitudinal section at the widened joint;

[0037] In the figure: 11 old bridge cap beam, 12 old bridge pier, 13 old bridge tie beam, 2 old bridge box beam, 21 supporting pier, 22 second threaded jack, 3 new bridge flange plate, 31 supporting frame, 32 first threaded jack, 4 hydraulic jack, 5 spliced ​​pavement layer, 51 steel plate, 52 steel mesh, 53 ordinary concrete, 54 UHPC concrete, 55 waterproof layer, 56 asphalt layer, 6 displacement meter, 71 first strain gauge, 72 second strain gauge, 73 third strain gauge, 74 fourth strain gauge, 75 fifth strain gauge, 101 spliced ​​wide joint. DETAILED DESCRIPTION

[0038] The following will be combined with specific embodiments and attached Figure 1-8 , the technical solutions in the embodiments of the invention are clearly and completely described. Obviously, the described embodiments are only part of the preferred embodiments of the invention, not all of the embodiments. Those skilled in the art can make similar modifications without violating the connotation of the invention, so the invention is not limited by the specific embodiments disclosed below.

[0039] A field experimental device for mechanical properties of widened joints of new and old bridges (such as Figure 1As shown), it includes an old bridge cover beam 11, an old bridge box beam 2, a new bridge flange plate 3, a loading mechanism, and a first adjustable top pressure mechanism. Two old bridge piers 12 distributed on the left and right are arranged at the bottom of the old bridge cover beam 11. An old bridge tie beam 13 located below the old bridge cover beam 11 is arranged between the two old bridge piers 12. The old bridge cover beam 11, the old bridge piers 12 and the old bridge tie beam 11 are all existing supporting structures of the old bridge. Therefore, when conducting experiments, there is no need to reconstruct this part of the structure, which not only saves experimental costs, but also helps to improve experimental efficiency. During the experiment, The old bridge tie beam 13 provides loading support for the new bridge flange plate 3, and the old bridge cover beam 11 provides reverse support for the loading of the old bridge box beam 2 and the new bridge flange plate 3. The old bridge box beam 2 is horizontally distributed between the old bridge cover beam 11 and the old bridge tie beam 13 along the front-to-back direction. A first adjustable supporting mechanism is arranged at the lower part of both ends of the old bridge box beam 2. The two first adjustable supporting mechanisms are used to realize the erection of the old bridge box beam 11 between the old bridge cover beam 11 and the old bridge tie beam 13. The old bridge box beam 2 can be obtained from the span of the old bridge that needs to be demolished, so there is no need to cast the old bridge box beam 2 before the experiment. It is also beneficial to save experimental costs and improve experimental efficiency; a support frame 31 is fixedly set on the upper part of the old bridge tie beam 13, and the bottom of the new bridge flange plate 3 is fixedly set on the upper part of the support frame 31 and the new bridge flange plate 3 is located on the right side of the old bridge box beam 2. Before conducting the experiment, it is necessary to prefabricate the unit segment new bridge flange plate 3 according to the design requirements of the new bridge. Because only the unit segment new bridge flange plate 3 needs to be prefabricated, there is no need to make a component model of the same proportion, which avoids pouring a lot of concrete, thereby reducing the experimental cost; in this specific embodiment, the support frame 31 includes two Connecting and fixing steel plates, four connecting support steel pipes are fixedly arranged between two connecting and fixing steel plates, and the connecting and fixing steel plates are fixedly connected with the corresponding old bridge tie beam or the bottom of the new bridge flange plate 3 by expansion bolts, the upper plane of the old bridge box beam 2 and the upper plane of the new bridge flange plate 3 are in the same horizontal plane, and a widening joint 101 is reserved between the old bridge box beam 2 and the new bridge flange plate 3, and the loading mechanism is used to realize vertical downward loading to the old bridge box beam 2 or the new bridge flange plate 3, and the first adjustable top pressure mechanism is used to realize the top pressure fixation of the upper right side of the new bridge flange plate 3. By using the above experimental device, an experimental platform for studying the mechanical properties of the widening joints of the new and old bridges can be quickly realized, with low cost and high efficiency. At the same time, destructive loading experiments can be carried out to obtain complete experimental data.

