Self-climbing construction elevator with upper machine room in building
By adopting the design of a built-in computer room self-climbing construction elevator in super high-rise buildings, and using the combined structure of the elevator guide rail installation platform and lifting platform, the problems of safety and efficiency of external construction elevators in super high-rise buildings are solved, achieving high efficiency , safe construction and transportation, and reduce equipment costs.
Patent Information
- Application Number
- CN202411244793.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-05
- Publication Date
- 2024-11-12
AI Technical Summary
The existing plug-in construction elevators have problems such as low safety factor, low transportation efficiency, large power consumption and facade damage in the construction of super high-rise buildings, which is difficult to meet the construction needs of super high-rise buildings.
Design a self-climbing construction elevator in the upper computer room inside the building, adopting the elevator guide rail installation platform, lifting platform and mobile computer room structure. The elevator self-climbing of the elevator is achieved through fixed pulleys, pulley wire ropes and rated load cable climbers. 6 are used during the lifting process. : 1. The rope winding method improves speed and safety.
It realizes safe and efficient construction elevator transportation in super high-rise buildings, reduces equipment costs, avoids facade damage, and improves construction efficiency and climbing speed.
Smart Images

Figure CN118929380A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of elevators, and in particular to a self-climbing construction elevator with a machine room located above a building. Background Art
[0002] With the rapid development of the construction industry, there are more and more high-rise and super high-rise buildings. When building super high-rise office buildings, external construction elevators are usually used to transport personnel and materials. This model has the following problems:
[0003] First, the safety factor is not high. The external construction elevator has the risk of overturning due to its own structural problems and must be stopped when encountering strong winds and rainstorms;
[0004] Second, the transportation efficiency is not high. Compared with elevators, external construction elevators have a slow transportation speed and cannot reach underground floors.
[0005] Third, since there is usually no equipment such as frequency converter, the power consumption is large and the cost is high;
[0006] Fourth, the fixed external elevator needs to destroy the building facade. After the building is built, it is time-consuming and labor-intensive to repair the facade. Therefore, the present invention proposes a solution of replacing the external construction elevator with a self-climbing construction elevator in the upper machine room of the building to solve the above problems for customers and general contractors. Summary of the invention
[0007] The purpose of the present invention is to provide a self-climbing construction elevator with a machine room located above a building, which has a high safety factor, high transportation efficiency and faster climbing speed.
[0008] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a self-climbing construction elevator with a machine room installed in a building, comprising an elevator shaft and an elevator guide rail installation platform, the inner wall of the elevator shaft is provided with elevator guide rails, a lifting platform is provided below the elevator guide rail installation platform, a mobile machine room is provided below the lifting platform, and an elevator system is provided below the mobile machine room.
[0009] The elevator guide rail mounting platform includes a load-bearing hanging beam, a fixed pulley is provided on the outer wall of the load-bearing hanging beam, a pulley wire rope is slidably connected to the outer wall of the fixed pulley, the fixed pulley is connected to a first supporting steel frame through the pulley wire rope, a first telescopic steel beam is provided on the top outer wall of the first supporting steel frame, and a first rated load cable climber is provided on the inner wall of the first supporting steel frame.
[0010] The lifting platform comprises a lifting base, a second supporting steel frame is welded to the top outer wall of the lifting base, a second rated load cable climber is arranged on the top outer wall of the lifting base, and a first wire rope drum is arranged on the top outer wall of the lifting base;
[0011] The mobile machine room comprises a control platform and a host platform. The control platform is arranged above the host platform, and an elevator control cabinet is fixedly connected to the inner wall of the control platform.
[0012] Preferably, a sliding block is provided on the bottom outer wall of the first supporting steel frame, and the elevator guide rail mounting platform is slidably connected to the elevator guide rail via the sliding block.
[0013] Preferably, a guide shoe is fixedly connected to the outer wall of the lifting base, and the lifting platform is slidably connected to the elevator guide rail via the guide shoe.
