Construction method of aerial high and heavy load formwork supporting system

Through the combination of vertical support system and support platform, the problems of the existing technology of high-volume heavy-load formwork support system with a large amount of materials and long working time are solved, the construction progress and cost reduction are improved, and a high efficiency is provided. support method.

CN118933404AActive Publication Date: 2024-11-12CHINA MCC22 GROUP CORP LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411055743.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-02
Publication Date
2024-11-12
Estimated Expiration
2044-08-02

AI Technical Summary

Technical Problem

The existing high-volume heavy-load formwork support system in the air has problems such as excessive materials, long working time, and inconvenient installation and dismantling during construction, which affects the construction progress and economy.

Method used

A combination of vertical support system and support platform is adopted to form a turnaround support system by embedding anchor bolts, mounting columns layer by layer, installing support platforms and plug-in struts, replacing the traditional full-house frame.

Benefits of technology

The turnoverability of supporting materials is achieved, the construction period is shortened, manpower and material resources are saved, construction costs are reduced, and construction efficiency is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933404A_ABST
    Figure CN118933404A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of supporting system construction, in particular to a construction method of an aerial high and large heavy-load formwork supporting system, which comprises the following steps that foundation bolts are embedded, a vertical supporting system is erected, the vertical supporting system is composed of a plurality of layers of stand columns, and the stand columns on the same layer are connected through horizontal tie bars; the upper ends and the lower ends of the stand columns are connected through connecting flanges, connecting bolts and connecting nuts. A supporting platform is mounted on the vertical supporting system, and a plurality of inserting cylinders are arranged on the supporting platform; supporting rods are inserted into the inserting cylinders at the preset positions, the multiple supporting rods jointly form an outer support of the pouring formwork, and an inner support, structural steel bars and the pouring formwork are arranged; the combination of the vertical supporting system and the supporting platform is used for replacing the full framing, the combination of the vertical supporting system and the supporting platform can be assembled, disassembled and transformed for multiple times, the turnover performance of construction materials is achieved, and the construction cost is reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of support system construction, in particular to a construction method for an aerial high and heavy-load formwork support system. Background Art

[0002] During construction, large concrete funnels are characterized by large volume and heavy mass, and are usually constructed by cast-in-place method. Before pouring concrete, it is necessary to tie steel bars and install the casting formwork. Since the concrete funnel needs to be suspended in the air, the support system setting of the casting formwork usually becomes a difficult point in construction. In the existing construction, a full-frame is used as the support system for support. For the construction of suspended concrete structures with large volume and heavy mass, such as large concrete funnels and cantilever beams, the step distance and span of the vertical poles will be reduced to ensure the support performance and prevent deformation after concrete pouring. Therefore, the existing aerial tall and heavy-load formwork support system has defects such as more materials, long operation time, and inconvenient installation and disassembly, which affects the construction progress and is worrying about the economic efficiency. Summary of the invention

[0003] In view of the deficiencies in the prior art, the purpose of the present invention is to provide a construction method for an aerial tall and heavy-load formwork support system which is convenient and fast to support and has strong turnover.

[0004] The technical solution adopted by the present invention to solve the technical problem is: A construction method for a high and heavy-loaded aerial formwork support system comprises the following steps: S1, pre-embedded anchor bolts: pour the foundation raft slab and pre-embed the anchor bolts in the foundation raft slab at preset positions; S2, vertical support system erection: The vertical support system consists of several layers of columns, which are installed layer by layer. The columns on the same layer are connected by horizontal tie rods. The upper and lower ends of the columns are provided with connecting flanges. The upper and lower columns are connected by connecting flanges, connecting bolts and connecting nuts. The lowest column is connected to the foundation raft by connecting flanges, anchor bolts and connecting nuts. S3, support platform installation: install the support platform on the vertical support system, and arrange a number of plug-in tubes on the support platform; S4, formwork support: insert the support rods on the plug-in tubes at the preset positions, and several support rods together constitute the outer support of the casting formwork, and set the inner support, structural steel bars and casting formwork; S5, concrete pouring: After the concrete is poured and reaches the demoulding strength, the inner support, outer support and pouring formwork are removed; S6, dismantling of support system: dismantling of the support platform and vertical support system.

[0005] Preferably, in step S1, the step of pre-embedding the anchor bolts includes: pouring the foundation raft slab cushion layer; after the foundation raft slab cushion layer is poured, projecting a cross-shaped centerline point thereon, and preliminarily positioning the position of the anchor bolt according to the centerline point, tying the raft slab steel bars, and fixing the anchor bolts on the raft slab steel bars according to the centerline point; to prevent the anchor bolt threads from being damaged, protective sleeves should be used to protect the anchor bolt threads; to ensure the correct position and elevation of the anchor bolts, supervision and observation should be carried out during concrete pouring, and if any changes are found, the construction personnel should be notified immediately for timely processing.

