Intelligent analysis management and control system for electric slag car
Through the intelligent analysis and control system of fixed and mobile monitoring units in underground engineering, the line of sight, space and communication restrictions of electric slag truck scheduling in underground excavation projects are solved, and comprehensive monitoring of underground environment and dynamic vehicle scheduling is achieved. Optimization improves construction safety and efficiency.
Patent Information
- Application Number
- CN202411086221.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-11-08
AI Technical Summary
In underground excavation projects, traditional electric dump truck scheduling methods face vision limitations, space limitations, communication challenges, safety risks, efficiency problems and environmental impacts. The existing technology is difficult to achieve comprehensive monitoring and real-time data processing, resulting in low construction efficiency and safety hazards.
The intelligent analysis and control system is adopted, combined with a fixed monitoring unit and a mobile monitoring unit, and data analysis and control signal generation are carried out through the processing unit to achieve comprehensive monitoring of the underground engineering environment and dynamic scheduling of vehicle units, enhancing construction safety and efficiency.
It realizes blind spot monitoring of underground projects, improves safety and efficiency during construction, reduces the risks brought about by monitoring blind spots and data processing delays, and provides technical support for intelligent management and safe construction.
Smart Images

Figure CN118915582A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of electric vehicle control and management, and in particular to an intelligent analysis and control system for electric muck trucks. Background Art
[0002] Underground excavation is a common method of subway and tunnel construction, which involves digging and supporting underground to form the required spatial structure. This type of project usually faces complex geological conditions, limited working space and strict construction safety requirements. In underground excavation projects, the dispatch of electric muck trucks is crucial to the construction progress and site safety management.
[0003] Electric muck trucks are key equipment used in underground projects to transport excavated muck to the surface or other designated areas. Their efficient scheduling can significantly improve construction efficiency, reduce construction costs, and ensure a safe working environment. However, due to the closed and complex nature of underground space, traditional methods of dispatching electric muck trucks face the following challenges:
[0004] Limited sight: Underground environments are often poorly lit, which limits operators’ sight and makes real-time monitoring and management of muck trucks difficult;
[0005] Space limitation: Underground working space is limited and often accompanied by complex terrain, which brings additional difficulties to the movement and scheduling of muck trucks;
[0006] Communication challenges: Underground structures may hinder the propagation of radio waves, resulting in weak or unstable communication signals, affecting the timely transmission of dispatch instructions;
[0007] Safety risks: There are many potential safety risks in underground working environments, such as collapse, equipment failure or operational errors, which require the dispatching system of muck trucks to have a high degree of safety and reliability;
[0008] Efficiency issues: Without an intelligent dispatching system, electric muck trucks may be stuck in traffic, run empty, or wait for loading and unloading, affecting construction efficiency;
[0009] Environmental impact: The impact of underground construction on the surrounding environment needs to be minimized, which requires that the dispatch of muck trucks should not only be efficient, but also reduce interference with the surrounding environment;
[0010] Construction progress coordination: The construction progress of underground tunneling projects needs to be closely coordinated with the scheduling of dump trucks to ensure that the project proceeds as planned.
[0011] The prior art rarely focuses on the control of muck trucks for underground projects, and most of them study the scheduling of muck trucks on the ground. For example, CN107507410A discloses a vehicle scheduling method and device for muck trucks, wherein the method includes: obtaining the air quality index of a selected section and the surrounding sections of the selected section, and calculating the air quality difference; obtaining a first threshold, and when the air quality difference is greater than the first threshold, obtaining the number of muck trucks traveling on the selected section within a first selected time, the driving time of each muck truck, the driving time and the driving standardization, so as to establish a relationship model with the air quality difference; and scheduling and controlling the muck trucks according to the relationship model.
[0012] However, for underground projects such as urban subway tunneling projects, traditional monitoring and management methods face many technical challenges. Existing technologies usually rely on manual inspections and fixed cameras for monitoring, but these methods are difficult to fully cover underground spaces, resulting in monitoring blind spots. At the same time, existing monitoring systems are insufficient in processing and analyzing real-time data and are unable to respond to emergencies in a timely manner. The imperfections in driver qualifications and behavior monitoring increase the risk of safety accidents. The problem of communication signal coverage in underground environments also affects the real-time transmission of information. The management and reduction of safety accident risks is an important issue for underground projects, but existing technologies lack an effective intelligent scheduling system, making it difficult to dynamically adjust transportation tasks and driving routes based on real-time data. Insufficient data recording and analysis capabilities limit the possibility of accident analysis and system optimization.
[0013] In addition, on the one hand, there are differences in understanding among those skilled in the art; on the other hand, the applicant studied a large number of documents and patents when making the present invention, but due to space limitations, not all details and contents are listed in detail. However, this does not mean that the present invention does not have the characteristics of these prior arts. On the contrary, the present invention already has all the characteristics of the prior art, and the applicant reserves the right to add relevant prior art to the background technology. Summary of the invention
[0014] The prior art has disclosed a technical solution for accurately monitoring the situation in the tunnel by setting up multiple groups of monitoring parts. For example, the patent document with publication number CN115981219A discloses a high-speed tunnel intelligent monitoring system, including: an external monitoring part and an internal monitoring part, wherein the external monitoring part is configured to obtain the running data of passing vehicles in real time at the tunnel entrance and tunnel exit, and judge whether there is a fault in the tunnel in combination with the acquired running data, and if so, send a control command to the internal monitoring part; the internal monitoring part includes a control part, a fixed monitoring part and a mobile monitoring part, and judges whether there is a fault in the tunnel through external monitoring, and then chooses to use a fixed monitoring or mobile monitoring method according to the situation in the tunnel, thereby greatly improving the efficiency and accuracy of tunnel monitoring. However, the mobile monitoring part in the technical solution is only enabled when the light in the tunnel does not exceed the preset threshold, and assists in accident judgment by capturing sound wave images. This setting method makes the mobile monitoring part operate independently of the fixed monitoring part, and there is no direct connection and control relationship between the two. Although such independence improves the flexibility of monitoring to a certain extent, it also brings an obvious limitation: the mobile monitoring part cannot supplement the area that the fixed monitoring part cannot cover. On the other hand, the technical solution is aimed at the scenario where the vehicle passes through the high-speed tunnel once. In this case, there is no continuous connection relationship between the vehicle and the monitoring system. Since the connection between the vehicle and the monitoring system needs to be established in advance, and the number of vehicles passing through the high-speed tunnel in one direction is huge, this undoubtedly increases the difficulty of establishing a data connection, and also brings a huge burden to the data processing system. This burden will cause delays in data processing, thereby affecting the timeliness and accuracy of tunnel monitoring. Therefore, the technical solution needs to avoid the use of a setting method that directly associates the vehicle with the monitoring part. On the contrary, the scenario of the present invention is a situation where an electric muck truck travels back and forth for a long time in the construction hole of an underground project. Unlike vehicles that pass through a high-speed tunnel once, the activities of an electric muck truck in the construction hole are periodic, which provides conditions for establishing a continuous monitoring connection. By associating the electric muck truck with the monitoring unit of the control system, it can be ensured that it is always within the construction monitoring range. This continuous association not only helps to monitor the working status of the electric muck truck in real time, but also can dynamically adjust its working mode according to the monitoring results, thereby achieving more efficient construction control.
