Preparation and dismantling method of sandy soil sample connected with three-way bending element probe
By using air-exhaust holes to tightly fit the rubber film and mold cylinder in the preparation of sandy soil samples, and layered and negative pressure, the uneven sample density and necking problems were solved, and efficient and accurate tests were achieved Sample preparation and removal improve the efficiency and accuracy of the three-way bending element probe test.
Patent Information
- Application Number
- CN202411225162.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-03
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2044-09-03
AI Technical Summary
In the prior art, when preparing sandy soil samples, it is difficult to ensure that the rubber film and the mold cylinder are closely fitted, resulting in uneven density of the sample and easily necking on the top, which affects the accuracy and reliability of the test data, and the removal process The final moisture content test was not performed to verify the accuracy of the test.
Through the assembly of the molding mold, the rubber film and the inner wall of the mold cylinder are vacuumed by using the air-exhaust holes to make it fit closely, and the sand and soil are compacted layer by layer. The bending element probe is installed, and negative pressure is applied to ensure the flatness and saturation of the sample. , the final moisture content test is performed during removal to verify the test data.
The uniformity of the sample density is achieved, the difficulty of bending element installation is reduced, the test efficiency and accuracy are improved, and the accuracy and reliability of the test data are ensured.
Smart Images

Figure CN118913852A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bending element testing in geotechnical tests, and in particular relates to a method for preparing and removing a sandy soil sample connected to a three-dimensional bending element probe. Background Art
[0002] Among the many mechanical parameters of soil, the small strain shear modulus (G0 or G max ) is an important mechanical index to characterize soil in a small strain range (usually 0.0001%-0.1%), and is often used in soil stability evaluation and numerical simulation. Soil may cause anisotropy during deposition or loading, which may lead to a small strain shear modulus of soil in the horizontal direction (G max,hh ) and vertical direction (G max,vh and G max,hv ), and accurately describing the anisotropy of the small strain shear modulus of soil is crucial in the analysis of engineering problems mainly based on deformation considerations, such as seismic resistance of underground structures, soil-structure interaction, and deformation prediction of deep foundation pits or tunnel excavation.
[0003] In order to test the small strain shear stiffness of sand samples in different directions and obtain the anisotropy of the samples, the shear wave velocity in the horizontal and vertical directions is usually measured by a triaxial test system in conjunction with a three-way bending element test system to obtain the shear modulus in the horizontal and vertical planes. For clay soil, the sample can be prefabricated, and the bending element fixing cap can be pasted on the rubber film in advance. After the rubber film is put on the sample, the horizontal bending element probe can be inserted into the sample and sealed with a rubber ring. However, for sandy soil, it is necessary to prepare samples directly on the base of the triaxial instrument using the currently commonly used pure cylindrical two-petal or three-petal membrane. The rubber membrane cannot be pasted with the bending element fixing cap in advance, and it is difficult to place the bending element probe after the sample is prepared. Alternatively, holes are dug on the surface of the sample maker, and two pairs of openings are cut in the middle of the rubber membrane to provide space for the bending element fixing cap in advance. The bending element sensor is then fixed to the sample using liquid rubber and the opening is sealed. However, this method cannot achieve vacuum extraction to ensure that the rubber membrane is in close contact with the sample maker, resulting in uneven sample density and prone to necking at the top of the sample, which in turn affects the accuracy and reliability of the test data. In addition, when dismantling samples for ordinary triaxial tests, the samples are generally dismantled directly without performing a final moisture content test, and the test accuracy cannot be verified by combining the data before and after the test. Summary of the invention
[0004] The purpose of the present invention is to provide a method for preparing and removing a sandy soil sample connected to a three-dimensional bending element probe, so as to solve the problems existing in the above-mentioned prior art.
[0005] To achieve the above object, the present invention provides a method for preparing a sandy soil sample connected to a three-dimensional bending element probe, comprising the following steps:
[0006] Step 1, assembly of molding die;
[0007] Step 2: Vacuum the space between the rubber film and the inner wall of the mold tube through the vacuum hole to make the rubber film fit closely with the inner wall of the mold tube;
[0008] Step 3: Add the sand and soil required for the sample into the mold cylinder in batches, compact the sand and soil layer by layer, record the initial mass of the sample, and install the bending element probe at the same time;
[0009] Step 4: Adjust and check the flatness of the sample;
[0010] Step 5, measuring the diameter and height of the sample, calculating the initial volume of the sample, and completing the preparation of the sandy soil sample;
[0011] Step 6: Saturate the sample.
