Rapid cooling and dewatering device and method for coal gas

Through the combination of the partition wall heat exchange device and the cyclone, the problems of low efficiency and insufficient safety of gas moisture removal in the prior art are solved, and efficient, fast and safe gas moisture removal is achieved, ensuring the gas flow rate and Stability of pressure.

CN118931600APending Publication Date: 2024-11-12ANGANG STEEL CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411208660.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-30
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

When removing saturated water and free water from coal gas, the flow rate and pressure of the coal gas are easily changed, and the process is complicated and there is a risk of leakage, making it difficult to achieve efficient, fast and safe moisture removal.

Method used

An efficient partition wall heat exchange device is adopted to reduce the gas temperature and increase the convection heat exchange effect through the circulation of the cyclone sheet and the evaporation medium, so as to achieve efficient and rapid removal of moisture in the gas without increasing the resistance of the gas pipeline.

Benefits of technology

The efficient, rapid and safe removal of moisture in the gas is achieved, with the removal efficiency reaching more than 70%, and it does not affect the gas flow rate, pressure and flow rate.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118931600A_ABST
    Figure CN118931600A_ABST
Patent Text Reader

Abstract

The invention relates to a device and a method for rapidly cooling and dehydrating coal gas. The device comprises a dehydration section and a drainage section which are arranged on a coal gas pipeline, the dehydration section consists of a spinning disk, an evaporation cavity, a heat insulation layer, a condensation cavity and a cooling cavity; the evaporation cavity is filled with an evaporation medium, and a plurality of spinning disks are arranged on the inner side of the inner wall of the evaporation cavity; the top of the evaporation cavity is provided with an evaporation pipe, the bottom of the evaporation cavity is provided with a condensation pipe, and two ends of the evaporation pipe and the condensation pipe are respectively communicated with the evaporation cavity and the condensation cavity; the drainage section is composed of a body pipeline and a drainage pipe. According to the invention, an efficient dividing wall type heat exchange mode is utilized, on the premise of not increasing the resistance of a gas pipeline, the removal of saturated water is realized by reducing the temperature of the gas, and meanwhile, the removal efficiency of free water is improved through the change of the flow direction of the gas, so that the efficient, rapid and safe removal of water in the gas is realized.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of steel production, and in particular to a device and method for rapid cooling and dehydration of coal gas. Background Art

[0002] Coal gas is an important energy source in the steel production process and is also the "blood" that drives the internal circulation of the steel production process. It mainly includes three types: blast furnace gas, coke oven gas, and converter gas. In the production conversion process, the solid fuel is first heated up and then reacted to generate a mixed gas containing a large amount of combustible components. Since a large amount of water is usually required during the production process, the coal gas obtained after production is in a saturated state and is accompanied by a large amount of free water particles. The presence of saturated water and free water will reduce the calorific value of the coal gas and cause corrosion of the gas transmission pipeline, so the water in the coal gas needs to be removed.

[0003] The Chinese utility model patent with application number CN202320842590.7 discloses "a blast furnace equalized pressure gas ejector dehydration device", which is installed on the gas inlet pipeline and includes an ejector and a dehydrator. The ejector includes a nozzle and a diffuser, and the nozzle and the diffuser are respectively arranged at both ends of the ejector. The nozzle is arranged on the gas inlet pipeline. The dehydrator includes an air inlet, an air outlet and a water outlet. The diffuser is connected to the air inlet, a dust removal box is arranged on the air outlet, and a cleaning component for cleaning the water outlet is arranged on the water outlet; the ejector can make the gas input into the gas inlet pipeline form a uniform flow rate, and the dehydrator can dehydrate the uniform flow rate gas input by the ejector, so as to avoid the condensation and enrichment of water in the gas, which will cause the downstream dust removal box to discharge ash unsmoothly, or the ash conveying system to be blocked; and the cleaning component can clean the water outlet of the dehydrator to avoid the adhesion of water and ash at the water outlet and blockage.