[0015] In view of the deficiencies in the prior art, the present invention provides an intelligent analysis and control system for an electric muck truck to solve at least some of the above-mentioned technical problems.
[0016] The present invention discloses an intelligent analysis and control system for electric muck trucks, which includes: a monitoring unit for acquiring real-time data information in a tunnel of an underground project, including image information; a vehicle unit for moving and transporting muck in the tunnel; and a processing unit for analyzing the data information acquired by the monitoring unit and generating a control signal. The monitoring unit includes a fixed monitoring unit arranged at a specific position in the tunnel and a mobile monitoring unit that can move in the tunnel to cover at least part of the area that the fixed monitoring unit cannot reach. The fixed monitoring unit can be communicatively connected with the processing unit, and can be communicatively connected with the vehicle unit and / or the mobile monitoring unit through a built-in communication component to realize information interaction. The processing unit determines the real-time situation in the tunnel by analyzing the data information to regulate the vehicle unit and / or the mobile monitoring unit, wherein the processing unit can drive the mobile monitoring unit to guide the vehicle unit during the passage period when the vehicle unit passes through a designated location.
[0017] Different from the prior art, the present invention realizes comprehensive monitoring of the environment in the underground engineering tunnel by combining a fixed monitoring unit and a mobile monitoring unit, and optimizes the operation efficiency and safety of the vehicle unit through intelligent analysis and control of the processing unit. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to realize the monitoring of the tunnel environment without blind spots in underground engineering, and how to improve the safety and efficiency in the construction process through real-time data analysis. Specifically, the fixed monitoring unit of the present invention is first responsible for monitoring the main area in the tunnel, while the mobile monitoring unit is responsible for supplementing the area that the fixed monitoring unit cannot cover. The collaborative work of the two ensures that there is no monitoring blind spot in the tunnel. Secondly, the processing unit performs real-time analysis on the data collected by the monitoring unit, and the generated control signal can adjust the operating status of the vehicle unit in real time, such as adjusting the speed, changing the route or suspending the operation, to deal with possible emergencies. The present invention effectively solves the problem of underground engineering monitoring blind spots and insufficient real-time data processing by integrating the functions of the monitoring unit, the vehicle unit and the processing unit. The collaborative work of the fixed monitoring unit and the mobile monitoring unit ensures comprehensive monitoring of all key areas and transition areas in the underground engineering tunnel, eliminating the monitoring blind spots. The processing unit analyzes the monitoring data in real time, and the generated control signal can adjust the operating status of the vehicle unit in real time, improve the ability to respond to emergencies, and enhance the safety of construction. In addition, the present invention also improves the construction efficiency of underground projects, reduces the risks caused by insufficient monitoring or data processing delays, and provides strong technical support for the intelligent management and safe construction of underground projects.
[0018] According to a preferred embodiment, at least some of the mobile monitoring units are configured with motion components for moving within the cave, and these mobile monitoring units can perform monitoring tasks based on planned motion plans within a designated range in response to control signals sent by the processing unit, wherein the range monitored by these mobile monitoring units can at least partially overlap with the key area where the fixed monitoring units are located, so that the mobile monitoring units can interact with the processing units through the built-in communication components of the fixed monitoring units when entering the overlapping area.
[0019] Unlike the prior art, the present invention achieves more flexible and comprehensive monitoring coverage by giving the mobile monitoring unit the ability to move autonomously and enabling it to communicate effectively with the fixed monitoring unit and the processing unit. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to realize dynamic and continuous monitoring of the tunnel environment in underground engineering, and how to improve monitoring efficiency and response speed through intelligent control. Specifically, the motion component equipped with the mobile monitoring unit of the present invention enables it to move flexibly in the tunnel, respond to the control signal of the processing unit, and perform monitoring tasks. Therefore, the mobile monitoring unit of the present invention can not only move autonomously to cover the blind spot of the fixed monitoring unit, but also dynamically adjust its monitoring path and tasks according to the real-time data analysis results of the processing unit, so as to achieve effective coordination with the fixed monitoring unit. This design not only solves the monitoring problem of the area that the fixed monitoring unit cannot cover, but also improves the utilization rate of resources and reduces costs. By partially overlapping the monitoring range of the fixed monitoring unit in the key area, the mobile monitoring unit can realize effective information interaction with the processing unit, thereby enhancing the flexibility and reliability of the monitoring system.
[0020] According to a preferred embodiment, a mobile monitoring unit equipped with a motion component can be equipped with a guiding component to guide the vehicle unit to move along an indicated path by projecting a light area onto the ground at a designated location, wherein the designated location is a location on the road where various interference factors that affect the normal driving of the vehicle unit exist.