[0012] Preferably, the molding mold includes a three-axis pressure chamber base, a rubber membrane and four arc-shaped mold pieces, the four mold pieces constitute a mold cylinder with a circular cross-section, the side of any mold piece is provided with a semi-circular arc-shaped protrusion, the protrusions of two adjacent mold pieces are spliced together to form a horizontal bending element channel with a cylindrical structure, a vacuum hole is opened on one mold piece, the rubber membrane is radially provided with four ears, the ears are arranged corresponding to the horizontal bending element channel, the rubber membrane is arranged in the mold cylinder, the top end of the three-axis pressure chamber base is inserted into the bottom end of the mold cylinder, and the three-axis pressure chamber base is sealed with the bottom end of the mold cylinder through the rubber membrane and the O-ring.
[0013] Preferably, in step 1, a negative pressure of 80 kPa is applied through the exhaust hole on the mold connected to a vacuum pump.
[0014] Preferably, in step 3, the mass of soil samples in each layer is the same, and the height of the drop of the same compacting hammer and the number of hammer blows in each layer are kept the same; a sleeve is sleeved on the top of the mold tube before the last layer of soil samples is compacted; after each layer of samples is compacted, the surface of the sand is scraped before the next step of compaction.
[0015] Preferably, in step 3, the installed bending element probes include a pair of vertical bending element probes and two pairs of horizontal bending element probes.
[0016] Preferably, before adjusting and inspecting the flatness of the top of the sample, a negative pressure of 20 kPa is applied to the sample by a vacuum pump.
[0017] Preferably, in step 6, saturating the sandy soil sample comprises the following steps:
[0018] Step 1: Install the confining pressure chamber and fill the confining pressure chamber with water and exhaust the air;
[0019] Step 2: Adjust the internal pressure of the sample to 0 kPa, and stabilize the external confining pressure of the sample to 20 kPa. Saturate the sample with CO2, water head and back pressure. When the pore pressure coefficient B value is greater than 0.95, the sample is considered to be fully saturated.
[0020] A method for removing a sandy soil sample connected to a three-dimensional bending element probe, characterized in that it comprises the following steps:
[0021] Step 1, dismantling the confining pressure chamber of the sample after the consolidation and bending element tests;
[0022] Step 2, collecting and weighing the sandy soil samples;
[0023] Step 3: Dry and weigh the collected sand and soil samples.
[0024] Preferably, in step 2, the confining pressure chamber is removed, and the water outside the base of the triaxial pressure chamber and the rubber membrane is wiped dry.
[0025] Preferably, in step 3, the collected samples include sand samples and the residual soil samples on the rubber membrane, the curved element probe, the permeable stone and the filter paper.
[0026] Compared with the prior art, the present invention has the following advantages and technical effects:
[0027] The present invention can ensure that the rubber mold can be close to the inner wall of the mold tube during the sample preparation process, minimize the necking phenomenon at the top of the sample, and ensure the uniformity of the sample; a horizontal bending element can be installed during the sample preparation process, greatly reducing the difficulty of installing the bending element and saving test time; after the sample preparation is completed, a negative pressure of 20kPa is applied to the sample in advance to ensure that the sample can stand upright and reduce the disturbance of the initial structure of the sample by subsequent operations; after the mold tube is removed, the diameter and height of the sample are measured using a vernier caliper to more accurately obtain the initial porosity of the sample; before the sample is saturated, the internal pressure and confining pressure of the sample are adjusted to reduce the influence of the internal and external pressure difference on the initial structure of the sample; and after the test is completed, the initial porosity of the sample is calculated by testing the final water content of the sample, and the initial porosity calculated by two different methods is compared to verify the accuracy and precision of the test. The technical method in the invention can be used to prepare a triaxial sample with high uniformity connected to a three-dimensional bending element probe, which can greatly save test time, improve test efficiency, and ensure test accuracy. BRIEF DESCRIPTION OF THE DRAWINGS
[0028] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments are briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For those of ordinary skill in the art, other drawings can be obtained based on these drawings without creative labor:
[0029] Figure 1 It is a cross-sectional view of the present invention when using the forming die plus sleeve combination to prepare the sample by the layered compaction method;
[0030] Figure 2 This is a schematic diagram of the structure of the forming die plus sleeve combination used in the present invention;
[0031] Among them: 1. Three-axis pressure chamber base; 2. Pressure chamber drain valve; 3. Back pressure valve; 4. Confining pressure valve; 5. O-ring; 6. Permeable stone; 7. Hose clamp; 8. Mold; 9. Rubber membrane; 10. Exhaust hole; 11. Sleeve; 12. Horizontal bending element channel; 13. Vertical bending element probe. DETAILED DESCRIPTION
[0032] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0033] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0034] This embodiment takes a triaxial dry sand sample with a diameter of 50 mm and a height of 100 mm commonly used in a laboratory and connected to a three-dimensional bending element probe as an example to illustrate the technical solution of the present invention.
