Phase change heat storage material combined small heat pipe frozen soil composite roadbed and construction method thereof

By setting up a combined structure of small heat pipes and phase change heat storage materials in the frozen soil roadbed, the problem of the failure to transfer the cooling effect of phase change heat storage materials in the frozen soil roadbed is solved, and the thermal stability of road projects in the frozen soil area is achieved and Improved structural stability.

CN118932807AActive Publication Date: 2024-11-12CCCC FIRST HIGHWAY CONSULTANTS CO LTD +1

Patent Information

Application Number
CN202410944704.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-11-12
Estimated Expiration
2044-07-15

AI Technical Summary

Technical Problem

The mixed phase-change heat storage materials in existing frozen soil roadbeds cannot effectively transfer the cooling effect to the underlying frozen soil, resulting in a reduction in the area of ​​the frozen soil plate with high temperature unstable and high cost.

Method used

Using phase change heat storage material combined with small heat pipe permafrost composite roadbed structure, small heat pipes are set up in the roadbed fill layer, the first phase change material heat storage layer and the silty clay layer, and two layers of phase change storage are laid at different locations. Thermal material is used to improve the cooling effect of the frozen soil by using a combination of small heat pipes and phase change heat storage materials.

Benefits of technology

It effectively expands the cooling effect of frozen soil roadbed on the underlying frozen soil, and prevents and controls frozen soil degradation through active and passive thermal conductivity and passive thermal conductivity and temperature control, improves the thermal stability and structural stability of road projects in frozen soil areas, and reduces engineering diseases.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932807A_ABST
    Figure CN118932807A_ABST
Patent Text Reader

Abstract

The invention relates to a phase change heat storage material and small heat pipe frozen soil combined composite roadbed and a construction method thereof. At present, the existing frozen soil roadbed mixed with the phase change heat storage material cannot transfer the cooling effect of the phase change heat storage material to underlying frozen soil. The roadbed comprises a gravel-containing clay layer, a silty clay layer, a roadbed filling layer and an asphalt pavement layer from bottom to top, a first phase change material heat storage layer is arranged between the silty clay layer and the roadbed filling layer, and a second phase change material heat storage layer is arranged between the roadbed filling layer and the asphalt pavement layer; the roadbed further comprises small heat pipes, and the small heat pipes are vertically arranged in the roadbed soil filling layer, the first phase change material heat storage layer and the silty clay layer. Two layers of phase change heat storage materials are arranged at different positions of a roadbed, the phase change heat storage capacity is improved through new material compatibility, small hot bars are added to the upper limit of natural frozen soil, the small hot bars and the phase change heat storage materials are combined to achieve the heat flux control effect, and the cooling effect of the phase change heat storage materials on underlying frozen soil is effectively further expanded.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of roadbed construction, and in particular to a phase-change heat storage material combined with a small heat pipe frozen soil composite roadbed and a construction method thereof. Background Art

[0002] Traffic roads that cross large areas of permafrost need to withstand the test of extreme environments. For example, the asphalt pavement absorbs heat, causing the permafrost beneath the roadbed to accelerate degradation, causing uneven settlement of the roadbed and affecting the smoothness of the road; the permafrost cold season is long, the road surface is severely affected by snow and frost, and the road capacity is reduced. In order to prevent and control traffic road diseases in permafrost areas, the roadbed structure and construction have been optimized based on the factors affecting heat exchange between the permafrost roadbed and the external environment, the heat transfer process of frozen soil under multi-field coupling, the quantitative calculation model of heat budget of the permafrost roadbed, and the response mechanism of the underlying frozen soil to thermal disturbances of highway engineering.

[0003] However, in order to ensure the thermal stability of the frozen soil roadbed, the overall thermal design of the ground-air coupled heat exchange system of the roadbed-foundation-air zone should be carried out. Especially for special roadbeds, the heat flux needs to be precisely controlled at other key interfaces such as the asphalt sub-base, the interface between the special roadbed structure layer and the fill, and the active layer top plate. At present, in order to achieve the purpose of precise control of heat flux, phase change thermal storage materials can be mixed into the frozen soil roadbed, which can have a certain effect on the lifting of the upper limit of the frozen soil of the underlying frozen soil of the frozen soil roadbed. However, due to the limitations of the mixing ratio and the mixing layer, and the high cost of phase change thermal storage materials, the cooling effect of the phase change thermal storage materials mixed in the frozen soil roadbed cannot be transferred to the high-temperature unstable frozen soil pan in the underlying frozen soil, thereby reducing the area of ​​the high-temperature unstable frozen soil pan.