[0021] Unlike the prior art, the present invention realizes dynamic guidance of the vehicle unit's driving path by integrating the guidance component into the mobile monitoring unit, especially in areas where interference factors exist. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to provide accurate and real-time navigation guidance for electric muck trucks in the complex and changeable environment of underground engineering to avoid the influence of interference factors on the normal driving of the vehicle. Specifically, the processing unit of the present invention can identify and predict interference factors that may affect the normal driving of the vehicle, such as construction obstacles, uneven road surface or temporary construction areas, and promptly issue instructions to the vehicle unit to avoid these areas through the guidance component. The guidance component of the mobile monitoring unit provides clear path guidance for the vehicle unit by projecting a light area onto the ground, especially at a designated location where interference factors exist. This innovative guidance method improves the navigation accuracy of the vehicle in a complex environment and reduces the risk of driving errors and accidents caused by environmental interference. Therefore, the mobile monitoring unit of the present invention can not only serve as a movable monitoring unit to provide comprehensive dynamic monitoring of the underground engineering construction process, but also serve as a guidance component to provide real-time dynamic path guidance for the vehicle.
[0022] According to a preferred embodiment, the vehicle unit includes a verification component for verifying the driver's identity information. The verification component uses biometric technology to verify the driver's identity. After completing the driver's identity verification, the vehicle unit can receive a driving score related to the driver from the processing unit and execute a corresponding control signal based on the score.
[0023] Unlike the prior art, the present invention realizes accurate verification of driver identity and personalized driving behavior management by integrating biometric technology and driving scoring system into the vehicle unit. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to improve the safety management level of electric dump truck drivers in underground projects, and how to optimize the operating efficiency and safety of vehicles through driver behavior analysis. Specifically, the vehicle unit of the present invention executes corresponding control signals according to the received driving score, such as adjusting the speed limit of the vehicle, starting safety warnings or optimizing the driving route to improve operating efficiency and safety. The verification component of the vehicle unit uses biometric technology to verify the driver's identity, which effectively improves the strictness and safety of driver management. By verifying the driver's identity, the system ensures that only qualified drivers can operate the vehicle, and at the same time receives driving scores related to the driver, further improving the safety and efficiency of vehicle operation.
[0024] According to a preferred embodiment, the processing unit can calculate the driving score based on the degree of match between the driver's historical driving conditions and the driving plan planned in the control signal generated by the driver, and can realize information interaction with the processing unit each time the vehicle unit passes through the communication range of the communication component to determine the degree of match between the current driving conditions and the planned driving plan, thereby adjusting the driving score of the corresponding driver in real time.
[0025] Unlike the prior art, the present invention realizes dynamic evaluation and instant feedback of driver behavior by introducing a real-time driving scoring system and an information interaction mechanism. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to realize real-time monitoring and evaluation of driver behavior in underground projects, and how to motivate drivers to comply with safety regulations and improve driving efficiency by dynamically adjusting driving scores. Specifically, the processing unit calculates the driving score based on the driver's historical driving conditions and the degree of matching of the driving plan planned by the control signal. This real-time evaluation mechanism can motivate the driver to comply with the planned driving plan, improve the standardization of driving behavior, and thus reduce the accident rate. By real-time monitoring of the driver's driving behavior and timely adjusting the driving score, the present invention helps to reduce accidents caused by improper driver operation and improve the construction safety of underground projects.
[0026] According to a preferred embodiment, the processing unit can set a first scoring threshold and a second scoring threshold for the driver's driving score, wherein when the driving score of the driver undergoing identity verification is lower than the first scoring threshold, the processing unit can drive the vehicle unit to maintain the engine off and replace the driver, and the second scoring threshold is set in a manner higher than the first scoring threshold so as to utilize the second scoring threshold to perform graded management of qualified drivers.
[0027] Unlike the prior art, the present invention achieves refined control and safety supervision of driver behavior by introducing a hierarchical management mechanism based on driving scores. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to implement differentiated management measures according to the driver's driving performance, and how to ensure that only drivers who meet safety standards can operate the vehicle through a systematic scoring mechanism. Specifically, the first scoring threshold and the second scoring threshold set by the processing unit of the present invention provide clear classification criteria for the driver's driving performance, making the management measures more targeted. When the driver's driving score is lower than the first scoring threshold, the processing unit can automatically drive the vehicle unit to shut down and force the driver to be replaced, thereby avoiding the safety hazards caused by unqualified drivers. The second scoring threshold is set higher than the first scoring threshold, allowing qualified drivers to be further graded, and providing corresponding incentives or training according to their driving performance to improve the overall driving level. By monitoring the driver's driving score in real time and dynamically adjusting the management measures according to the scoring threshold, the present invention can respond to changes in driver behavior in a timely manner and improve the real-time and effectiveness of construction safety management. The scoring threshold set by the processing unit provides an effective driver classification management method. By classifying the driving scores of the drivers, the system can take corresponding management measures for drivers of different levels, such as replacing the driver when the driving score is lower than the first scoring threshold, which further improves the pertinence and effectiveness of construction safety management. By ensuring that only drivers with good performance operate the vehicle, the present invention helps to reduce construction delays caused by driving errors, thereby improving construction efficiency.
[0028] According to a preferred embodiment, the processing unit is capable of setting drivers whose driving scores are between a first scoring threshold and a second scoring threshold as Category 1 drivers, and setting drivers whose driving scores are higher than the second scoring threshold as Category 2 drivers, wherein the processing unit is capable of determining the planning order based on the order in which the application information of the vehicle units is submitted and / or the driving scores or categories of the corresponding drivers when performing driving plan planning, so that the later planned path can ensure that it does not overlap with the previously planned path in terms of time attributes.
[0029] Unlike the prior art, the present invention realizes the optimized management of underground engineering traffic flow by introducing a dynamic driving scheme planning mechanism based on driver scores and categories. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to reasonably arrange the working time of different drivers in underground engineering to avoid time conflicts and improve construction efficiency. When planning the driving scheme, the processing unit considers the order of application information submission of the vehicle unit and the driving score or category of the driver. This comprehensive consideration method optimizes the planning order of the driving scheme and ensures that there is no overlap in time attributes, thereby improving the orderliness and safety of underground engineering traffic flow. Specifically, the processing unit of the present invention divides the drivers into Class I drivers and Class II drivers according to the driving scores of the drivers. This classification helps to manage the drivers differently. By reasonably arranging the working time of drivers of different categories, the present invention ensures that the later planned path does not overlap with the earlier planned path in terms of time attributes, effectively avoiding potential time conflicts. By optimizing the planning order of the driving scheme, the present invention helps to reduce waiting time and traffic congestion during the construction process and improve construction efficiency.