[0040] On the basis of the above-mentioned embodiment, the specific implementation method of the first adjustable pressing mechanism is as follows: the first adjustable pressing mechanism includes two first threaded jacks 32. In actual application, the reverse support of the old bridge cover beam 11 to the first threaded jacks 32 can enable the first threaded jacks 32 to apply a stable pressure to the top of the new bridge flange plate 3, thereby facilitating the effective and firm fixation of the new bridge flange plate 3 on the support frame 31, and the first threaded jacks 32 have a reliable self-locking function, thereby achieving continuous and effective pressure on the new bridge flange plate 3.

[0041] On the basis of the above embodiment, the specific implementation method of the first adjustable support mechanism is as follows: the first adjustable support mechanism includes a support pier 21 and two second threaded jacks 22. The support pier 21 is fixedly set on the ground, and the two second threaded jacks 22 are set on the upper part of the support pier 21. In practical applications, it is necessary to use the on-site experimental requirements to cast the support pier 21 on-site, so as to achieve stable support of the old bridge box girder 2. Before the formwork casting of the support pier 21, it is necessary to determine the position of the support pier 21 based on the experimental relative position between the old bridge box girder 2 and the new bridge flange plate 3, so that after the old bridge box girder 2 is subsequently installed on the support pier 21, the simulation of the widening structure of the new and old bridges can be realized; the second threaded jack 22 can be used to realize the effective adjustment of the height of the old bridge box girder 2, and then it is convenient to adjust the horizontal height between the old bridge box girder 2 and the new bridge flange plate 3.

[0042] During the experiment, in order to facilitate destructive loading and realize the adjustability and visualization of the loading load, the loading mechanism is a hydraulic jack 4. The hydraulic jack 4 utilizes the characteristics of the hydraulic transmission system to realize super-large load loading. At the same time, the hydraulic oil supply system matched with the hydraulic jack 4 can realize the adjustability and visualization of the loading load. Therefore, during the experiment, it is convenient to effectively control the loading load according to the experimental requirements, thereby ensuring the accuracy of the experimental loading load.

[0043] The present invention also provides a field test method for the mechanical properties of the widened joint of a new and old bridge, comprising the field test device for the mechanical properties of the widened joint of a new and old bridge according to the above content, and the field test method also includes the following steps:

[0044] S1. At the construction site, a span node supporting pier of an old bridge is selected according to the demand, and the supporting pier includes the old bridge cap beam 11, the old bridge tie beam 13 and the old bridge pier 12;

[0045] S2. Cast two of the supporting piers 21 on both sides of the selected span node supporting piers according to the experimental requirements. After the supporting piers 21 are solidified and formed, two of the second threaded jacks 22 are set on the supporting piers 21 and the fixed ends of the second threaded jacks 22 are fixedly set on the supporting piers 21. The supporting frame 31 is fixedly set at the corresponding position of the tie beam 13 of the old bridge. When the second threaded jacks 22 are used to support the box girder 2 of the old bridge and the supporting frame 31 is used to support the flange plate 3 of the new bridge, it is necessary to ensure that the width of the widened joint 101 between the box girder 2 of the old bridge and the flange plate 3 of the new bridge is equal to the designed width of the widened joint of the new and old bridges; the width of the widened joint in the experimental site is equal to the width of the widened joint of the new and old bridges, which is conducive to improving the authenticity of the experimental simulation;

[0046] S3. According to the design requirements for widening the new and old bridges, the corresponding span of the old bridge is dismantled. During the dismantling process, the two dismantled box girders 2 of the old bridge are transported to the implementation site, and one of the box girders 2 of the old bridge is installed using hoisting equipment. When installing the box girder 2 of the old bridge, ensure that the two second threaded jacks 22 on the supporting piers 21 realize the end support of the box girder 2 of the old bridge;

