External prestress auxiliary stay cable replacement construction method

By using extracorporeal prestressing facilities during the replacement of cable lacing, a single or multi-point prestressing support structure is formed, the problems of changes in the beam body and uneven prestress distribution in traditional methods are solved, and construction safety and application are improved scope.

CN118932888APending Publication Date: 2024-11-12SUNTECH CONSTR GRP CO LTD +1
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202410872711.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-01
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The traditional cable-stayed cable replacement method causes changes in the structural stress of the beam body, which increases the risk of replacement of the cable-stayed cables of larger spacing and thicker main beams, and the prestress distribution is uneven, affecting safety.

Method used

Using extracorporeal prestressing facilities, through the installation of steering support and chemical anchors, a single or multi-point prestressing support structure is formed, and the tensioning and tensioning are graded to ensure that the main beam is always supported by prestress during the replacement process, which is suitable for different Replace cables with thickness and spacing.

Benefits of technology

The deflection and structural stress influence on the main beam during the replacement process is reduced, construction safety is improved, and prestress uniform distribution is achieved. It is suitable for cable-stayed cable replacement of longer spacing and thicker main beams.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118932888A_ABST
    Figure CN118932888A_ABST
Patent Text Reader

Abstract

The invention discloses an external prestressing auxiliary stay cable replacement construction method which comprises the following steps: sequentially measuring the cable force and cable length of an old cable on a bridge body, measuring the elevation of a bridge floor, preparing construction machinery and materials, mounting an external prestressing facility at an outer web of a main beam needing cable replacement, dismantling ancillary facilities of the old cable, and detecting the initial loose cable force of the cable body. Grading tensioning of the external pre-stress facility and grading releasing of the old stay cable are conducted synchronously, new cable transportation to a bridge, cable unfolding on a beam surface, tower end hanging, beam end traction, tower end traction, grading releasing of the external pre-stress facility and grading tensioning of the new cable are conducted synchronously, accessories are installed and checked, and the next cable is replaced to remove the external pre-stress facility; by arranging the external prestress facility, when the bridge body stay cable is subjected to replacement construction operation, prestress can be provided for the main beam all the time in the cable replacement process, the influence on the deflection and structural stress of the main beam in the cable replacement process is reduced, and the safety of the main beam structure in the cable replacement process is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of cable-stayed bridge cable replacement construction, and more specifically to an external prestressed auxiliary cable-stayed cable replacement construction method. Background Art

[0002] The cable-stayed bridge is an extremely important form of modern bridge technology. It is a type of truss structure. The bridge deck is tied to the tower body through one or more groups of cable stays, and the cables bear the main load. The cable stay is one of the key components of the cable-stayed bridge. It is responsible for transferring the bridge deck load to the bridge tower. It is usually composed of multiple high-strength steel wires or steel strands tied together and connected to the bridge deck and bridge tower through specific anchors. It has good mechanical properties and durability. According to different cable structure types, it can be subdivided into parallel wire cables, locking cables, spiral cables, etc.

[0003] The prior art CN114673101B records a construction method for replacing the cable of a long-serving steel cable-stayed bridge, including: installation of measuring points, wherein the removal of the old cable includes releasing the old cable force, removing the beam end anchorage of the old cable, removing the tower end anchorage of the old cable, and installing the new cable includes transporting the new cable, hanging the tower end, installing and anchoring the beam end, and tensioning the new cable force. No temporary cable is set during the replacement process, and the cable is unloaded and tensioned one by one, which reduces the risk of safety accidents of the bridge during the cable replacement process, speeds up the speed of bridge cable replacement construction, ensures the safety of construction, and reduces the management cost of construction.

[0004] In order to ensure the safety and stability of the bridge, it is very important to regularly maintain and inspect the cable-stayed cables. As one of the main load-bearing components of the cable-stayed bridge, the cable-stayed cables are generally designed to have a service life of 20 years. They are generally exposed to the air for a long time and are always in a high-stress working state. They are prone to defects such as cable aging that affect structural safety. Therefore, replacing the cable-stayed cables is a common method to extend the life of the cable-stayed bridge. The traditional method of replacing the cable-stayed cables will inevitably affect the deflection of the main beam area and the changes in structural stress, which not only causes certain damage to the main beam structure, but also brings greater safety hazards to the smooth progress of the construction work. Summary of the invention

[0005] The purpose of the present invention is to provide an external prestressed auxiliary cable replacement construction method to solve the existing problems.

[0006] The problem to be solved by the present invention is:

[0007] 1. The traditional technology directly replaces the cable-stayed bridge. The beam without the cable will lose tension, causing the stress of the beam structure to change, increasing the risk of replacing the cable-stayed bridge.

[0008] 2. Secondly, the traditional technology is not suitable for the replacement of cables with large spacing. When the spacing between multiple groups of inclined cables in the bridge body is large, the single-point prestressed support structure cannot evenly distribute the prestress on the main beam, and the use effect is poor;

[0009] 3. Secondly, the traditional technology is not well suited for the replacement of the inclined cables of thicker main beams, because the single-point prestressed support structure uses a steel strand for auxiliary support, which makes it unable to meet the needs of thicker main beams, reducing its scope of use.