[0004] A Chinese patent application with application number CN202111595822.5 discloses a "method for removing naphthalene, dehydrating and removing tar from coke oven raw gas". The water vapor formed by the moisture brought into the coking coal and the water generated by coal pyrolysis enters the bridge pipe through the riser along with the raw gas. The non-water-soluble coolant sprayed in the bridge pipe directly cools the raw gas, and the temperature drops to 105-110°C. It is then merged into the gas collecting pipe and drawn into the electric tar precipitator through the suction pipe by the gas fan to remove tar droplets. It then enters the dehumidification tower, fluidizes, mixes and cools with the powder desiccant sprayed into the tower. The water vapor in the gas is condensed, and the desiccant absorbs the condensed water and adsorbs tar, naphthalene, etc. in the raw gas. The desiccant after desiccant absorption is directly sent to the cylindrical mixer of the sintering process as a sintering raw material and mixed with other sintering raw materials for granulation.

[0005] The Chinese utility model patent with application number CN202222322774.9 discloses "a gas dehydration and drainage device for a gas pipeline". The dehydration cylinder is an upright cylindrical body, the gas pipeline is connected to the opposite sides of the upper part of the dehydration cylinder, the movable baffle is vertically placed inside the dehydration cylinder, the upper end of the movable baffle is connected to the top surface of the dehydration cylinder, the two sides of the movable baffle are respectively in contact with the inner walls of the two sides of the dehydration cylinder, the float is placed below the movable baffle, and the overflow pipe is located below the float. It can separate and remove the water content of the gas in the gas pipeline and prevent gas leakage.

[0006] At present, the methods used to remove water from pipeline gas mainly include chemical adsorption, absorption, freezing and mechanical methods. Among them, the mechanical method can only be used to remove free water in gas. Although the other methods can remove saturated water in gas, most of them change the gas flow rate from the structure to the process, reduce the gas pressure, or have the risk of gas leakage due to the complex process. Summary of the invention

[0007] The present invention provides a device and method for rapidly cooling and dehydrating coal gas, which utilizes an efficient partition wall heat exchange method to remove saturated water by lowering the coal gas temperature without increasing the resistance of the gas pipeline. At the same time, the removal efficiency of free water is improved by changing the flow direction of the coal gas, thereby achieving efficient, rapid and safe removal of water from the coal gas.

[0008] In order to achieve the above object, the present invention adopts the following technical solutions:

[0009] A coal gas rapid cooling and dehydration device comprises a dehydration section and a drainage section which are sequentially arranged on a coal gas pipeline along the coal gas flow direction; the dehydration section is composed of a swirl sheet, an evaporation chamber, an insulation layer, a condensation chamber and a cooling chamber; the evaporation chamber, the insulation layer, the condensation chamber and the cooling chamber are sequentially arranged from the inside to the outside, and the evaporation chamber, the condensation chamber and the cooling chamber are all annular closed chambers; the evaporation chamber is filled with an evaporation medium, the internal space surrounded by the evaporation chamber is a coal gas channel, and a plurality of swirl sheets are arranged on the inner side of the inner wall of the evaporation chamber along the axial direction and the radial direction; a row of evaporation tubes is arranged along the axial direction at the top of the evaporation chamber, and a row of condensation tubes is arranged along the axial direction at the bottom of the evaporation chamber, and the evaporation tubes and the condensation tubes are both arranged in the insulation layer, and the two ends of the evaporation tubes and the two ends of the condensation tubes are respectively connected with the evaporation chamber and the condensation chamber; a cooling water inlet and a cooling water outlet are respectively arranged at the two ends of the cooling chamber; the drainage section is composed of a main body pipeline and a drainage pipe, and a drainage port is arranged at the bottom of the main body pipeline and connected with the drainage pipe.

[0010] Furthermore, flange connections are adopted between the dehydration section and the drainage section, between the dehydration section and the gas pipeline, and between the drainage section and the gas pipeline.

[0011] Furthermore, the inner diameter of the evaporation chamber and the inner diameter of the main pipe are the same as the outer diameter of the gas pipe.

[0012] Furthermore, along the gas flow direction, the cooling water inlet is arranged at the bottom of the cooling chamber downstream, and the cooling water outlet is arranged at the top of the cooling chamber upstream.

[0013] Furthermore, the inner wall of the evaporation chamber, the inner wall of the condensation chamber, the inner wall of the cooling chamber and the swirl plate are all made of high thermal conductivity and corrosion-resistant materials; the high thermal conductivity and corrosion-resistant materials include one or more of carbon fiber, aluminum alloy, copper alloy and iron alloy.

[0014] Furthermore, the axial angle between the swirl blade and the evaporation chamber is 10° to 45°.