[0014] Preferably, a protective top is fixedly connected to the top outer wall of the control platform, and a pulley block is provided on the top outer wall of the protective top. The pulley block is connected to a steel wire rope on a second rated load cable climber of the upper lifting platform to form a lifting system.
[0015] Preferably, outer walls of the control platform and the host platform are fixedly connected with second telescopic support steel beams, and the second telescopic support steel beams are arranged around the bottom of the control platform and the host platform.
[0016] Preferably, a third rated load cable climber is fixedly connected to the inner wall of the control platform and located on one side of the elevator control cabinet, and a second wire rope drum is provided on the inner wall of the control platform.
[0017] Preferably, a traction machine support beam is fixedly connected between the inner walls of the main engine platform, and a traction machine is fixedly connected to the top outer wall of the traction machine support beam.
[0018] Preferably, the elevator system includes an elevator car, an electric hoist is fixedly connected to the bottom outer wall of the main engine platform, the main engine platform is connected to the elevator car through the electric hoist, a counterweight is provided on one side of the elevator car, and the counterweight is connected to the elevator car through a traction rope via a traction wheel.
[0019] Preferably, the steel wire rope of the first rated load cable climber is wound in a 2:1 manner, and the steel wire rope of the second rated load cable climber is wound in a 6:1 manner.
[0020] Compared with the related art, the self-climbing construction elevator with a machine room in a building provided by the present invention has the following beneficial effects:
[0021] 1. The present invention provides a self-climbing construction elevator with an upper machine room in a building. Compared with the common construction elevator with a lower machine room and a shaft, the present invention adopts the structure of an upper machine room, and is applicable to the hoisting height of the shaft without restriction, which meets the construction requirements of super high-rise elevators. In addition, super high-rise buildings generally cannot meet the requirements of the construction elevator with a lower machine room, which requires opening holes on the shear wall on the side of the pit and reserving machine room space.
[0022] 2. Compared with the upper machine room shaft construction elevator using hydraulic jacking mode, the cable climber and pulley assembly lifting equipment used in the present invention has lower cost, no need to contact the general contractor in advance to leave holes on the shaft wall, and a single climb has a greater height and faster speed, thereby improving the efficiency of building construction.
[0023] 3. Compared with the upper machine room shaft construction elevator which also uses cable climbers and pulley blocks, the present invention uses a lifting platform instead of using the elevator guide rail as a lifting load-bearing device, making the lifting process more stable and safe. In addition, 6:1 rope winding is used instead of 8:1 rope winding, and the climbing speed is faster. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a schematic diagram of the overall structure of the present invention;
[0025] Figure 2 It is a schematic diagram of the structure of the present invention in an elevator shaft;
[0026] Figure 3 It is a partial structural schematic diagram of the present invention;
[0027] Figure 4 This is a schematic diagram of the structure of the elevator guide rail installation platform of the present invention;
[0028] Figure 5 It is a schematic diagram of the structure of the lifting platform of the present invention;
[0029] Figure 6 It is a structural schematic diagram of the mobile machine room of the present invention.
[0030] In the figure: 1, elevator shaft; 2, elevator guide rail; 3, elevator guide rail installation platform; 301, load-bearing hanging beam; 302, fixed pulley; 303, pulley wire rope; 304, first supporting steel frame; 305, first rated load cable climber; 306, slider; 307, first telescopic steel beam; 4, lifting platform; 401, lifting base; 402, second supporting steel frame; 403, second rated load cable climber; 404, first Wire rope drum; 5. Mobile machine room; 501. Control platform; 502. Main machine platform; 503. Protective roof; 504. Pulley block; 505. Second telescopic support steel beam; 506. Elevator control cabinet; 507. Third rated load cable climber; 508. Second wire rope drum; 509. Traction machine support beam; 510. Traction machine; 6. Elevator system; 601. Car; 602. Electric hoist; 603. Counterweight. DETAILED DESCRIPTION
[0031] The technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments; based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the present invention.