[0010] The purpose of the present invention can be achieved through the following technical solutions:

[0011] An external prestressed auxiliary stay cable replacement construction method comprises the following steps:

[0012] Step S1, construction preparation, measuring the old cable force and cable length on the bridge body, measuring the bridge deck elevation, and preparing construction machinery and materials;

[0013] Step S2, installing an external prestressing facility, installing an external prestressing facility at the outer web of the main beam where the cable needs to be replaced;

[0014] Step S3, dismantling the old cables and their ancillary facilities, detecting the initial loosening force of the cable body, and synchronously performing the staged tensioning of the external prestressing facilities and the staged release of the old inclined cables;

[0015] Step S4, installing new cables, transporting new cables to the bridge, laying cables on the beam surface, hanging them at the tower end, traction at the beam end and traction at the tower end, synchronously performing staged tensioning of the external prestressing facilities and staged tensioning of the new cables, and installing accessories;

[0016] Step S5, check and replace the next cable;

[0017] Step S6, dismantling the external prestressing facilities;

[0018] Step S7, repeat steps S1-S6 to complete the replacement of all the inclined cables in sequence.

[0019] As a further technical solution of the present invention, when installing the extracorporeal prestressed facility in step S2, a finite element model is established according to the actual engineering situation, the number of steel strands arranged and the tensioning control stress are calculated, the installation position of the anchoring device is at the web of the main beam corresponding to the positions of the two adjacent cables of the replaced inclined cable, and is fixed to the anchoring area of ​​the web of the main beam by chemical anchors, and the installation position of the steering support is at the web of the main beam corresponding to the position of the replaced inclined cable, and is fixed to the anchoring area of ​​the web of the main beam by chemical anchors, so that the steel strand abuts against the lower end of the steering support, and the external prestressed steel strand has a V-shaped structure as a whole. The setting of a single steering support forms a single-point prestressed support structure between the external prestressed steel strand and the main beam, and the position of the lower end of the inclined cable is used as the prestressing point, and prestress is applied to it through the two adjacent inclined cables on both sides thereof, so as to avoid the main beam bending downward due to loss of tension when the inclined cable is disassembled.

[0020] As a further technical solution of the present invention, when installing the extracorporeal prestressed facility in step S2, a group of steering supports are installed at the web of the main beam corresponding to the position where the inclined cable needs to be replaced, and several groups of steering supports are successively installed at the webs of the main beam on both sides of the position where the inclined cable needs to be replaced, and the heights of the several groups of steering supports are in a decreasing state. The steel strand is passed through the lower part of the several groups of steering supports so that the steel strand is in an arc shape, and the two ends of the steel strand are respectively fixed at the webs of the main beam corresponding to the positions of two adjacent cables of the replaced inclined cable by using an anchoring device. Compared with the single-point prestressed support structure, the arrangement of multiple steering supports allows the external prestressed steel strand to form an arc-shaped prestressed support structure, so that a multi-point support structure is formed between the steel strand and the main beam, so that the prestress applied by the steel strand to the main beam is more uniform, thereby improving the safety of the main beam.

[0021] As a further technical solution of the present invention, step S2 installs external prestressed facilities, and sets multiple groups of external prestressed facilities. One group of steering supports is installed at the web of the main beam corresponding to the position where the inclined cable needs to be replaced, and another group of steering supports is installed at the lower position of the previous group of steering supports. Steel strands are installed at the lower parts of several groups of steering supports, and the two ends of several groups of steel strands are respectively fixed at the web of the main beam corresponding to the positions of two adjacent cables of the replaced inclined cables by anchoring devices, so that the multiple groups of external prestressed facilities are vertically distributed to form a multi-point prestressed support structure. Through the setting of multiple external prestressed facilities, multiple groups of prestressed support structures are sequentially set from top to bottom at the position where the inclined cable needs to be replaced, so that the position where the inclined cable needs to be replaced forms multi-point support, thereby improving its safety.

[0022] As a further technical solution of the present invention, when the old cable is removed in step S3, the external prestressing force needs to be tensioned in stages, specifically 30%→60%→80%→90%→100%, and the stages are synchronized with the tensioning of the old cable. The inclined cable at the tower end is tensioned using a hydraulic jack, and the two inclined cables with the same cable number should be tensioned symmetrically during tensioning; after the inclined cable at the tower end is tensioned, the inclined cable at the beam end is tensioned using a winch, and the cable body is pulled by the winch to separate the anchor cup nut from the anchor pad, the anchor cup nut at the beam end is removed, and the winch traction system is loosened until the anchor cup at the beam end is withdrawn from the cable guide tube and the winch traction system is not stressed; after the beam end is tensioned, the tower end inclined cable is removed, and the winch set at the top of the tower is used to slowly lower the inclined cable, and the winch is used to pull the beam end anchor cup at the beam end to synchronously pull it in the anchoring direction, and a single-axle trolley is placed at a certain distance when the cable body is lowered, and the cable body is transported by the single-axle trolley, and the cable body is pulled out of the construction area and waits for cutting.