[0015] Furthermore, the thermal insulation layer is made of thermal insulation material, and the thermal insulation material includes one or more of high-aluminum fiber, glass fiber, asbestos and nano thermal insulation blanket.

[0016] Furthermore, the evaporation medium is an organic or inorganic substance with an evaporation temperature lower than 35° C. and a latent heat of vaporization higher than 100 kJ / kg.

[0017] A method for rapid cooling and dehydrating coal gas, wherein the coal gas with a temperature of more than 35°C transported by a coal gas pipeline enters a dehydration section along the coal gas pipeline, exchanges heat with an evaporation medium through the inner wall of an evaporation chamber, and vaporizes after the temperature of the evaporation medium reaches a temperature above the boiling point, and the vapor evaporation medium enters a condensation chamber from an evaporation tube at the top of the evaporation chamber, exchanges heat with low-temperature cooling water introduced into the cooling chamber through the outer wall of the condensation chamber and condenses, and the condensed liquid evaporation medium returns to the evaporation chamber from the condensation tube at the bottom of the evaporation chamber, and the cycle is repeated in this way, so that the temperature of the coal gas is reduced to a set dehydration temperature after passing through the dehydration section, thereby removing saturated water in the coal gas; a swirl sheet arranged in the evaporation chamber causes the coal gas to generate a swirl, thereby increasing the convection heat exchange effect between the coal gas and the evaporation chamber, thereby removing free water in the coal gas; the water removed from the coal gas is discharged through a drainage pipe in a drainage section.

[0018] Furthermore, the set dehydration temperature is 25-35°C.

[0019] Compared with the prior art, the present invention has the following beneficial effects:

[0020] 1) Adopting efficient partition heat exchange device to heat and cool the gas in the gas pipeline to remove saturated water, and using swirl blades to make the gas swirl in the gas pipeline to achieve the purpose of removing free water and saturated water at the same time;

[0021] 2) By reasonably controlling the temperature and pressure parameters of coal gas, without affecting the gas flow rate, pressure, flow rate, composition, etc., the saturated water and free water in the coal gas can be removed quickly and efficiently, and the removal efficiency can reach more than 70%. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is an appearance diagram of a coal gas rapid cooling and dehydration device according to the present invention.

[0023] Figure 2 It is a front cross-sectional view of a coal gas rapid cooling and dehydration device according to the present invention.

[0024] Figure 3 yes Figure 2 Side cross-sectional view of .

[0025] In the figure: 1. Gas pipeline 2. Flange 3. Evaporation chamber 4. Cooling water outlet pipe 5. Evaporation chamber 6. Insulation layer 7. Condensation chamber 8. Cooling chamber 9. Swirl sheet 10. Drain pipe 11. Cooling water inlet pipe 13. Gas rapid cooling and dehydration device DETAILED DESCRIPTION

[0026] The specific implementation of the present invention will be further described below in conjunction with the accompanying drawings:

[0027] The coal gas rapid cooling and dehydration device described in the present invention adopts a high-efficiency partition wall heat exchange device to heat and cool the coal gas transported in the gas pipeline to remove saturated water, and at the same time uses a swirl sheet to make the coal gas produce a swirl, so as to achieve the purpose of removing free water and saturated water at the same time.

[0028] like Figure 1 As shown, a gas rapid cooling and dehydration device 13 of the present invention is composed of a dehydration section and a drainage section, which are arranged on a gas pipeline 1 and are connected by a flange 2.

[0029] like Figure 2 , Figure 3 As shown, the dehydration section of the coal gas rapid cooling and dehydration device 13 is composed of an evaporation chamber 3, an evaporation tube, an insulation layer 6, a condensation chamber 7, a cooling chamber 8, a swirl sheet 9, etc.; wherein, the evaporation chamber 3 is an annular sealed chamber, and its inner diameter is the same as the outer diameter of the coal gas pipeline 1, and the two ends of the evaporation chamber 3 are welded and sealed with two flanges of the dehydration section. A row of evaporation tubes is welded axially at the top of the evaporation chamber 3, and a row of condensation tubes is welded axially at the bottom of the evaporation chamber 3. The inner ends of the evaporation tubes and the condensation tubes are both connected to the evaporation chamber 3, and the outer ends of the evaporation tubes and the condensation tubes are both connected to the condensation chamber 7. The condensation chamber 7 is an annular sealed chamber, and the two ends of the condensation chamber 7 are welded and sealed with the two flanges of the dehydration section; an insulation layer 6 is arranged between the condensation chamber 7 and the evaporation chamber 3. The outside of the condensation chamber 7 is a cooling chamber 8 which is also an annular sealed chamber, and the two ends of the cooling chamber 8 are welded and sealed with the flanges of the dehydration section. The cooling water outlet at one end of the top of the cooling chamber 8 is connected to the cooling water outlet pipe 4 , and the cooling water inlet at the other end of the bottom of the cooling chamber 8 is connected to the cooling water inlet pipe 11 .

