Secondary beam supporting device and method and application of secondary beam supporting device and method in floor concrete pouring
By using frame beams and flexible support systems in the secondary beam support device, combined with adjustment components and walking parts, the problem of lateral instability of secondary beams during concrete pouring is solved, and construction safety and economicality are improved.
Patent Information
- Application Number
- CN202411094135.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-11-12
AI Technical Summary
In high-rise buildings, secondary beams are prone to lateral instability due to their own weight during concrete pouring, resulting in increased construction safety risks, and it is difficult for the prior art to effectively prevent lateral instability.
采用包括楼面结构、角柱、框架梁、水平柔性支撑体系和纵向连接件的次梁支撑装置,通过预拉力形成侧向刚度较大的端桁架,并在必要时使用调节组件和行走件以调节拉力分布,确保次梁的侧向稳定。
It effectively improves the lateral stiffness of secondary beams during concrete construction, reduces construction safety risks, improves construction economy, and avoids the occurrence of lateral instability.
Smart Images

Figure CN118933181A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building structure construction, and particularly relates to a secondary beam supporting device, a supporting method and an application thereof in pouring floor concrete. Background Art
[0002] The floor structure of a high-rise building is generally composed of frame beams, secondary beams and steel truss floor decks. When designing the secondary beams, the reinforcement effect of the steel truss floor decks on the secondary beams can be fully utilized, that is, it is equivalent to a composite beam component consisting of the secondary beam and part of the floor deck. The advantage of this is that it can improve the utilization rate of materials and there is no need to set up lateral supports to limit lateral instability, thereby achieving the purpose of saving materials and improving construction economy.
[0003] The Chinese patent with application number CN201710367272.9 discloses a steel structure node for preventing lateral instability, which is used to connect the strut and the main beam. The steel structure node includes two lower ear plates, four upper ear plates and two inclined cables. The two lower ear plates are extended from the two flanges of the strut I-beam, and the four upper ear plates are arranged on one end of the main beam connected to the strut. Each of the lower ear plates is arranged between the two upper ear plates to form an articulated assembly, and the two lower ear plates and the four upper ear plates are connected through a pin shaft. The two inclined cables are arranged on both sides of the strut. Compared with the prior art, it has the advantages of effectively preventing the out-of-plane instability of the concave tensioned beam and improving the overall safety of the structure. However, the span of such secondary beams is often large, and during the pouring of floor concrete, the concrete does not form sufficient strength before hardening. When the secondary beam is made of I-beam, due to the large span of the secondary beam and the large web height, the ratio of the external moment of inertia of the secondary beam to the in-plane moment of inertia will be small. Therefore, if there is no lateral support restriction, the secondary beam will tend to be lateral unstable due to its own weight when pouring concrete on the floor.
[0004] The lateral instability of the secondary beam will bring serious safety risks to the construction of the floor structure of high-rise buildings. Due to the low lateral stiffness of the secondary beam, construction workers may cause large lateral displacement when working on the floor, thus causing unnecessary safety accidents. In addition, if a construction platform needs to be set up on the floor during construction, the lateral instability of the secondary beam may cause devastating damage under the influence of equipment load and wind load. Summary of the invention
[0005] The object of the present invention is to provide a secondary beam supporting device, a supporting method and an application thereof in floor concrete pouring, so as to avoid safety problems caused by lateral instability of the floor secondary beam during concrete pouring construction.
[0006] To achieve the above object, the present invention provides the following technical solutions: A secondary beam support device comprises a floor structure, wherein four corners of the floor structure are provided with corner columns, and the corner columns support the four corners of the floor structure; The floor structure includes frame beams distributed in an array, and the two ends of the frame beams are respectively connected to the opposite sides of two adjacent corner columns, and the frame beams and the corner columns together form a frame frame, and the frame frame is provided with secondary beams distributed in an array, and the top of the frame frame is provided with a steel truss floor deck, and the top of the secondary beam is connected to the steel truss floor deck; Both ends of the floor structure are provided with a horizontal flexible support system and a longitudinal connection piece arranged horizontally along the longitudinal direction of the floor structure.
[0007] Preferably, the horizontal flexible support system forms an end truss together with the secondary beam at both ends of the floor structure, and the horizontal flexible support system comprises horizontal cross connectors arranged in an array at the ends of the floor structure, one end of the horizontal cross connector is connected to the frame beam, and the other end of the horizontal cross connector is connected to the secondary beam; A rigid tie rod is provided between two adjacent horizontal cross-connecting members, one end of the rigid tie rod is connected to the frame beam, and the other end of the rigid tie rod is connected to the secondary beam.
