Construction method for pulling out joint pipe in wall section connection construction of underground diaphragm wall
By determining the minimum and actual pipe removal ages and controlling the pipe removal process parameters, the construction difficulties in connecting underground continuous wall segments were solved, ensuring construction safety and seepage prevention.
Patent Information
- Application Number
- CN202411009918.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-26
- Publication Date
- 2024-11-12
AI Technical Summary
In existing technologies, the process of pulling out the joint pipe during the construction of underground continuous wall segments is difficult to control, which can easily lead to the collapse of the concrete borehole wall and pipe casting accidents, affecting construction safety and seepage prevention.
By determining the minimum and actual pipe removal ages, the parameters of the pipe removal process are controlled, including gradually pulling out the joint pipe after the concrete reaches a certain strength, and filling the pipe with mud and adjusting the speed during the pipe removal process to ensure construction stability.
This ensured the safe and stable construction of the underground continuous wall segment connection, avoided concrete borehole wall collapse and pipe casting accidents, and guaranteed the borehole quality of the anti-seepage wall.
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of continuous wall construction, in particular to a construction method for pulling out a joint pipe during the construction of connecting wall sections of an underground continuous wall. Background Art
[0002] The anti-seepage wall is generally made up of various unit wall sections. The construction method without wall section is only available in the self-setting mortar anti-seepage wall. The joints between wall sections are the weak links of the anti-seepage wall; if the connection is not good, concentrated leakage may occur, reducing the anti-seepage effect. The basic requirements for the connection of wall sections are close contact, long seepage diameter and good integrity. According to different construction methods, the connection of wall sections can be divided into drilling method, joint pipe (plate) method, double reverse arc method, cutting (milling) method and other construction methods.
[0003] The construction procedure of the joint pipe method is: before pouring the first phase slot hole, joint pipes are set at both ends of the slot hole. After a certain period of time, the joint pipes are gradually pulled out to form a joint hole, and then the joint hole is used as the end hole of the adjacent second phase slot hole. The construction of pulling out pipes to form holes requires high technical capabilities, management level and more practical experience. At the same time, it is affected by factors such as the characteristics of concrete, hole diameter, hole depth, pouring speed, temperature, etc. If the pulling is started too early, the concrete hole wall will collapse and the hole cannot be formed; if the pulling is started too late, it will cause a pipe casting accident and even endanger the safety of the hole mouth. Therefore, the control of the pipe pulling construction process is extremely difficult. Summary of the invention
[0004] In response to the problems in the control process of the above-mentioned pipe pulling process, the present invention has studied and developed a construction method for pulling out the joint pipe during the construction of underground continuous wall section connections, which provides detailed parameter control guidance for each stage of the pipe pulling process and provides a basis for stable operation of on-site pipe pulling construction.
[0005] In order to achieve the above object, the present invention adopts the following technical scheme: a construction method for pulling out a joint pipe during the construction of connecting wall sections of an underground continuous wall, comprising the following steps:
[0006] S1. Determine the minimum age of pipe removal: Take samples to form compressive strength test blocks when concrete is poured. When the strength reaches 0.02-0.04MPa, the age of the test block is determined as the minimum age of pipe removal;
[0007] S2. Casting and pipe pulling: Start micro-movement 3-5 hours after casting. After that, the interval of the movable joint pipe should not exceed 30 minutes, and lift 1-2 cm each time. When the age of the concrete at the bottom of the pipe reaches the determined minimum pipe removal age, gradually pull out the joint pipe according to the concrete casting speed;
[0008] S3. Process control in the final stage of pipe pulling construction: the pipe should be filled with mud and the pipe pulling speed should be appropriately reduced. The last section of pipe should stay in the hole for 1-2 hours.
[0009] Preferably, in step S1, 6 to 8 compressive strength test blocks are sampled and formed, and after 3 to 4 hours, one block is demolded every 0.5 to 1.0 hours to observe its coagulation and forming conditions.
[0010] Preferably, the age of the concrete should be calculated from the time when the bottom of the pouring conduit is above this point and the concrete at this point is in a static state.
[0011] Specifically, in some embodiments of the present invention, the step S2 further includes determining whether the hole forming is normal, if so, continuing to pull out the pipe; if not, the bottom door is opened normally, extending the pipe removal age of the concrete, and suspending the pipe pulling.
[0012] Specifically, in some embodiments of the present invention, in step S2, if the tube removal resistance is too small, the tube removal should be suspended or the tube removal speed should be reduced by no more than 0.01 m / min; when the hole formation is normal but the tube removal resistance is too large, the tube removal speed should be accelerated to 0.6-0.7 m / min.
[0013] Preferably, the extubation resistance ranges from 4 to 10 MPa.
[0014] Preferably, in step S3, a movable joint pipe is required during the stay process.