[0023] As a further technical solution of the present invention, when installing a new cable in step S4, the cable to be installed is transported to the bridge by a flatbed truck, the cable body is pulled out a certain distance by the tower top hanger and placed on the beam surface, and a connecting sleeve and a tensioning rod are installed at the rear end of the anchor cup of the cable; a winch is arranged in the tower, and a steel wire rope is led downward from the corresponding cable guide tube in the tower to connect the main bridge deck cable; during lifting, the tower top hanger and the winch in the tower cooperate with each other to lead the tensioning end anchor cup out of the tower end anchor pad, and then the tensioning equipment in the tower is installed; when the cable is a long cable, it is necessary to extend the cable on the beam surface after the tower end of the cable is hung;

[0024] The anchor cups of the beam-end and tower-end cables need to be pulled to the designed position of the cable guide tube. This pulling is soft pulling.

[0025] After the soft traction of the tower end and beam end inclined cables is completed, the tower end inclined cables still need hard traction; the hard traction method is tensioning, and the auxiliary tensioning rod is installed at the rear end of the main tension rod, and the auxiliary tensioning rod is tensioned until the main tension rod is pulled out of the hydraulic jack, and the main tension rod nut is installed, and the traction is continued until the anchor cup nut is installed to the flat cap state, and the traction is stopped and the auxiliary tensioning rod is removed.

[0026] As a further technical solution of the present invention, after the installation of the tensioning equipment in the tower is completed, tensioning begins. Each group of the inclined cables is tensioned synchronously and graded according to the bidirectional symmetry of a single tower, and each tensioning force should be tensioned graded at 30%→60%→80%→90%→100% of the final cable force; when the tower end is tensioned, the external prestress at the beam end position of the two adjacent inclined cables of the cable is released synchronously and graded, and the external prestress is released graded according to 70%→40%→20%→10%→0% of the final tensioning force;

[0027] Installation accessories include built-in shock absorbers, anchor cup anti-corrosion and protective covers, waterproof covers, stainless steel sheaths, etc.

[0028] As a further technical solution of the present invention, step S5 checks and replaces the next cable. According to the actual situation on site, after the new cable is installed, the cable force, bridge deck elevation and stress are measured, and the bridge deck is checked for cracks or changes in crack width to ensure that it meets the design requirements and meets the functional and safety requirements. After the inspection is completed, the above steps are repeated to continue replacing the next cable.

[0029] As a further technical solution of the present invention, the extracorporeal prestressed facility in step S2 includes an anchoring device, a jack, a steel strand and a steering support, the steel strand is located at the lower part of the steering support, and the anchoring device and the jack are both arranged at both ends of the steel strand.

[0030] As a further technical solution of the present invention, when the steering support is in use, the rotating cap is rotated so that the rotating cap drives the threaded rod to rotate, and the threaded rod uses the threaded structure to drive the lifting rod to move up and down, so that the lifting rod adjusts the use height of the guide wheel.

[0031] Beneficial effects of the present invention:

[0032] 1. By setting up external prestressing facilities, when the bridge body inclined cables are replaced, prestressing can be provided to the main beam all the time during the cable replacement process, reducing the impact on the main beam deflection and structural stress during the cable replacement process, and ensuring the safety of the main beam structure during the cable replacement process;

[0033] During operation, the installation position of the anchor device is at the web of the main beam corresponding to the positions of the two adjacent cables of the replaced inclined cable, and the anchor device is fixed to the anchor area of ​​the web of the main beam by chemical anchor bolts. The installation position of the steering support is at the web of the main beam corresponding to the position of the replaced inclined cable, and is fixed to the anchor area of ​​the web of the main beam by chemical anchor bolts, so that the steel strand abuts against the lower end of the steering support, and the guide wheel at the lower end of the steering support is used to dock the steel strand, so that the external prestressed steel strand is in a V-shaped structure as a whole. The setting of a single steering support forms a single-point prestressed support structure between the external prestressed steel strand and the main beam, and the position of the lower end of the inclined cable is used as the prestressing point. The two ends of the steel strand are respectively fixed to the lower position of the adjacent cables on both sides, and prestress is applied to it through the two adjacent inclined cables on both sides, so as to avoid the main beam bending downward due to loss of tension when the inclined cable is disassembled:

[0034] When removing the old cables, the external prestressing force needs to be tensioned in stages, specifically 30% → 60% → 80% → 90% → 100%, and the stages are synchronized with the tensioning of the old cables. The inclined cables at the tower end are tensioned using hydraulic jacks, and the two inclined cables with the same cable number should be tensioned symmetrically during tensioning. After the inclined cables at the tower end are tensioned, the inclined cables at the beam end are tensioned using a winch. The cable body is pulled by the winch to separate the anchor cup nut from the anchor pad, the anchor cup nut at the beam end is removed, and the winch traction system is loosened until the anchor cup at the beam end is withdrawn from the cable guide tube and the winch traction system is not stressed. After the beam end is tensioned, the tower end inclined cables are removed, and the winch installed on the top of the tower is used to slowly lower the inclined cables. The winch is used at the beam end to pull the anchor cup at the beam end in the direction of anchoring. When the cable body is lowered, a single-axle trolley is placed at a certain distance, and the cable body is transported by the single-axle trolley, and the cable body is pulled out of the construction area and waits for cutting.