[0004] Therefore, it is necessary to propose new measures to overcome the above-mentioned defects. Summary of the invention

[0005] The purpose of the present invention is to provide a phase change thermal storage material combined with a small heat pipe frozen soil composite roadbed and a construction method thereof, so as to solve the problem that the current frozen soil roadbed mixed with phase change thermal storage material cannot transfer the cooling effect of the phase change thermal storage material to the underlying frozen soil.

[0006] In order to achieve the above object, the technical solution adopted by the present invention is:

[0007] A phase-change thermal storage material combined with a small heat pipe frozen soil composite roadbed, wherein the roadbed includes, from bottom to top, a gravel-containing clay layer, a silty clay layer, a roadbed fill layer, and an asphalt pavement layer;

[0008] A first phase change material heat storage layer is provided between the silty clay layer and the roadbed fill layer, and a second phase change material heat storage layer is provided between the roadbed fill layer and the asphalt pavement layer;

[0009] The roadbed also includes small heat pipes, which are vertically arranged in the roadbed fill layer, the first phase change material heat storage layer and the silty clay layer.

[0010] Furthermore, the top of the silty clay layer is an active layer, the active layer is a part of the silty clay layer, and the area between the active layer and the silty clay layer is the upper limit of frozen soil;

[0011] The first phase change material heat storage layer is located above the active layer, and the small heat pipe passes through the active layer.

[0012] Furthermore, the small heat pipe is a two-phase closed thermosyphon heat pipe, which includes a condensation section, a transition section and an evaporation section from top to bottom;

[0013] The condensation section is located in the roadbed filling layer, the transition section is located in the first phase change material heat storage layer and the active layer, and the evaporation section is located in the active layer and penetrates into the silty clay layer below the active layer.

[0014] Furthermore, the first phase change material heat storage layer and the second phase change material heat storage layer are paved with phase change heat storage material;

[0015] The phase change thermal storage material includes RT2-HC, RT3-HC and RT-4.

[0016] Furthermore, in the phase change thermal storage material, the volume mixing ratio of RT2-HC, RT3-HC and RT-4 is 6:2:2.

[0017] Furthermore, the small heat pipes are arranged within the road shoulder range and the road surface range between the road shoulders on both sides.

[0018] Furthermore, a semi-rigid base layer is laid on the top of the roadbed fill layer, and an asphalt pavement layer is laid on top of the semi-rigid base layer;

[0019] The second phase change material heat storage layer is located below the semi-rigid base layer.

[0020] On the other hand, a construction method of the phase change thermal storage material combined with a small heat pipe frozen soil composite roadbed is provided, the method comprising:

[0021] Clean the original surface, i.e. the silty clay layer, and compact the foundation;

[0022] Drill holes in the silty clay layer and place the evaporation section of the small heat pipe vertically in the hole;

[0023] Spreading a first phase change material heat storage layer and surrounding the transition section of the small heat pipe;

[0024] A roadbed fill layer is spread on the first phase change material heat storage layer to cover the condensation section of the small heat pipe;

[0025] After the roadbed fill is rolled and compacted layer by layer, the second phase change material heat storage layer is laid and rolled;

[0026] Laying a semi-rigid base layer on the second phase change material heat storage layer, and then laying an asphalt pavement layer on the upper layer;

[0027] On the left and right shoulders and slope protection of the asphalt pavement layer.

[0028] Furthermore, RT2-HC, RT3-HC, and RT-4 are uniformly mixed at a volume mixing ratio of 6:2:2 to obtain a first phase change material heat storage layer and a second phase change material heat storage layer.

[0029] Furthermore, in the small heat pipe, the liquid working medium is heated in the evaporation section and the working medium vapor rises. After passing through the transition section and reaching the condensation section, the rising working medium vapor condenses as the temperature drops and flows back to the evaporation section.