[0008] Preferably, both ends of the longitudinal connector are respectively connected to two end trusses, the longitudinal connector intersects with the ends of the secondary beams distributed in the frame, and a fixed connection is formed at the intersection of the longitudinal connector and the secondary beams.
[0009] Preferably, the longitudinal connecting member comprises a horizontal cable, which is arranged at the end of the secondary beam, and a fixed connection is formed between the horizontal cable and the secondary beam, and the horizontal cable provides lateral support for the secondary beam.
[0010] Preferably, the longitudinal connector comprises a plurality of horizontal cables, which are distributed at the ends of the secondary beam at the same intervals, and the horizontal cables are fixedly connected to the secondary beam at their intersections, and the horizontal cables provide lateral support for the secondary beam.
[0011] Preferably, an adjustment component is provided between two adjacent secondary beams, and the adjustment component includes symmetrically arranged sliding tracks, and the two sliding tracks are respectively connected to the corresponding bottoms of the secondary beams. An array-distributed adjustment part is provided between the two adjacent sliding tracks, and both ends of the adjustment part are connected to walking parts through steel cables, and the walking parts slide back and forth on the sliding tracks.
[0012] Preferably, the adjusting portion comprises a hollow cylinder, both ends of the hollow cylinder are provided with through holes, and the interior of the hollow cylinder is provided with symmetrically distributed telescopic parts; A fixed disk is provided at the output end of the telescopic member, and the fixed disk is slidably connected to the hollow cylinder in an axial limited position. An elastic member is provided at the end of the fixed disk, and a movable disk is provided at the end of the elastic member, and the movable disk is slidably connected to the hollow cylinder in an axial limited position. The end of the movable disk is connected to the steel cable, and one end of the steel cable passes through the through hole and is connected to the walking member.
[0013] Preferably, the walking member comprises a frame connected to the steel cable, and an end of the frame facing the sliding track is provided with walking wheels distributed in an array, and the walking wheels are slidably connected to the sliding track; A transmission wheel is provided at one end of the walking wheel extending into the frame, and a transmission belt is commonly connected between the transmission wheels located on the same side. A transmission gear is provided at the end of the transmission wheel, and a driving gear is meshed on the outer side of the transmission gear. A driving device is provided at the end of the driving gear, and the driving device is connected to the frame.
[0014] A supporting method for a secondary beam supporting device, the supporting method comprising the following steps: S1. For a floor structure, first install the frame beams with both ends connected to the corner columns, so that the frame beams and the corner columns together form a frame, and then complete the installation of the secondary beams in the frame; S2. Install a horizontal flexible support system between two adjacent frame beams and secondary beams at both ends of the floor structure to form an end truss with greater lateral stiffness after the pre-tensioning force is applied; S3. Lay one or more longitudinal connectors so that both ends of the longitudinal connectors are connected to the end trusses at both ends of the floor structure. After applying the pre-tension force, connect the longitudinal connectors to the secondary beams; S4. Finally, install the floor steel trusses and pour the concrete floor slab. At this time, the floor structure has sufficient lateral rigidity and will not be lateral instability. S5. And so on, install the floor structures of subsequent floors in sequence.
[0015] The invention discloses an application of a secondary beam supporting device in pouring floor concrete.
[0016] Technical effects and advantages of the present invention: 1. The present invention uses a flexible support system to form an integral lateral-resistant structure for the floor structure, which effectively improves the lateral stiffness of the secondary beam during concrete pouring construction and ensures construction safety; steel cables or rods are used for reinforcement, and the material cost is low and can be reused repeatedly, which effectively improves the economy of construction; the steel cables or rods are light in weight, convenient to transport, and easy to install and remove, which can effectively reduce the difficulty of installation and improve construction efficiency; the reinforcement measures are only set up in the floor, which ensures the vertical space of the floor, so there is no interference with the lifting of components.
[0017] 2. The present invention sets an adjustment component and detects the values of tension sensors distributed on both sides of the secondary beam to obtain the buckling direction and buckling angle of the secondary beam, and controls the corresponding telescopic parts to stretch the steel cable according to the buckling direction and buckling angle of the secondary beam. The steel cable applies tension in the anti-buckling direction to the bottom wing plate of the secondary beam to avoid the possibility of further buckling of the secondary beam.