[0035] 2. By setting up multiple steering supports of different heights, the steel strands are installed in an arc-shaped state on the web of the main beam, so that it has an arc-shaped prestressed support structure, making the prestress distribution of the main beam more uniform, which can be better applied to the replacement operation of the inclined cables with longer spacing;

[0036] During operation, a group of steering supports are installed on the web of the main beam corresponding to the position where the inclined cable needs to be replaced, and several groups of steering supports are installed in sequence on the webs of the main beam on both sides of the position where the inclined cable needs to be replaced. The heights of the several groups of steering supports are in a decreasing state. When adjusting the height of the steering supports, the rotating cap is rotated to drive the threaded rod to rotate, and the threaded rod uses the threaded structure to drive the lifting rod to move up and down, so that the lifting rod adjusts the use height of the guide wheel, and the steel strand is passed through the lower part of several groups of steering supports, so that the steel strand is in an arc shape, and the two ends of the steel strand are respectively fixed on the web of the main beam corresponding to the positions of two adjacent cables of the replaced inclined cable by using anchoring devices. Compared with the single-point prestressed support structure, the setting of multiple steering supports allows the external prestressed steel strand to form an arc-shaped prestressed support structure, so that a multi-point support structure is formed between the steel strand and the main beam, so that the prestress applied by the steel strand to the main beam is more uniform, thereby improving the safety of the main beam.

[0037] 3. By setting up multiple sets of external prestressing facilities, the steel strands are evenly spaced up and down, so that it has a multi-point prestressed support structure, which can cope with the replacement operation of the inclined cables on the main beams of different thicknesses and improve the prestressed support strength of the main beam structure;

[0038] When in use, multiple groups of external prestressed facilities are set up, one group of steering supports is installed on the web of the main beam corresponding to the position where the inclined cable needs to be replaced, and another group of steering supports is installed at the lower position of the previous group of steering supports. Steel strands are installed at the lower parts of several groups of steering supports, and the two ends of several groups of steel strands are respectively fixed on the web of the main beam corresponding to the positions of two adjacent cables of the replaced inclined cables by using anchoring devices, so that the multiple groups of external prestressed facilities are distributed vertically to form a multi-point prestressed support structure. Through the arrangement of multiple external prestressed facilities, multiple groups of prestressed support structures are arranged in sequence from top to bottom at the position where the inclined cable needs to be replaced, so that the position where the inclined cable needs to be replaced forms multi-point support, thereby improving the prestressed support strength and safety of the main beam structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] The present invention will be further described below in conjunction with the accompanying drawings.

[0040] Figure 1 It is a flow chart of a construction method for replacing an external prestressed auxiliary inclined cable according to the present invention;

[0041] Figure 2 It is a structural schematic diagram of a bridge body in a construction method for replacing external prestressed auxiliary inclined cables according to the present invention;

[0042] Figure 3 The invention relates to a method for replacing a single-point prestressed cable in a construction method for replacing an external prestressed cable. Figure 2 The enlarged view of point A in the middle;

[0043] Figure 4 The invention relates to an arc-shaped prestressed support structure in a construction method for replacing an external prestressed auxiliary inclined cable. Figure 2 The enlarged view of point A in the middle;

[0044] Figure 5 The invention relates to a multi-point prestressed support structure in the construction method for replacing an external prestressed auxiliary inclined cable. Figure 2 The enlarged view of point A in the middle;

[0045] Figure 6 It is a planar structural diagram of a steering support in an external prestressed auxiliary inclined cable replacement construction method of the present invention.

[0046] In the figure: 1. inclined cable; 2. main beam; 3. anchoring device; 4. jack; 5. steel strand; 6. steering support; 7. guide wheel; 8. lifting rod; 9. threaded rod; 10. rotating cap. DETAILED DESCRIPTION

[0047] In order to further explain the technical means and effects adopted by the present invention to achieve the predetermined invention purpose, the specific implementation mode, structure, characteristics and effects of the present invention are described in detail below in combination with the accompanying drawings and preferred embodiments.

[0048] like Figure 1 As shown, a construction method for replacing an external prestressed auxiliary cable-stayed cable comprises the following steps:

[0049] Step S1, construction preparation, measuring the old cable force and cable length on the bridge body, measuring the bridge deck elevation, and preparing construction machinery and materials;

[0050] Step S2, installing an external prestressing facility, installing an external prestressing facility at the outer web of the main beam 2 where the cable needs to be replaced;

[0051] Step S3, dismantle the old cable, dismantle the old cable ancillary facilities, detect the initial loose cable force of the cable body, and synchronously perform the staged tensioning of the external prestressing facilities and the staged release of the old inclined cable 1;

[0052] Step S4, installing new cables, transporting new cables to the bridge, laying cables on the beam surface, hanging them at the tower end, traction at the beam end and traction at the tower end, synchronously performing staged tensioning of the external prestressing facilities and staged tensioning of the new cables, and installing accessories;

[0053] Step S5, check and replace the next cable;

[0054] Step S6, dismantling the external prestressing facilities;

[0055] Step S7, repeat steps S1-S6 to complete the replacement of all the inclined cables 1 in sequence.