[0047] S4. Prefabricate the new bridge flange plate 3 of the unit segment according to the design requirements of the new bridge, and fix the prepared new bridge flange plate 3 to the upper part of the mounting support frame 31. After the new bridge flange plate 3 is installed and fixed, adjust the corresponding second threaded jack 22 so that the upper plane of the old bridge box girder 2 and the upper plane of the new bridge flange plate 3 are in the same horizontal plane;

[0048] S5. After adjusting the horizontal height of the old bridge box girder 2, the old bridge box girder 2 and the new bridge flange plate 3 are spliced ​​and the bridge deck is paved, that is, the splicing pavement layer 5 is constructed between the old bridge box girder 2 and the new bridge flange plate 3. The splicing and bridge deck paving construction requirements are consistent with the design and construction requirements of the new and old bridges. Specifically, a steel plate 51 is arranged on the upper part of the old bridge box girder 2 and the new bridge flange plate 3, and the steel plate 51 spans directly above the splicing widened joint 101 between the two. The length direction of the steel plate 51 is in the same direction as the width direction of the splicing widened joint 101, and the left-right symmetry axis of the steel plate 51 is coaxial with the left-right symmetry axis of the splicing widened joint 101. Specifically, the length of the steel plate 51 is 700 mm, and the width is 300 mm. The thickness of the steel plate is determined according to the design requirements.After the steel plate 51 is laid, a plurality of first strain gauges 71 are arranged in the horizontal middle and left and right ends of the steel plate 51. In this specific embodiment, three first strain gauges 71 are arranged in the horizontal middle and left and right ends of the steel plate 51, and the center distance between two adjacent first strain gauges 71 is 300 mm, and the center distance between two adjacent first strain gauges 71 is 125 mm. After all the first strain gauges 71 are arranged, a steel mesh 52 is laid on the upper part of the steel plate 51, and the steel mesh 52 spans the entire width range of the old bridge box girder 2 and the new bridge flange plate 3. After the reinforcement mesh 52 is laid, a second strain gauge 72 corresponding to the first strain gauge 71 is arranged on the reinforcement mesh 52. After the second strain gauge 72 is arranged, UHPC concrete 54 is poured in the overlapping area between the reinforcement mesh 52 and the steel plate 51, and ordinary concrete 53 is poured in the remaining covering position of the reinforcement mesh 52. After the UHPC concrete 54 and the ordinary concrete 53 are both solidified and formed, a third strain gauge 73 is arranged on the upper part of the UHPC concrete 54. Specifically, three third strain gauges 73 can be arranged on the UHPC concrete 54, and the three third strain gauges 73 are respectively arranged in front of and behind the steel plate 3 The three first strain gauges 73 on the symmetric axis correspond to each other one by one in sequence, and a fourth strain gauge 74 is arranged on the upper part of the ordinary concrete 53. Specifically, one fourth strain gauge 74 is arranged on the ordinary concrete 53 on the left and right sides of the UHPC concrete 54, respectively. The two fourth strain gauges 74 are distributed on the same axis where the three third strain gauges 73 are distributed, and the center distance between the fourth strain gauge 74 and the adjacent third strain gauge 73 is 300 mm. After the third strain gauge 73 and the fourth strain gauge 74 are arranged, a waterproof layer 55 is laid on the upper part of the UHPC concrete 54 and the ordinary concrete 53. The waterproof layer After the paving is completed, the fifth strain gauge 75 is arranged on the upper part of the waterproof layer 55. Specifically, five fifth strain gauges 75 are arranged on the waterproof layer 55, wherein two fifth strain gauges 75 correspond to the two fourth strain gauges 74 in upper and lower parts, and the remaining three fifth strain gauges 75 correspond to the three third strain gauges 73 in upper and lower parts in sequence. After the fifth strain gauge 75 is arranged, an asphalt layer 76 is laid on the upper part of the waterproof layer 55. The above strain gauges are all electrically connected to the static data collector, which is a mature technical product in the prior art. Therefore, the structure and working principle of the static data collector are not described in detail here.

