Barge type transfer platform of wharf-free liquefied natural gas floating transmission system

By designing a barge-type transit platform with a floating transmission system without docks, the problem of imperfect monitoring and early warning systems in the floating transmission system without docks is solved, and the safe and efficient transmission of liquefied natural gas is achieved, and the specific design and dynamic compensation control are improved. System realization and security.

CN118928665APending Publication Date: 2024-11-12NINGBO INST OF DALIAN UNIV OF TECH
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411232372.7
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-04
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing dockless floating transmission system has no actual products and applications in China. In particular, the monitoring and early warning system of the floating transmission system is incomplete, and the specific floating transit platform design is lacking, making it difficult to achieve safe and efficient transmission of liquefied natural gas. .

Method used

A barge transfer platform with a dockless liquefied natural gas floating transmission system was designed, including a barge transfer platform with floating structure, equipped with jumper hoses, floating hoses, tower crane systems, reel systems, circulating cooling systems, and flow Pressure sensors, fender systems, ranging sensors, dynamic tension compensation systems and monitoring and early warning systems realize the specific design and dynamic compensation control of the transit platform.

Benefits of technology

Through the specific design and configuration of the transit platform, monitoring and early warning of the liquefied natural gas transmission process and dynamic compensation control are achieved, ensuring the relative stability between the platform and the transport ship, and improving the realization and safety of the transmission system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118928665A_ABST
    Figure CN118928665A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of offshore energy transmission, and discloses a barge type transfer platform of a wharf-free liquefied natural gas floating transmission system, which comprises a barge type transfer platform, the barge type transfer platform is of a floating structure, and the length-width ratio of the deck surface of the barge type transfer platform is 2: 1; a main control room is arranged on the deck surface of the barge type transfer platform; a bridging hose and a floating hose are arranged on the barge type transfer platform, and a tower crane system and a reel system are arranged on the barge type transfer platform. The transfer platform is specifically designed, including arrangement of a platform deck surface, laying and storage of a floating hose, application of an air bridging hose and arrangement of a monitoring and early warning system on the transfer platform; the design of the transfer platform of the wharf-free floating transmission system is more specific, and particularly, the design of the movement state of the transfer platform, monitoring and early warning in the transmission process, dynamic compensation control over relative movement between the transfer platform and a transport ship and the like can be achieved, and the transfer platform is closer to reality and has realizability.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of offshore energy transmission, and in particular to a barge-type transfer platform of a dockless liquefied natural gas floating transmission system. Background Art

[0002] In recent years, liquefied natural gas (LNG) has accounted for an increasingly larger proportion of my country's natural gas imports. Moreover, when my country exploits natural gas in the deep sea, it is generally liquefied and stored in LNG offshore terminals, which are then transported to coastal LNG terminals by LNG tankers. Therefore, coastal ports need to build new LNG terminals, or build new LNG ports in suitable coastal areas. However, the construction of large-scale infrastructure projects, or the shallow draft of ports or their susceptibility to extreme weather, makes the traditional mode of transporting liquefied natural gas from ships to shore-based terminals not ideal.

[0003] The dockless floating transfer system is a floating technology that can safely and efficiently transfer liquefied natural gas between a carrier vessel and an offshore or onshore terminal without a dock.

[0004] The conceptual design idea of ​​the dockless floating transfer system is to use a floating transfer platform that can be freely towed or freely navigated in any sea area as a transfer hub to realize the transportation of LNG from LNG tankers to shore-based terminals;

[0005] However, the domestic dockless floating transmission system is currently at the conceptual design stage, with no corresponding actual products and practical applications;

[0006] The design of the dockless floating transmission system mainly focuses on the design of the low-temperature floating hose and the overall design of the transmission system. There are fewer specific designs for the floating transfer platform, especially the monitoring and early warning system of the floating transmission system is not perfect.

[0007] Therefore, a barge-type transfer platform for a dockless liquefied natural gas floating transmission system is proposed. Summary of the invention

[0008] The object of the present invention is to provide a barge-type transfer platform for a dockless liquefied natural gas floating transmission system to solve the problems raised in the above-mentioned background technology.