[0032] Embodiment 1:
[0033] See also Figure 1-3 The present invention provides a technical solution: a self-climbing construction elevator with a machine room installed in a building, comprising an elevator shaft 1 and an elevator guide rail installation platform 3, the inner wall of the elevator shaft 1 is provided with an elevator guide rail 2, a lifting platform 4 is provided below the elevator guide rail installation platform 3, a mobile machine room 5 is provided below the lifting platform 4, and an elevator system 6 is provided below the mobile machine room 5.
[0034] The elevator guide rail installation platform 3, the lifting platform 4, the mobile machine room 5, and the elevator system 6 are described in detail below.
[0035] See also Figure 4 The elevator guide rail installation platform 3 includes a load-bearing hanging beam 301, the outer wall of the load-bearing hanging beam 301 is provided with a fixed pulley 302, the outer wall of the fixed pulley 302 is slidably connected with a pulley wire rope 303, the fixed pulley 302 is connected to a first supporting steel frame 304 through the pulley wire rope 303, the top outer wall of the first supporting steel frame 304 is provided with a first telescopic steel beam 307, the inner wall of the first supporting steel frame 304 is provided with a first rated load cable climber 305, the bottom outer wall of the first supporting steel frame 304 is provided with a slider 306, and the elevator guide rail installation platform 3 is slidably connected to the elevator guide rail 2 through the slider 306.
[0036] In this embodiment, the first part is the elevator guide rail installation platform 3. The main function of the elevator guide rail installation platform 3 is to install the elevator guide rail 2 within the climbing range. All platforms and elevator systems run on the elevator guide rail 2. The main structure of the elevator guide rail 2 guide rail installation platform 3 is an aluminum alloy construction platform conventionally used in elevator installation. The power output is a 1000kg first rated load cable climber 305. A load-bearing hanging beam 301 and a fixed pulley 302 for the reverse rope of the first rated load cable climber 305 are fixed above the elevator guide rail 2 installation platform. The first rated load cable climber 305 wire rope adopts a 2:1 rope winding method.
[0037] See also Figure 5The lifting platform 4 includes a lifting base 401, the outer wall of the lifting base 401 is fixedly connected with a guide shoe, the lifting platform 4 is slidably connected to the elevator guide rail 2 through the guide shoe, the top outer wall of the lifting base 401 is welded with a second supporting steel frame 402, the top outer wall of the lifting base 401 is provided with a second rated load cable climber 403, and the top outer wall of the lifting base 401 is provided with a first wire rope drum 404.
[0038] In this embodiment, the second part is a lifting platform 4, and the main function of the lifting platform 4 is to lift the mobile machine room 5 below. The main structure of the lifting platform 4 is a lifting base 401, and the lifting platform 4 can run on the elevator guide rail 2 through a guide shoe, and is equipped with a retractable support steel beam. A 2000kg second rated load cable climber 403 is fixed on the lifting platform 4, which serves as a power output device for lifting the mobile machine room 5 below through a pulley block 504.
[0039] See also Figure 5 The mobile machine room 5 includes a control platform 501 and a host platform 502. The control platform 501 is arranged above the host platform 502. The inner wall of the control platform 501 is fixedly connected with an elevator control cabinet 506. The top outer wall of the control platform 501 is fixedly connected with a protective roof 503. The top outer wall of the protective roof 503 is provided with a pulley block 504. The pulley block 504 is connected with the steel wire rope on the second rated load climbing cable 403 of the upper lifting platform 4 to form a lifting system. The outer wall of the control platform 501 and the host platform 502 are connected to each other. The walls are fixedly connected with a second telescopic support steel beam 505, which is arranged around the bottom of the control platform 501 and the main platform 502. The inner wall of the control platform 501 and one side of the elevator control cabinet 506 is fixedly connected with a third rated load cable climber 507. The inner wall of the control platform 501 is provided with a second wire rope drum 508. The inner walls of the main platform 502 are fixedly connected with a traction machine support beam 509, and the top outer wall of the traction machine support beam 509 is fixedly connected with a traction machine 510.