[0018] 3. The present invention sets a walking member and an adjusting part, and controls the walking member to drive the adjusting part to gather toward the maximum buckling area according to the area where the maximum buckling angle is distributed on the secondary beam, so that multiple telescopic members pull the maximum buckling area synchronously, avoiding that a single adjusting component cannot exert sufficient pulling force, resulting in the buckling phenomenon not being alleviated; at the same time, when the buckling angle of the maximum buckling area exceeds the threshold, the walking members on the secondary beam corresponding to the maximum buckling area gather in the direction of the maximum buckling area, and the rest diffuse outward, avoiding that the tension generated by the steel cable is concentrated in one area, increasing the risk of lateral instability of the secondary beams on both sides. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the main structure of the present invention; Figure 2 It is a top view schematic diagram of the main structure of the present invention; Figure 3 For the present invention Figure 2 Schematic diagram of the cross-sectional structure of the AA part and the BB part; Figure 4 It is a structural schematic diagram of the horizontal flexible support system of the present invention; Figure 5 It is a schematic diagram of the distribution of the adjustment components between the secondary beams of the present invention; Figure 6 The present invention is Figure 5 A schematic diagram of the enlarged structure at A in the middle; Figure 7 It is a structural schematic diagram of the regulating assembly of the present invention; Figure 8 It is a structural schematic diagram of the regulating part of the present invention; Fig. 9 It is a structural schematic diagram of the walking member of the present invention; Fig.10 It is a schematic diagram of the state after the secondary beam of the present invention is tilted; Fig.11 It is a schematic diagram of the state of the regulating component of the present invention when it is working; Fig.12 This is another schematic diagram of the working state of the regulating component of the present invention.
[0020] In the figure: 1. floor structure; 101. frame beam; 102. secondary beam; 103. steel truss floor deck; 2. corner column; 3. horizontal flexible support system; 301. horizontal cross connector; 302. rigid tie rod; 303. longitudinal connector; 4. adjustment assembly; 401. sliding track; 402. adjustment part; 4021. hollow cylinder; 4022. through hole; 4023. telescopic part; 4024. fixed plate; 4025. elastic part; 4026. movable plate; 403. steel cable; 404. walking part; 4041. frame; 4042. walking wheel; 4043. transmission wheel; 4044. transmission belt; 4045. transmission gear; 4046. driving gear. DETAILED DESCRIPTION
[0021] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Example
[0022] Reference Figures 1 to 3 As shown, the present invention discloses a secondary beam supporting device, comprising a floor structure 1 , wherein four corners of the floor structure 1 are provided with corner columns 2 , and the corner columns 2 support the four corners of the floor structure 1 .
[0023] The floor structure 1 includes an array of frame beams 101, both ends of which are connected to opposite sides of two adjacent corner columns 2 respectively. The frame beams 101 and the corner columns 2 together form a frame, in which an array of secondary beams 102 are arranged, and a steel truss floor deck 103 is arranged on the top of the frame, and the top of the secondary beams 102 is connected to the steel truss floor deck 103.
[0024] In this embodiment, the number of corner columns 2 and frame beams 101 is set to four. The four frame beams 101 are distributed between the four corner columns 2. The corner columns 2 support the frame beams 101. The tops of the four frame beams 101 are at the same horizontal height.
[0025] The frame beam 101 and the secondary beam 102 are both I-beam components. The web of the frame beam 101 is connected to the end of the secondary beam 102 through a connecting piece. The connecting piece includes a rib plate, which is arranged on the web of the frame beam 101. Clamping plates are provided on both sides of the rib plate, and positioning bolts are provided on the clamping plates. The rib plates on the frame beam 101 and the web of the secondary beam 102 are clamped and positioned by the clamping plates and the positioning bolts. The connection between the frame beam 101 and the secondary beam 102 by connecting pieces belongs to the prior art and will not be elaborated here.
[0026] Both ends of the floor structure 1 are provided with a horizontal flexible support system 3 and a longitudinal connector 303 arranged horizontally along the longitudinal direction of the floor structure 1. The horizontal flexible support system 3 and the longitudinal connector 303 form an integral lateral resistance structure of the floor structure 1, which effectively improves the lateral stiffness of the secondary beam 102 during the pouring of concrete, thereby ensuring construction safety.
[0027] Reference Figure 1 and Figure 2 As shown, the horizontal flexible support system 3 forms an end truss together with the secondary beam 102 at both ends of the floor structure 1. The horizontal flexible support system 3 includes horizontal cross connectors 301 arranged in an array at the end of the floor structure 1, one end of the horizontal cross connector 301 is connected to the frame beam 101, and the other end of the horizontal cross connector 301 is connected to the secondary beam 102.
[0028] The horizontal cross connection member 301 includes a horizontal cross tie rod or a cable, one end of which is fixedly connected to the frame beam 101 , and the other end of which is fixedly connected to the secondary beam 102 .
[0029] A rigid tie rod 302 is provided between two adjacent horizontal cross-connecting members 301 , one end of the rigid tie rod 302 is connected to the frame beam 101 , and the other end of the rigid tie rod 302 is connected to the secondary beam 102 .