[0009] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a barge-type transfer platform of a dockless liquefied natural gas floating transmission system, comprising a barge-type transfer platform for providing transfer for liquefied natural gas from a transport ship to a shore base,

[0010] The barge-type transfer platform is a floating structure, and the length-to-width ratio of the deck surface of the barge-type transfer platform is 2:1;

[0011] The deck of the barge-type transfer platform is provided with a main control room;

[0012] The barge-type transfer platform is equipped with a jumper hose and a floating hose, and is equipped with a tower crane system and a reel system. The tower crane system is located in the middle of the deck of the barge-type transfer platform, and the reel system is arranged at one end of the deck of the barge-type transfer platform along the length direction;

[0013] The front and rear floating hoses on the top of the barge-type transfer platform are symmetrically provided with jumper manifold brackets, and a crossover hose bracket is fixedly provided on one side of the corresponding jumper manifold bracket. A circulating cooling system is provided at the connection between the deck surface of the barge-type transfer platform and the floating hose. The circulating cooling system cools the liquefied natural gas transmitted from the jumper hose to the floating hose. A flow pressure sensor is provided at the interface between the crossover hose and the floating hose. A fender system and a distance sensor are provided on the barge-type transfer platform.

[0014] A fence is arranged at the outer edge of the deck surface of the barge-type transfer platform, and a dynamic tension compensation system and a quick-release cable guide device are arranged on the fence. A ballast tank is fixedly arranged at one end of the deck surface of the barge-type transfer platform away from the reel system, and an uninterruptible backup power supply and lighting system are arranged on the deck surface of the barge-type transfer platform.

[0015] Preferably, the jumper hose is an aerial suspended hose, the floating hose is a floating cryogenic hose, the barge-type transfer platform, together with the jumper hose and the floating hose, constitutes the core transmission component of the dockless floating transmission system, and the barge-type transfer platform itself has a power system, and the power propulsion system is arranged in the bottom cabin.

[0016] Preferably, the ballast tank includes ballast tank 1 and ballast tank 2, and the ballast tank 1 and ballast tank 2 are symmetrically arranged front to back. Ballast pumps are fixedly provided on the front and rear sides of the deck surface of the barge-type transfer platform corresponding to the reel system, and the ballast pumps include ballast pump 1 and ballast pump 2. Water curtain spray systems are arranged on the front and rear sides of the barge-type transfer platform, and the water curtain spray systems include water curtain spray system 1 and water curtain spray system 2.

[0017] Preferably, the deck surface of the barge-type transfer platform is symmetrically provided with a life-saving system and a fire-extinguishing system, the life-saving system includes a life-saving system 1 and a life-saving system 2, and the fire-extinguishing system includes a fire-extinguishing system 1 and a fire-extinguishing system 2.

[0018] Preferably, the deck surface of the barge-type transfer platform is provided with a bell-mouth device on the left side of the corresponding reel system to facilitate the retraction and laying of the jumper hose, the bottom surface of the bell-mouth device is fixedly connected to the deck surface of the barge-type transfer platform, the bottom of the jumper tube manifold bracket is fixedly connected to the deck surface of the barge-type transfer platform, the jumper tube manifold bracket is equipped with rollers, which is conducive to docking with the interface of the LNG transport ship, and the cross-border hose bracket is divided into two, namely, cross-border hose bracket one and cross-border hose bracket two.

[0019] Preferably, a video surveillance system and a posture sensor are arranged on the outside of the top of the main control room, the video surveillance system includes a first video surveillance head and a second video surveillance head, and a control computer is arranged in the main control room to connect the video surveillance system and the posture sensor signals.

[0020] Preferably, the fender system includes fender tube one, fender tube two, fender tube three, fender tube four, fender tube five and fender tube six, and the fender tube one, fender tube two, fender tube three, fender tube four, fender tube five and fender tube six are uniformly installed in sequence on the outer side of the barge-type transfer platform, and the ranging sensor includes ranging sensor one, ranging sensor two, ranging sensor three and ranging sensor four, and the ranging sensor one, ranging sensor two, ranging sensor three and ranging sensor four are all fixedly arranged on the outer edge of the deck surface of the barge-type transfer platform.