[0030] According to a preferred embodiment, the processing unit can reserve corresponding fault-tolerant spaces according to the driving scores of the drivers corresponding to different vehicle units when planning the driving plan, so that when the fault-tolerant spaces are taken into consideration, the positions occupied by the vehicle units on the corresponding paths include the positions occupied by the vehicle units themselves and the positions occupied by their fault-tolerant spaces.
[0031] Unlike the prior art, the present invention achieves precise control of the position occupied by the vehicle unit on the path by introducing a tolerance space in the driving plan planning to adapt to the uncertainty of the driver's operation and environmental changes. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to achieve precise path planning for the vehicle unit in underground engineering, while taking into account the uncertainty of the driver's operation and environmental changes, so as to improve the safety and efficiency during the construction process. Specifically, the position occupied by the vehicle unit of the present invention on the path includes the position occupied by itself and the position occupied by its tolerance space. This precise control helps to reduce potential conflicts between vehicles. The lower the driver's driving score, the larger the tolerance space reserved by the processing unit for it. The tolerance space can be understood as the vehicle unit operated by the driver. When traveling along the moving path according to the planned driving plan, there are no other vehicle units in the space within a certain range from the vehicle unit, so that the vehicle unit can avoid collision with other vehicle units even if it slightly deviates from the planned driving plan. The tolerance space reserved by the processing unit for the vehicle unit is dynamically adjusted according to the driver's driving score. This design takes into account the uncertainty of the driver's operation and the influence of environmental changes, provides a greater safety buffer for the vehicle, and reduces the risk of collision.
[0032] According to a preferred embodiment, when the processing unit determines that there is a designated location within an area that is under the responsibility of any mobile monitoring unit based on real-time data information obtained by the mobile monitoring unit, the processing unit can check the driving plans of all vehicle units to determine the vehicle units whose moving paths pass through the designated location, and determine the fault tolerance space of the corresponding vehicle units based on the driving scores of the drivers corresponding to each vehicle unit, thereby calculating the travel time period of each vehicle unit to drive the mobile monitoring unit to be in a guiding state at the designated location within the corresponding travel time period.
[0033] Unlike the prior art, the present invention achieves precise control of the passage time period and fault tolerance space of vehicle units through real-time data analysis and dynamic traffic management. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to achieve precise scheduling of vehicle passage in the complex environment of underground engineering, and how to optimize the safety and efficiency of traffic flow through real-time monitoring and evaluation. Specifically, the processing unit of the present invention checks the driving plans of all vehicle units based on the real-time data information obtained by the mobile monitoring unit, and calculates the passage time period and fault tolerance space of each vehicle unit. This precise time period management ensures the orderly passage of vehicles at designated locations and improves the accuracy and efficiency of traffic management. The fault tolerance space of each vehicle unit is determined based on the driver's driving score. This personalized fault tolerance space setting takes into account the driver's skills and experience, and improves the adaptability and safety of traffic management.
[0034] According to a preferred embodiment, the passage time period is calculated based on the tolerance space of the corresponding vehicle unit, wherein the starting timing point of the passage time period is when the front end of the tolerance space of the corresponding vehicle unit reaches the specified position, and the ending timing point of the passage time period is when the rear end of the tolerance space of the corresponding vehicle unit reaches the specified position.
[0035] Different from the prior art, the present invention determines the travel time period by accurately calculating the fault tolerance space of the vehicle unit, thereby achieving strict control over the vehicle travel time. Based on the above-mentioned distinguishing technical features, the problems to be solved by the present invention may include: how to achieve accurate time management of vehicle travel in underground projects to avoid time conflicts and improve traffic safety in construction areas. Specifically, the calculation method of the travel time period of the present invention is based on the fault tolerance space of the vehicle unit, and provides a clear travel time window for each vehicle unit. This precise time-based management further improves the accuracy of vehicle scheduling, reduces the possibility of congestion and collision, and ensures the smoothness and safety of traffic flow in underground projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0036] Figure 1 It is a hardware connection diagram of an intelligent analysis and control system according to a preferred embodiment of the present invention;
[0037] Figure 2 It is a communication connection schematic diagram of a fixed monitoring unit and a mobile monitoring unit according to a preferred embodiment of the present invention;
[0038] Figure 3 It is a schematic diagram of the configuration of a key area of an intelligent analysis and control system in an underground project according to a preferred embodiment of the present invention;
[0039] Figure 4 It is a schematic diagram of a mobile monitoring unit guiding a vehicle unit at a designated position according to a preferred embodiment of the present invention.
[0040] Reference numerals list
[0041] 100: fixed monitoring unit; 110: communication component; 200: mobile monitoring unit; 210: motion component; 220: storage component; 230: guidance component; 300: vehicle unit; 310: verification component; 400: processing unit. DETAILED DESCRIPTION
[0042] The following is a detailed description with reference to the accompanying drawings.
[0043] like Figure 1 As shown, the present invention discloses an intelligent analysis and control system for electric muck trucks, which includes: one or more monitoring units, used to obtain real-time data information in a tunnel of an underground project, the data information including image information; a vehicle unit 300, used to move and transport muck in the tunnel; a processing unit 400, used to analyze the data information obtained by the monitoring unit and generate a control signal for dispatching the vehicle unit 300.
[0044] Preferably, the monitoring unit may include a fixed monitoring unit 100 and a mobile monitoring unit 200, wherein the fixed monitoring unit 100 may be set at a specific position in the tunnel to obtain image information of a key area where the specific position is located, and the specific position may be, for example, an accident-prone location such as an entrance and exit of a concrete room; the mobile monitoring unit 200 may move in the tunnel to obtain image information of a section of the tunnel, and the section of the tunnel may preferably be a path between any two fixed monitoring units 100 set in the tunnel.