[0035] The method for preparing and removing a sandy soil sample connected to a three-dimensional bending element probe of the present invention requires the following auxiliary devices in addition to conventional test auxiliary parts such as a permeable stone 6 with a round hole in the middle, filter paper, a compacting hammer, a water-absorbing ball, silicone ester, a vernier caliper, a vertical bending element probe, and a horizontal bending element probe:
[0036] 1) If Figure 1 to Figure 2As shown, the molding mold includes a three-axis pressure chamber base 1, a rubber membrane 9 and four arc-shaped mold pieces 8, the four mold pieces 8 constitute a mold cylinder with a circular cross-section, the side of any mold piece 8 is provided with a semi-circular arc-shaped protrusion, the protrusions of two adjacent mold pieces are spliced together to form a horizontal bending element channel 12 with a cylindrical structure, a suction hole 10 is opened on one mold piece, the rubber membrane 9 is provided with four ears along the radial direction, the ears are arranged corresponding to the horizontal bending element channel 12, the rubber membrane 9 is arranged in the mold cylinder, the top end of the three-axis pressure chamber base 1 is inserted into the bottom end of the mold cylinder, and the three-axis pressure chamber base 1 is sealed with the bottom end of the mold cylinder through the rubber membrane 9 and the O-ring 5; the height of the rubber membrane 9 is slightly greater than the height of the mold piece 8, the diameter of the ear is equal to the inner diameter of the horizontal bending element channel 12, the rubber membrane 9 is integrally formed, which can ensure the sealing of the sample and improve the efficiency of sample preparation.
[0037] 2) The confining pressure chamber and the vacuum pump with adjustable pressure are both commercially available, and the operating principle is based on existing technology.
[0038] Reference Figure 1 to Figure 2 As shown, the method for preparing a sandy soil sample using the above-mentioned forming mold and auxiliary parts includes the following steps:
[0039] Step 1. Clean the base 1 of the three-axis pressure chamber, evenly apply a proper amount of silicone ester on the side of the base 1 of the three-axis pressure chamber, and then place the permeable stone 6 with a round hole in the middle and the filter paper in turn, and use a vernier caliper to measure the thickness of the special rubber membrane 9 with four ears, once at each end, and then put the rubber membrane 9 on the base 1 of the three-axis pressure chamber and tighten it with an O-ring 5; put the four ears of the rubber membrane 9 on the four horizontal curved channels 12 on the mold cylinder respectively, and fix them with small O-rings.
[0040] Step 2: Connect a vacuum pump through the air extraction hole 10 to apply a negative pressure of 80 kPa to the space between the mold tube and the rubber film 9, so that the rubber film 9 is tightly attached to the inner wall of the mold tube.
[0041] Step 3: Samples are prepared by layered compaction, that is, a certain mass of sand is added into the mold cylinder in five batches, and the compaction tool is used to tap evenly. To control the uniformity of the sample, the mass and height of each layer of soil samples are kept the same, and the height of the compaction hammer and the number of hammer strikes are kept the same. After each layer of sample is compacted, the surface of the sand needs to be scraped before the next step of compaction to ensure the continuity of the sample and prevent stratification. When the sample is loaded close to the horizontal bending element channel 12 of the mold, place the bending element probe at the four ears of the rubber membrane 9, and put the four ears on the rubber membrane 9 on the bending element probe respectively, and fasten them with a small O-ring, then pour a certain mass of sample, and compact the next layer of sample. After the last layer of sample is compacted, place a permeable stone on the top of the sample, a top cap with a bending element, turn up the rubber membrane, and fix it on the top cap of the sample with a small O-ring, and record the initial mass m1 of the sample, adjust the vacuum pump pressure to 20kPa, connect the vacuum pump to the back pressure channel of the base 1 of the triaxial pressure chamber, apply a negative pressure of 20kPa to the sample, keep the sample upright, and reduce the disturbance of the subsequent operations to the sample.