[0021] Preferably, the dynamic tension compensation system includes dynamic tension compensation system one, dynamic tension compensation system two, dynamic tension compensation system three and dynamic tension compensation system four, and the quick release cable guide device includes quick release cable guide device one, quick release cable guide device two, quick release cable guide device three and quick release cable guide device four.

[0022] Compared with the prior art, the invention has the following beneficial effects: the barge-type transfer platform of the dockless liquefied natural gas floating transmission system is

[0023] 1) Through the specific design of the transfer platform, including the platform deck layout, the laying and storage of floating hoses, the application of aerial jumper hoses, and the layout of monitoring and early warning systems on the transfer platform; the transfer platform design of the dockless floating transmission system is more specific, especially the design of the movement state of the transfer platform, the monitoring and early warning during the transmission process, and the dynamic compensation control of the relative movement between the transfer platform and the transport ship, which is closer to reality and makes it feasible;

[0024] 2) By utilizing a barge-type transfer platform with a power system, a reel system and a tower crane system that can accommodate floating hoses are loaded. The configuration of the tower crane system makes the operation of the entire system no longer dependent on whether the LNG ship is equipped with a tower crane to complete the docking of the aerial jumper pipe; the reel and floating hose are stored on the platform deck, which is more conducive to the laying and storage of the floating hose, and no longer requires the shore base and the platform to maintain real-time synchronization; the dynamic tension compensation system constrains the relative movement between the platform and the transport ship, and can dynamically adjust the relative movement between the platform and the transport ship in real time to ensure relative stability between the two; the platform deck is equipped with a corresponding monitoring and early warning system, which can process the monitoring data in real time to achieve better early warning effects; the deck layout of the transfer platform is designed in detail, and the design of the core components of the dockless floating transmission system is completed. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a three-dimensional rear top view of the overall structure of the present invention;

[0026] Figure 2 It is a three-dimensional schematic diagram of the overall front structure of the present invention.

[0027] In the figure: barge transfer platform 1, jumper hose 2, floating hose 3, tower crane system 4, reel system 5, bell mouth device 6, jumper manifold bracket 7, crossover hose bracket 8, crossover hose bracket 1 801, crossover hose bracket 2 802, circulating cooling system 9, flow pressure sensor 10, main control room 11, camera monitoring head 1 1201, camera monitoring head 2 1202, attitude sensor 13, fender tube 1 1401, fender tube 2 1402, fender tube 3 1403, fender tube 5 1405, fender tube 6 1406, distance sensor 1 1501, distance sensor 2 1502, distance sensor 3 1503, distance sensor 4 1504, dynamic tension compensation system Unified 1601, dynamic tension compensation system 2 1602, dynamic tension compensation system 3 1603, dynamic tension compensation system 4 1604, quick release cable guide device 1 1701, quick release cable guide device 2 1702, quick release cable guide device 3 1703, quick release cable guide device 4 1704, ballast tank 1 1801, ballast tank 2 1802, ballast pump 1 1901, ballast pump 2 1902, water curtain sprinkler system 1 2001, water curtain sprinkler system 2 2002, life-saving system 1 2101, life-saving system 2 2102, fire extinguishing system 1 2201, fire extinguishing system 3 2203, fire extinguishing system 4 2204, uninterruptible backup power supply 23, lighting system 24. DETAILED DESCRIPTION

[0028] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0029] Embodiment 1:

[0030] See also Figure 1-Figure 2 The present invention provides a technical solution: a barge-type transfer platform of a dockless liquefied natural gas floating transmission system, comprising a barge-type transfer platform 1 for providing a transfer function for liquefied natural gas from a transport ship to a shore base,

[0031] The barge transfer platform 1 is a floating structure, and the length-to-width ratio of the deck surface of the barge transfer platform 1 is 2:1;

[0032] A main control room 11 is provided on the deck of the barge-type transfer platform 1;

[0033] The barge transfer platform 1 is equipped with a jumper hose 2 and a floating hose 3. The barge transfer platform 1 is equipped with a tower crane system 4 and a reel system 5. The tower crane system 4 is located in the middle of the deck surface of the barge transfer platform 1. The reel system 5 is arranged at one end of the deck surface of the barge transfer platform 1 along the length direction.