[0045] The fixed monitoring unit 100 can solve the problem of blind monitoring areas in underground engineering environments, especially in key areas such as the entrances and exits of concrete chambers, which are prone to safety accidents due to space limitations and line of sight obstruction. Underground engineering (such as subway dark excavation projects) usually has a long length, and the monitoring range of the fixed monitoring unit 100 is difficult to cover the entire underground engineering. Considering factors such as cost, one or more specific locations can be determined in key areas such as the entrances and exits of concrete chambers, and corresponding fixed monitoring units 100 can be set at at least some of the specific locations. In addition to key areas, underground engineering also includes several transition areas. Although these transition areas are more difficult to cause safety accidents than key areas, there are still certain safety hazards due to factors such as the dim light in the cave and the uneven level and quality of drivers. Especially in the case of people and vehicles working together, the risk of safety accidents will also increase accordingly. Therefore, the mobile monitoring unit 200 set in the present invention mainly solves the monitoring problem of areas that cannot be covered by the fixed monitoring unit 100, and reduces the cost problem caused by the large-scale deployment of fixed monitoring units 100, thereby improving the utilization rate of resources.
[0046] Preferably, the data information acquired by the monitoring unit can be sent to the processing unit 400, so that the processing unit 400 can generate a control signal for dispatching the vehicle unit 300 by analyzing the real-time situation in the current cave. Since it is usually difficult to achieve full coverage of communication signals in underground projects, especially for underground projects with large underground spaces and high complexity, if you want to achieve full coverage of communication signals, you need to consider not only the high installation difficulty caused by factors such as the layout, obstacles, humidity and temperature of the underground project, but also more configuration and maintenance costs. Therefore, the fixed monitoring unit 100 and the processing unit 400 set at a specific position in the cave of the present invention can be connected by wire, and the fixed monitoring unit 100 can be configured with a communication component 110 to achieve communication connection with the mobile monitoring unit 200 and / or the vehicle unit 300 by using the communication component 110. Further preferably, the communication component 110 and the mobile monitoring unit 200 and / or the vehicle unit 300 can be connected wirelessly.
[0047] Such a setting enables the fixed monitoring unit 100 to solve the problem of real-time data transmission and processing, ensure the real-time and accuracy of monitoring information transmission, and utilize the communication component 110 configured in the fixed monitoring unit 100 to achieve communication connection with the mobile monitoring unit 200 and / or the vehicle unit 300, so that the fixed monitoring unit 100 can be used as a transit station for information transmission, solving the problem of difficulty in full coverage of communication information in underground projects.
[0048] Preferably, the mobile monitoring unit 200 and the vehicle unit 300 can both move in the hole of the underground project, and the communication component 110 has a certain communication range. When the mobile monitoring unit 200 and / or the vehicle unit 300 enter the communication range of any communication component 110, the communication component 110 can realize information exchange with the mobile monitoring unit 200 and / or the vehicle unit 300 until the mobile monitoring unit 200 and / or the vehicle unit 300 leave its communication range. For example, Figure 2 It shows the situation that the mobile monitoring unit 200 enters the communication range of the fixed monitoring unit 100. Preferably, the communication component 110 can be built into the fixed monitoring unit 100, or can be independently set at a designated position, wherein the designated position can be, for example, a stop position designated for the mobile monitoring unit 200 and / or the vehicle unit 300. This is because the stop position selected by the mobile monitoring unit 200 and / or the vehicle unit 300 after completing the current task must be within the communication range of any communication component 110, so that the processing unit 400 can flexibly schedule the mobile monitoring unit 200 and the vehicle unit 300 that have not performed the task.
[0049] Preferably, the high-definition camera of the fixed monitoring unit 100 may be equipped with an infrared night vision function to ensure that clear image information can be obtained even in a low-light environment, thereby achieving comprehensive monitoring of key areas and reducing the risk of accidents.
[0050] Preferably, if Figure 3 As shown, the communication range of the fixed monitoring unit 100 can generally cover the key areas of the underground project, so that when the vehicle unit 300 enters the key areas of the underground project, the fixed monitoring unit 100 can send the real-time image information it acquires to the vehicle unit 300, so as to facilitate the vehicle unit 300 to move within the key areas.
[0051] Preferably, the mobile monitoring unit 200 may be configured with a motion component 210 for realizing movement in the cave, wherein the motion component 210 may be, for example, a drone. Preferably, the mobile monitoring unit 200 may move along a predetermined path in a defined area according to a control signal generated by the processing unit 400, and acquire real-time image information in the area during the movement, wherein the mobile monitoring unit 200 may be configured with a storage component 220 for storing the acquired real-time image information according to a time series, and sending the stored real-time image information to the communication component 110 when the mobile monitoring unit 200 enters the communication range of any communication component 110. Preferably, the processing unit 400 may determine the real-time situation in the cave according to the data information acquired by the fixed monitoring unit 100 and / or the mobile monitoring unit 200, and may adjust the movement plan of the mobile monitoring unit 200 accordingly.
[0052] Preferably, part of the mobile monitoring unit 200 can be mounted on the vehicle unit 300, so that when the vehicle unit 300 moves in the cave, it can obtain image information on the path in real time and store it in the storage component 220, so that when the vehicle unit 300 enters the communication range of the communication component 110, the mobile monitoring unit 200 on the vehicle unit 300 can upload the image information in the storage component 220 to the processing unit 400 through the communication component 110.
[0053] Preferably, the main structure of the vehicle unit 300 can be configured as an electric vehicle having a receiving cavity for transporting slag, wherein, based on the electric vehicle, the vehicle unit 300 can also be configured with multiple functions to facilitate safe driving. Preferably, considering factors such as cost, most of the electric vehicles currently used for transporting slag in the tunnel are operated by drivers, and different drivers have different driving habits. Especially for drivers with bad driving habits, driving in a tunnel with insufficient light is prone to traffic accidents.