[0006] Preferably, in step S2, the specific process of installing the columns layer by layer is that each layer of columns is a horizontal frame as a lifting unit, each lifting unit needs to be pre-assembled as a whole on the ground, and each layer of columns is connected and fixed by a horizontal tie beam; installed layer by layer from bottom to top, the bottom layer of columns is connected and fixed to the anchor bolts by connecting nuts, and after each layer of columns is installed in place, the installation elevation of the next layer of columns is adjusted by adding a pad on the top of the column.

[0007] Preferably, in step S3, the support platform includes a support platform and a column top platform, and both the support platform and the column top platform are made of I-beams. The specific installation process includes: S301: first install the underpinning platform, which is a mesh structure and is connected and fixed to the connection flange at the top of the vertical support system by connecting bolts. When connecting the underpinning platform and the vertical support system, tighten the connection nodes from the middle to both ends along the longitudinal axis; S302: After the support platform is fixed, the column top platform is installed on the support platform. The column top platform consists of an intermediate section fixed to the support platform and an extension section connected to both sides of the intermediate section. The intermediate section includes a plurality of first beams, and the extension section includes a plurality of second beams. The second beams are connected to both ends of the first beams and are coaxially arranged with the first beams. The plug-in tube is arranged on the upper flanges of the first beams and the second beams. A plurality of through holes are arranged at intervals along the length of the second beams, and a full-length longitudinal rib is penetrated in the through holes. The full-length longitudinal rib is arranged perpendicular to the second beams to provide further connection for the plurality of second beams on the left or right side of the intermediate section.

[0008] Preferably, walkway boards are laid in the gaps between the first cross beams and the gaps between the second cross beams to facilitate construction workers to walk on the supporting platform.

[0009] Preferably, the two ends of the web of the first beam are hingedly connected to the ends of the web of the second beam by means of a pin seat and a pin; the top surfaces at both ends of the upper flange plate of the first beam and the bottom surfaces at both ends of the lower flange plate are also provided with limit plates; it also includes a diagonal brace rod, the lower end of which is hinged on the column of the vertical support system, and the upper end is hinged on the lower flange plate of the second beam of the extension section; after the middle section and the support platform are fixed in step S302, it also includes; S303: the output end of the diagonal brace is extended, and the extension sections on both sides are extended to the same horizontal plane as the middle section. At this time, the upper flange of the second beam is attached to the lower side of the limit plate of the first beam, and the limit plate and the upper flange of the second beam are fixed by bolts.

[0010] Preferably, the diagonal brace adopts a jack push rod or a hydraulic push rod.

[0011] Compared with the prior art, the present invention adopting the above technical solution has the following outstanding features: The present invention uses a vertical support system and a support platform combination to replace the full-height frame. The vertical support system and the support platform combination can be installed, dismantled and modified many times, thereby realizing the turnover of construction materials and reducing construction costs. In addition, the tooling designed by this construction method is easy to modify and can also be applied to the support system of conventional beams and slabs with high and large formwork. Compared with setting up a full-height frame, this method can greatly shorten the construction period, is safe and efficient, saves a lot of manpower and material resources, and creates good conditions for the further development of the project. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a structural schematic diagram of the vertical support system in the embodiment of the present invention; Figure 2 It is a schematic diagram of the connection structure between the support platform and the vertical support system in the embodiment of the present invention; Figure 3 Schematic diagram of the structure of the underpinning platform in the embodiment of the present invention; Figure 4 It is a schematic diagram of the structure of the column top platform in the embodiment of the present invention; Figure 5 is another structural schematic diagram of the column top platform in the embodiment of the present invention; Figure 6 is a schematic diagram of the connection structure between the first crossbeam and the second crossbeam in an embodiment of the present invention; Figure 7 It is a structural schematic diagram of the aerial tall and heavy-load formwork support system in an embodiment of the present invention.

[0013] Explanation of the reference numerals in the accompanying drawings: 1. Column; 2. Horizontal tie rod; 3. Connecting flange; 4. Support platform; 401. Connecting base plate; 5. Column top platform; 501. First cross beam; 502. Second cross beam; 503. Full-length longitudinal rib; 6. Diagonal brace; 7. Pin seat; 8. Limiting plate; 9. Connecting ear; 10. Plug-in tube; 11. External support; 12. Casting formwork; 13. Jack. DETAILED DESCRIPTION

[0014] The present invention is further described below in conjunction with specific embodiments, the purpose of which is only to provide a better understanding of the content of the present invention. Therefore, the examples given do not limit the protection scope of the present invention.

