Drilling device for mountainous area iron tower pile well and mountainous area iron tower pile foundation construction method
By using support modules and diameter-reducing mechanisms in the drilling device of the pile well in the mountainous tower, combined with drilling and splitting devices, the problem of low construction efficiency of existing mechanized equipment in mountainous areas is solved, and efficient pile hole excavation is achieved to adapt to mountainous areas. Complex conditions.
Patent Information
- Application Number
- CN202411208365.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-11-12
AI Technical Summary
The existing large-scale mechanized equipment with excavation and spiral excavation operations as working modules is difficult to successfully achieve construction work or construction efficiency in the context of shortage of hydropower resources in mountainous areas and difficult transportation.
A drilling device for pile wells in mountainous iron towers is designed, using a support module and a diameter-reducing mechanism. The support module is positioned through the shoe mechanism, and the diameter-reducing mechanism can rotate and telescope to adapt to different apertures, combining drilling and splitting devices. Achieve flexible homework.
It improves construction efficiency, adapts to the complex terrain and traffic conditions in mountainous areas, reduces project preparation time, enhances the modularity of the equipment, facilitates manual transportation and cableway transportation, and reduces construction risks.
Smart Images

Figure CN118933588A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of mountain power pile foundation construction, and in particular to a tower pile well drilling device for mountain areas and a tower pile foundation construction method for mountain areas. Background Art
[0002] During the power construction in mountainous areas, the pile foundation construction of high-voltage towers is an important project, and pile hole excavation is the "throat" of the current pile foundation construction. The mountainous terrain is rugged, the roads are narrow and dangerous, and the transportation conditions are poor, which makes the pile hole excavation process difficult to construct and has high safety risks.
[0003] At present, the pile hole construction process is mainly completed by manual labor with the help of manual tools. Common manual drilling tools include pneumatic picks, pneumatic drills, water grinding drills, etc., and supporting tools include slag removal buckets and cranes. The use of these tools can easily lead to low construction efficiency, long construction cycles, and great safety hazards during the construction process. Manual operations can easily lead to long construction cycles, many safety accidents, and increased construction costs.
[0004] In addition, most of the drilling equipment on the market is only suitable for areas with convenient transportation. High-voltage towers are mostly in mountainous areas. Due to terrain restrictions, most equipment cannot reach the operating location, and there are practical problems such as limited water and electricity resources. Moreover, the existing construction machinery has high power, heavy modules, single aperture, and poor aperture adaptability. Combined with the actual situation in mountainous areas, that is, in the context of shortage of water and electricity resources and difficult transportation in mountainous areas, the existing large-scale mechanized equipment with tunneling and rotary drilling as working modules is difficult to smoothly realize construction operations or has low construction efficiency, which is not conducive to pile hole excavation in mountainous environments.
[0005] Therefore, it is necessary to improve the existing tower pile foundation pile hole excavation equipment and construction methods in view of the typical environmental conditions faced in mountainous areas so as to make them adapt to the construction conditions in mountainous areas. Summary of the invention
[0006] The purpose of the present invention is to provide a tower pile well drilling device and a tower pile foundation construction method in mountainous areas, so as to solve the technical problems that the existing large-scale mechanized equipment with tunneling and rotary drilling as working modules is difficult to smoothly implement construction operations or has low construction efficiency when excavating the pile holes of the tower pile foundation under the background of shortage of water and electricity resources and difficult transportation in mountainous areas.
[0007] In order to solve the above technical problems, the present invention adopts the following technical solutions: In a first aspect, the present invention discloses a pile well drilling device for a mountain iron tower, which is used for digging a pile hole of an iron tower pile foundation, and comprises a support module, wherein the support module is used for supporting and positioning the pile well drilling device for a mountain iron tower; The support module is rotatably connected with a diameter-changing mechanism, and the diameter-changing mechanism can rotate around the support module; The diameter-changing mechanism can be extended or folded back in the radial direction with the support module as the center, so that the extended diameter of the diameter-changing mechanism increases or decreases; A drilling device is installed on the diameter-changing mechanism. When working, the drilling working end of the drilling device faces the working surface at the bottom of the pile hole of the iron tower pile foundation, and the drilling device can drill the working surface.
[0008] During actual construction, a construction well is first drilled in the working area, the inner diameter of the construction well matches the outer circumferential size of the tower pile well drilling device used in mountainous areas, and then the equipment disclosed in the present invention is installed on the lifting joint and lowered to the designated working area in the construction well, and then the diameter-changing mechanism is extended to a preset extended diameter, so that the drilling device moves to the designated drilling position to perform rock drilling work.
[0009] As one of the implementation methods for supporting and positioning a tower pile well drilling device in mountainous areas, the support module includes a support column, a shoe mechanism is fixed to the top of the support column, and the shoe mechanism is used to tighten the inner wall of the pile hole of the tower pile foundation; the bottom of the support column has a tip, which is used to tighten the bottom of the pile hole of the tower pile foundation; The shoe support mechanism comprises a support disk, which is a circular disk, and a plurality of shoe support plates are evenly arranged along the circumference of the support disk; a telescopic rod is fixed between each shoe support plate and the support disk, and the telescopic rod can be extended and retracted along the radial direction of the support disk.