[0030] Compared with the prior art, the present invention has the following beneficial effects:

[0031] The present invention provides a phase change thermal storage material combined with a small heat pipe frozen soil composite roadbed and a construction method thereof. On the basis of adding phase change thermal storage material to the frozen soil roadbed, the two layers of phase change thermal storage material at different positions are optimized, and the phase change thermal storage capacity is improved by utilizing new material combinations. Small heat rods are added between the roadbed filling area and the upper limit of natural frozen soil, so that the cooling effect of the frozen soil roadbed mixed with phase change thermal storage material on the underlying frozen soil can be further expanded. Phase change thermal storage material and small heat pipes are used to conduct heat and control the temperature of the roadbed. Through active and passive methods, the roadbed can be cooled to prevent and control frozen soil degradation, and the integrity of the roadbed can be maintained to ensure traffic capacity, thereby helping to reduce engineering diseases and improve the thermal stability and structural stability of highway projects in frozen soil areas. The roadbed can be widely used in the technical field of prevention and control of freeze-thaw disasters of roadbeds in frozen soil areas. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, drawings of other embodiments can be obtained based on these drawings without paying creative work.

[0033] Figure 1 It is a schematic diagram of roadbed temperature control of the present invention.

[0034] Figure 2 It is a roadbed structure diagram of the present invention.

[0035] Figure 3It is an enlarged view of the local structure of the present invention.

[0036] Figure 4 It is a schematic diagram of the plane layout of the heat pipe points of the present invention.

[0037] Figure 5 It is a structural diagram of a small heat pipe of the present invention.

[0038] Figure 6 This is a statistical comparison chart of the maximum annual melting depth of different roadbeds.

[0039] Figure 7 It is a comparison diagram of the upper limits of frozen soil of different roadbeds. Among them, A is a schematic diagram of the upper limit of frozen soil of the roadbed without measures, B is a partial enlarged diagram of the roadbed in A, C is a schematic diagram of the upper limit of frozen soil of the roadbed of the present invention, and D is a partial enlarged diagram of the roadbed in C.

[0040] The symbols in the figure are:

[0041] 1- gravel-containing clay layer, 2- silty clay layer, 3- active layer, 4- first phase change material heat storage layer, 5- roadbed fill layer, 6- second phase change material heat storage layer, 7- semi-rigid base layer, 8- asphalt pavement layer, 9- small heat pipes, 10- fully weathered mudstone layer, 11- condensation section, 12- transition section, 13- evaporation section, 14- upper limit of frozen soil, 15- slope protection, 16- road shoulder, 17- natural surface. DETAILED DESCRIPTION

[0042] In order to facilitate the understanding of the present invention, the present invention will be described more fully below with reference to the relevant drawings. The preferred embodiments of the present invention are given in the drawings. However, the present invention can be implemented in many different forms and is not limited to the embodiments described herein. On the contrary, the purpose of providing these embodiments is to make the disclosure of the present invention more thoroughly understood.

[0043] In the description of the present invention, it is necessary to understand that the terms "upper", "lower", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0044] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the term "disposed" and the like should be understood in a broad sense, for example, it can be fixedly connected or disposed, or detachably connected or disposed, or integrally connected or disposed. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0045] Meanwhile, in the description of the present invention, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance. Of course, such objects can be interchanged where appropriate, so that the embodiments of the present application described herein can be implemented in an order other than that illustrated or described herein.

[0046] It should also be noted that although the order of steps is mentioned in the method description, in some cases, they may be performed in an order different from that shown here, and this should not be construed as a limitation on the order of the steps.

[0047] Frozen soil is a special rock with a temperature of 0℃ or below and contains ice. It is very sensitive to temperature changes. Climate warming and engineering construction will cause the frozen soil to warm up and degrade, affecting the stability of the upper road. Understanding the heat exchange mechanism of frozen soil roadbed is the basis for ensuring the thermal stability of frozen soil roadbed. The heat exchange process of frozen soil roadbed in the ground-air coupling system is a complex non-steady-state heat exchange process, which is affected by multiple factors such as climate environment, its own physical properties and engineering design scheme.

[0048] Phase change thermal storage materials can store heat latently to construct temperature-controlled pavement. By controlling the temperature distribution of asphalt / concrete pavement, it can melt ice and snow on the pavement, reduce road diseases, and extend the service life of the road.