[0042] Step 4: Place the micro level on top of the sample, and check and fine-tune the flatness of the sample by observing the vial.
[0043] Step 5. After the sample is leveled, loosen the upper and lower throat clamps of the mold barrel and remove the four mold pieces 8 around the sample; use a vernier caliper to measure the diameters of the sample at the top, middle and bottom respectively, take the average value and subtract twice the thickness of the rubber film 9 to obtain the true diameter (d) of the sample; and the height of both sides of the sample, take the average value (h), which is the true height of the sample, and calculate the initial volume of the sample, where the true diameter of the sample is the average value of the diameter minus twice the thickness of the rubber film.
[0044] Step 6: Install the confining pressure chamber and close the exhaust valve at the top of the confining pressure chamber after the chamber is filled with water and the bubbles are discharged.
[0045] The present invention discloses a method for preparing and removing a sandy soil sample connected to a three-way bending element probe. In order to reduce the impact of the pressure relief process on the initial structure of the sample, the following gradual pressure relief method is adopted: first, close the back-pressure valve 3 and the confining pressure valve 4, adjust the vacuum pump pressure to 10 kPa, connect the confining pressure valve through the outlet pipe of the three-axis confining pressure controller, adjust the confining pressure to 10 kPa, and open the back-pressure valve 3 and the confining pressure valve 4 at the same time after the confining pressure stabilizes. At this time, the negative pressure inside the sample is reduced to 10 kPa, the confining pressure outside the sample is 10 kPa, and the overall pressure of the sample is still 20 kPa; after the pressure inside and outside the sample stabilizes, close the back-pressure valve 3 and the confining pressure valve 4 again, turn off the vacuum pump, adjust the confining pressure to 20 kPa, and after the confining pressure stabilizes, open the back-pressure valve and the hole pressure valve connected to the inside of the sample. Finally, the pressure inside the sample is 0, and the confining pressure outside the sample is 20 kPa.
[0046] Then, according to the conventional triaxial operation, the sample is saturated with CO2, water head and back pressure until the pore pressure coefficient B value is greater than 0.95. The sample is considered to be fully saturated, that is, the preparation of the sandy soil sample connected to the three-way bending element probe is completed, and then consolidation and bending element tests can be carried out.
[0047] The present invention provides a method for removing a sandy soil sample connected to a three-dimensional bending element probe, comprising the following steps:
[0048] Step 1: After the consolidation and bending element test, close the back pressure valve and unload the confining pressure and back pressure in turn. Drain the water in the confining pressure chamber through the pressure chamber drain valve 2, dismantle the confining pressure chamber, and wipe off the moisture on the sample base and rubber membrane.
[0049] Step 2: Prepare a soil sample bowl and weigh the bowl (m2). Remove the sample from the base together with the bottom permeable stone and rubber film, and try to minimize the scattering of the sample inside the rubber mold during this process. Put them all into the bowl, remove the permeable stone and filter paper, and weigh the wet weight of the sample (m3).
[0050] Step 3: Place the soil sample in the bowl into an oven for drying and record the mass of the soil sample after drying (m4). Thus, the final moisture content of the sample w f =(m3-m4) / (m4-m2).
[0051] Evaluation of the test accuracy of a triaxial specimen connected to a three-dimensional bending probe. The specific method is as follows:
[0052] The present invention adopts two methods to verify the accuracy of the test, taking a dry sand sample as an example. First, the initial specific volume v of the sample is calculated using equations (1) and (2) respectively: i , the accuracy of the test is verified by comparing the difference between the two and the average value. Usually when the difference is within ±0.02, it means that the test accuracy is high and the test data is true and reliable.
[0053]
[0054] Among them, v i is the initial specific volume of the sample; G s is the particle specific gravity of the sand sample, which is generally 2.65 for quartz sand; w is the bulk density of water, 9.8kN / m 3 ; γ di is the initial dry bulk density of the sample; w f is the final moisture content of the sample; ε vol It is the volume change of the sample during the consolidation process and can be obtained by the back pressure volume controller of the triaxial apparatus.
[0055] In the description of the present invention, it should be understood that the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.
[0056] The above are only preferred specific implementations of the present application, but the protection scope of the present application is not limited thereto. Any changes or substitutions that can be easily conceived by any technician familiar with the technical field within the technical scope disclosed in the present application should be covered within the protection scope of the present application.