[0010] When the support shoe mechanism is pressed against the inner wall of the pile hole of the tower pile foundation, the support shoe mechanism is in a stationary state relative to the inner wall of the pile hole of the tower pile foundation; during preparation work, when the tip of the bottom of the support module contacts the working surface, the support shoe mechanism presses against the hole wall to complete the positioning of the equipment in the hole.
[0011] As another embodiment of the shoe support mechanism, the shoe support mechanism includes a support plate, an adjustment telescopic rod and a supporting telescopic rod; both ends of the adjustment telescopic rod are respectively hinged to the support plate and the middle section of the supporting telescopic rod; one end of the supporting telescopic rod is hinged to the support plate, and the other end of the supporting telescopic rod has a tightening head; the adjustment telescopic rod and the supporting telescopic rod can be telescoped respectively; a plurality of lifting ears are fixed to the top of the support plate, and the lifting ears are symmetrically distributed with the center of the support plate as the center of the circle.
[0012] During operation, the length of the telescopic rod is controlled and adjusted to make the supporting telescopic rod reach the specified working angle, and the tightening head of the supporting telescopic rod is driven to tighten the inner wall of the pile hole of the tower pile foundation to realize the underground positioning of the equipment; each lifting lug is used to be suspended on the crane by ropes during construction, which is convenient for the crane to control it, making it less likely for the equipment to rotate and overturn during the lifting process.
[0013] As one of the implementations that the diameter-changing mechanism can rotate around the support module, a rotating assembly is provided in the middle section of the support column below the shoe-gripping mechanism, and the rotating assembly includes an active rotating mechanism and a swivel seat respectively connected to the support column in rotation; The active rotating mechanism is close to the supporting plate and can be driven to rotate by external force, and the swivel seat is close to the bottom tip of the supporting column; The drilling device is installed on the reducing mechanism through a drill arm, and the drill arm includes a guide rail column. The drilling device is slidably connected to the guide rail column. A compensating telescopic rod is fixed to the side of the guide rail column away from the drilling device, and a built-in telescopic rod is fixed inside the corresponding guide rail column. The fixed end of the built-in telescopic rod is fixedly connected to the telescopic end of the compensating telescopic rod, and the telescopic end of the built-in telescopic rod is fixedly connected to the drilling device.
[0014] Specifically, a rubber block is fixed at the bottom of the guide rail column 501. In this way, the variable diameter mechanism 300 is first adjusted according to the size of the pile hole diameter of the tower pile foundation, so that the support shoe mechanism 200 is pressed against the inner wall of the pile hole of the tower pile foundation to achieve the underground positioning of the equipment; then the compensating telescopic rod 502 is driven to make the rubber block fixed at the bottom of the guide rail column 501 contact the ground, thereby increasing the contact area and improving the stability of the drilling rig; then the built-in telescopic rod 503 is driven to push the drilling device to perform drilling operations; and at the same time, the active rotating mechanism 103 is driven to achieve full-circle operation in the underground space.
[0015] As a first embodiment of the diameter-changing mechanism, the diameter-changing mechanism includes a first swing arm, and correspondingly, the active rotation mechanism includes a first rotation support seat, and one end of the first swing arm is hinged to the first rotation support seat; Correspondingly, one end of a swing arm telescopic rod is hinged on the swivel seat, and the other end of the swing arm telescopic rod and the other end of the first swing arm are hinged on the drill arm at the same time, and the drill arm can drive the drilling device to telescopic movement.
[0016] In this way, during construction, the diameter-changing mechanism first extends the swing arm telescopic rod according to the hole size. When the swing arm telescopic rod is extended or retracted, it can drive the first swing arm to swing up and down in the vertical direction, and then drive the drill arm and the drilling device to swing along the radial direction, so as to expand or reduce the operating diameter of the drilling device.
[0017] In addition, there is always a certain angle between the first swing arm and the axis of the supporting column. Therefore, due to the parallelogram principle, the drill arm always maintains a certain angle with the axis of the column, so that the drilling device can drill holes at a certain angle to prevent over-digging and under-digging during construction, and to prevent the equipment from colliding with the well wall during operation, causing equipment damage. A shock-absorbing top block is set at the front end of the guide rail column to increase the contact area between the equipment and the working surface and buffer the vibration generated during operation.
[0018] As a preferred solution of embodiment 1 of the diameter-changing mechanism, the diameter-changing mechanism also includes a second swing arm, and correspondingly, the active rotation mechanism includes a second rotating support seat, one end of the second swing arm is hinged to the second rotating support seat; the other end of the second swing arm is hinged to the side of the guide rail column away from the drilling device, and the first swing arm and the second swing arm are equal in length and are arranged in parallel.
[0019] If there is only the first swing arm, although it can expand the operating diameter of the drill arm as the swing arm telescopic rod is extended, the movement state of the drill arm is parallel movement during the extension and retraction process, and the direction of the working end of the drilling device installed on the drill arm is also parallel movement, and the operable diameter is small; after adding the second swing arm, the drill arm can perform non-parallel movement when swinging, that is, the swing amplitude of the lower section of the drill arm will be greater than the swing amplitude of the upper end of the drill arm, thereby increasing the operable diameter of the drill arm.