[0049] Based on this, the present invention provides a phase change thermal storage material combined with a small heat pipe frozen soil composite roadbed (PCM-SHP), such as Figure 1-4 The roadbed includes a gravel clay layer 1, a silty clay layer 2, a roadbed fill layer 5 and a semi-rigid base layer 7 from bottom to top, and an asphalt pavement layer 8 is laid on the semi-rigid base layer 7. The top of the silty clay layer 2 is an active layer 3, and between the active layer 3 and the silty clay layer 2 is a frozen soil upper limit 14. The active layer 3 changes with the seasonal temperature, and the thickness changes accordingly. It is a part of the top of the silty clay layer 2, and the frozen soil upper limit 14 also changes with the seasonal temperature. The semi-rigid base 7 is a structure with a certain rigidity but relatively low strength. Materials such as cement stabilized, cement fly ash stabilized or fly ash stabilized can be selected. It has both load-bearing capacity and good flexibility and toughness, and can adapt to sections with relatively rough terrain.

[0050] Among them, a first phase change material heat storage layer 4 is arranged between the silty clay layer 2 and the roadbed fill layer 5, and a second phase change material heat storage layer 6 is arranged between the roadbed fill layer 5 and the semi-rigid base layer 7. The first phase change material heat storage layer 4 and the second phase change material heat storage layer 6 are paved with phase change heat storage materials, and the phase change heat storage materials include RT2-HC, RT3-HC, and RT-4 (manufactured by Rubitherm Technologies GmbH, UK). In the phase change heat storage material, the volume mixing ratio of RT2-HC, RT3-HC, and RT-4 is 6:2:2.

[0051] In addition, the roadbed also includes a small heat pipe 9, which is vertically arranged in the roadbed fill layer 5, the first phase change material heat storage layer 4, and the silty clay layer 2. The small heat pipe 9 is a two-phase closed thermosyphon heat pipe, which includes a condensation section 11, a transition section 12, and an evaporation section 13 from top to bottom, wherein the transition section 12 is also an insulating section. The condensation section 11 is located in the roadbed fill layer 5, the transition section 12 is located in the first phase change material heat storage layer 4 and the active layer 3, the evaporation section 13 is located in the active layer 3 and penetrates into the silty clay layer 2 below the active layer 3, and the evaporation section 13 passes through the upper limit of frozen soil 14. The small heat pipe 9 is arranged in the range of the shoulder 16 and the road surface range between the shoulders 16 on both sides.

[0052] In the roadbed of the present invention, the small heat rod 9 is an active defense structure, and the first phase change material heat storage layer 4 and the second phase change material heat storage layer 6 are passive insulation structures. The structure of the present invention comprehensively adopts active defense and passive insulation measures, which can effectively prevent disasters in the cold season roadbed and significantly improve the anti-freeze-thaw stability of the roadbed structure in the frozen soil area.

[0053] The construction method of the above-mentioned phase change thermal storage material combined with a small heat pipe frozen soil composite roadbed specifically includes the following steps:

[0054] S1: clean the original surface, i.e., the silty clay layer 2, and compact the foundation;

[0055] S2: Drill a hole in the silty clay layer 2 and vertically place the evaporation section 13 of the small heat pipe 9 in the hole;

[0056] S3: Spreading the first phase change material heat storage layer 4 and surrounding the transition section 12 of the small heat pipe 9;

[0057] S4: Spreading a roadbed filling layer 5 on the first phase change material heat storage layer 4, covering the condensation section 11 of the small heat pipe 9;

[0058] S5: After the roadbed fill is rolled and compacted layer by layer, a second phase change material heat storage layer 6 is laid and rolled;

[0059] S6: Laying a semi-rigid base layer 7 on the second phase change material heat storage layer 6, and then laying an asphalt pavement layer 8 on the upper layer;

[0060] S7: On the left and right shoulders 16 and the slope protection 15 of the asphalt pavement layer 8.

[0061] Among them, RT2-HC, RT3-HC, and RT-4 are uniformly mixed at a volume mixing ratio of 6:2:2 to obtain a first phase change material heat storage layer 4 and a second phase change material heat storage layer 6.

[0062] In addition, the small heat pipe 9 is a two-phase closed thermosiphon heat pipe. After the liquid working medium is heated in the evaporation section 13, the working medium vapor rises, passes through the transition section 12 and reaches the condensation section 11. As the temperature drops, the rising working medium vapor condenses and flows back to the evaporation section 13.