[0015] like Figures 1 to 7 As shown, this embodiment provides a construction method for a high and heavy-loaded aerial formwork support system, comprising the following steps: S1, embedded anchor bolts: pour the foundation raft and embed the anchor bolts in the foundation raft at the preset position; specifically, including: S101: pouring of foundation raft slab cushion layer.

[0016] S102: Project a cross-shaped centerline point on the foundation raft slab cushion layer and preliminarily locate the position of the anchor bolts based on the centerline point.

[0017] S102: Tie up the raft reinforcement and fix the anchor bolts on the raft reinforcement according to the center line point; first tie up the anchor bolts and raft reinforcement, and then check the position. After the check, weld the anchor bolts and raft reinforcement. To prevent the anchor bolt threads from being damaged during welding and concrete pouring, protective sleeves should be used to protect the anchor bolt threads; to ensure the correct position and elevation of the anchor bolts, they should be watched and observed during the raft concrete pouring. If any changes are found, the construction personnel should be notified immediately for timely processing.

[0018] S2, vertical support system erection: Figure 1 As shown, the vertical support system consists of several layers of columns 1, which are installed layer by layer. Connecting flanges 3 are set at the upper and lower ends of the columns 1. The upper and lower columns 1 are connected by connecting flanges 3, connecting bolts and connecting nuts. The lowest column 1 is connected to the foundation raft slab by connecting flanges 3, anchor bolts and connecting nuts.

[0019] In step S2, the specific process of installing the columns 1 layer by layer is as follows: each layer of columns 1 is horizontally formed into a lifting unit, and each lifting unit needs to be pre-assembled as a whole on the ground. Several columns 1 on each layer are connected and fixed by horizontal tie beams; they are installed layer by layer from bottom to top, and the bottom layer of columns 1 is connected and fixed to the anchor bolts by connecting nuts. After each layer of columns 1 is installed in place, the installation elevation of the next layer of columns 1 is adjusted by adding a pad on the top of the column 1.

[0020] S3, support platform installation: Figure 2 As shown, a support platform is installed on the vertical support system, and a plurality of plug-in tubes 10 are arranged on the support platform; wherein the support platform includes a support platform 4 and a column top platform 5, and both the support platform 4 and the column top platform 5 are made of I-beams.

[0021] The specific installation process of the support platform includes: S301: Install the underpinning platform 4 first, such as Figure 3 As shown, the underpinning platform 4 is in a mesh structure, and the I-beams arranged horizontally and vertically on the underpinning platform 4 are welded and fixed to each other; a connecting base plate 401 is provided at the bottom of the underpinning platform 4 corresponding to the connecting flange 3 at the top of the vertical support system, and the underpinning platform 4 is connected and fixed to the connecting flange 3 at the top of the vertical support system through the connecting base plate 401 by connecting bolts and connecting nuts; when connecting the underpinning platform 4 and the vertical support system, the connecting nodes are tightened from the middle to both ends along the longitudinal axis.

[0022] S302: After the underpinning platform 4 is fixed, the column top platform 5 is installed on the underpinning platform 4. Figure 4 As shown, the column top platform 5 is composed of an intermediate section fixed to the underpinning platform 4 and an extension section connected to both sides of the intermediate section. The intermediate section includes a plurality of first beams 501, and the extension section includes a plurality of second beams 502. The first beams 501 are welded and fixed to the underpinning platform 4, and the second beams 502 are connected to both ends of the first beams 501 and are coaxially arranged with the first beams 501. The column top platform 5 is also provided with a plurality of plug-in tubes 10, which are arranged perpendicular to the column top platform 5, and the bottom of the plug-in tubes 10 is welded and fixed to the upper flange of the first beam 501 or the second beam 502. The first beam 501 is also provided with a plurality of jacks 13 for supporting the casting formwork 12, and the jacks can also be replaced by sandboxes or U-shaped brackets.

[0023] like Figure 5 As shown, a number of through holes are arranged at intervals along the length of the second cross beam 502, and a full-length longitudinal rib 503 is passed through the through holes. The full-length longitudinal rib 503 is arranged perpendicular to the second cross beam 502 to provide further connection for a number of second cross beams 502 in the extension sections on both sides of the middle section; in this embodiment, the through holes have a diameter of 45 mm and an interval of 450 mm, and the full-length longitudinal rib 503 adopts D42 steel pipe.