[0015] Specifically, in some embodiments, the present invention further comprises step S4. Before the joint pipe is brought out, the actual hole depth should be measured and recorded.
[0016] Compared with the prior art, the present invention has the following beneficial effects:
[0017] 1. The present invention provides a construction method for pulling out a joint pipe during the construction of connecting wall sections of an underground continuous wall. By determining the minimum pipe-pulling age at which the cut-off wall concrete can be pierced, and controlling and judging the actual pipe-pulling age during the pipe-pulling process, the pipe-pulling construction process is ensured to be carried out safely and stably, the hole formation is stable, the concrete hole wall collapse and the pipe casting accident problem are avoided, and a theoretical basis and guidance are provided for on-site operations of the pipe-pulling construction. DETAILED DESCRIPTION
[0018] In order to make the technical scheme of the present invention more clearly understood by those skilled in the art, the following embodiments are listed for illustration. It should be pointed out that the following embodiments do not limit the protection scope of the present invention.
[0019] The invention provides a construction method for pulling out a joint pipe during the construction of connecting wall sections of an underground continuous wall. By determining a minimum pipe pulling age and an actual pipe pulling age, pipe pulling process parameters are controlled to ensure stable hole forming during pipe pulling and hole forming construction.
[0020] This embodiment provides a construction method for pulling out a joint pipe during construction of connecting wall sections of an underground continuous wall, comprising the following steps:
[0021] S1. Determine the minimum age of pipe removal: Take samples to form compressive strength test blocks when concrete is poured. When the strength reaches 0.02-0.04MPa, the age of the test block is determined as the minimum age of pipe removal;
[0022] S2. Casting and pipe pulling: Start micro-movement 3-5 hours after casting. After that, the interval of the movable joint pipe should not exceed 30 minutes, and lift 1-2 cm each time. When the age of the concrete at the bottom of the pipe reaches the determined minimum pipe removal age, gradually pull out the joint pipe according to the concrete casting speed;
[0023] S3. Process control in the final stage of pipe pulling construction: the pipe should be filled with mud and the pipe pulling speed should be appropriately reduced. The last section of pipe should stay in the hole for 1-2 hours.
[0024] Specifically, in step S1, the minimum pipe-out age of the anti-seepage wall concrete that can form holes is related to the characteristics of the concrete, hole diameter, hole depth, pouring speed, temperature and other factors. It is generally 5 to 8 hours, or even longer. It must be determined through experiments and sampled and verified when pouring. Generally speaking, the pipe-out age of concrete is not equal to the initial setting time of concrete, but the time that concrete can be formed under a certain pressure (equivalent to the time required for the concrete strength to reach 0.1 to 0.2 MPa). It must also be pointed out that the age of concrete should be calculated from the time when the bottom of the pouring conduit is higher than this position (after the concrete at this point is in a static state).
[0025] In this embodiment, in order to avoid the error between the conditions and results of the indoor test and the actual situation, 6 to 8 compressive strength test pieces must be sampled and formed when the concrete is poured. After 3 to 4 hours, one piece is demolded every 0.5 to 1.0 hours to observe its coagulation and forming conditions. When its strength reaches 0.02-0.04MPa, the age of the test piece can be determined as the minimum pipe-out age.
[0026] Furthermore, in order to grasp the actual age of the concrete at each contact part outside the joint pipe, the pouring of the concrete must be mastered in detail. In the step S2, the construction process should be recorded in a timely and accurate manner during construction. The pouring construction and the pipe pulling construction should be closely coordinated, and the pouring speed should not be too fast. Micro-movement begins 3 hours after the pouring. After that, the interval time of the movable joint pipe should not exceed 30 minutes, and it should be lifted 1 to 2 cm each time to break the adhesion of the concrete. The time of micro-movement should not be too early or too frequent, otherwise it will be detrimental to the coagulation of the concrete and the stability of the hole wall. When the age of the concrete at the bottom of the pipe reaches the determined age for pipe removal, the joint pipe can be gradually pulled out according to the pouring speed of the concrete.
[0027] It should be noted that since the determined pipe removal age is not necessarily very accurate, the actual pipe removal age cannot be completely consistent with the determined pipe removal age. Therefore, during the pipe removal process, it is necessary to pay attention to the pipe removal resistance, the changes in the mud surface in the pipe, and the opening and closing of the valve at the bottom of the pipe at any time, and adjust the pipe removal time and pipe removal speed in time. When the bottom door is opened during pipe removal, the slurry surface in the pipe drops after pipe removal, indicating that the hole formation of the part that has been removed is normal, otherwise it means that the concrete at the bottom of the pipe is followed up and cannot be normally formed. At this time, it should be checked whether the bottom door can be opened normally. If there is no problem with the valve, it means that the pipe removal time is too early, the concrete removal age should be extended, and the pipe removal should be suspended. When the pipe removal resistance reflected by the pressure gauge is too small, the pipe removal should be suspended or the pipe removal speed should be reduced (the pipe removal speed is 0.01m / min); when the hole formation is normal but the pipe removal resistance is too large, the pipe removal speed should be appropriately accelerated (the pipe removal speed is 0.6-0.7m / min). Preferably, the pipe removal resistance range is 4 to 10MPa.