[0063] Example:

[0064] The structure and construction method of the present invention are further described in detail below through specific construction implementation:

[0065] The construction of composite roadbed in frozen soil area is as follows from bottom to top:

[0066] 1. Gravel-containing clay layer 1;

[0067] 2. Silty clay layer 2;

[0068] 3. Active layer 3, whose thickness varies with seasonal temperature, is part of the top of silty clay layer 2;

[0069] 4. The first phase change material heat storage layer 4, which has a thickness of about 0.5m and is evenly laid under the roadbed. When laying, the phase change heat storage material is extended to both ends;

[0070] 5. Roadbed fill layer 5, the fill height of which is about 1.85m, and the shoulder 16 is also covered with fill;

[0071] 6. The second phase change material heat storage layer 6, the laying thickness of this layer of phase change heat storage material is about 0.2m, and the laying width is the same as the width of the asphalt road surface;

[0072] 7. Semi-rigid base layer 7, the laying thickness of this layer is about 0.33m, and the laying width is the same as the width of the asphalt pavement;

[0073] 8. Asphalt pavement layer 8, which is the roadbed surface layer, has a paving thickness of about 0.12m and a paving width of the entire width excluding 1.5m on both sides of the shoulder 16;

[0074] 9. Small heat pipes 9 are placed vertically and spaced apart between the silty clay layer 2, the active layer 3, the first phase change material heat storage layer 4 and the roadbed fill layer 5;

[0075] 10. The slope of the slope protection 15 on both sides of the roadbed structure is 1:1.5.

[0076] The small heat pipe 9 is a two-phase closed thermosyphon heat pipe, which is divided into a condensation section 11, a transition section 12, and an evaporation section 13 from top to bottom; the condensation section 11 and the evaporation section 13 are 1.5 m long, the transition section 12 is 1 m long, the inner diameter of the heat pipe is 0.08 m, the outer diameter is 0.1 m, and the heat transfer coefficient of the inner wall surface of the evaporation section 13 is 5000 [W·(m 2 ℃)-1] The heat transfer coefficient of the inner wall surface of the transition section 12 is 6000 [W·(m 2 ℃) -1 ], the heat transfer coefficient of the inner wall surface of the condensation section 11 is 6000 [W·(m2·℃) -1 ], the thermal conductivity of the heat pipe wall is 10[W·(m 2 ℃) -1 ], in the evaporation section 13, the liquid working medium is heated and the working medium vapor rises, passes through the transition section 12 and reaches the condensation section 11, where the rising vapor condenses as the temperature drops and flows back to the evaporation section 13.

[0077] Heat transfer in a heat pipe consists of six main steps: (1) heat conduction through the solid wall of the heat pipe evaporation section; (2) evaporation (boiling) heat transfer through the heat pipe evaporation section; (3) condensation heat transfer through the heat pipe condensation section; (4) heat conduction through the solid wall of the heat pipe condensation section; (5) axial heat conduction through the solid wall from the evaporation section to the condensation section; and (6) heat transfer between the outer wall of the heat pipe condensation section and the cold source.

[0078] Each heat pipe is arranged at intervals in a direction perpendicular to the extension direction of the heat pipe. The entire evaporation section 13 of the heat pipe is placed in the silty clay layer 2, 0.5m of the transition section 12 is placed in the active layer 3, and the remaining 0.5m is placed in the first phase change thermal storage material layer 4. The condensation section 11 is placed in the roadbed fill layer 5. The distance between two adjacent heat pipes is 12.85m. Of course, according to actual needs and the size of the frozen soil roadbed, the number of heat pipes and the distance between the heat pipes can be appropriately adjusted to ensure that the evaporation section of the heat pipe is in the lower layer of the upper limit of the natural frozen soil under the roadbed. At the same time, the terminal of the condensation section 11 is in the middle layer of the roadbed. The heat pipe roadbed system of the frozen soil roadbed shown in the present invention includes three heat pipes. In a specific embodiment, the heat pipe roadbed system of the frozen soil roadbed can also include one, three or more heat pipes of other numbers. The setting of multiple heat pipes can increase the intensity of regulating the frozen soil roadbed through heat pipes, improve the regulation efficiency, and is more conducive to the internal temperature regulation of the frozen soil roadbed.