[0024] Further, such as Figure 6 As shown, both ends of the web of the first cross beam 501 are hingedly connected to the ends of the web of the second cross beam 502 through a pin seat 7 and a pin; limit plates 8 are provided on the top surfaces of both ends of the upper flange plate of the first cross beam 501 and the bottom surfaces of both ends of the lower flange plate; it also includes 6 diagonal braces, the lower ends of the diagonal braces 6 are hingedly connected to the columns 1 of the vertical support system through connecting ears 9 and pins, and the upper ends are hingedly connected to the lower flange plate of the second cross beam 502 of the extension section through connecting ears 9 and pins; wherein, the diagonal braces 6 can adopt a jack push rod or a hydraulic push rod.

[0025] The column top platform 5 is installed by integral hoisting, and there are four hoisting points, which are arranged on both sides of the middle section, at 1 / 5 and 4 / 5 of the longitudinal side span.

[0026] S303: After the middle section and the underpinning platform 4 are fixed, the extension sections are installed on both sides of the middle section, and then the diagonal brace 6 is installed. The output end of the diagonal brace 6 is extended so that the extension section and the middle section are on the same horizontal plane. When the middle section and the extension section are connected, the upper flange of the second cross beam 502 is attached to the lower side of the upper flange limit plate 8 of the first cross beam 501, and the lower flange of the second cross beam 502 is attached to the upper side of the lower flange limit plate 8 of the first cross beam 501. The limit plate 8 and the upper and lower flanges of the second cross beam 502 are fixed by bolts.

[0027] S304: To facilitate construction workers to walk on the support platform, walkway boards are laid in the gaps between the first beams 501 and the gaps between the second beams 502.

[0028] S4, Formwork support: Figure 7 As shown, a support rod is inserted into the plug-in tube 10 at a preset position, and a plurality of support rods together constitute the outer support 11 of the casting template 12; a structural internal support, structural reinforcement and the casting template 12 are provided; in this embodiment, the plug-in tube 10 is made of D63 steel pipe and is 100mm-150mm high.

[0029] S5, concrete pouring: After the concrete is poured and reaches the demoulding strength, the inner support, outer support 11 and pouring formwork 12 are removed.

[0030] S6, support system removal: the steps for removal include; S601: First, unload the jack 13 and remove the walkway plate and the full-length longitudinal rib 503 on the supporting platform, and then remove the diagonal brace 6.

[0031] S602: Use a fall chain to dismantle the second beam 502. One end of the fall chain is hung on the embedded plate of the concrete structure, and the other end is hung in the through hole of the web of the second beam 502. Remove the connection node between the first beam 501 and the second beam 502 pin shaft and the limit plate, and use the fall chain to slowly drop the second beam 502 to the ground.

[0032] S603: Connect the first cross beam 501 with a fall chain, with one end of the fall chain hung on the embedded concrete structure plate and the other end hung in the pin hole of the first cross beam 501 .

[0033] S604: Remove the connecting bolts between the bottom column 1 and the second-to-last column 1, use the fall chain to lift the replacement platform 4 and the vertical support system except the first section, disassemble the bottom column 1 one by one, and then lower the vertical support system. At this time, the original second-to-last column 1 is the bottom layer.

[0034] S605: Repeat S604 until only the uppermost columns and the underpinning platform 4 are left, and lower the uppermost columns and the underpinning platform 4 to the ground using a fall chain for dismantling.

[0035] It should be noted that when an external retaining wall is designed on the outside of the aerial concrete structure, if there is a conflict between the supporting platform and the external retaining wall, the external retaining wall needs to be cast and constructed in sections. First, the external retaining wall on the lower side of the supporting platform should be constructed, and then the external retaining wall and rib wall above the supporting platform should be constructed.

[0036] The present invention uses a vertical support system and a support platform to replace the full-floor scaffolding on the lower side of the aerial concrete structure, which makes disassembly and assembly simpler and more convenient, improves construction efficiency, and the system can be used cyclically, saving construction costs.

[0037] The above description is only the preferred embodiment of the present invention, and does not limit the scope of rights of the present invention. All equivalent changes made by using the contents of the present invention specification and its drawings are included in the scope of rights of the present invention.