[0056] To solve the problem of deflection in the main beam area and structural stress changes, such as Figure 3 As shown, when installing the external prestressed facility in step S2, a finite element model is established according to the actual engineering situation, the arrangement quantity of the steel strand 5 and the tensioning control stress are calculated, the installation position of the anchor device 3 is at the web of the main beam 2 corresponding to the positions of the two adjacent cables of the replaced inclined cable 1, and it is fixed to the web anchoring area of ​​the main beam 2 by chemical anchor bolts, and the installation position of the steering support 6 is at the web of the main beam 2 corresponding to the position of the replaced inclined cable 1, and it is fixed to the web anchoring area of ​​the main beam 2 by chemical anchor bolts, so that the steel strand 5 abuts against the lower end of the steering support 6, and the external prestressed steel strand 5 is a V-shaped structure as a whole. The setting of a single steering support 6 forms a single-point prestressed support structure between the external prestressed steel strand 5 and the main beam 2, and the position of the lower end of the inclined cable 1 is used as the prestressing point, and prestress is applied to it through the two adjacent inclined cables on both sides thereof, so as to avoid the main beam 2 bending downward due to loss of tension when the inclined cable 1 is disassembled.

[0057] To solve the problem of replacing cables with longer spacing, such as Figure 4As shown, in step S2, when installing the external prestressed facility, a group of steering supports 6 are installed at the web of the main beam 2 corresponding to the position of the inclined cable 1 to be replaced, and several groups of steering supports 6 are installed in sequence at the webs of the main beam 2 on both sides of the position of the inclined cable 1 to be replaced, and the heights of the several groups of steering supports 6 are in a decreasing state. The steel strand 5 is passed through the lower part of the several groups of steering supports 6, so that the steel strand 5 is in an arc shape, and the two ends of the steel strand 5 are respectively fixed at the web of the main beam 2 corresponding to the positions of two adjacent cables of the replaced inclined cable 1 by using the anchoring device 3. Compared with the single-point prestressed support structure, the arrangement of multiple steering supports 6 allows the external prestressed steel strand 5 to form an arc-shaped prestressed support structure, so that a multi-point support structure is formed between the steel strand 5 and the main beam 2, so that the prestress applied by the steel strand 5 to the main beam 2 is more uniform, thereby improving the safety of the main beam 2.

[0058] To solve the problem of cable replacement in thick beams, Figure 5 As shown, step S2 installs external prestressed facilities, sets up multiple groups of external prestressed facilities, installs one group of steering supports 6 at the web of the main beam 2 corresponding to the position of the inclined cable 1 to be replaced, and installs another group of steering supports 6 at the lower position of the previous group of steering supports 6, and the lower parts of several groups of steering supports 6 are all installed with steel strands 5, and the two ends of several groups of steel strands 5 are respectively fixed at the web of the main beam 2 corresponding to the positions of two adjacent cables of the replaced inclined cable 1 by using anchoring devices 3, so that the multiple groups of external prestressed facilities are vertically distributed to form a multi-point prestressed support structure, and through the setting of multiple external prestressed facilities, multiple groups of prestressed support structures are sequentially set from top to bottom at the position of the inclined cable 1 to be replaced, so that the position of the inclined cable 1 to be replaced forms multi-point support, thereby improving its safety.

[0059] When the old cable is removed in step S3, the external prestressing force needs to be tensioned in stages, specifically 30%→60%→80%→90%→100%, and the tensioning is synchronized with the tensioning of the old cable. The inclined cable 1 at the tower end is tensioned using a hydraulic jack, and the two inclined cables 1 with the same cable number should be tensioned symmetrically during tensioning; after the inclined cable 1 at the tower end is tensioned, the inclined cable 1 at the beam end is tensioned using a winch, and the cable body is pulled by the winch to separate the anchor cup nut from the anchor pad, the anchor cup nut at the beam end is removed, and the winch traction system is loosened until the anchor cup at the beam end is withdrawn from the cable guide tube and the winch traction system is not stressed; after the beam end is tensioned, the tower end inclined cable 1 is removed, and the winch set on the top of the tower is used to slowly lower the inclined cable 1, and the winch is used to pull the anchor cup at the beam end to the anchoring direction at the beam end. A single-axle trolley is placed at a certain distance when the cable body is lowered, and the cable body is transported by the single-axle trolley, and the cable body is pulled out of the construction area to wait for cutting.

[0060] When installing a new cable in step S4, the cable-stayed cable 1 to be installed is transported to the bridge by a flatbed truck, and the cable body is pulled out a certain distance by the tower top hanger and placed on the beam surface, and a connecting sleeve and a tensioning rod are installed at the rear end of the anchor cup of the cable-stayed cable 1; a winch is arranged in the tower, and a steel wire rope is led downward from the corresponding cable guide tube in the tower to connect the main bridge deck cable-stayed cable 1. During lifting, the tower top hanger and the winch in the tower cooperate with each other to lead the anchor cup of the tensioning end out of the tower end anchor pad, and then install the tensioning equipment in the tower; when the cable-stayed cable 1 is a long cable, it is necessary to extend the cable on the beam surface after the tower end of the cable-stayed cable 1 is hung;

[0061] The anchor cups of the beam-end inclined cables 1 and tower-end inclined cables 1 need to be pulled to the designed position of the cable guide tube. This pulling is soft pulling.