[0030] According to the saturated gas water content curve, 25℃ and 35℃ are two critical temperature points where the water content in coal gas changes significantly. Below 25℃, the water content in coal gas increases steadily and linearly, within the range of 25-35℃, the water content in coal gas increases at a rate, and above 35℃, the water content in coal gas increases in a gradient. Therefore, the commonly used optimal dehydration temperature of coal gas is between 25 and 35℃.

[0031] In view of the above rules, the present invention can fill the evaporation chamber 3 with evaporation media of different boiling points that meet the requirements. The evaporation medium is an organic or inorganic substance with an evaporation temperature of less than 35°C and a latent heat of vaporization greater than 100k / kg, preferably ether, dimethyl alcohol, polypropylene or chloroform. Heat exchange is carried out through the high thermal conductivity wall surface in contact with the coal gas in the evaporation chamber 3. When the heat exchange temperature reaches above the boiling point of the evaporation medium, the evaporation medium vaporizes and enters the condensation chamber 7 from the evaporation tube. The cooling chamber 8 outside the condensation chamber 7 is filled with water through the cooling water inlet pipe 11 and discharged through the cooling water outlet pipe 4 to realize the circulation of cooling water and ensure that the cooling chamber 8 is always filled with low-temperature cooling water. The evaporation medium vaporized in the condensation chamber 7 is cooled down by heat exchange with the high thermal conductivity wall surface between the cooling chamber 8 and the condensation chamber 7 to become liquid. Under the action of gravity, it returns to the evaporation chamber 3 through the condensation tube between the condensation chamber 7 and the evaporation chamber 3. In this way, the temperature of the coal gas is reduced to the set temperature through the vaporization-liquefaction cycle of the evaporation medium.

[0032] The present invention arranges a plurality of swirl sheets 9 on the inner wall of the evaporation chamber 3, so that the coal gas generates swirl in the coal gas channel inside the evaporation chamber 3, thereby increasing the convection heat transfer coefficient between the coal gas and the evaporation chamber 3, increasing the heat exchange area, and allowing the free water removed from the coal gas to quickly condense on the inner wall surface of the evaporation chamber 3 and finally be discharged from the drainage pipe 10 of the drainage section.

[0033] The drainage section and the dehydration section can be an integrated structure or an independent structure; when an independent structure is adopted, the dehydration section, the drainage section and the gas pipeline 1 are all connected by flanges, which is convenient for removal for inspection and replacement when the drainage outlet is blocked.

[0034] The coal gas rapid cooling and dehydration device described in the present invention involves the following relevant material selection and process parameters:

[0035] (1) The length of the dehydration section depends on the temperature, flow rate and flow rate of the coal gas. The specific value range is selected according to Table 1.

[0036] (2) The inner wall of the evaporation chamber that is in direct contact with the coal gas is made of high thermal conductivity, high strength, and corrosion-resistant materials, which may be selected but not limited to carbon fiber, aluminum alloy tube, copper alloy, iron alloy, etc.;

[0037] (3) The evaporating medium is selected according to the gas terminal temperature requirement. The optional evaporating medium is shown in Table 1.

[0038] (4) The circulating cooling water temperature in the cooling chamber is 5 to 10°C lower than the boiling point of the evaporating medium, and low-temperature water inside the steel enterprise can be used.

[0039] (5) The thickness of the insulation layer between the evaporation chamber and the condensation chamber can be determined according to the thermal conductivity of the selected insulation material. The insulation material can be selected from but is not limited to high aluminum fiber, glass fiber, asbestos, nano insulation blanket and other materials.

[0040] (6) The axial angle between the swirl blade and the inner wall of the evaporation chamber is 10° to 45°.