Claims

1. A construction method for a high and heavy-loaded aerial formwork support system, characterized in that: The method comprises the following steps: S1, pre-embedded anchor bolts: pouring a foundation raft slab and pre-embedded anchor bolts in the foundation raft slab at preset positions; S2, vertical support system erection: The vertical support system consists of several layers of columns, which are installed layer by layer. The columns on the same layer are connected by horizontal tie rods. The upper and lower ends of the columns are provided with connecting flanges. The upper and lower columns are connected by connecting flanges, connecting bolts and connecting nuts. The lowest column is connected to the foundation raft by connecting flanges, anchor bolts and connecting nuts. S3, support platform installation: install the support platform on the vertical support system, and arrange a number of plug-in tubes on the support platform; S4, formwork support: insert the support rods on the plug-in tubes at the preset positions, and several support rods together constitute the outer support of the casting formwork, and set the inner support, structural steel bars and casting formwork; S5, concrete pouring: After the concrete is poured and reaches the demoulding strength, the inner support, outer support and pouring formwork are removed; S6, dismantling of support system: dismantling of the support platform and vertical support system.

2. The construction method of the aerial high and heavy-load formwork support system according to claim 1 is characterized in that: In step S1, the steps of pre-embedding the anchor bolts include: pouring the foundation raft slab cushion layer; after the foundation raft slab cushion layer is poured, projecting a cross-shaped center line point on it, and preliminarily positioning the position of the anchor bolt according to the center line point, tying the raft slab steel bars, and fixing the anchor bolts on the raft slab steel bars according to the center line point; to prevent the anchor bolt threads from being damaged, protective sleeves should be used to protect the anchor bolt threads; to ensure the correct position and elevation of the anchor bolts, supervision and observation should be carried out during concrete pouring, and if any changes are found, the construction personnel should be notified immediately for timely processing.

3. The construction method of the aerial high and heavy-load formwork support system according to claim 1 is characterized in that: In step S2, the specific process of installing the columns layer by layer is as follows: each layer of columns is a horizontal frame as a lifting unit, each lifting unit needs to be pre-assembled on the ground, and each layer of columns is connected and fixed by a horizontal tie beam; install layer by layer from bottom to top, the bottom layer of columns is connected and fixed to the anchor bolts by connecting nuts, and after each layer of columns is installed in place, the installation elevation of the next layer of columns is adjusted by adding a pad on the top of the column.

4. The construction method of the aerial high and heavy-load formwork support system according to claim 1 is characterized in that: In step S3, the supporting platform includes a support platform and a column top platform, both of which are made of I-beams. The specific installation process includes: S301: first install the underpinning platform, which is a mesh structure and is connected and fixed to the connection flange at the top of the vertical support system by connecting bolts. When connecting the underpinning platform and the vertical support system, tighten the connection nodes from the middle to both ends along the longitudinal axis; S302: After the support platform is fixed, the column top platform is installed on the support platform. The column top platform consists of an intermediate section fixed to the support platform and an extension section connected to both sides of the intermediate section. The intermediate section includes a plurality of first beams, and the extension section includes a plurality of second beams. The second beams are connected to both ends of the first beams and are coaxially arranged with the first beams. The plug-in tube is arranged on the upper flanges of the first beams and the second beams. A plurality of through holes are arranged at intervals along the length of the second beams, and a full-length longitudinal rib is penetrated in the through holes. The full-length longitudinal rib is arranged perpendicular to the second beams to provide further connection for the plurality of second beams on the left or right side of the intermediate section.

5. The construction method of the aerial high and heavy-load formwork support system according to claim 4 is characterized in that: Walkway boards are laid in the gaps between the first cross beams and the gaps between the second cross beams.

6. The construction method of the aerial high and heavy load formwork support system according to claim 4 is characterized in that: The two ends of the web of the first beam are hingedly connected to the ends of the web of the second beam through pin seats and pins; limit plates are also provided on the top surfaces of the two ends of the upper flange plate of the first beam and the bottom surfaces of the two ends of the lower flange plate; it also includes a diagonal brace rod, the lower end of the diagonal brace rod is hinged on the column of the vertical support system, and the upper end is hinged on the lower flange plate of the second beam of the extension section; after the middle section and the support platform are fixed in step S302, it also includes, S303: the output end of the diagonal brace is extended, and the extension sections on both sides are extended to the same horizontal plane as the middle section. At this time, the upper flange of the second beam is attached to the lower side of the limit plate of the first beam, and the limit plate and the upper flange of the second beam are fixed by bolts.

7. The construction method of the aerial high and heavy-load formwork support system according to claim 6 is characterized in that: The diagonal brace adopts jack push rod or hydraulic push rod.

Citation Information

Patent Citations

  • Construction method for support structure of coal tower template for tamping type coke oven

    CN101886466A

  • Bailey beam suspension formwork supporting system and construction method thereof

    CN104141383A

  • Construction method for conical concrete funnel

    CN107939094A

  • Large-scale concrete funnel template support method

    CN109025292A

  • Cast-in-place construction method for reinforced concrete large-diameter conical shell top structure

    CN117365096A