[0020] As a second embodiment of the diameter-changing mechanism, the diameter-changing mechanism includes a first swing arm, and correspondingly, the active rotation mechanism includes a first rotation support seat, and both ends of the first swing arm are respectively hinged to the first rotation support seat and a side of the guide rail column away from the drilling device; The two ends of the first telescopic arm are respectively hinged between the first swing arm and the first rotating support seat; the two ends of the second telescopic arm are respectively hinged between the first swing arm and the side of the guide rail column away from the drilling device.
[0021] During construction, the diameter-changing mechanism controls the telescopic length of the first telescopic arm and the second telescopic arm according to the size of the hole, thereby driving the first swing arm to swing up and down in the vertical direction, and then driving the drill arm and the drilling device to swing along the radial direction to expand or reduce the operating diameter of the drilling device.
[0022] As a preferred solution for the tower pile well drilling device in mountainous areas, a plurality of reducing mechanisms are rotatably connected to the support column, and a drilling device or a splitting device is respectively installed on each of the reducing mechanisms. When working, the splitting end of the splitting device faces the working surface at the bottom of the pile hole of the tower pile foundation. The splitting device can split the rock on the working surface to cooperate with the drilling device to perform drilling operations. During construction, the drilling device is first started to perform drilling operations. When encountering rocks and other media that are difficult to drill, the splitting device is started after the drilling device completes the drilling work, and the splitting device is extended to the drilled hole to perform rock crushing work.
[0023] In a second aspect, the present invention further discloses a method for constructing a mountain tower pile foundation, which is implemented using the above-mentioned mountain tower pile well drilling device, and comprises the following steps: S1. Carry out construction preparation and measurement and layout according to the design data; S2, excavate the earthwork of the first section of the pile hole, then carry out the construction of the lock and retaining wall, and the protection construction of the first section of the pile hole; S3, assembling the tower pile well drilling device for mountain areas; S4, lowering the mountain tower pile well drilling device to the bottom of the first pile hole, and adjusting the mountain tower pile well drilling device to a working ready state; S5. Start the drilling device to drill holes according to the designed drilling points; S6, starting the splitting device, and moving the splitting device to the corresponding drill hole to perform the splitting operation; S7, after the rock splitting is completed, the shoe support mechanism and the drill arm are retracted, and the mountain tower pile well drilling device is taken out from the pile hole; then the slag and gravel in the pile hole are cleaned, and the hole formation is checked. If it meets the design requirements, the operation is stopped and step S8 is executed. If it does not meet the requirements, steps S5 and S6 are repeated until the hole formation meets the requirements; S8. Make a steel cage and install it in the hole, then pour the pile core concrete to complete the construction of the mountain power tower pile foundation.
[0024] Preferably, in step S5, the designed points include a plurality of drilling points at the outer edge of the working surface and a plurality of splitting hole points arranged in an array at the center of the working surface. The specific method of starting the drilling device to drill holes respectively according to the designed drilling points includes: S5.1. The drilling device first drills holes in sequence along the outer edge of the working surface to form a free-standing surface; S5.2, the drilling device moves sequentially to a plurality of splitting hole points arranged in an array at the center of the working surface to drill splitting holes; S5.3. After the drilling of each splitting hole is completed, the splitting module is driven to move to the splitting holes in the middle area to perform rock splitting in sequence.
[0025] The present invention has the following beneficial effects: the structure of the iron tower pile well drilling device for mountainous areas is simple and uncomplicated, and the operating diameter can be flexibly adjusted through the diameter-changing mechanism. When not working, the diameter-changing mechanism can be folded, and the volume is small and the weight is light. There is no need to use large equipment or large transportation equipment, and there is no need for a large construction site, so that it is more suitable for the narrow working space and complex terrain in mountainous areas, and more suitable for environmental conditions in mountainous areas where water and electricity resources are scarce and transportation is difficult. It can reduce project preparation time, improve mobility and applicability, and improve working efficiency. The iron tower pile well drilling device for mountainous areas of the present invention also improves the modularity of the equipment. Through modular design, the equipment structure is compact, easy to disassemble and assemble, and convenient for manual transportation and cableway transportation, thereby adapting to the complex terrain and traffic conditions in mountainous areas. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] In order to make the purpose, technical solution and advantages of the invention more clear, the present invention will be further described in detail below with reference to the accompanying drawings, in which: Figure 1 It is a schematic diagram of the overall structure of the iron tower pile well drilling device for mountain areas according to the present invention.
[0027] Figure 2 It is an exploded view of the structure of the iron tower pile well drilling device for mountain areas according to the present invention.
[0028] Figure 3 It is a schematic structural diagram of the second embodiment of the diameter-changing mechanism and the second embodiment of the support shoe mechanism of the present invention.
[0029] Figure 4 It is a schematic diagram of the construction process of the mountain tower pile foundation construction method of the present invention.