[0054] Preferably, a verification component 310 for verifying the driver's identity information may be provided in the vehicle unit 300 to ensure that only qualified drivers can operate the vehicle unit 300, thereby improving the safety and efficiency of the vehicle unit 300 during transportation. Preferably, the verification component 310 may use biometric technology to verify the driver's identity, wherein the biometric technology may include fingerprint recognition technology, voiceprint recognition technology, facial recognition technology, etc. Preferably, after the vehicle unit 300 completes the driver's identity recognition using the verification component 310, it may retrieve the driving score related to the driver from the processing unit 400 through the communication component 110, wherein the driving score may be obtained by statistical calculation based on the driver's historical driving situation. Further preferably, the processing unit 400 can calculate the driving score based on the matching degree between the driver's historical driving situation and the driving scheme planned in the control signal generated by it, and the driving score can be used to characterize the driver's compliance with the driving scheme generated by the processing unit 400. Since the processing unit 400 generates a control signal for dispatching the vehicle unit 300 according to the real-time situation in the tunnel, the control signal includes the optimal driving plan for all the vehicle units 300 in the tunnel. The driver only needs to operate the corresponding vehicle unit 300 according to the planned driving plan to avoid most safety accidents. Preferably, the driving score of each driver can be stored in the processing unit 400 and updated in real time, wherein the processing unit 400 can be provided with a first scoring threshold. When the driving score of the driver undergoing identity information verification is lower than the first scoring threshold, the processing unit 400 can drive the vehicle unit 300 to maintain the engine off state and replace the driver. Furthermore, the driver whose driving score is lower than the first scoring threshold needs to reset his driving score after training and assessment before he can obtain the authority to continue to operate the vehicle unit 300.
[0055] Preferably, the vehicle unit 300 that performs the corresponding task in response to the control signal with the driving scheme generated by the processing unit 400 can travel along the predetermined path under the operation of the driver, and realize information interaction with the processing unit 400 each time it passes through the communication range of the communication component 110, so as to determine the matching degree between the current driving situation and the planned driving scheme. Preferably, the timing for the processing unit 400 to determine the matching degree between the current driving situation and the planned driving scheme usually occurs when the vehicle unit 300 enters the communication range of the communication component 110 built into the fixed monitoring unit 100, because the vehicle unit 300 is usually required to slow down when entering the key area where the fixed monitoring unit 100 is located. At this time, the vehicle unit 300 passing at a lower speed has sufficient time to realize information interaction with the processing unit 400 through the communication component 110 built into the fixed monitoring unit 100, and receive the control signal fed back by the processing unit 400.
[0056] Preferably, when the matching degree is low, the processing unit 400 can send a new control signal to the vehicle unit 300 after recalculation, so that the vehicle unit 300 moves according to the driving plan attached to the new control signal, that is, it does not affect the normal operation of other vehicle units 300. This situation usually occurs when the driving speed does not match (for example, speeding). By limiting the speed of the next trip, it can return to the originally planned driving plan to avoid affecting the normal operation of other vehicle units 300. Preferably, when the matching degree is zero, the processing unit 400 can drive the vehicle unit 300 to stop running while ensuring safety, and drive the vehicle unit 300 to continue to complete the task after replanning the driving plan (including the moving path) according to the current real-time situation in the tunnel. This situation usually occurs when the moving path does not match (for example, taking the wrong road). By replanning the path by taking the current stop position as the new starting point, the normal operation of other vehicle units 300 may be affected. The processing unit 400 needs to comprehensively consider all vehicle units 300 when replanning the path. Furthermore, at the end of the next trip, the vehicle unit 300 can again interact with the processing unit 400 through the communication component 110 to re-determine the matching situation. Further, if the vehicle unit 300 has multiple low or zero matching levels while traveling along a planned moving path, the processing unit 400 can perform real-time settlement of the driving score of the driver operating the vehicle unit 300. When the driving score of the driver is lower than the first score threshold after real-time settlement, the processing unit 400 can directly use the communication component 110 to drive the vehicle unit 300 to park on the side of the road to restrict the driver from continuing to operate the vehicle unit 300. Preferably, if the driver has objections to the driving score given by the processing unit 400 (including the driving score settled in real time), the image information and other sensor data obtained by the mobile monitoring unit 200 set on the vehicle unit 300 can be uploaded to the processing unit 400 as evidence, so that the processing unit 400 can judge the rationality of the driving score given by it according to the actual operation of the vehicle unit 300. The above situation may occur in special circumstances such as obstacles suddenly appearing on the planned moving path and requiring emergency obstacle avoidance, or the vehicle unit 300 itself has a fault, so as to avoid misjudgment of the driver due to the influence of special circumstances. Further, when the processing unit 400 confirms that the objection is established, it can give the driver an accurate driving score again.
[0057] Preferably, the processing unit 400 may be provided with a second scoring threshold for the driving score of the driver, wherein the second scoring threshold may be higher than the first scoring threshold, so as to use the second scoring threshold to perform hierarchical management on qualified drivers. Preferably, the driver whose driving score is between the first scoring threshold and the second scoring threshold is set as a first-class driver, and the driver whose driving score is higher than the second scoring threshold is set as a second-class driver. When planning the driving scheme, the processing unit 400 may plan the driving scheme for the vehicle unit 300 operated by the first-class driver first, and then plan the driving scheme for the vehicle unit 300 operated by the second-class driver second, so as to improve the safety of driving in the tunnel, wherein the above situation includes the situation of initially planning the driving scheme and the situation of re-planning the driving scheme. Preferably, when the hierarchical management of the first-class driver and the second-class driver is applied to the driving scheme planning, the processing unit 400 also has differences in the scoring criteria for the first-class driver and the second-class driver, that is, the first-class driver who enjoys the driving scheme planning first has a higher scoring weight than the second-class driver, and when the driving process thereof does not match the expected driving scheme, more driving scores may be deducted.
[0058] Preferably, when the processing unit 400 performs driving plan planning, it can perform sequential planning according to the order in which the application information of the vehicle unit 300 is submitted, or it can perform unified planning after collecting a preset number of application information and / or after a preset time interval, wherein, when performing sequential planning, only the order in which the application information is submitted can be considered to determine the planning order, and the path planned later must ensure that it does not overlap with the path planned earlier in terms of time attributes; when performing unified planning, the order in which the application information is submitted and the driving score or category of the corresponding driver can be combined to determine the planning order, and the path planned later must ensure that it does not overlap with the path planned earlier in terms of time attributes. Preferably, the above-mentioned "no overlap in time attributes" means that at the same time node, the positions occupied by any two vehicle units 300 on the corresponding path do not overlap.