[0062] After the soft traction of the tower end and beam end inclined cable 1 is completed, the tower end inclined cable 1 still needs hard traction; the hard traction method is tensioning, and an auxiliary tensioning rod is installed at the rear end of the main tension rod, and the auxiliary tensioning rod is tensioned until the main tension rod is pulled out of the hydraulic jack, and the main tension rod nut is installed, and the traction is continued until the anchor cup nut is installed to the flat cap state, and the traction is stopped and the auxiliary tensioning rod is removed.

[0063] When the tensioning equipment in the tower is installed, tensioning begins. Each group of inclined cables 1 is tensioned synchronously and symmetrically in two directions on a single tower. Each tensioning force should be tensioned in stages from 30% to 60% to 80% to 90% to 100% of the final cable force. When tensioning the tower end, the external prestress at the beam end of the two adjacent inclined cables 1 of the cable is released synchronously and in stages. The external prestress is released in stages from 70% to 40% to 20% to 10% to 0% of the final tensioning force.

[0064] Installation accessories include built-in shock absorbers, anchor cup anti-corrosion and protective covers, waterproof covers, stainless steel sheaths, etc.

[0065] Step S5 checks and replaces the next cable. According to the actual situation on site, after the new cable is installed, measure the cable force, bridge deck elevation and stress, check whether there are cracks or changes in crack width on the bridge deck to ensure that it meets the design requirements and meets the functional and safety requirements. After the inspection is completed, repeat the above steps and continue to replace the next cable.

[0066] In step S2 , the external prestressed equipment includes an anchoring device 3 , a jack 4 , a steel strand 5 and a steering support 6 . The steel strand 5 is located at the lower part of the steering support 6 , and the anchoring device 3 and the jack 4 are both arranged at both ends of the steel strand 5 .

[0067] like Figure 6 As shown, when the steering support 6 is in use, the rotating cap 10 is rotated so that the rotating cap 10 drives the threaded rod 9 to rotate, and the threaded rod 9 drives the lifting rod 8 to move up and down by using the thread structure, so that the lifting rod 8 adjusts the use height of the guide wheel 7.

[0068] When using it, the traditional technology directly replaces the cable on the bridge body. The beam position without the cable will lose tension, causing the stress of the beam structure to change, increasing the risk of replacing the cable.

[0069] To this end, by setting up an external prestressing facility, when the inclined cable 1 of the bridge body is replaced, prestressing can always be provided to the main beam 2 during the cable replacement process, reducing the impact on the deflection and structural stress of the main beam 2 during the cable replacement process, and ensuring the safety of the main beam 2 structure during the cable replacement process;

[0070] During operation, the installation position of the anchor device 3 is at the web of the main beam 2 corresponding to the positions of the two adjacent cables of the replaced inclined cable 1, and the anchor device 3 is fixed to the web anchoring area of ​​the main beam 2 by chemical anchor bolts. The installation position of the steering support 6 is at the web of the main beam 2 corresponding to the position of the replaced inclined cable 1, and is fixed to the web anchoring area of ​​the main beam 2 by chemical anchor bolts, so that the steel strand 5 abuts against the lower end of the steering support 6, and the guide wheel 7 at the lower end of the steering support 6 is used to dock the steel strand 5, so that the external prestressed steel strand 5 is in a V-shaped structure as a whole. The setting of a single steering support 6 forms a single-point prestressed support structure between the external prestressed steel strand 5 and the main beam 2, with the position of the lower end of the inclined cable 1 as the prestressing point, and the two ends of the steel strand 5 are respectively fixed to the lower position of the adjacent cables on both sides, and prestress is applied to it by the two adjacent inclined cables 1 on both sides, so as to prevent the main beam 2 from bending downward due to loss of tension when the inclined cable 1 is disassembled:

[0071] When removing the old cable, the external prestressing force needs to be tensioned in stages, specifically 30% → 60% → 80% → 90% → 100%, and the tensioning is synchronized with the tensioning of the old cable. The inclined cable 1 at the tower end is tensioned using a hydraulic jack 4. When tensioning, the two inclined cables 1 with the same cable number should be tensioned symmetrically; after the inclined cable 1 at the tower end is tensioned, the inclined cable 1 at the beam end is tensioned using a winch, and the cable body is pulled by the winch to separate the anchor cup nut from the anchor pad, and the anchor cup nut at the beam end is removed, and the winch traction system is loosened until the anchor cup at the beam end is withdrawn from the cable guide tube and the winch traction system is not stressed; after the beam end is tensioned, the tower end inclined cable 1 is removed, and the winch installed on the top of the tower is used to slowly lower the inclined cable 1, and the winch is used to pull the anchor cup at the beam end to the anchoring direction at the beam end. When the cable body is lowered, a single-axle trolley is placed at a certain distance, and the cable body is transported by the single-axle trolley, and the cable body is pulled out of the construction area to wait for cutting;