[0041] Table 1

[0042]

[0043] In order to make the purpose, technical scheme and technical effect of the present invention clearer, the technical scheme in the embodiment of the present invention is now clearly and completely described. However, the embodiments described below are only part of the embodiments of the present invention, not all of the embodiments. In combination with the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0044] [Example 1]

[0045] like Figure 1 As shown, in this embodiment, the gas rapid cooling and dehydration device 13 is composed of a dehydration section and a drainage section, which are arranged on the gas pipeline 1 and are connected by a flange 2.

[0046] like Figure 2 , Figure 3 As shown, in this embodiment, the dehydration section of the coal gas rapid cooling and dehydration device 13 is composed of an evaporation chamber 3, an evaporation tube, an insulation layer 6, a condensation chamber 7, a cooling chamber 8, a swirl sheet 9, etc.; wherein, the evaporation chamber 3 is an annular sealed chamber, and its inner diameter is the same as the outer diameter of the coal gas pipeline 1, and the two ends of the evaporation chamber 3 are welded and sealed with two flanges of the dehydration section. A row of evaporation tubes is welded axially at the top of the evaporation chamber 3, and a row of condensation tubes is welded axially at the bottom of the evaporation chamber 3. The inner ends of the evaporation tubes and the condensation tubes are both connected to the evaporation chamber 3, and the outer ends of the evaporation tubes and the condensation tubes are both connected to the condensation chamber 7. The condensation chamber 7 is an annular sealed chamber, and the two ends of the condensation chamber 7 are welded and sealed with the two flanges of the dehydration section; an insulation layer 6 is arranged between the condensation chamber 7 and the evaporation chamber 3. The outside of the condensation chamber 7 is a cooling chamber 8 which is also an annular sealed chamber, and the two ends of the cooling chamber 8 are welded and sealed with the flanges of the dehydration section. The cooling water outlet at one end of the top of the cooling chamber 8 is connected to the cooling water outlet pipe 4 , and the cooling water inlet at the other end of the bottom of the cooling chamber 8 is connected to the cooling water inlet pipe 11 .

[0047] In this embodiment, the gas rapid cooling and dehydration device 13 is used to cool and dehydrate the converter gas.

[0048] The initial temperature of the gas transported by the gas pipeline is 70° C., and the target temperature after cooling by the gas rapid cooling and dehydration device 13 is 35° C. The diameter of the gas pipeline 1 is 500 mm, and the gas flow rate in the gas pipeline 1 is 3 m / s.

[0049] The evaporation chamber is filled with an evaporation medium, and in this embodiment, ether is used as the evaporation medium.

[0050] In this embodiment, the total length of the dehydration section is 11800 mm, the outer diameter of the evaporation chamber is 550 mm, the outer diameter of the condensation chamber is 600 mm, and the mass of the evaporation medium poured into the evaporation chamber is 323 kg.

[0051] In this embodiment, the heat exchange capacity of the gas rapid cooling and dehydration device 13 is 103855 KJ / h, and 500 swirl blades with an axial angle of 40° are arranged on the inner wall of the evaporation chamber, with a total heat exchange area of ​​69m 2 , the total water removal of coal gas reaches more than 82%.

[0052] [Example 2]

[0053] This embodiment uses the same gas rapid cooling and dehydration device 13 as in Embodiment 1 to cool and dehydrate the coke oven gas.

[0054] The initial temperature of the gas transported by the gas pipeline is 50° C., and the target temperature after cooling by the gas rapid cooling and dehydration device 13 is 25° C. The diameter of the gas pipeline 1 is 800 mm, and the gas flow rate in the gas pipeline 1 is 8 m / s.

[0055] The evaporation chamber is filled with an evaporation medium, and in this embodiment, ether is used as the evaporation medium.

[0056] In this embodiment, the total length of the dehydration section is 17300 mm, the outer diameter of the evaporation chamber is 850 mm, the outer diameter of the condensation chamber is 900 mm, and the mass of the evaporation medium poured into the evaporation chamber is 768 kg.

[0057] In this embodiment, the heat exchange capacity of the gas rapid cooling and dehydration device 13 is 506419 KJ / h, and 800 swirl blades with an axial angle of 30° are arranged on the inner wall of the evaporation chamber, with a total heat exchange area of ​​213 m 2 , the total water removal of coal gas reaches more than 76%.