[0030] Reference Figure 1 and Figure 2 As shown, both ends of the longitudinal connector 303 are connected to the two end trusses respectively, and the longitudinal connector 303 intersects with the ends of the secondary beams 102 distributed in the frame, and the intersection of the longitudinal connector 303 and the secondary beams 102 forms a fixed connection.
[0031] The longitudinal connecting member 303 includes a longitudinal tie rod or cable, one end of which is connected to one of the end trusses at both ends of the floor structure 1, and the other end of the longitudinal tie rod or cable is connected to the other end truss. The middle part of the longitudinal tie rod or cable is fixedly connected to the intersection of the secondary beam 102 distributed on the frame, and the longitudinal tie rod or cable provides lateral support for the secondary beam 102 distributed on the frame.
[0032] Specifically, the longitudinal connecting member 303 includes a horizontal cable, which is arranged at the end of the secondary beam 102 . The horizontal cable forms a fixed connection with the secondary beam 102 at the intersection, and the horizontal cable provides lateral support for the secondary beam 102 .
[0033] Specifically, the longitudinal connector 303 includes a plurality of horizontal cables, which are distributed at the ends of the secondary beam 102 at the same intervals. The intersections of the horizontal cables and the secondary beam 102 form a fixed connection, and the horizontal cables provide lateral support for the secondary beam 102 .
[0034] When installing the floor structure 1 , first install the frame beams 101 with both ends connected to the corner columns 2 so that four frame beams 101 form a frame, and then complete the installation of the secondary beams 102 in the frame, thus completing the preliminary installation of the floor structure 1 .
[0035] After the secondary beam 102 is installed, a horizontal flexible support system 3 is installed between the secondary beam 102 and the frame beam 101 at both ends of the floor structure 1. Specifically, an array of horizontal cross connectors 301 and rigid tie rods 302 are installed between the secondary beam 102 and the frame beam 101, so that the secondary beam 102 and the frame beam 101 at both ends of the floor structure 1 form an end truss with greater lateral stiffness.
[0036] Then, one or more longitudinal connectors 303 are laid on the secondary beam 102, so that the two ends of the longitudinal connector 303 are connected to the end trusses at the two ends of the floor structure 1. After the pre-tensioning force is applied, the longitudinal connector 303 and the secondary beam 102 are fixed at their intersections. Specifically, the longitudinal connector 303 and the secondary beam 102 can be welded together by welding.
[0037] After the longitudinal connector 303 is installed, both ends of the longitudinal connector 303 apply a pulling force to both sides of the secondary beam 102 , and at the same time connect the secondary beams 102 to form a whole, further improving the lateral supporting force of the secondary beam 102 .
[0038] It should be noted that the number of longitudinal connectors 303 is determined based on the stability calculation of the floor structure 1 under the action of its own weight when pouring concrete.
[0039] Finally, the floor steel trusses are installed and the concrete floor slabs are poured. At this time, the floor structure 1 has sufficient lateral rigidity and will not suffer from lateral instability. Example
[0040] Although the above embodiment 1 can provide lateral support for the secondary beam 102 through the horizontal flexible support system 3 and the longitudinal connector 303, in the actual application process, if the lateral support is insufficient, or the actual stress condition of the secondary beam 102 is not fully considered in the design, it will still lead to insufficient lateral support in some areas, thereby affecting the overall stability of the secondary beam 102. Therefore, improvements are made on the basis of embodiment 1, and the specific solutions are as follows: Reference Figures 1 to 12As shown, this example is different from Example 1 in that an adjustment component 4 is provided between two adjacent secondary beams 102, the adjustment component 4 includes symmetrically arranged sliding rails 401, the two sliding rails 401 are respectively connected to the bottom of the corresponding secondary beams 102, the sliding rails 401 are fixedly connected to the wing plate part at the bottom of the secondary beam 102, an array-distributed adjustment part 402 is provided between the two adjacent sliding rails 401, both ends of the adjustment part 402 are connected to a walking part 404 through a steel cable 403, and the walking part 404 can slide back and forth on the sliding rails 401.
[0041] The walking member 404 is driven by a driving device. After the driving device is started, the walking member 404 can move freely on the sliding track 401. When the walking member 404 moves on the sliding track 401, it simultaneously drives the adjusting part 402 to move, thereby changing the relative position of the adjusting part 402 between the two secondary beams 102.