[0030] Figure 5 The present invention is a schematic diagram of the installation position of the iron tower pile well drilling device used in mountain areas during construction.
[0031] Figure 6 It is a schematic diagram of the designed drilling points of the present invention.
[0032] Description of reference numerals: 100, supporting column; 101, tip; 102, lifting ear; 103, active rotating mechanism; 104, swivel seat; 200, shoe support mechanism; 201, supporting plate; 202, shoe support plate; 203, telescopic rod; 300, diameter-changing mechanism; 301, first swing arm; 302, first rotating support seat; 303, second swing arm; 304, second rotating support seat; 305, swing arm telescopic rod; 306, second swing arm telescopic rod; 307, second swing arm telescopic rod; 308, second swing arm telescopic rod; 309, second swing arm telescopic rod; 310, second swing arm telescopic rod; 311, second swing arm telescopic rod; 312, second swing arm telescopic rod; 313, second swing arm telescopic rod; 314, second swing arm telescopic rod; 315, second swing arm telescopic rod; 316, second swing arm telescopic rod; 317, second swing arm telescopic rod; 318, second swing arm telescopic rod; 319, second swing arm telescopic rod; 320, second swing arm telescopic rod; 321, second swing arm telescopic rod; 322, second swing arm telescopic rod; 323, second swing arm telescopic rod; 324, second swing arm telescopic rod; 325, second swing arm telescopic rod; 326, second swing arm telescopic rod; 327, second swing arm telescopic rod; 328, second swing arm telescopic rod; 329, second swing arm telescopic rod; 329, second swing arm telescopic rod; 321, first swing arm telescopic rod; 329, second swing arm telescopic rod; 320, second swing arm telescopic rod; 321, first swing arm telescopic rod; 321, first swing arm telescopic rod; 322, first 6. First telescopic arm; 307. Second telescopic arm; 308. Adjust telescopic rod; 309. Support telescopic rod; 310. Tightening head; 401. Drilling device; 402. Splitting device; 501. Guide rail column; 502. Compensating telescopic rod; 503. Built-in telescopic rod; 504. Drilling device; 601. First section of pile hole; 602. Crane; 603. Design drilling point; 604. Drilling device for iron tower pile well in mountainous area. DETAILED DESCRIPTION
[0033] To make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the accompanying drawings in the embodiments of the present invention.
[0034] It should be noted that similar numbers and letters represent similar items in the following drawings, so once an item is defined in one drawing, it does not need to be further defined and explained in the subsequent drawings. In the description of the present invention, it should be noted that the orientation or position relationship indicated by the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. is based on the orientation or position relationship shown in the drawings, or the orientation or position relationship in which the invention product is usually placed when used, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation of the present invention. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance. In addition, the terms "horizontal", "vertical", etc. do not mean that the components are absolutely horizontal or suspended, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted. In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0035] The present invention can be applied to the excavation and construction of pile holes for iron tower pile foundations in environmental conditions where there is a shortage of hydropower resources and difficult transportation in mountainous areas, or in environmental conditions where there is a shortage of hydropower resources and difficult transportation due to other situations. It solves the technical problem that, when carrying out the excavation and construction of pile holes for iron tower pile foundations, existing large-scale mechanized equipment with tunneling and rotary drilling as working modules has difficulty in smoothly implementing construction operations or has low construction efficiency under the background of shortage of hydropower resources and difficult transportation in mountainous areas.
[0036] The present invention proposes a tower pile well drilling device and a construction method for mountainous areas, which can replace manual pile hole excavation construction work, and can also replace large-scale mechanized equipment with tunneling and rotary drilling operations as working modules. It can well adapt to the adverse construction conditions in mountainous areas, can smoothly construct, and improve construction efficiency.
[0037] The iron tower pile well drilling device for mountain areas of the present invention is designed for specific engineering requirements of shaft diameters ranging from 1 meter to 3 meters, depths ranging from 10 meters to 20 meters, and rock geological structures (geological strength ≤ 90MPa), ensuring that the design and performance are capable of performing the excavation tasks required by the project.
[0038] First, see Figure 1 and Figure 2 , based on the technical problems solved above, the present invention discloses a mountain iron tower pile well drilling device, which is used for digging iron tower pile foundation pile holes, including a support module, and the support module is used to support and position the mountain iron tower pile well drilling device; The supporting module is rotatably connected with a diameter reducing mechanism 300, and the diameter reducing mechanism 300 can rotate around the supporting module; The diameter-changing mechanism 300 can be extended or folded back in the radial direction with the support module as the center, so that the extended diameter of the diameter-changing mechanism 300 increases or decreases; The diameter-changing mechanism 300 is provided with a drilling device 401 . When working, the drilling working end of the drilling device 401 faces the working surface at the bottom of the pile hole of the iron tower pile foundation, and the drilling device 401 can drill the working surface.
[0039] During actual construction, a construction well is first drilled in the working area, the inner diameter of the construction well matches the outer circumference size of the tower pile well drilling device used in mountainous areas, and then the equipment disclosed in the present invention is installed on the lifting joint and lowered to the designated working area in the construction well, and then the diameter-changing mechanism 300 is extended to a preset extended diameter, so that the drilling device 401 moves to the designated drilling position to perform rock drilling work.