[0058] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A coal gas rapid cooling and dehydration device, characterized in that: It comprises a dehydration section and a drainage section which are arranged on the gas pipeline in sequence along the gas flow direction; the dehydration section is composed of a swirl sheet, an evaporation chamber, an insulation layer, a condensation chamber and a cooling chamber; the evaporation chamber, the insulation layer, the condensation chamber and the cooling chamber are arranged in sequence from the inside to the outside, and the evaporation chamber, the condensation chamber and the cooling chamber are all annular closed chambers; the evaporation chamber is filled with an evaporation medium, the internal space surrounded by the evaporation chamber is a gas channel, and a plurality of swirl sheets are arranged on the inner side of the inner wall of the evaporation chamber along the axial direction and the radial direction; a row of evaporation tubes are arranged along the axial direction at the top of the evaporation chamber, and a row of condensation tubes are arranged along the axial direction at the bottom of the evaporation chamber, and the evaporation tubes and the condensation tubes are both arranged in the insulation layer, and the two ends of the evaporation tubes and the two ends of the condensation tubes are respectively connected with the evaporation chamber and the condensation chamber; the two ends of the cooling chamber are respectively provided with a cooling water inlet and a cooling water outlet; the drainage section is composed of a main body pipeline and a drainage pipe, and a drainage port is arranged at the bottom of the main body pipeline and connected with the drainage pipe.

2. The coal gas rapid cooling and dehydration device according to claim 1, characterized in that: Flange connections are adopted between the dehydration section and the drainage section, between the dehydration section and the gas pipeline, and between the drainage section and the gas pipeline.

3. The coal gas rapid cooling and dehydration device according to claim 1, characterized in that: The inner diameter of the evaporation chamber and the inner diameter of the main body pipeline are both the same as the outer diameter of the gas pipeline.

4. The coal gas rapid cooling and dehydration device according to claim 1, characterized in that: Along the gas flow direction, the cooling water inlet is arranged at the bottom of the cooling chamber downstream, and the cooling water outlet is arranged at the top of the cooling chamber upstream.

5. The coal gas rapid cooling and dehydration device according to claim 1, characterized in that: The inner wall of the evaporation chamber, the inner wall of the condensation chamber, the inner wall of the cooling chamber and the swirl sheet are all made of high thermal conductivity and corrosion-resistant materials; the high thermal conductivity and corrosion-resistant materials include one or more of carbon fiber, aluminum alloy, copper alloy and iron alloy.

6. A coal gas rapid cooling and dehydration device according to claim 5, characterized in that: The axial angle between the swirl plate and the evaporation chamber is 10° to 45°.

7. The coal gas rapid cooling and dehydration device according to claim 1, characterized in that: The thermal insulation layer is made of thermal insulation material, and the thermal insulation material includes one or more of high-aluminum fiber, glass fiber, asbestos and nano thermal insulation blanket.

8. The coal gas rapid cooling and dehydration device according to claim 1, characterized in that: The evaporation medium is an organic substance or an inorganic substance with an evaporation temperature lower than 35° C. and a latent heat of vaporization higher than 100 kJ / kg.

9. A method for rapid cooling and dehydration of coal gas based on the coal gas rapid cooling and dehydration device according to any one of claims 1 to 8, characterized in that: After the coal gas with a temperature of more than 35°C transported by the coal gas pipeline enters the dehydration section along the coal gas pipeline, it exchanges heat with the evaporation medium through the inner wall of the evaporation chamber. The evaporation medium vaporizes after its temperature reaches above the boiling point. The vapor evaporation medium enters the condensation chamber from the evaporation tube at the top of the evaporation chamber, exchanges heat with the low-temperature cooling water introduced into the cooling chamber through the outer wall of the condensation chamber and condenses. The condensed liquid evaporation medium returns to the evaporation chamber from the condensation tube at the bottom of the evaporation chamber. This cycle is repeated so that the temperature of the coal gas is reduced to the set dehydration temperature after passing through the dehydration section, thereby removing the saturated water in the coal gas. The swirl sheet arranged in the evaporation chamber causes the coal gas to generate swirl, thereby increasing the convection heat exchange effect between the coal gas and the evaporation chamber, thereby removing the free water in the coal gas. The water removed from the coal gas is discharged through the drainage pipe of the drainage section.

10. A method for rapid cooling and dehydration of coal gas according to claim 9, characterized in that: The set dehydration temperature is 25-35℃.