[0059] Preferably, since it is difficult to achieve full coverage of communication signals in underground projects, the control signal generated by the processing unit 400 cannot be transmitted at any time, so that the scheduling plan for the vehicle unit 300 in the tunnel has a lag, and the processing unit 400 cannot immediately complete the regulation of all the vehicle units 300 in the tunnel according to the real-time situation in the tunnel. Therefore, the processing unit 400 needs to complete the optimal planning of all paths in advance, and requires the driver to perform the driving operation as much as possible according to the driving plan planned in the control signal when operating the vehicle unit 300. Further, when planning the driving plan, the processing unit 400 can reserve corresponding fault tolerance space according to the driving scores of the drivers corresponding to different vehicle units 300, wherein the lower the driving score of the driver, the larger the fault tolerance space reserved by the processing unit 400 for it, and the fault tolerance space can be understood as when the vehicle unit 300 operated by the driver moves along the moving path according to the planned driving plan, there are no other vehicle units 300 in the space within a certain range from the vehicle unit 300, so that even if the vehicle unit 300 slightly deviates from the planned driving plan, it can still avoid collision with other vehicle units 300. Preferably, in the case of considering the fault-tolerant space, the position occupied by the vehicle unit 300 on the corresponding path may include the position occupied by the vehicle unit 300 itself and the position occupied by its fault-tolerant space. Therefore, in the case of considering the fault-tolerant space, the above-mentioned "no overlap in time attribute" means that at the same time node, the positions occupied by any two vehicle units 300 themselves on the corresponding path and the positions occupied by their fault-tolerant spaces do not overlap. Preferably, the processing unit 400 can make a secondary judgment on any two vehicle units 300 that are operated by the second type of drivers and have "no overlap in time attributes", wherein, at the same time node, the position occupied by any of the two vehicle units 300 on the corresponding path itself does not overlap with the position occupied by the other vehicle unit 300 on the corresponding path itself and the position occupied by its fault-tolerant space, and the rationality of the driving plan can be recognized and released.
[0060] Preferably, the fault tolerance space reserved by the processing unit 400 for each vehicle unit 300 can be adjusted according to the real-time driving score of the corresponding driver, so that when the fault tolerance space of any vehicle unit 300 changes, the processing unit 400 can determine whether the driving plans of other vehicle units 300 need to be adjusted, wherein whether the driving plan needs to be adjusted can be based on whether the driving plans executed by all current vehicle units 300 meet the condition of "no overlap in time attributes".
[0061] Preferably, if Figure 4As shown, the processing unit 400 can drive the mobile monitoring unit 200 equipped with the motion component 210 to provide guidance at a designated location during the driving of the vehicle unit 300, wherein the designated location can be a location on the road where there are obstacles, construction workers and / or various interference factors that affect the normal driving of the vehicle unit 300. Further, these locations are usually not in the key area and are difficult to be captured by the fixed monitoring unit 100. As in the key area, the fixed monitoring unit 100 cannot send the image information in the key area to the vehicle unit 300 that enters the key area and slows down to pass through the key area through the communication component 110. Therefore, it is necessary for the mobile monitoring unit 200 to guide the vehicle unit 300 before the vehicle unit 300 is about to reach the designated location, so as to avoid safety accidents. Preferably, the mobile monitoring unit 200 may be configured with a guiding component 230, which may guide the vehicle unit 300 to move along the indicated path by projecting a light area onto the ground at a designated position, wherein the light area projected by the guiding component 230 at least avoids interference factors such as the above-mentioned obstacles and construction workers. When the light area on the ground is blocked by new interference factors after the guiding component 230 projects the light area, an alarm may be issued and / or the position of the light area may be adjusted to ensure smooth passage of the vehicle unit 300 in the light area.
[0062] Since the mobile monitoring unit 200 needs to move back and forth within a designated area to collect real-time data information, and the mobile monitoring unit 200 usually does not directly monitor the driving status of the vehicle unit 300, the mobile monitoring unit 200 can neither stay at a designated position for a long time nor autonomously switch the monitoring status and the guiding status according to the real-time position of the vehicle unit 300. Based on this, when the processing unit 400 of the present invention determines that there is a designated location in an area that the mobile monitoring unit 200 is responsible for based on the real-time data information obtained by any mobile monitoring unit 200, it can check the driving plans of all vehicle units 300 to determine the vehicle unit 300 whose moving path needs to pass through the designated location, and determine the fault tolerance space of the corresponding vehicle unit 300 according to the driving score of the driver corresponding to each vehicle unit 300, so as to calculate the passage time period of each vehicle unit 300, so as to drive the mobile monitoring unit 200 to be in a guiding state at the designated location within the corresponding passage time period, wherein the passage time period is calculated based on the fault tolerance space of the corresponding vehicle unit 300, that is, when the front end of the fault tolerance space of the corresponding vehicle unit 300 reaches the designated location, it is the starting timing point of the passage time period, and when the rear end of the fault tolerance space of the corresponding vehicle unit 300 reaches the designated location, it is the ending timing point of the passage time period.
[0063] Preferably, when there are multiple designated locations to be guided in the area that any mobile monitoring unit 200 is responsible for, and these designated locations are passed by different vehicle units 300 at similar times, the processing unit 400 can determine the priority of guidance based on the driving scores of the drivers corresponding to the vehicle units 300 that meet the requirements, so that the mobile monitoring unit 200 can guide the vehicle units 300 operated by the drivers with higher priorities, wherein "passing at similar times" means that the time when different vehicle units 300 pass through the corresponding designated locations is similar, and so similar that it is difficult for the mobile monitoring unit 200 to realize the guidance function for all of these vehicle units 300. Further, the processing unit 400 can assign a higher priority to the vehicle units 300 operated by the drivers with relatively lower driving scores, and assign a lower priority to the vehicle units 300 operated by the drivers with relatively higher driving scores, so that the mobile monitoring unit 200 can give priority to guiding the vehicle units 300 operated by the drivers with relatively lower driving scores, so as to reduce the probability of safety accidents.