[0028] Among them, the bottom pipe valve is a valve that can prevent concrete from entering the pipe and facilitate the entry and exit of mud. The valve should be able to open and close automatically. Through the reverse rotation of the top pulley of the pipe, the valve is automatically controlled by a small steel wire rope connected in sections and a counterweight slightly heavier than the valve. During pouring, the valve is closed under the action of the counterweight, and concrete cannot enter the pipe. When pulling the pipe, the pressure of the mud in the pipe exceeds the upward pulling force of the counterweight and the steel wire rope, the valve opens, and the mud in the pipe flows out. The valve can also be pulled by a spring or elastic tape.
[0029] Furthermore, in step S3, in the final stage of the pipe pulling construction, attention should be paid to timely filling the pipe with mud and appropriately reducing the pipe pulling speed. The last section of the pipe should stay in the hole for a longer time (which can be extended by 1-2 hours, and the joint pipe must be movable during the extension process) to prevent the hole from collapsing.
[0030] In this embodiment, step S4 is also included, before the joint pipe is brought out, the actual hole depth should be measured and recorded.
[0031] The principles and implementation methods of the present invention are described in this article using specific examples. The description of the above embodiments is only used to help understand the method and core idea of the present invention. At the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
[0032] The principles and implementation methods of the present invention are described in this article using specific examples. The description of the above embodiments is only used to help understand the method and core idea of the present invention. At the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
Claims
1. A construction method for pulling out a joint pipe during the construction of connecting wall sections of an underground continuous wall, characterized in that: The following steps are involved: S1. Determine the minimum age of pipe removal: Take samples to form compressive strength test blocks when concrete is poured. When the strength reaches 0.02-0.04MPa, the age of the test block is determined as the minimum age of pipe removal; S2. Casting and pipe pulling: Start micro-movement 3-5 hours after casting. After that, the interval of the movable joint pipe should not exceed 30 minutes, and lift 1-2 cm each time. When the age of the concrete at the bottom of the pipe reaches the determined minimum pipe removal age, gradually pull out the joint pipe according to the concrete casting speed; S3. Process control in the final stage of pipe pulling construction: the pipe should be filled with mud and the pipe pulling speed should be appropriately reduced. The last section of pipe should stay in the hole for 1-2 hours.
2. A construction method for pulling out a joint pipe during construction of connecting wall sections of an underground continuous wall according to claim 1, characterized in that: In the step S1, 6 to 8 compressive strength test blocks are sampled and formed, and after 3 to 4 hours, one block is demolded every 0.5 to 1.0 hours to observe the coagulation and forming conditions.
3. A construction method for pulling out a joint pipe during construction of underground continuous wall segment connection according to claim 1, characterized in that: The step S2 also includes judging whether the hole forming is normal, if so, continuing to pull out the pipe; if not, the bottom door is opened normally, extending the pipe removal age of the concrete and suspending the pipe pulling.
4. A construction method for pulling out a joint pipe during construction of underground continuous wall segment connection according to claim 1 or 3, characterized in that: In step S2, if the tube removal resistance is too small, the tube removal should be suspended or the tube removal speed should be reduced by no more than 0.01 m / min; when the hole formation is normal but the tube removal resistance is too large, the tube removal speed should be accelerated to 0.6-0.7 m / min.
5. The construction method for pulling out the joint pipe during the construction of connecting wall sections of an underground continuous wall according to claim 1, characterized in that: In step S3, the joint pipe must be movable during the stay process.
6. A construction method for pulling out a joint pipe during construction of underground continuous wall segment connection according to claim 1, characterized in that: The method also includes step S4. Before the joint pipe is brought out, the actual hole depth should be measured and recorded.
7. A construction method for pulling out a joint pipe during construction of connecting wall sections of an underground continuous wall according to claim 1, characterized in that: The age of concrete should be calculated from the time when the bottom of the pouring pipe is above this point and the concrete at this point is in a static state.
8. The construction method for pulling out the joint pipe during the construction of connecting wall sections of an underground continuous wall according to claim 4, characterized in that: The extubation resistance ranges from 4 to 10 MPa.
Citation Information
Cited By
Hole forming method and mold for reserved drill hole of laboratory cement test piece
CN120791926A
Pipe drawing control method and system for joint pipe of ultra-deep diaphragm wall
CN120867350A
Three-valued method concrete strength detection system and diaphragm wall joint pipe pulling method