[0040] As a support module, one of the implementation methods for supporting and positioning the iron tower pile well drilling device used in mountainous areas, please refer to Figure 1 and Figure 2 The support module includes a support column 100, a shoe mechanism 200 is fixed to the top of the support column 100, and the shoe mechanism 200 is used to tighten the inner wall of the pile hole of the iron tower pile foundation; the bottom of the support column 100 has a tip 101, which is used to tighten the bottom of the pile hole of the iron tower pile foundation; The shoe support mechanism 200 includes a support disk 201, which is a circular disk. A plurality of shoe support plates 202 are evenly arranged along the circumference of the support disk 201; a telescopic rod 203 is fixed between each shoe support plate 202 and the support disk 201, and the telescopic rod 203 can be extended and retracted along the radial direction of the support disk 201.
[0041] When the support shoe mechanism 200 is pressed against the inner wall of the pile hole of the tower pile foundation, the support shoe mechanism 200 is in a stationary state relative to the inner wall of the pile hole of the tower pile foundation; during preparation, when the tip 101 of the bottom of the support module contacts the working surface, the support shoe mechanism 200 presses against the hole wall to complete the positioning of the equipment in the hole.
[0042] For details, please refer to Figure 1 and Figure 2 The surface of the shoe plate 202 facing away from the support plate 201 has a serrated texture, which can increase the contact area with the inner wall surface of the hole, thereby increasing the friction between the shoe plate 202 and the inner wall surface of the hole, and strengthening the axial and circumferential fixing effect of the device; each shoe plate 202 is extended and retracted at the same time, so that the mountain tower pile well drilling device always maintains the axial position in the well, which is convenient for the drilling positioning of the mountain tower pile well drilling device.
[0043] As one embodiment of the layout of the shoe plate 202, please refer to Figure 1 and Figure 2 There are five support shoe plates 202 , and they are evenly arranged along the circumference of the support plate 201 .
[0044] As one implementation of the shoe support plate 202 structure, the shoe support plate 202 has a surface that is used to press against the hole wall and has a serrated structure or a peak structure.
[0045] For details, please refer to Figure 1 and Figure 2 A plurality of lifting ears 102 are fixed on the top of the support plate 201. The lifting ears 102 are symmetrically distributed with the center of the support plate 201 as the center. The lifting ears 102 are used to be suspended on a crane by ropes during construction, so that the crane can control them conveniently, making it difficult for the equipment to rotate and overturn during the lifting process.
[0046] As another embodiment of the shoe mechanism 200, please refer to Figure 3 The shoe support mechanism 200 includes a support plate 201, an adjustable telescopic rod 308 and a supporting telescopic rod 309; the two ends of the adjustable telescopic rod 308 are respectively hinged to the support plate 201 and the middle section of the supporting telescopic rod 309; one end of the supporting telescopic rod 309 is hinged to the support plate 201, and the other end of the supporting telescopic rod 309 has a tightening head 310; the adjustable telescopic rod 308 and the supporting telescopic rod 309 can be extended and retracted respectively; a plurality of lifting ears 102 are fixed on the top of the support plate 201, and each lifting ear 102 is centrally symmetrically distributed with the center of the support plate 201 as the center of the circle.
[0047] During operation, the supporting telescopic rod 309 reaches a specified working angle by controlling and adjusting the length of the telescopic rod 203, and the tightening head 310 of the supporting telescopic rod 309 is driven to tighten the inner wall of the pile hole of the tower pile foundation to achieve the underground positioning of the equipment; each lifting lug 102 is used to be suspended on a crane by a rope during construction, which is convenient for the crane to control it, making it less likely for the equipment to rotate and overturn during the lifting process.
[0048] As one of the implementation methods of the variable diameter mechanism 300 being able to rotate around the support module, please refer to Figure 1 and Figure 2 A rotating assembly is provided in the middle section of the support column 100 below the shoe support mechanism 200, and the rotating assembly includes an active rotating mechanism 103 and a swivel seat 104 which are rotatably connected to the support column 100 respectively; the active rotating mechanism 103 is close to the support plate 201 and can be driven to rotate by external force, and the swivel seat 104 is close to the bottom tip 101 of the support column 100; the drilling device 401 is installed on the reducing mechanism 300 through a drill arm, and the drill arm includes a guide rail column 501, and the drilling device 401 is slidably connected to the guide rail column 501, and a compensating telescopic rod 502 is fixed on the side of the guide rail column 501 away from the drilling device 401, and a built-in telescopic rod 503 is fixed inside the corresponding guide rail column 501, and the fixed end of the built-in telescopic rod 503 is fixedly connected to the telescopic end of the compensating telescopic rod 502, and the telescopic end of the built-in telescopic rod 503 is fixedly connected to the drilling device 401.