[0072] Traditional technology is not suitable for cable replacement operations with large spacing. When the spacing between multiple groups of inclined cables in the bridge is large, the single-point prestressed support structure cannot evenly distribute the prestress on the main beam, and the use effect is poor;

[0073] To this end, by providing a plurality of steering supports 6 of different heights, the steel strands 5 are installed in an arc-shaped state at the web of the main beam 2, so that it has an arc-shaped prestressed support structure, making the prestress distribution of the main beam 2 more uniform, and can be better suitable for the replacement operation of the inclined cable 1 with a longer spacing;

[0074] During operation, a group of steering supports 6 is installed at the web of the main beam 2 corresponding to the position of the inclined cable 1 to be replaced, and several groups of steering supports 6 are sequentially installed at the webs of the main beam 2 on both sides of the position of the inclined cable 1 to be replaced. The heights of the several groups of steering supports 6 are in a decreasing state. When the height of the steering supports 6 is adjusted, the rotating cap 10 is rotated to drive the threaded rod 9 to rotate, and the threaded rod 9 uses the threaded structure to drive the lifting rod 8 to move up and down, so that the lifting rod 8 adjusts the use height of the guide wheel 7, and the steel strand 5 is passed through the lower part of several groups of steering supports 6, so that the steel strand 5 is in an arc shape, and the two ends of the steel strand 5 are respectively fixed at the web of the main beam 2 corresponding to the positions of two adjacent cables of the replaced inclined cable 1 by using the anchoring device 3. Compared with the single-point prestressed support structure, the setting of multiple steering supports 6 allows the external prestressed steel strand 5 to form an arc-shaped prestressed support structure, so that a multi-point support structure is formed between the steel strand 5 and the main beam 2, so that the prestress applied by the steel strand 5 to the main beam 2 is more uniform, thereby improving the safety of the main beam 2;

[0075] Traditional technology is not suitable for the replacement of the cable of thicker main beams, because the single-point prestressed support structure uses a steel strand for auxiliary support, which makes it unable to meet the requirements of thicker main beams, reducing its scope of use;

[0076] To this end, multiple sets of external prestressing facilities are provided to make the steel strands 5 equally spaced up and down, so that it has a multi-point prestressed support structure, so that it can cope with the replacement operation of the inclined cables 1 on the main beams 2 of different thicknesses, and improve the prestressed support strength of the main beam 2 structure;

[0077] When in use, multiple groups of external prestressed facilities are set up, one group of steering supports 6 is installed at the web of the main beam 2 corresponding to the position of the inclined cable 1 to be replaced, and another group of steering supports 6 is installed at the lower position of the previous group of steering supports 6. The lower parts of several groups of steering supports 6 are all installed with steel strands 5, and the two ends of several groups of steel strands 5 are respectively fixed at the web of the main beam 2 corresponding to the positions of two adjacent cables of the replaced inclined cables 1 by using anchoring devices 3, so that the multiple groups of external prestressed facilities are vertically distributed to form a multi-point prestressed support structure. Through the arrangement of multiple external prestressed facilities, multiple groups of prestressed support structures are arranged in sequence from top to bottom at the position of the inclined cable 1 to be replaced, so that the position where the inclined cable 1 is to be replaced forms multi-point support, thereby improving the prestressed support strength and safety of the main beam 2 structure.

[0078] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any brief modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.

Claims

1. A construction method for replacing an external prestressed auxiliary cable, characterized in that: The following steps are involved: Step S1, construction preparation, measuring the old cable force and cable length on the bridge body, measuring the bridge deck elevation, and preparing construction machinery and materials; Step S2, installing an external prestressing device, installing an external prestressing device at the outer web of the main beam (2) where the cable needs to be replaced; Step S3, dismantling the old cables and their ancillary facilities, detecting the initial loosening force of the cable body, and synchronously performing the staged tensioning of the external prestressing facilities and the staged release of the old inclined cables (1); Step S4, installing new cables, transporting new cables to the bridge, laying cables on the beam surface, hanging them at the tower end, traction at the beam end and traction at the tower end, synchronously performing staged tensioning of the external prestressing facilities and staged tensioning of the new cables, and installing accessories; Step S5, check and replace the next cable; Step S6, dismantling the external prestressing facilities; Step S7, repeat steps S1-S6 to complete the replacement of all the inclined cables (1) in sequence.

2. The construction method for replacing an external prestressed auxiliary cable according to claim 1 is characterized in that: When installing the extracorporeal prestressing facility in step S2, the arrangement quantity of the steel strands (5) and the tensioning control stress are calculated, the installation position of the anchor device (3) is at the web of the main beam (2) corresponding to the positions of the two adjacent cables of the replaced inclined cable (1), and is fixed to the web anchoring area of ​​the main beam (2) by chemical anchor bolts, and the installation position of the steering support (6) is at the web of the main beam (2) corresponding to the position of the replaced inclined cable (1), and is fixed to the web anchoring area of ​​the main beam (2) by chemical anchor bolts, so that the steel strands (5) abut against the lower end of the steering support (6).