[0040] In this embodiment, the third part is the mobile machine room 5. The function of the mobile machine room 5 is the same as that of a conventional elevator machine room, providing power output and control for the normal operation of the elevator system 6 below. The mobile machine room can be divided into two parts: the upper part is the control platform 501, and the lower part is the host platform 502. The protective top 503 set on the upper layer of the control platform 501 can prevent foreign objects from falling above the shaft. A pulley block 504 is also set on the protective top 503, and the pulley block 504 is connected with the steel wire rope of the second rated load cable climber 403 of the upper lifting platform 4 to form a lifting system, which adopts 6:1 rope winding. The control platform 501 is installed with electrical equipment such as the elevator control cabinet 506, the second steel wire rope drum 508, and the elevator accompanying cable fixing bracket; the host platform 502 is installed with the elevator traction machine 510, the traction machine support beam 509, the speed limiter, the rope head and other conventional elevator machine room equipment, and a telescopic support steel beam is configured.
[0041] See also Figure 6 The elevator system 6 includes an elevator car 601, an electric hoist is fixedly connected to the bottom outer wall of the main platform 502, the main platform 502 is connected to the elevator car 601 through the electric hoist, a counterweight 602 is arranged on one side of the elevator car 601, and the counterweight 602 is connected to the elevator car 601 through a traction rope via a traction wheel.
[0042] In this implementation scheme, the fourth part is the elevator system 6, which has the same structure as a conventional elevator system. During the building construction process, it can efficiently transport construction personnel and materials, and adjust the lifting height synchronously with the climbing of the equipment above. When the building is completed, the equipment will be delivered to the customer as a permanent elevator.
[0043] Embodiment 2:
[0044] See also Figure 1-6 On the basis of the first embodiment, the present invention provides a technical solution: a self-climbing construction elevator with a machine room installed in a building, comprising an elevator shaft 1, an elevator guide rail 2, an elevator guide rail mounting platform 3, a lifting platform 4, a lifting platform 4, a mobile machine room 5, and an elevator system 6. It is possible to consider increasing the rated load and the rope winding ratio of the cable climber supporting the guide rail mounting platform. Under the premise of ensuring safe construction, the lifting platform and the guide rail mounting platform are integrated into one, so as to further reduce the number of equipment and improve the climbing efficiency.
[0045] Working principle: The whole system of the present invention can climb upwards synchronously multiple times as the building is constructed. The single climbing process is as follows:
[0046] The first step is to use the elevator guide rail installation platform 3 to install the elevator guide rail 2 of the climbing part, then move the elevator guide rail installation platform 3 to the position adjacent to the lifting platform 4, connect the elevator guide rail installation platform 3 and the lifting platform 4 with a sling, operate the lifting platform 4 to retract the steel beam, and the elevator guide rail installation platform 3 drives the lifting platform 4 to climb upward to the designated position, and operate the lifting platform 4 to extend the steel beam. The two ends of the steel beam are respectively fixed to the ground at the hall door and the rear wall support bracket.
[0047] The second step is to operate the 2000kg second rated load cable climber 403 fixed on the lifting platform 4, and lift the entire mobile machine room 5 (including the main platform 502 and the control platform 501) through the 6:1 rope pulley group 504. When the lifting work starts, the second telescopic support steel beam 505 at the bottom of the main platform 502 is retracted. After the mobile machine room 5 is lifted into place, the second telescopic support steel beam 505 of the main platform 502 is extended. The two ends of the second telescopic support steel beam 505 are respectively fixed to the ground at the hall door and the rear wall support bracket.
[0048] The third step is to use a 5T electric hoist to connect the main platform 502 above and the elevator car 601 below, operate the electric hoist to lift the elevator car 601 to an appropriate position below the main platform 502, and at the same time loosen the rope head of the elevator traction wire rope, synchronously extend the wire rope and release the accompanying cable. After the car 601 is lifted, tighten the traction wire rope to adjust the tension and re-fix the rope head.
[0049] The fourth step is to install elevator shaft components such as leveling sensors, carry out debugging work, and restore the normal operation of the construction elevator.