[0064] It should be noted that the above-mentioned specific embodiments are exemplary, and those skilled in the art can come up with various solutions inspired by the disclosure of the present invention, and these solutions also belong to the disclosure scope of the present invention and fall within the protection scope of the present invention. Those skilled in the art should understand that the present invention specification and its drawings are illustrative and do not constitute a limitation of the claims. The scope of protection of the present invention is defined by the claims and their equivalents. The present invention specification contains multiple inventive concepts, such as "preferably" or "according to a preferred embodiment", which means that the corresponding paragraph discloses an independent concept, and the applicant reserves the right to file a divisional application based on each inventive concept. Throughout the text, the features guided by "preferably" are only an optional method and should not be understood as a must-have setting. Therefore, the applicant reserves the right to abandon or delete the relevant preferred features at any time.
Claims
1. An intelligent analysis and control system for electric muck trucks, characterized in that: It includes: A monitoring unit, used to obtain real-time data information inside the underground engineering hole, including image information; A vehicle unit (300) for moving in the cave and transporting the soil; A processing unit (400) is used to analyze the data information obtained by the monitoring unit and generate a control signal, The monitoring unit comprises a fixed monitoring unit (100) arranged at a specific position in the tunnel and a mobile monitoring unit (200) capable of moving in the tunnel to cover at least a portion of the area that the fixed monitoring unit (100) cannot reach. The fixed monitoring unit (100) can be connected to the processing unit (400) for communication, and can be connected to the vehicle unit (300) and / or the mobile monitoring unit (200) for communication through a built-in communication component (110) to achieve information exchange. The processing unit (400) determines the real-time situation in the tunnel by analyzing data information to control the vehicle unit (300) and / or the mobile monitoring unit (200), wherein the processing unit (400) can drive the mobile monitoring unit (200) to guide the vehicle unit (300) during the passage period when the vehicle unit (300) passes through a designated position.
2. The system according to claim 1, characterized in that At least some of the mobile monitoring units (200) are configured with motion components (210) for achieving movement in the cave, and these mobile monitoring units (200) can respond to control signals sent by the processing unit (400) and perform monitoring tasks within a defined range based on a planned motion plan, wherein the range that these mobile monitoring units (200) are responsible for monitoring can at least partially overlap with the key area where the fixed monitoring unit (100) is located, so that the mobile monitoring unit (200) can interact with the processing unit (400) through the built-in communication component (110) of the fixed monitoring unit (100) when entering the overlapping area.
3. The system according to claim 1 or 2, characterized in that: The mobile monitoring unit (200) equipped with the motion component (210) can be equipped with a guiding component (230) to guide the vehicle unit (300) to move along an indicated path by projecting a light area onto the ground at a designated location, wherein the designated location is a location on a road where various interference factors that affect the normal travel of the vehicle unit (300) exist.
4. The system according to any one of claims 1 to 3, characterized in that: The vehicle unit (300) comprises a verification component (310) for verifying the identity information of the driver. The verification component (310) uses biometric technology to verify the identity of the driver. After completing the driver identity verification, the vehicle unit (300) can receive a driving score related to the driver from the processing unit (400) and execute a corresponding control signal according to the score.
5. The system according to any one of claims 1 to 4, characterized in that: The processing unit (400) can calculate a driving score based on the matching degree between the driver's historical driving situation and the driving plan planned in the control signal generated by the driver, and can implement information interaction with the processing unit (400) each time the vehicle unit (300) passes through the communication range of the communication component (110) to determine the matching degree between the current driving situation and the planned driving plan, thereby adjusting the driving score of the corresponding driver in real time.
6. The system according to any one of claims 1 to 5, characterized in that: The processing unit (400) can be configured with a first scoring threshold and a second scoring threshold for the driver's driving score, wherein when the driving score of the driver undergoing identity information verification is lower than the first scoring threshold, the processing unit (400) can drive the vehicle unit (300) to maintain the engine off state and replace the driver, and the second scoring threshold is configured in a manner higher than the first scoring threshold, so as to utilize the second scoring threshold to perform graded management on qualified drivers.
7. The system according to any one of claims 1 to 6, characterized in that: The processing unit (400) is capable of setting a driver whose driving score is between a first scoring threshold and a second scoring threshold as a first-category driver, and setting a driver whose driving score is higher than the second scoring threshold as a second-category driver, wherein the processing unit (400) is capable of determining a planning sequence based on the order in which the application information of the vehicle unit (300) is submitted and / or the driving scores or categories of the corresponding drivers when planning a driving plan, so that a later-planned path can be guaranteed not to overlap with a previously-planned path in terms of time attributes.
8. The system according to any one of claims 1 to 7, characterized in that: The processing unit (400) can reserve corresponding fault tolerance spaces according to the driving scores of the drivers corresponding to different vehicle units (300) when planning a driving plan, so that when the fault tolerance spaces are taken into consideration, the positions occupied by the vehicle units (300) on the corresponding paths include the positions occupied by the vehicle units (300) themselves and the positions occupied by their fault tolerance spaces.
9. The system according to any one of claims 1 to 8, characterized in that: The processing unit (400) can check the driving plans of all the vehicle units (300) to determine the existence of a designated location in an area that the mobile monitoring unit (200) is responsible for based on the real-time data information obtained by any mobile monitoring unit (200), so as to determine the vehicle unit (300) whose moving path passes through the designated location, and determine the fault tolerance space of the corresponding vehicle unit (300) based on the driving score of the driver corresponding to each vehicle unit (300), so as to calculate the passing time period of each vehicle unit (300) so as to drive the mobile monitoring unit (200) to be in a guiding state at the designated location within the corresponding passing time period.
10. The system according to any one of claims 1 to 9, characterized in that: The pass time period is calculated based on the tolerance space of the corresponding vehicle unit (300), wherein the start timing point of the pass time period is when the front end of the tolerance space of the corresponding vehicle unit (300) reaches the specified position, and the end timing point of the pass time period is when the rear end of the tolerance space of the corresponding vehicle unit (300) reaches the specified position.