[0034] The jumper hose 2 is an aerial suspended hose, the floating hose 3 is a floating cryogenic hose, and the barge-type transfer platform 1, the jumper hose 2 and the floating hose 3 form the core transmission component of the dockless floating transmission system. The barge-type transfer platform 1 itself has a power system, and the power propulsion system is configured in the bottom cabin;

[0035] The front and rear floating hoses 3 on the top of the barge transfer platform 1 are symmetrically provided with a jumper manifold bracket 7, and a crossover hose bracket is fixedly provided on one side of the corresponding jumper manifold bracket 7. A circulating cooling system 9 is provided at the connection between the deck surface of the barge transfer platform 1 and the floating hose. The circulating cooling system 9 cools the liquefied natural gas transmitted from the jumper hose 2 to the floating hose 3. A flow pressure sensor 10 is provided at the interface between the crossover hose 2 and the floating hose 3. A fender system and a distance sensor are provided on the barge transfer platform 1.

[0036] A fence is provided on the outer edge of the deck of the barge transfer platform 1, and a dynamic tension compensation system and a quick-release cable guide device are provided on the fence. A ballast tank is fixedly provided on one end of the deck of the barge transfer platform 1 away from the reel system 5. An uninterruptible backup power supply 23 and a lighting system 24 are provided on the deck of the barge transfer platform 1;

[0037] In order to facilitate the reeling and laying of the jumper hose 2, a bell-mouth device 6 is arranged on the left side of the corresponding reel system 5 on the deck of the barge-type transfer platform 1. The bottom of the bell-mouth device 6 is fixedly connected to the deck of the barge-type transfer platform 1. The bottom of the jumper manifold bracket 7 is fixedly connected to the deck of the barge-type transfer platform 1. The jumper manifold bracket 7 is equipped with rollers, which is convenient for docking with the interface of the LNG transport ship. There are two cross-border hose brackets, namely, cross-border hose bracket 1 801 and cross-border hose bracket 2 802; a camera monitoring system and a posture sensor 13 are arranged on the outside of the top of the main control room 11. The camera monitoring system includes a camera monitoring head 1201 and a camera monitoring head 2 1202. A control computer is arranged in the main control room 11 to connect the camera monitoring system and the posture sensor 13 signals.

[0038] Furthermore, this embodiment utilizes a barge-type transfer platform 1 with a power system, loads a reel system 5 and a tower crane system 4 that can accommodate a floating hose 3, and the configuration of the tower crane system 4 makes the operation of the entire system no longer dependent on whether a tower crane is configured on the LNG ship to complete the docking of the aerial jumper pipe; the reel and the floating hose 3 are stored on the platform deck, which is more conducive to the laying and storage of the floating hose 3, and no longer requires the shore base and the platform to maintain real-time synchronization; the dynamic tension compensation system 16 constrains the relative movement between the platform and the transport ship, and can dynamically adjust the relative movement between the platform and the transport ship in real time to ensure relative stability between the two; the platform deck is arranged with a corresponding monitoring and early warning system, which can process the monitoring data in real time to achieve a better early warning effect; the deck layout of the transfer platform is designed in detail, and the design of the core components of the dockless floating transmission system is completed;

[0039] Furthermore, this embodiment makes the transfer platform design of the dockless floating transmission system more specific by carrying out specific design of the transfer platform, including the platform deck surface layout, the laying and storage of the floating hose 3, the application of the aerial jumper hose 2, and the layout of the monitoring and early warning system on the transfer platform. In particular, the design of the transfer platform can be made more specific, especially the motion state of the transfer platform, the monitoring and early warning during the transmission process, and the dynamic compensation control of the relative motion between the transfer platform and the transport ship, which is closer to reality and makes it feasible.

[0040] Embodiment 2

[0041] See also Figure 1-Figure 2 , and based on the first embodiment, further obtain:

[0042] The ballast tank includes a ballast tank 1 1801 and a ballast tank 2 1802, which are symmetrically arranged front and back. Ballast pumps are fixedly arranged on the front and rear sides of the corresponding reel system 5 on the deck surface of the barge-type transfer platform 1. The ballast pumps include a ballast pump 1901 and a ballast pump 2 1902. Water curtain spray systems are arranged on the front and rear sides of the barge-type transfer platform 1. The water curtain spray systems include a water curtain spray system 1 2001 and a water curtain spray system 2 2002. The life-saving system and the fire-extinguishing system are symmetrically arranged on the deck surface of the barge-type transfer platform 1. The life-saving system includes a life-saving system 1 2101 and a life-saving system 2102. The fire-extinguishing system includes a fire-extinguishing system 1 2201 and a fire-extinguishing system 2.