[0042] Reference Figure 8 As shown, the adjustment part 402 includes a hollow cylinder 4021, both ends of the hollow cylinder 4021 are provided with through holes 4022, and the interior of the hollow cylinder 4021 is provided with symmetrically distributed telescopic parts 4023; the telescopic parts 4023 include electric push rods or hydraulic push rods, and when the telescopic parts 4023 are in a retracted state, the pulling force of the steel cable 403 on the secondary beam 102 is increased, and when the telescopic parts 4023 are in an extended state, the pulling force of the steel cable 403 on the secondary beam 102 is reduced.
[0043] A fixed disk 4024 is provided at the output end of the telescopic member 4023, and the fixed disk 4024 is axially limited and slidably connected to the hollow cylinder 4021. An elastic member 4025 is provided at the end of the fixed disk 4024, and a movable disk 4026 is provided at the end of the elastic member 4025. The movable disk 4026 is axially limited and slidably connected to the hollow cylinder 4021, and the end of the movable disk 4026 is connected to the steel cable 403, and one end of the steel cable 403 passing through the through hole 4022 is connected to the walking member 404.
[0044] The elastic member 4025 includes a spring, one end of which is connected to the fixed disk 4024, and the other end of the spring is connected to the movable disk 4026. A tension sensor is provided at the connection between the elastic member 4025 and the fixed disk 4024. By detecting the tension sensor value inside the adjusting cylinder, it is possible to determine whether the secondary beam 102 area corresponding to the adjusting cylinder is in a buckling state.
[0045] Reference Fig. 9 As shown, the walking member 404 includes a frame 4041 connected to the steel cable 403 , and one end of the frame 4041 facing the sliding track 401 is provided with an array of walking wheels 4042 , and the walking wheels 4042 are slidably connected to the sliding track 401 .
[0046] A transmission wheel 4043 is provided at one end of the walking wheel 4042 extending into the frame 4041, and a transmission belt 4044 is commonly connected between the transmission wheels 4043 on the same side. A transmission gear 4045 is provided at the end of the transmission wheel 4043, and a driving gear 4046 is meshed on the outer side of the transmission gear 4045. A driving device is provided at the end of the driving gear 4046, and the driving device is connected to the frame 4041.
[0047] The driving device includes a driving motor. After the driving motor is started, it drives the driving gear 4046 to rotate. The driving gear 4046 drives the driving wheel 4043 to rotate through the transmission gear 4045. The driving wheel 4043 drives the two walking wheels 4042 on the same side to rotate through the transmission belt 4044. The walking wheel 4042 drives the frame 4041 to move on the sliding track 401.
[0048] It should be noted that: the peripheral side of the traveling wheel 4042 is provided with an array of electromagnetic latches, and the sliding track 401 is provided with an array of slots, and the electromagnetic latches are plugged into the slots.
[0049] A control terminal is provided on the end truss formed by the frame beam 101 and the secondary beam 102 . A control system is provided inside the control terminal. The control system is used to control the specific operation of the regulating component 4 .
[0050] After the longitudinal connector 303 is laid, a sliding track 401 is installed at the bottom wing plates of two adjacent secondary beams 102, and a plurality of corresponding adjustment components 4 are arranged between the two adjacent sliding tracks 401, and the distance between the plurality of adjustment components 4 is at a set value.
[0051] After the adjustment component 4 is installed, the electromagnetic pins distributed on the control walking wheel 4042 are popped out to be plugged into the slots distributed on the track. Then the telescopic part 4023 inside the hollow cylinder 4021 is controlled to contract. The telescopic part 4023 pulls the elastic part 4025 to move toward the middle area of the hollow cylinder 4021 through the fixed disk 4024. The elastic part 4025 drives the steel cable 403 to move toward the middle area of the hollow cylinder 4021 through the movable disk 4026, so that the steel cable 403 is in a straight state. At this time, the elastic parts 4025 located at both ends of the hollow cylinder 4021 are in a stretched state, and the difference between the values detected by the tension sensors on the two elastic parts 4025 is in a stable state.
[0052] It should be noted that: when pouring concrete on the floor, the control system can control some hollow tubes 4021 on two adjacent secondary beams 102 to collide with the wing plates at the bottom of the secondary beams 102. After the wing plates of the secondary beams 102 are hit, a certain degree of vibration will be generated. Since the top of the secondary beam 102 is connected to the steel truss floor decking 103, the vibration generated by the secondary beam 102 can be transmitted to the poured concrete through the steel truss floor decking 103, so that the distribution of the poured concrete on the steel truss floor decking 103 is more even, avoiding uneven distribution of the poured concrete on the steel truss floor decking 103, causing the strength of some areas of the floor to be higher or lower than other areas, affecting the load distribution on the secondary beam 102.