[0050] After completing the above steps, the single climbing operation is completed. As the building height increases, if you need to continue climbing, just repeat the above steps.
Claims
1. A self-climbing construction elevator with a machine room in a building, comprising an elevator shaft (1) and an elevator guide rail installation platform (3), characterized in that: The inner wall of the elevator shaft (1) is provided with an elevator guide rail (2), a lifting platform (4) is provided below the elevator guide rail mounting platform (3), a mobile machine room (5) is provided below the lifting platform (4), and an elevator system (6) is provided below the mobile machine room (5); The elevator guide rail installation platform (3) comprises a load-bearing hanging beam (301), the outer wall of the load-bearing hanging beam (301) is provided with a fixed pulley (302), the outer wall of the fixed pulley (302) is slidably connected with a fixed pulley wire rope (303), the fixed pulley (302) is connected to a first supporting steel frame (304) through the pulley wire rope (303), the top outer wall of the first supporting steel frame (304) is provided with a first telescopic steel beam (307), and the inner wall of the first supporting steel frame (304) is provided with a first rated load cable climber (305); The lifting platform (4) comprises a lifting base (401), a second supporting steel frame (402) is welded to the top outer wall of the lifting base (401), a second rated load cable climber (403) is arranged on the top outer wall of the lifting base (401), and a first wire rope drum (404) is arranged on the top outer wall of the lifting base (401); The mobile machine room (5) comprises a control platform (501) and a host platform (502), wherein the control platform (501) is arranged above the host platform (502), and an elevator control cabinet (506) is fixedly connected to the inner wall of the control platform (501).
2. A self-climbing construction elevator with a machine room in a building according to claim 1, characterized in that: The bottom outer wall of the first supporting steel frame (304) is provided with a sliding block (306), and the elevator guide rail mounting platform (3) is slidably connected to the elevator guide rail (2) via the sliding block (306).
3. The self-climbing construction elevator with a machine room in a building according to claim 1, characterized in that: The outer wall of the lifting base (401) is fixedly connected with a guide shoe, and the lifting platform (4) is slidably connected to the elevator guide rail (2) via the guide shoe.
4. The self-climbing construction elevator with a machine room in a building according to claim 1, characterized in that: The top outer wall of the control platform (501) is fixedly connected with a protective top (503), and the top outer wall of the protective top (503) is provided with a pulley block (504). The pulley block (504) is connected with a steel wire rope on a second rated load cable climber (403) of the upper lifting platform (4) to form a lifting system.
5. The self-climbing construction elevator with a machine room in a building according to claim 1, characterized in that: The outer walls of the control platform (501) and the host platform (502) are both fixedly connected with a second telescopic support steel beam (505), and the second telescopic support steel beam (505) is arranged around the bottom of the control platform (501) and the host platform (502).
6. The self-climbing construction elevator with a machine room in a building according to claim 1, characterized in that: A third rated load cable climber (507) is fixedly connected to the inner wall of the control platform (501) and located on one side of the elevator control cabinet (506), and a second wire rope drum (508) is provided on the inner wall of the control platform (501).
7. The self-climbing construction elevator with a machine room in a building according to claim 1, characterized in that: A traction machine support beam (509) is fixedly connected between the inner walls of the main engine platform (502), and a traction machine (510) is fixedly connected to the top outer wall of the traction machine support beam (509).
8. The self-climbing construction elevator with a machine room in a building according to claim 1, characterized in that: The elevator system (6) comprises an elevator car (601), an electric hoist is fixedly connected to the bottom outer wall of the main engine platform (502), the main engine platform (502) and the elevator car (601) are connected via the electric hoist, a counterweight (602) is arranged on one side of the elevator car (601), and the counterweight (602) is connected to the elevator car (601) via a traction rope via a traction wheel.
9. The self-climbing construction elevator with a machine room in a building according to claim 1, characterized in that: The steel wire rope of the first rated load cable climber (305) is wound in a 2:1 manner, and the steel wire rope of the second rated load cable climber (403) is wound in a 6:1 manner.