[0049] Specifically, a rubber block is fixed at the bottom of the guide rail column 501. In this way, the variable diameter mechanism 300 is first adjusted according to the size of the pile hole diameter of the tower pile foundation, so that the support shoe mechanism 200 is pressed against the inner wall of the pile hole of the tower pile foundation to achieve the underground positioning of the equipment; then the compensating telescopic rod 502 is driven to make the rubber block fixed at the bottom of the guide rail column 501 contact the ground, thereby increasing the contact area and improving the stability of the drilling rig; then the built-in telescopic rod 503 is driven to push the drilling device to perform drilling operations; and at the same time, the active rotating mechanism 103 is driven to achieve full-circle operation in the underground space.
[0050] As a first embodiment of the diameter reducing mechanism 300, please refer to Figure 1 and Figure 2 The diameter-changing mechanism 300 includes a first swing arm 301. Correspondingly, the active rotation mechanism 103 includes a first rotation support seat 302. One end of the first swing arm 301 is hinged to the first rotation support seat 302. Correspondingly, one end of a swing arm telescopic rod 305 is hinged on the swivel seat 104, and the other end of the swing arm telescopic rod 305 and the other end of the first swing arm 301 are hinged on the drill arm at the same time, and the drill arm can drive the drilling device 401 to telescopic movement.
[0051] In this way, during construction, the diameter-changing mechanism 300 first extends the swing arm telescopic rod 305 according to the hole size. When the swing arm telescopic rod 305 is extended or retracted, it can drive the first swing arm 301 to swing up and down in the vertical direction, and then drive the drill arm and the drilling device 401 to swing along the radial direction, so as to expand or reduce the operating diameter of the drilling device 401.
[0052] In addition, the first swing arm 301 always has a certain angle with the axis of the support column 100. Therefore, due to the parallelogram principle, the drill arm always maintains a certain angle with the axis of the column, so that the drilling device 401 can drill holes at a certain angle to prevent over-digging and under-digging during construction, and also prevent the equipment from colliding with the well wall during operation, causing equipment damage. A shock-absorbing top block is set at the front end of the guide rail column 501 to increase the contact area between the equipment and the working surface and buffer the vibration generated during operation.
[0053] Specifically, as a driving mode of the active rotating mechanism 103, hydraulic driving or electric driving is adopted.
[0054] During specific implementation, the active rotation mechanism 103 may adopt a mechanical structure type of a motor, a rotary joint, a turntable, a rotary cylinder, a rotary pump, or a rotary valve, all of which can realize the required active rotation function in this solution.
[0055] Specifically, an upper slide is fixed on the telescopic end of the built-in telescopic rod 503 , and the drilling device 401 is detachably mounted on the upper slide to achieve a fixed connection between the telescopic end of the built-in telescopic rod 503 and the drilling device 401 .
[0056] As a preferred solution of the first embodiment of the diameter reducing mechanism 300, please refer to Figure 1 and Figure 2 The variable diameter mechanism 300 also includes a second swing arm 303. Correspondingly, the active rotation mechanism 103 includes a second rotation support seat 304. One end of the second swing arm 303 is hinged to the second rotation support seat 304; the other end of the second swing arm 303 is hinged to the side of the guide rail column 501 away from the drilling device 401, and the first swing arm 301 and the second swing arm 303 are equal in length and are arranged in parallel.
[0057] If there is only the first swing arm 301, although it can follow the extension of the swing arm telescopic rod 305 to expand the operating diameter of the drill arm, during the extension and retraction process, the movement state of the drill arm is parallel movement, and the direction of the working end of the drilling device 401 installed on the drill arm is also parallel movement, and the operable diameter is small; after adding the second swing arm 303, the drill arm can perform non-parallel movement when swinging, that is, the swing amplitude of the lower section of the drill arm will be greater than the swing amplitude of the upper end of the drill arm, thereby increasing the operable diameter of the drill arm.
[0058] As a second embodiment of the diameter reducing mechanism 300, please refer to Figure 3 The diameter-changing mechanism 300 includes a first swing arm 301, and correspondingly, the active rotation mechanism 103 includes a first rotation support seat 302, and both ends of the first swing arm 301 are respectively hinged to the first rotation support seat 302 and the side of the guide rail column 501 away from the drilling device 401; The two ends of the first telescopic arm 306 are respectively hinged between the first swing arm 301 and the first rotating support seat 302; the two ends of the second telescopic arm 307 are respectively hinged between the first swing arm 301 and the side of the guide rail column 501 away from the drilling device 401.
[0059] During construction, the variable diameter mechanism 300 controls the telescopic length of the first telescopic arm 306 and the second telescopic arm 307 according to the hole size, thereby driving the first swing arm 301 to swing up and down in the vertical direction, and then driving the drill arm and the drilling device 401 to swing along the radial direction to expand or reduce the operating diameter of the drilling device 401.
[0060] As a preferred solution for mountain tower pile well drilling equipment, please refer to Figure 1 and Figure 2, a plurality of reducing mechanisms 300 are rotatably connected to the support column 100, and a drilling device 401 or a splitting device 402 is installed on each of the reducing mechanisms 300. When working, the splitting end of the splitting device 402 faces the working surface at the bottom of the pile hole of the tower pile foundation. The splitting device 402 can split the rock on the working surface to cooperate with the drilling device 401 to perform drilling operations. During construction, the drilling device 401 is first started to perform drilling operations. When encountering a medium that is difficult to drill, such as rock, the splitting device 402 is started after the drilling device 401 completes the drilling work, and the splitting device 402 is extended to the drilled hole to perform rock crushing work.