[0049] S6, using the old bridge cap beam 11, press the two first threaded jacks 32 onto the asphalt layer 76 on the left side of the upper part of the new bridge flange plate;

[0050] S7, a displacement meter 6 is set at the lower part of the upper flange adjacent to the flange plate 3 of the old bridge box girder 2 and the lower part of the flange plate 3 of the new bridge, and the displacement meter 6 is located on both sides of the widened joint 101. Specifically, the distance between the measuring point of the displacement meter 6 and the corresponding edge of the upper flange plate of the old bridge box girder 2 and the edge of the flange plate 3 of the new bridge is 100 mm; and two displacement meters 6 are located on the left and right sides of the lower middle part of the widened joint 101, and displacement meters 6 are set at both ends, the middle span and the lower part of 1 / 4 span of the old bridge box girder 2, and the displacement meter 6 is electrically connected to the static data acquisition instrument;

[0051] S8, performing experimental load loading;

[0052] The hydraulic jack 4 is arranged on the upper part of the asphalt layer of the old bridge box girder, and the hydraulic jack can realize the vertical downward loading of the old bridge box girder by using the support of the old bridge cover beam; the distance between the load application point of the hydraulic jack 4 to the old bridge box girder 2 and the side surface of the upper edge plate of the old bridge box girder 2 is 100 mm;

[0053] The hydraulic jack 4 is used to perform a graded loading experiment on the box girder 2 of the old bridge. Specifically, the loading load can be controlled according to the lower deflection of the box girder 2 of the old bridge to control the design load and overload. The loading process is: loading to the control load in sequence of 20%, 30%, and 50%, and then continuing to load until the box girder 2 of the old bridge or the splicing part is damaged. During the loading process, the static data acquisition instrument collects and records the relevant data after each loading;

[0054] After the above loading experiment is finished, when the old bridge box girder 2 is not damaged but only the splicing part is damaged, all the original splicing materials are cleaned up, and then the above steps S5-S7 are repeated to complete the re-splicing and paving of the splicing part; when the old bridge box girder 2 is damaged but the splicing part is not damaged, the old bridge box girder 2 is transported away by hoisting equipment and the splicing materials on the new bridge flange plate 3 are cleaned up, and then an old bridge box girder 2 is reinstalled. After the old bridge box girder 2 is installed, the above steps S5-S7 are repeated to complete the re-splicing and paving of the splicing part;

[0055] After the re-splicing and paving are completed, the hydraulic jack 4 is set on the asphalt layer on the upper part of the flange plate 3 of the new bridge. Specifically, the loading position of the hydraulic jack 4 on the flange plate 3 of the new bridge is 300mm away from the loading position on the old bridge 2; then, the flange plate 3 of the new bridge is loaded according to the above loading process until the box girder 2 of the old bridge or the splicing part is damaged; during the loading process, the static data acquisition instrument collects and records the relevant data after each loading.

[0056] In order to facilitate the data collection change process of the distance displacement meter 6, a high-definition camera is arranged near the displacement meter 6, and the high-definition camera is used to record the change process of the displacement meter 6 reading at all times.

[0057] The crack observation areas during the experiment were mainly the joints, the flanges and webs of the old bridge box girders and the new bridge flange plates. In order to closely observe the changes in cracks at the joints, grids were drawn on the surfaces of the new bridge flange plates 3 and the old bridge box girders 2 on both sides of the widened joints. At the same time, high-definition cameras were set up in each crack observation area to record the development and changes of cracks during the entire experiment.

[0058] Except for the technical features described in the specification, all other technical features are known technologies to those skilled in the art.