[0053] The specific action of the hollow tube 4021 hitting the wing plate at the bottom of the secondary beam 102 is: controlling the two telescopic parts 4023 inside the hollow tube 4021 to retract and release the steel cable 403 in different states, so that the hollow tube 4021 hits the wing plate at the bottom of the secondary beam 102, specifically, when one telescopic part 4023 contracts (when the telescopic part 4023 contracts, the steel cable 403 is retracted into the hollow tube 4021), the other telescopic part 4023 extends (when the telescopic part 4023 extends, the steel cable 403 extends from the hollow tube 4021), so that the hollow tube 4021 can move back and forth between two adjacent secondary beams 102, and by controlling the change in the telescopic amount of the telescopic part 4023, the telescopic part 4023 can be controlled to hit the wing plate at the bottom of the secondary beam 102.
[0054] The control system can obtain the bending direction and bending angle of the secondary beam 102 by detecting the values of the tension sensors distributed on both sides of the secondary beam 102, and control the corresponding adjustment component 4 to perform corresponding actions according to the bending direction and bending angle of the secondary beam 102.
[0055] When the control system detects that the difference between the tension sensors distributed on both sides of the secondary beam 102 exceeds the set value, it indicates that the lateral force on the secondary beam 102 is too large, and the longitudinal connector 303 cannot provide lateral support for the secondary beam 102, causing the secondary beam 102 to buckle.
[0056] by Fig.10 For example, when secondary beam A bends in the left direction, the straight-line distance between the bottom wing plate of secondary beam A and the bottom wing plate of secondary beam B is shortened, and the straight-line distance between the bottom wing plate of secondary beam A and the bottom wing plate of secondary beam C is increased, resulting in a decrease in the value detected by the tension sensor between secondary beam A and secondary beam B, and an increase in the value detected by the tension sensor between secondary beam A and secondary beam C.
[0057] It should be noted that: when the A secondary beam bends in the left direction, the value detected by the tension sensor located between the A secondary beam and the C secondary beam increases, that is, the elastic member 4025 inside the hollow tube 4021 located between the A secondary beam and the C secondary beam drives the steel cable 403 to apply an oblique upward tension to the bottom wing plate of the A secondary beam, thereby reducing the possibility of further buckling of the A secondary beam.
[0058] When the control system detects that the A-beam is buckling in the left direction, the telescopic member 4023 inside the hollow cylinder 4021 on the left side of the A-beam is controlled to contract synchronously according to the difference between the tension sensors distributed on both sides of the A-beam. The telescopic member 4023 drives the elastic member 4025 to stretch the steel cable 403, and finally the difference between the tension sensors distributed on both sides of the A-beam is in a stable state. Fig.10 As shown, during the synchronous contraction of the two telescopic members 4023 on the left side of the A secondary beam, the steel cable 403 on the left side of the A secondary beam applies an oblique downward pulling force to the bottom wing plate of the A secondary beam to prevent the A secondary beam from further buckling.
[0059] It should be noted that: the steel cable 403 on the left side of the A secondary beam applies a downward oblique pulling force to the bottom wing plate of the A secondary beam, and the steel cable 403 on the right side of the A secondary beam applies an upward oblique pulling force to the bottom wing plate of the A secondary beam, so that the A secondary beam has a tendency to rotate, thereby avoiding the aggravation of the buckling phenomenon of the A secondary beam, which may cause the floor structure 1 to collapse.
[0060] The control system can obtain the buckling direction and buckling angle of the secondary beam 102 according to the values of the tension sensors distributed on both sides of the secondary beam 102, and further determine the area on the secondary beam 102 where the maximum buckling angle is located.
[0061] When the control system detects the area on the secondary beam 102 where the maximum buckling angle is located (hereinafter referred to as the S1 area), the adjustment components 4 on both sides of the S1 area are controlled to gather toward the area. The specific actions are: the electromagnetic pin is controlled to disengage from the slot, that is, the walking wheel 4042 and the sliding track 401 are in a sliding connection state, and then the driving device is started, the driving device drives the driving gear 4046 to rotate, the driving gear 4046 drives the transmission wheel 4043 to rotate through the transmission gear 4045, and the transmission wheel 4043 drives the two walking wheels 4042 on the same side to rotate through the transmission belt 4044. After the walking wheel 4042 drives the frame 4041 to move to the S1 area, the electromagnetic pin is controlled to be plugged into the slot, and the walking wheel 4042 and the sliding track 401 are in a fixed connection state.
[0062] After the frame 4041 moves to the S1 region, the telescopic member 4023 inside the hollow cylinder 4021 corresponding to the deflection direction of the secondary beam 102 is controlled to contract synchronously, and the telescopic member 4023 drives the elastic member 4025 to pull the S1 region. Fig.11As shown, it is avoided that the adjustment component 4 corresponding to the S1 area cannot exert sufficient pulling force, resulting in the buckling phenomenon not being alleviated.