[0061] As an embodiment of a tower pile well drilling device for mountainous areas, the number of drill arms provided therein may be one or more, and the working device installed on the drill arm may be a plurality of drilling devices 401 or a combination of a drilling device 401 and a splitting device 402, depending on the actual properties of the medium to be excavated on site.
[0062] As an embodiment of the built-in telescopic rod 503 driving the drilling device 401 or the splitting device 402 to extend and retract, in addition to using the telescopic rod 203, a chain drive or a rope drive can also be used instead.
[0063] Specifically, the active rotating mechanism 103 and the swivel seat 104 are rotatably connected to the support column 100 via swivel bearings.
[0064] Specifically, when the swivel seat 104 rotates, only axial pressure is transmitted without transmitting torque, thereby ensuring that the tip 101 at the bottom of the support column 100 is always pressed against the working surface without rotating.
[0065] Specifically, the drilling device 401 is a rock drilling device, which is used to drill the rock to be excavated, and the splitting device 402 is used to split the rock to be excavated.
[0066] For details, please refer to Figure 2 When the drilling device 401 is a rock drilling device, a drill support 504 is fixed below the guide rail column 501 to limit the vibration of the drill rod of the rock drilling device within a certain range and improve the stability of the rock drilling device.
[0067] Specifically, a shock-absorbing top block is installed above the guide rail column 501 for shock prevention.
[0068] During specific implementation, the present invention can also match the number and type of working modules according to different requirements.
[0069] Specifically, each of the above-mentioned components with telescopic function can be hydraulically driven or electrically driven to be telescopic.
[0070] The use of the tower pile well drilling device disclosed in the present invention for mountain areas has the following technical effects: 1. The iron tower pile well drilling device for mountainous areas of the present invention has a simple and uncomplicated structure, and can flexibly adjust the operating diameter through a diameter-changing mechanism. When not working, the diameter-changing mechanism can be folded, and the device has a small size and a light weight. It does not require the use of large equipment or large transportation equipment, nor does it require a large construction site, making it more suitable for the narrow working space and complex terrain in mountainous areas, and more suitable for environmental conditions such as shortage of water and electricity resources and difficult transportation in mountainous areas. It can reduce project preparation time, improve mobility and applicability, and improve operating efficiency. The iron tower pile well drilling device for mountainous areas of the present invention also improves the modularity of the equipment. Through modular design, the device has a compact structure, is easy to disassemble and assemble, and is convenient for manual transportation and cableway transportation, thereby adapting to the complex terrain and traffic conditions in mountainous areas.
[0071] 2. The iron tower pile well drilling device for mountain areas of the present invention is suitable for well engineering in mountainous areas and can adapt to terrain that cannot be reached by vehicles and crawler chassis, ensuring smooth construction.
[0072] 3. The tower pile well drilling device for mountain areas of the present invention meets the requirements of the engineering object: for the specific engineering requirements of the shaft diameter ranging from 1 meter to 3 meters, the depth of 10 meters to 20 meters, and the rock geological structure (geological strength ≤ 90MPa), it ensures that the design and performance are competent for the excavation tasks required by the project, and considering the shortage of water resources, it is also necessary to save energy and water resources.
[0073] 4. The tower pile well drilling device for mountain areas of the present invention has a simple working mode and supports unmanned underground construction, that is, there is no need for personnel to directly enter the wellbore during underground operations, and professionals can operate and monitor the equipment outside the wellbore. In actual application, it can be selected to access the remote control and intelligent control system, which can realize the automation of the entire excavation and milling process, reduce the personnel risks at the construction site, ensure personnel safety, and thus improve construction safety and efficiency.
[0074] 5. The support shoe mechanism of the present invention can be extended and retracted at the same time when supporting the hole wall, ensuring that the iron tower pile well drilling device used in mountainous areas is always in the center of the pile hole, ensuring the drilling direction and ensuring the accuracy of the construction.
[0075] 6. The tower pile well drilling device for mountain areas of the present invention can rotate for operation, and can realize all-round and cyclic operation in the hole, thus improving the construction efficiency.
[0076] 7. The variable diameter mechanism of the present invention utilizes a parallelogram mechanism to improve the stability of the drill arm while ensuring the range of motion of the drill arm. Due to the parallelogram principle, the equipment always maintains a certain angle with the equipment axis during drilling to prevent over-digging, under-digging and collision between the equipment and the well wall.
[0077] 8. The two-stage telescopic drill arm of the present invention can flexibly adjust the working diameter, can adapt to the excavation requirements of different working diameters and depths, and enhances the versatility of the equipment.
[0078] In summary, the tower pile well drilling device for mountainous areas of the present invention can meet the specific needs of mountainous environmental projects, improve construction efficiency and safety, and provide reliable technical support for power transmission and transformation pile foundation excavation projects in mountainous areas.