[0059] The above description, in combination with the accompanying drawings, details the preferred implementation modes and embodiments of the invention, but the invention is not limited to the above implementation modes and embodiments. For ordinary technicians in this technical field, several improvements and modifications can be made without departing from the concept of the invention, and these improvements and modifications should also be regarded as the scope of protection of the invention.

Claims

1. A field test device for mechanical properties of widened joints of new and old bridges, characterized in that: The invention comprises an old bridge cover beam, an old bridge box beam, a new bridge flange plate, a loading mechanism and a first adjustable top-pressing mechanism. Two old bridge piers distributed left and right are arranged at the bottom of the old bridge cover beam. An old bridge tie beam located below the old bridge cover beam is arranged between the two old bridge piers. The old bridge box beam is horizontally distributed between the old bridge cover beam and the old bridge tie beam along the front-back direction. A first adjustable supporting mechanism is arranged at the lower part of both ends of the old bridge box beam. A supporting frame is fixedly arranged at the upper part of the old bridge tie beam. The bottom of the new bridge flange plate is fixedly arranged at the upper part of the supporting frame and the new bridge flange plate is located on the right side of the old bridge box beam. The upper plane of the old bridge box beam and the upper plane of the new bridge flange plate are in the same horizontal plane and a widened joint is reserved between the old bridge box beam and the new bridge flange plate. The loading mechanism is used to realize vertical downward loading to the old bridge box beam or the new bridge flange plate. The first adjustable top-pressing mechanism is used to realize top-pressing and fixing of the upper right side of the new bridge flange plate.

2. The on-site experimental device for mechanical properties of widened joints of new and old bridges according to claim 1 is characterized in that: The first adjustable pressing mechanism includes two first threaded jacks.

3. The on-site experimental device for mechanical properties of widened joints of new and old bridges according to claim 2 is characterized in that: The first adjustable support mechanism includes a support pier and two second threaded jacks. The support pier is fixed on the ground, and the two second threaded jacks are arranged on the upper part of the support pier.

4. The on-site experimental device for mechanical properties of widened joints of new and old bridges according to claim 3 is characterized in that: The loading mechanism is a hydraulic jack.