[0063] It should be noted that: when the flexion angle of the S1 region exceeds the threshold value, when multiple groups of adjustment components 4 pull the S1 region in the same region, it is easy to cause excessive tension on the secondary beams 102 on both sides, increasing the risk of lateral instability of the secondary beams 102 on both sides; therefore, when the flexion angle of the S1 region exceeds the threshold value, the running parts 404 on the secondary beams 102 corresponding to the S1 region gather in the direction of the S1 region, and the running parts 404 on the secondary beams 102 on both sides of the S1 region spread outward from the S1 region, as shown in FIG. Fig.12 As shown, the telescopic member 4023 inside the hollow cylinder 4021 is controlled to shrink synchronously, so that the tension generated by the steel cable 403 can be dispersed on the secondary beams 102 on both sides, avoiding the tension generated by the steel cable 403 being concentrated in one area, resulting in excessive tension on the secondary beams 102 on both sides, and increasing the risk of lateral instability of the secondary beams 102 on both sides.
[0064] The present invention arranges an adjustment component 4 and detects the values of tension sensors distributed on both sides of the secondary beam 102 to obtain the bending direction and bending angle of the secondary beam 102, and controls the corresponding telescopic member 4023 to stretch the steel cable 403 according to the bending direction and bending angle of the secondary beam 102. The steel cable 403 applies tension in the anti-bending direction to the bottom wing plate of the secondary beam 102 to avoid the possibility of further buckling of the secondary beam 102.
[0065] At the same time, according to the area where the maximum flexion angle is distributed on the secondary beam 102, the walking member 404 is controlled to drive the adjusting part 402 to gather towards the maximum flexion area, so that multiple telescopic members 4023 pull the maximum flexion area synchronously. When the flexion angle of the maximum flexion area exceeds the threshold, the walking member 404 on the secondary beam 102 corresponding to the maximum flexion area gathers in the direction of the maximum flexion area, and the rest diffuses to the outside of the maximum flexion area, so that the tension generated by the steel cable 403 can be dispersed on the secondary beams 102 on both sides, avoiding the tension generated by the steel cable 403 being concentrated in one area, resulting in excessive tension on the secondary beams 102 on both sides, and increasing the risk of lateral instability of the secondary beams 102 on both sides. Example
[0066] The present invention also discloses a supporting method of a secondary beam supporting device, the supporting method comprising the following steps: S1. For a floor structure 1, first install a frame beam 101 whose two ends are connected to the corner columns 2, so that the frame beam 101 and the corner columns 2 together form a frame, and then complete the installation of the secondary beam 102 in the frame; S2, installing a horizontal flexible support system 3 between two adjacent frame beams 101 and secondary beams 102 at both ends of the floor structure 1, and forming an end truss with greater lateral stiffness after applying pre-tension; S3, laying one or more longitudinal connectors 303, so that the two ends of the longitudinal connector 303 are connected to the end trusses at the two ends of the floor structure 1, and after the pre-tensioning force is applied, the longitudinal connector 303 is connected to the intersection of the secondary beam 102; S4. Finally, the floor steel trusses are installed and the concrete floor slabs are poured. At this time, the floor structure 1 has sufficient lateral rigidity and will not be lateral instability. S5, and so on, install the floor structure 1 of the subsequent floors in sequence.
[0067] Although embodiments of the present invention have been shown and described, it will be apparent to those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A secondary beam support device, characterized in that: It comprises a floor structure (1), wherein four corners of the floor structure (1) are provided with corner columns (2), and the corner columns (2) support the four corners of the floor structure (1); The floor structure (1) comprises frame beams (101) distributed in an array, the two ends of the frame beams (101) are respectively connected to opposite sides of two adjacent corner columns (2), the frame beams (101) and the corner columns (2) together form a frame, the frame is provided with secondary beams (102) distributed in an array, the top of the frame is provided with a steel truss floor deck (103), and the top of the secondary beams (102) is connected to the steel truss floor deck (103); Both ends of the floor structure (1) are provided with a horizontal flexible support system (3) and a longitudinal connection piece (303) arranged horizontally along the longitudinal direction of the floor structure (1).
2. The secondary beam supporting device according to claim 1, characterized in that: The horizontal flexible support system (3) forms an end truss together with the secondary beam (102) at both ends of the floor structure (1), and the horizontal flexible support system (3) comprises horizontal cross-connectors (301) arranged in an array at the ends of the floor structure (1), one end of the horizontal cross-connectors (301) being connected to the frame beam (101), and the other end of the horizontal cross-connectors (301) being connected to the secondary beam (102); A rigid tie rod (302) is provided between two adjacent horizontal cross-connecting members (301), one end of the rigid tie rod (302) is connected to the frame beam (101), and the other end of the rigid tie rod (302) is connected to the secondary beam (102).