Claims
1. A method for preparing a sandy soil sample connected to a three-dimensional bending element probe, characterized in that: The following steps are involved: Step 1, assembly of molding die; Step 2: Vacuum the space between the rubber film and the inner wall of the mold tube through the vacuum hole; Step 3: Add the soil samples required for the sample into the mold cylinder in batches, complete the compaction of the soil samples layer by layer and record the initial mass of the samples, and install the bending element probe at the same time; Step 4: Adjust and check the flatness of the top of the sample; Step 5, measuring the diameter and height of the sample, and calculating the initial volume of the sample; Step 6: Saturate the sample to complete the preparation of the sandy soil sample.
2. The method for preparing a sandy soil sample connected to a three-dimensional bending element probe according to claim 1 is characterized in that: In the step 1, the molding mold includes a three-axis pressure chamber base, a rubber membrane and four arc-shaped mold pieces, the four mold pieces constitute a mold cylinder with a circular cross-section, the side of any mold piece is provided with a semi-circular arc-shaped protrusion, the protrusions of two adjacent mold pieces are jointly spliced into a horizontal bending element channel of a cylindrical structure, a vacuum hole is opened on one mold piece, the rubber membrane is provided with four ears along the radial direction, the ears are arranged corresponding to the horizontal bending element channel, the rubber membrane is arranged in the mold cylinder, the top end of the three-axis pressure chamber base is inserted into the bottom end of the mold cylinder, and the three-axis pressure chamber base is sealed with the bottom end of the mold cylinder through the rubber membrane and the O-ring.
3. The method for preparing a sandy soil sample connected to a three-dimensional bending element probe according to claim 1, characterized in that: In the step 2, a negative pressure of 80 kPa is applied through the exhaust hole on the mold connected to a vacuum pump.
4. The method for preparing a sandy soil sample connected to a three-dimensional bending element probe according to claim 1, characterized in that: In step 3, the mass of soil samples in each layer is the same, and the height of the drop of the same compacting hammer and the number of hammer blows in each layer are kept the same. Before the last layer of soil samples is compacted, a sleeve is placed on the top of the mold tube. After each layer of samples is compacted, the surface of the soil sample is scraped before the next step of compaction.
5. The method for preparing a sandy soil sample connected to a three-dimensional bending element probe according to claim 1, characterized in that: In step 3, the installed bending element probes include a pair of vertical bending element probes and two pairs of horizontal bending element probes.
6. The method for preparing a sandy soil sample connected to a three-dimensional bending element probe according to claim 1, characterized in that: Before adjusting and checking the flatness of the top of the sample, a negative pressure of 20 kPa is applied to the sample.
7. The method for preparing a sandy soil sample connected to a three-dimensional bending element probe according to claim 1, characterized in that: In step 6, saturating the sandy soil sample comprises the following steps: Step 1: Install a confining pressure chamber and fill the confining pressure chamber with water and exhaust the air; Step 2: Adjust the internal pressure of the sample to 0 kPa, stabilize the external confining pressure of the sample to 20 kPa, saturate the sample with CO2, water head and back pressure, and complete the saturation of the sample when the pore pressure coefficient B value is greater than 0.
95.
8. A method for removing a sandy soil sample connected to a three-dimensional bending element probe, characterized in that: The following steps are involved: Step 1, dismantling the confining pressure chamber of the sample after the consolidation and bending element tests; Step 2: Collect and weigh the samples; Step 3: Dry the collected samples and weigh them.
9. A method for removing a sandy soil sample connected to a three-dimensional bending element probe according to claim 8, characterized in that: In the step 1, after the confining pressure chamber is removed, the water outside the base of the triaxial pressure chamber and the rubber membrane is wiped dry.
10. The method for removing a sandy soil sample connected to a three-dimensional bending element probe according to claim 8, characterized in that: In step 3, the collected samples include sandy soil samples and the rubber membrane, the curved element probe, the permeable stone and the residual soil sample on the filter paper.
Citation Information
Patent Citations
Preparation device and method for cohesionless soil sample for geotechnical test
CN108663249A
Simple shear test remolding soil sample preparation device and preparation method thereof
CN109060476A
Sandy soil sample preparation device suitable for indoor three-way bending element experiment system
CN115931497A
Improved rigid wall permeameter capable of preventing side wall leakage
CN116046628A
Cited By
Device for detecting uniformity of fiber reinforced solidified soil
CN120628846A