[0079] The present invention uses two phase change heat storage layers to isolate a large amount of heat exchange between the roadbed and the road surface and a large amount of heat exchange between the roadbed and the natural frozen soil. The second phase change material heat storage layer 6 set in the composite roadbed is mainly used to isolate the heat exchange between the asphalt pavement layer 8 and the roadbed fill layer 5, mainly to isolate solar radiation. The first phase change heat storage layer 4 set in the composite roadbed is mainly used to isolate the heat exchange between the roadbed fill layer 5 and the silty clay layer 3, mainly to prevent the leakage of underground cold. At the same time, small heat pipes 9 are placed vertically and equidistantly in the four layers of silty clay layer 2, active layer 3, first phase change material heat storage layer 4 and roadbed fill layer 5. On the one hand, the heat generated by the frozen soil is refluxed through the heat pipes set in the frozen soil roadbed to maintain the internal temperature balance of the frozen soil. On the other hand, the excess heat in the frozen soil is temporarily exported to prevent heat accumulation and accelerate the melting process of the frozen soil.

[0080] The specific construction method is as follows: first, clean the original surface, that is, the silty clay layer and the active layer, and tamp the foundation. Use a drilling machine in the silty clay layer and the active layer. Take the center as the base point and extend 12.85m to the left and right on the roadbed, and drill 3 cylindrical holes with a depth of more than 2m and a diameter greater than 0.1m every 2m along the road. Place the evaporation section of the two-phase closed thermosyphon heat pipe on the lower side and place it vertically in the hole. Make sure that the insulation section of the heat pipe is 0.5m in the silty clay layer. Then fill and tamp the soil taken out of the hole. When filling, pay attention to protecting the heat pipe wall from damage and keep it vertical. Spread the first layer of phase change thermal storage material on the surface. The thickness of the phase change thermal storage layer is about 0.5m. Roll it until the compaction degree meets the standard. When laying, extend the phase change thermal storage material to both ends. When laying the phase change material layer, pay attention to avoid the heat pipe placement point when compacting. Use small compaction equipment to compact around the heat pipe to prevent damage to the heat pipe. At this point in the construction, it is necessary to ensure that the condensation section of the heat pipe is completely placed in the air and the insulation section is not exposed to the air area; then spread the roadbed fill on the first layer of phase change insulation material, the gravel particle size is not more than 10mm, the sand content is not more than 5%, and the landfill height of the fill after compaction is about 1.85m. For the condensation section of the heat pipe, the soil is directly covered, and the treatment method is the same as the treatment method in the above-mentioned phase change thermal storage material layer. After the heat pipe is completely covered; use compaction equipment to roll and compact the roadbed fill layer by layer. During the rolling process, the starting heat pipe position and the adjacent heat pipe spacing are combined for precise positioning. This ensures seamless contact between the roadbed and the heat pipe, and ensures that the spacing between adjacent heat pipes meets the design requirements. After the roadbed fill layer is treated, the second layer of phase change heat storage material is laid and rolled. The laying thickness of this layer of phase change heat storage material is about 0.2m, and the laying width is the same as the width of the asphalt pavement. It is compacted by mechanical equipment. When the compaction degree test is qualified, a semi-rigid base layer is laid on the second layer of phase change heat storage material, and compacted by mechanical equipment. The thickness after compaction is about 0.33m. After paving, asphalt is laid on the upper layer. After compaction, the thickness of the asphalt is about 0.12m and the width is about 24m. Extend 1.5m on the left and right sides of the asphalt layer according to the slope foot coordinate point, with a slope ratio of 1:1.5, and fill and cover and compact.

[0081] like Figure 6 ,

[0082] like Figure 7 ,

[0083] The above specific examples are used to illustrate the present invention, which is only used to help understand the present invention and is not intended to limit the present invention. For those skilled in the art, according to the concept of the present invention, some simple deductions, modifications or substitutions can be made.

Claims

1. Phase change thermal storage material combined with small heat pipe frozen soil composite roadbed, characterized by: The roadbed comprises, from bottom to top, a gravel-containing clay layer (1), a silty clay layer (2), a roadbed fill layer (5) and an asphalt pavement layer (8); A first phase change material heat storage layer (4) is provided between the silty clay layer (2) and the roadbed fill layer (5), and a second phase change material heat storage layer (6) is provided between the roadbed fill layer (5) and the asphalt pavement layer (8); The roadbed further comprises a small heat pipe (9), wherein the small heat pipe (9) is vertically arranged in the roadbed fill layer (5), the first phase change material heat storage layer (4) and the silty clay layer (2).

2. The phase change thermal storage material combined with small heat pipe frozen soil composite roadbed according to claim 1 is characterized by: The top of the silty clay layer (2) is an active layer (3), the active layer (3) is a part of the silty clay layer (2), and the upper limit of frozen soil (14) is between the active layer (3) and the silty clay layer (2); The first phase change material heat storage layer (4) is located above the active layer (3), and the small heat pipe (9) passes through the active layer (3).