3. The secondary beam supporting device according to claim 2, characterized in that: The two ends of the longitudinal connecting member (303) are respectively connected to the two end trusses, the longitudinal connecting member (303) intersects with the ends of the secondary beams (102) distributed in the frame, and the intersection of the longitudinal connecting member (303) and the secondary beams (102) forms a fixed connection.
4. The secondary beam supporting device according to claim 3, characterized in that: The longitudinal connecting member (303) comprises a horizontal cable, which is arranged at the end of the secondary beam (102). The horizontal cable forms a fixed connection with the secondary beam (102) at the intersection, and the horizontal cable provides lateral support for the secondary beam (102).
5. The secondary beam supporting device according to claim 3, characterized in that: The longitudinal connecting member (303) comprises a plurality of horizontal cables, which are distributed at the ends of the secondary beam (102) at the same intervals, and the horizontal cables are fixedly connected to the secondary beam (102) at their intersections, and the horizontal cables provide lateral support for the secondary beam (102).
6. The secondary beam supporting device according to claim 1, characterized in that: An adjustment component (4) is provided between two adjacent secondary beams (102), the adjustment component (4) comprising symmetrically arranged sliding rails (401), the two sliding rails (401) being respectively connected to the bottom of the corresponding secondary beam (102), an array-distributed adjustment portion (402) is provided between the two adjacent sliding rails (401), both ends of the adjustment portion (402) are connected to a walking member (404) via a steel cable (403), and the walking member (404) slides back and forth on the sliding rails (401).
7. The secondary beam supporting device according to claim 6, characterized in that: The adjusting portion (402) comprises a hollow cylinder (4021), both ends of the hollow cylinder (4021) are provided with through holes (4022), and the interior of the hollow cylinder (4021) is provided with symmetrically distributed telescopic parts (4023); The output end of the telescopic member (4023) is provided with a fixed disk (4024), the fixed disk (4024) is axially limited and slidably connected to the hollow cylinder (4021), an elastic member (4025) is provided at the end of the fixed disk (4024), a movable disk (4026) is provided at the end of the elastic member (4025), the movable disk (4026) is axially limited and slidably connected to the hollow cylinder (4021), the end of the movable disk (4026) is connected to the steel cable (403), and one end of the steel cable (403) passing through the through hole (4022) is connected to the walking member (404).
8. The secondary beam supporting device according to claim 6, characterized in that: The walking member (404) comprises a frame (4041) connected to the steel cable (403); one end of the frame (4041) facing the sliding track (401) is provided with walking wheels (4042) distributed in an array; the walking wheels (4042) are slidably connected to the sliding track (401); A transmission wheel (4043) is provided at one end of the walking wheel (4042) extending into the interior of the frame (4041); a transmission belt (4044) is commonly connected between the transmission wheels (4043) located on the same side; a transmission gear (4045) is provided at the end of the transmission wheel (4043); a driving gear (4046) is meshed on the outer side of the transmission gear (4045); a driving device is provided at the end of the driving gear (4046); and the driving device is connected to the frame (4041).
9. A supporting method for a secondary beam supporting device, characterized in that: The supporting method is implemented by using the secondary beam supporting device according to claim 5, comprising the following steps: S1. For a floor structure (1), firstly install a frame beam (101) whose two ends are connected to the corner columns (2), so that the frame beam (101) and the corner columns (2) together form a frame, and then complete the installation of the secondary beam (102) in the frame; S2, installing a horizontal flexible support system (3) between two adjacent frame beams (101) and the secondary beam (102) at both ends of the floor structure (1), and forming an end truss with greater lateral stiffness after applying pre-tensioning force; S3, laying one or more longitudinal connectors (303) so that both ends of the longitudinal connectors (303) are connected to the end trusses at both ends of the floor structure (1), and after applying the pre-tensioning force, the longitudinal connectors (303) are connected to the secondary beams (102); S4. Finally, the floor steel trusses are installed and the concrete floor slab is poured. At this point, the floor structure (1) has sufficient lateral stiffness and will not suffer from lateral instability. S5. Similarly, the installation of the floor structure (1) of subsequent floors is carried out in sequence.
10. Use of the secondary beam support device according to claim 1 in pouring floor concrete.
Citation Information
Cited By
Steel structure connecting joint adjusting mechanism and adjusting method
CN119571919A
Steel structure connecting joint adjusting mechanism and adjusting method
CN119571919B