3. The construction method for replacing an external prestressed auxiliary cable according to claim 1 is characterized in that: In step S2, when installing the external prestressing facility, a group of steering supports (6) are installed at the web of the main beam (2) corresponding to the position of the inclined cable (1) to be replaced, and several groups of steering supports (6) are installed in sequence at the webs of the main beam (2) on both sides of the position of the inclined cable (1) to be replaced, and the heights of the several groups of steering supports (6) are in a decreasing state. The steel strand (5) is passed through the lower part of the several groups of steering supports (6) so that the steel strand (5) is in an arc shape, and the two ends of the steel strand (5) are respectively fixed to the webs of the main beam (2) corresponding to the positions of two adjacent cables of the replaced inclined cable (1) by using the anchoring device (3).

4. The construction method for replacing an external prestressed auxiliary cable according to claim 1 is characterized in that: Step S2 is to install the external prestressing facilities, and to set up a plurality of groups of external prestressing facilities. A group of steering supports (6) is installed at the web of the main beam (2) corresponding to the position of the inclined cable (1) to be replaced, and another group of steering supports (6) is installed at the lower position of the previous group of steering supports (6). The lower parts of the plurality of groups of steering supports (6) are all installed with steel strands (5), and the two ends of the plurality of groups of steel strands (5) are respectively fixed at the web of the main beam (2) corresponding to the positions of two adjacent cables of the replaced inclined cable (1) by using anchoring devices (3), so that the plurality of groups of external prestressing facilities are vertically distributed.

5. The construction method for replacing an external prestressed auxiliary cable according to claim 1 is characterized in that: When removing the old cable in step S3, the external prestressing force needs to be tensioned in stages, specifically 30%→60%→80%→90%→100%, and the tensioning is synchronized with the tensioning of the old cable. The inclined cable (1) at the tower end is tensioned using a hydraulic jack, and the two inclined cables (1) with the same cable number are tensioned symmetrically during tensioning. After the inclined cable (1) at the tower end is tensioned, the inclined cable (1) at the beam end is tensioned using a winch, and the cable body is pulled by the winch to separate the anchor cup nut from the anchor pad, and the anchor cup nut at the beam end is removed, and the winch traction system is relaxed until the anchor cup at the beam end is withdrawn from the cable guide tube and the winch traction system is not stressed. After the beam end is tensioned, the tower end inclined cable (1) is removed, and the inclined cable (1) is slowly lowered using a winch arranged at the top of the tower.

6. The construction method for replacing an external prestressed auxiliary inclined cable according to claim 1 is characterized in that: In step S4, when installing a new cable, the cable (1) to be installed is transported to the bridge by a flatbed truck, and the cable body is pulled out a certain distance and placed on the beam surface by using the tower top hanger, and a connecting sleeve and a tensioning rod are installed at the rear end of the anchor cup of the cable (1); a winch is arranged in the tower, and a steel wire rope is led downward from the corresponding cable guide tube in the tower to connect the main bridge deck cable (1). During lifting, the tower top hanger and the winch in the tower cooperate with each other to lead the tensioning end anchor cup out of the tower end anchor pad, and then install the tensioning equipment in the tower; when the cable (1) is a long cable, it is necessary to extend the cable on the beam surface after the tower end of the cable (1) is hung; The beam end inclined cable (1) and the tower end inclined cable (1) both need to pull the anchor cup to the designed position of the cable guide tube, and this pulling is soft pulling; After the soft traction of the tower end and beam end inclined cables (1) is completed, the tower end inclined cables (1) still need hard traction; the hard traction method is tensioning, installing an auxiliary tensioning rod at the rear end of the main tension rod, tensioning the auxiliary tensioning rod, installing the main tension rod nut, and continuing to pull until the anchor cup nut is installed to the flat cap state, stopping the traction, and removing the auxiliary tensioning rod.

7. The construction method for replacing an external prestressed auxiliary cable according to claim 1 is characterized in that: When the tensioning equipment in the tower is installed, tensioning begins, and each group of the inclined cables (1) is tensioned in stages according to the bidirectional symmetry of a single tower.

8. The construction method for replacing an external prestressed auxiliary cable according to claim 1 is characterized in that: Step S5 is to check and replace the next cable. After the new cable is installed, the cable force, bridge deck elevation and stress are measured to check whether cracks appear on the bridge deck or whether the crack width changes.

9. The construction method for replacing external prestressed auxiliary inclined cables according to claim 7, characterized in that: In step S2, the external prestressed equipment comprises an anchoring device (3), a jack (4), a steel strand (5) and a steering support (6), wherein the steel strand (5) is located at the lower part of the steering support (6), and the anchoring device (3) and the jack (4) are both arranged at both ends of the steel strand (5).

10. The construction method for replacing external prestressed auxiliary inclined cables according to claim 3, characterized in that: When the steering support (6) is in use, the rotating cap (10) is rotated so that the rotating cap (10) drives the threaded rod (9) to rotate, and the threaded rod (9) drives the lifting rod (8) to move up and down by using the thread structure, so that the lifting rod (8) adjusts the use height of the guide wheel (7).