3. The phase change thermal storage material combined with small heat pipe frozen soil composite roadbed according to claim 2 is characterized by: The small heat pipe (9) is a two-phase closed thermosyphon heat pipe, and comprises, from top to bottom, a condensation section (11), a transition section (12) and an evaporation section (13); The condensation section (11) is located in the roadbed fill layer (5), the transition section (12) is located in the first phase change material heat storage layer (4) and the active layer (3), and the evaporation section (13) is located in the active layer (3) and penetrates into the silty clay layer (2) below the active layer (3).

4. The phase change thermal storage material combined with small heat pipe frozen soil composite roadbed according to claim 3 is characterized by: The first phase change material heat storage layer (4) and the second phase change material heat storage layer (6) are paved with phase change heat storage material; The phase change thermal storage material includes RT2-HC, RT3-HC and RT-4.

5. The phase change thermal storage material combined with small heat pipe frozen soil composite roadbed according to claim 4 is characterized by: In the phase change thermal storage material, the volume mixing ratio of RT2-HC, RT3-HC and RT-4 is 6:2:

2.

6. The phase change thermal storage material combined with small heat pipe frozen soil composite roadbed according to claim 5 is characterized by: The small heat pipe (9) is arranged within the range of the road shoulder (16) and within the range of the road surface between the road shoulders (16) on both sides.

7. The phase change thermal storage material combined with small heat pipe frozen soil composite roadbed according to claim 6 is characterized by: A semi-rigid base layer (7) is laid on the top of the roadbed fill layer (5), and an asphalt pavement layer (8) is laid on top of the semi-rigid base layer (7); The second phase change material heat storage layer (6) is located below the semi-rigid base layer (7).

8. The construction method of the phase change thermal storage material combined with small heat pipe frozen soil composite roadbed according to claim 7, characterized in that: The method comprises: Clean the original surface, i.e. the silty clay layer (2), and compact the foundation; Drill a hole in the silty clay layer (2), and vertically place the evaporation section (13) of the small heat pipe (9) in the hole; Laying a first phase change material heat storage layer (4) and surrounding a transition section (12) of the small heat pipe (9); Spreading a roadbed filling layer (5) on the first phase change material heat storage layer (4) to cover and bury the condensation section (11) of the small heat pipe (9); After the roadbed fill is rolled and compacted layer by layer, a second phase change material heat storage layer (6) is laid and rolled; Laying a semi-rigid base layer (7) on the second phase change material heat storage layer (6), and then laying an asphalt pavement layer (8) on the upper layer; On the asphalt pavement layer (8) are left and right shoulders (16) and slope protection (15).

9. The construction method of the phase change thermal storage material combined with small heat pipe frozen soil composite roadbed according to claim 8 is characterized by: RT2-HC, RT3-HC and RT-4 are uniformly mixed at a volume mixing ratio of 6:2:2 to obtain a first phase change material heat storage layer (4) and a second phase change material heat storage layer (6).

10. The construction method of the phase change thermal storage material combined with small heat pipe frozen soil composite roadbed according to claim 9, characterized in that: In the small heat pipe (9), the liquid working medium is heated in the evaporation section (13), and the working medium vapor rises. After passing through the transition section (12) and reaching the condensation section (11), the rising working medium vapor condenses as the temperature drops, and flows back to the evaporation section (13).

Citation Information

Patent Citations

  • Pavement structure based on phase change temperature adjusting material and construction method

    CN114481747A

  • Method for maintaining thermal stability of frozen soil foundation all year round through heat pipe system

    CN117904917A

  • Hot pin compound road bed of block stone layer cooling

    CN206034218U

  • Novel permafrost region roadbed temperature control structure

    CN218756815U

Cited By

  • Composite roadbed structure and composite roadbed structure construction method

    CN119321073A

  • Composite roadbed structure and method for constructing a composite roadbed structure

    CN119321073B

  • Two-phase closed thermosiphon device for power transmission and transformation foundation and construction method of two-phase closed thermosiphon device

    CN120700936A

  • Two-phase closed thermosyphon device for power transmission infrastructure and method of construction thereof

    CN120700936B

  • Railway roadbed multi-energy cross-seasonal heat storage system based on toughness prediction and control method

    CN122384295A