5. A field test method for mechanical properties of widened joints of new and old bridges, characterized in that: The invention comprises a field test device for mechanical properties of widened joints of new and old bridges according to claim 4, and the field test method further comprises the following steps: S1. At the construction site, a span node supporting pier of an old bridge is selected according to the demand, and the supporting pier includes the old bridge cap beam, the old bridge tie beam and the old bridge pier; S2. Cast two supporting piers on both sides of the selected span node supporting bridge pier according to the experimental requirements. After the supporting piers are solidified and formed, two second threaded jacks are set on the supporting piers and the fixed ends of the second threaded jacks are fixedly set on the supporting piers. The supporting frame is fixedly set at the corresponding position of the tie beam of the old bridge. When the second threaded jacks are used to support the box girder of the old bridge and the supporting frame is used to support the flange plate of the new bridge, it is necessary to ensure that the width of the widened joint between the box girder of the old bridge and the flange plate of the new bridge is equal to the designed width of the widened joint between the old and new bridges. S3. According to the design requirements of the width of the new and old bridges, the corresponding span of the old bridge is dismantled. During the dismantling process, the two dismantled box girders of the old bridge are transported to the implementation site, and one of the box girders of the old bridge is installed using lifting equipment. When installing the box girder of the old bridge, ensure that the two second threaded jacks on the supporting piers realize the end support of the box girder of the old bridge; S4. Prefabricate the new bridge flange plate of the unit segment according to the design requirements of the new bridge, and fix the prepared new bridge flange plate to the upper part of the support frame. After the new bridge flange plate is installed and fixed, adjust the corresponding second threaded jack so that the upper plane of the old bridge box girder and the upper plane of the new bridge flange plate are in the same horizontal plane; S5. After adjusting the horizontal height of the box girder of the old bridge, the box girder of the old bridge and the flange plate of the new bridge are spliced ​​and the bridge deck is paved. The construction requirements of splicing and bridge deck paving are consistent with the design and construction requirements of widening the new and old bridges. Specifically, a steel plate is set on the upper part of the box girder of the old bridge and the flange plate of the new bridge, and the steel plate spans directly above the widening joint between the two. After the steel plate is laid, a number of first strain gauges are set in the horizontal middle and left and right ends of the steel plate. After the first strain gauge is set, a steel mesh is laid on the upper part of the steel plate. The steel mesh spans the entire width range of the box girder of the old bridge and the flange plate of the new bridge. After the steel mesh is laid, the steel mesh is set with the first strain gauges corresponding to the upper and lower parts of the first strain gauge. Two strain gauges, after the second strain gauge is set, UHPC concrete is poured in the upper and lower overlapping areas of the steel mesh and the steel plate, and ordinary concrete is poured in the remaining covering position of the steel mesh. After the UHPC concrete and the ordinary concrete are both solidified and formed, a third strain gauge is set on the upper part of the UHPC concrete, and a fourth strain gauge is set on the upper part of the ordinary concrete. After the third and fourth strain gauges are set, a waterproof layer is laid on the upper part of the UHPC concrete and the ordinary concrete. After the waterproof layer is laid, a fifth strain gauge is set on the upper part of the waterproof layer. After the fifth strain gauge is set, an asphalt layer is laid on the upper part of the waterproof layer. The above strain gauges are all electrically connected to the static data acquisition instrument; S6. Use the old bridge cap beam to press the two first threaded jacks onto the asphalt layer on the left side of the upper part of the new bridge flange plate; S7. Displacement meters are set at the lower part of the upper flange adjacent to the flange plate of the old bridge box girder and the new bridge and at the lower part of the flange plate of the new bridge, and the displacement meters are located on both sides of the widened joint. Displacement meters are set at both ends, mid-span and lower part of 1 / 4 span of the old bridge box girder, and the displacement meters are electrically connected to the static data acquisition instrument; S8, performing experimental load loading; The hydraulic jack is arranged on the upper part of the asphalt layer of the box girder of the old bridge, and the hydraulic jack can realize vertical downward loading on the box girder of the old bridge by using the support of the cap beam of the old bridge; The hydraulic jack is used to conduct graded loading experiments on the box girder of the old bridge. Specifically, the loading load can be controlled according to the downward deflection of the box girder of the old bridge to control the design load and overload. The loading process is: load to the control load in sequence of 20%, 30%, and 50%, and then continue to load until the box girder or the splicing part of the old bridge is damaged. During the loading process, the static data acquisition instrument collects and records the relevant data after each loading; After the above loading experiment is finished, when the old bridge box girder is not damaged but only the splicing part is damaged, all the original splicing materials are cleaned up, and then the above steps S5-S7 are repeated to complete the re-splicing and paving of the splicing part; when the old bridge box girder is damaged but the splicing part is not damaged, the old bridge box girder is transported away by hoisting equipment and the splicing materials on the flange plate of the new bridge are cleaned up, and then an old bridge box girder is reinstalled. After the old bridge box girder is installed, then the above steps S5-S7 are repeated to complete the re-splicing and paving of the splicing part; After the re-splicing and paving are completed, the hydraulic jack is set on the asphalt layer on the upper part of the flange plate of the new bridge. Then, the flange plate of the new bridge is loaded according to the above loading process until the box girder or splicing part of the old bridge is damaged. During the loading process, the static data collector collects and records the relevant data after each loading.

6. The on-site test method for mechanical properties of widened joints of new and old bridges according to claim 5 is characterized in that: A high-definition camera is set near the displacement meter, and the high-definition camera is used to record the change process of the displacement meter reading at all times.

7. The on-site test method for mechanical properties of widened joints of new and old bridges according to claim 6 is characterized by: Draw a grid on the surface of the flange plate of the new bridge and the surface of the box girder of the old bridge on both sides of the widened joint.