[0043] The fender system includes a fender tube 1401, a fender tube 2 1402, a fender tube 3 1403, a fender tube 4, a fender tube 5 1405 and a fender tube 6 1406, which are uniformly installed on the outer side of the barge-type transfer platform 1 in sequence, and the distance measuring sensor includes a distance measuring sensor 1 1501, a distance measuring sensor 2 1502, a distance measuring sensor 3 1503 and a distance measuring sensor 4 1504, which are fixedly installed on the outer edge of the deck surface of the barge-type transfer platform 1;

[0044] The dynamic tension compensation system includes dynamic tension compensation system 1 1601, dynamic tension compensation system 2 1602, dynamic tension compensation system 3 1603 and dynamic tension compensation system 4 1604, and the quick release cable guide device includes quick release cable guide device 1 1701, quick release cable guide device 2 1702, quick release cable guide device 3 1703 and quick release cable guide device 4 1704.

[0045] When in use, by utilizing the barge-type transfer platform 1 with a power system, a reel system 5 and a tower crane system 4 that can accommodate the floating hose 3 are loaded. The configuration of the tower crane system 4 makes the operation of the entire system no longer depend on whether the LNG ship is equipped with a tower crane to complete the docking of the aerial jumper pipe; the reel and the floating hose 3 are stored on the platform deck, which is more conducive to the laying and storage of the floating hose 3, and it is no longer necessary to keep the shore base and the platform synchronized in real time; the dynamic tension compensation system 16 constrains the relative movement between the platform and the transport ship, and can dynamically adjust the relative movement between the platform and the transport ship in real time to ensure relative stability between the two; the corresponding monitoring and early warning system is arranged on the platform deck, which can process the monitoring data in real time to achieve better early warning effect; the deck layout of the transfer platform is designed in detail, and the design of the core component of the dockless floating transmission system is completed.

[0046] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A barge-type transfer platform for a dockless liquefied natural gas floating transmission system, comprising a barge-type transfer platform (1) for providing a transfer function for liquefied natural gas from a transport ship to a shore base, The barge-type transfer platform (1) is a floating structure, and the length-to-width ratio of the deck surface of the barge-type transfer platform (1) is 2:1; The deck surface of the barge-type transfer platform (1) is provided with a main control room (11); The barge-type transfer platform (1) is provided with a jumper hose (2) and a floating hose (3), and is characterized in that: The barge-type transfer platform (1) is provided with a tower crane system (4) and a reel system (5), wherein the tower crane system (4) is located in the middle of the deck surface of the barge-type transfer platform (1), and the reel system (5) is arranged at one end of the deck surface of the barge-type transfer platform (1) in the length direction; The front and rear floating hoses (3) on the top of the barge-type transfer platform (1) are symmetrically provided with jumper manifold brackets (7), and a crossover hose bracket is fixedly provided on one side of the jumper manifold bracket (7). A circulating cooling system (9) is provided on the deck of the barge-type transfer platform (1) at the connection with the floating hose. The circulating cooling system (9) cools the liquefied natural gas transmitted from the jumper hose (2) to the floating hose (3). A flow pressure sensor (10) is provided at the interface between the crossover hose (2) and the floating hose (3). A fender system and a distance sensor are provided on the barge-type transfer platform (1); The deck surface of the barge-type transfer platform (1) is provided with a fence at the outer edge, and a dynamic tension compensation system and a quick-release cable guide device are provided on the fence. A ballast tank is fixedly provided at one end of the deck surface of the barge-type transfer platform (1) away from the reel system (5). The deck surface of the barge-type transfer platform (1) is provided with an uninterruptible backup power supply (23) and a lighting system (24).

2. The barge-type transfer platform of the dockless liquefied natural gas floating transmission system according to claim 1, characterized in that: The jumper hose (2) is an aerial suspended hose, the floating hose (3) is a floating low-temperature hose, and the barge-type transfer platform (1) is matched with the jumper hose (2) and the floating hose (3) to form the core transmission component of the dockless floating transmission system. The barge-type transfer platform (1) itself has a power system, and the power propulsion system is arranged in the bottom cabin.

3. The barge-type transfer platform of the dockless liquefied natural gas floating transmission system according to claim 1, characterized in that: The ballast tank comprises ballast tank 1 (1801) and ballast tank 2 (1802), and the ballast tank 1 (1801) and ballast tank 2 (1802) are symmetrically arranged front and back. Ballast pumps are fixedly arranged on the front and back sides of the deck surface of the barge-type transfer platform (1) corresponding to the reel system (5), and the ballast pumps comprise ballast pump 1 (1901) and ballast pump 2 (1902). Water curtain spray systems are arranged on the front and back sides of the barge-type transfer platform (1), and the water curtain spray systems comprise water curtain spray system 1 (2001) and water curtain spray system 2 (2002).

4. The barge-type transfer platform of the dockless liquefied natural gas floating transmission system according to claim 1, characterized in that: The deck surface of the barge-type transfer platform (1) is symmetrically provided with a life-saving system and a fire-extinguishing system, wherein the life-saving system comprises a life-saving system 1 (2101) and a life-saving system 2 (2102), and the fire-extinguishing system comprises a fire-extinguishing system 1 (2201) and a fire-extinguishing system 2.

5. The barge-type transfer platform of the dockless liquefied natural gas floating transmission system according to claim 1, characterized in that: The deck surface of the barge-type transfer platform (1) is provided with a bell-mouth device (6) on the left side of the corresponding reel system (5) to facilitate the reeling and laying of the jumper hose (2); the bottom surface of the bell-mouth device (6) is fixedly connected to the deck surface of the barge-type transfer platform (1); the bottom of the jumper tube manifold bracket (7) is fixedly connected to the deck surface of the barge-type transfer platform (1); the jumper tube manifold bracket (7) is provided with rollers to facilitate docking with the interface of the LNG transport ship; the jumper hose bracket is divided into two, namely, a jumper hose bracket 1 (801) and a jumper hose bracket 2 (802).

6. The barge-type transfer platform of the dockless liquefied natural gas floating transmission system according to claim 1, characterized in that: A video monitoring system and a posture sensor (13) are arranged on the outside of the top of the main control room (11), and the video monitoring system includes a video monitoring head 1 (1201) and a video monitoring head 2 (1202). A control computer is arranged in the main control room (11) and is connected to the video monitoring system and the posture sensor (13) by signals.

7. The barge-type transfer platform of the dockless liquefied natural gas floating transmission system according to claim 1, characterized in that: The fender system comprises a fender tube 1 (1401), a fender tube 2 (1402), a fender tube 3 (1403), a fender tube 4, a fender tube 5 (1405) and a fender tube 6 (1406). The fender tube 1 (1401), the fender tube 2 (1402), the fender tube 3 (1403), the fender tube 4, the fender tube 5 (1405) and the fender tube 6 (1406) are uniformly installed on the outer side of the barge-type transfer platform (1) in sequence. The distance measuring sensor comprises a distance measuring sensor 1 (1501), a distance measuring sensor 2 (1502), a distance measuring sensor 3 (1503) and a distance measuring sensor 4 (1504). The distance measuring sensor 1 (1501), the distance measuring sensor 2 (1502), the distance measuring sensor 3 (1503) and the distance measuring sensor 4 (1504) are all fixedly arranged on the outer edge of the deck surface of the barge-type transfer platform (1).

8. The barge-type transfer platform of the dockless liquefied natural gas floating transmission system according to claim 1, characterized in that: The dynamic tension compensation system includes dynamic tension compensation system one (1601), dynamic tension compensation system two (1602), dynamic tension compensation system three (1603) and dynamic tension compensation system four (1604), and the quick release cable guide device includes quick release cable guide device one (1701), quick release cable guide device two (1702), quick release cable guide device three (1703) and quick release cable guide device four (1704).