[0079] Second, see Figure 4 The present invention also discloses a method for constructing a mountain iron tower pile foundation, which is implemented by using the above-mentioned mountain iron tower pile well drilling device 604, and includes the following steps: S1. Carry out construction preparation and measurement and layout according to the design data; S2, excavating the earthwork of the first section pile hole 601, and then carrying out the construction of the lock buckle and the retaining wall, as well as the construction of the hole mouth protection of the first section pile hole 601; S3, assembling the tower pile well drilling device 604 for mountain areas; S4, lowering the mountain tower pile well drilling device 604 to the bottom of the first pile hole 601, and adjusting the mountain tower pile well drilling device 604 to a working ready state; S5, starting the drilling device to drill holes according to the designed drilling points 603; S6, starting the splitting device, and moving the splitting device to the corresponding drill hole to perform the splitting operation; S7, after the rock splitting is completed, the shoe support mechanism and the drill arm are retracted, and the mountain tower pile well drilling device 604 is taken out from the pile hole; then the slag and gravel in the pile hole are cleaned, and the hole formation is checked. If it meets the design requirements, the operation is stopped and step S8 is executed. If it does not meet the requirements, steps S5 and S6 are repeated until the hole formation meets the requirements; S8. Make a steel cage and install it in the hole, then pour the pile core concrete to complete the construction of the mountain power tower pile foundation.
[0080] Specifically, in step S4, please refer to Figure 5First, it is necessary to install a vertical conveyor and a crane 602 above the opening of the first pile hole 601. The vertical conveyor is used to transport construction materials. The crane 602 is used to connect and fix with the lifting lug on the top of the assembled mountain tower pile well drilling device 604 through ropes, so as to facilitate the subsequent lowering of the mountain tower pile well drilling device 604 into the first pile hole 601. The crane 602 lowers the equipment to the designated working position until the bottom of the support module contacts the rock at the bottom of the well and stops lowering.
[0081] Preferably, in step S4, the tower pile well drilling device 604 for mountain areas is adjusted to a working ready state. First, the telescopic rods of the support shoe mechanism need to be driven to extend radially, and each support shoe plate needs to be pressed against the rock wall surface of the pile hole to complete the axial positioning of the equipment in the pile hole.
[0082] Specifically, in step S5, it is necessary to design a corresponding drilling arrangement diagram according to the size of the pile hole, the rock environment, and the type of drilling tools to obtain the designed drilling points 603.
[0083] As a preferred embodiment, in step S5, refer to Figure 6 The designed points include a plurality of drilling points at the outer edge of the working surface and a plurality of splitting hole points arranged in an array at the center of the working surface. The specific method of starting the drilling device to drill holes respectively according to the designed drilling points 603 includes: S5.1. The drilling device first drills holes in sequence along the outer edge of the working surface to form a free-standing surface; S5.2, the drilling device moves sequentially to a plurality of splitting hole points arranged in an array at the center of the working surface to drill splitting holes; S5.3. After the drilling of each splitting hole is completed, the splitting module is driven to move to the splitting holes in the middle area to perform rock splitting in sequence.
[0084] Specifically, in step S5.1, after a hole is drilled, the active rotation mechanism is started to rotate the drilling device to the next designed drilling point for drilling; in step S5.2, after the hole on the outer edge of the working surface is drilled, the swing arm telescopic rod is started, the drill arm is retracted to the splitting hole point, and the built-in telescopic rod and the supplementary telescopic rod are opened, the drilling device is adjusted to the designed drilling point, and the drilling device is started for drilling until all the designed drilling points are drilled.
[0085] The mountain tower pile foundation construction method disclosed by the present invention has the following technical effects: 1. The mountain iron tower pile foundation construction method of the present invention is suitable for shafts with a diameter ranging from 1 meter to 3 meters, a depth of 10 meters to 20 meters, and rock geological structures (geological strength ≤ 90MPa).
[0086] 2. The mountain tower pile foundation construction method of the present invention is suitable for well engineering in mountainous areas and can adapt to terrain that cannot be reached by vehicles and crawler chassis, ensuring smooth construction.
[0087] 3. The mountain tower pile foundation construction method of the present invention is simple and supports unmanned construction underground, that is, there is no need for personnel to directly enter the shaft during underground operations, and professionals can operate and monitor the equipment outside the shaft. In actual application, it is possible to choose to access the remote control and intelligent control system, which can realize the automation of the entire excavation and milling process, reduce the personnel risks at the construction site, ensure personnel safety, and thus improve construction safety and efficiency.
[0088] It is understood that the present invention is described by some embodiments, and those skilled in the art are aware that various changes or equivalent substitutions may be made to these features and embodiments without departing from the spirit and scope of the present invention. Under the teachings of the present invention, these features and embodiments may be modified to adapt to specific circumstances and materials without departing from the spirit and scope of the present invention. The embodiments described in the present invention are part of the embodiments of the present invention, rather than all of the embodiments. The components of the embodiments of the present invention generally described and shown in the drawings herein may be arranged and designed in various different configurations. Therefore, the following detailed description of the embodiments of the present invention provided in the drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Therefore, the present invention is not limited to the specific embodiments disclosed herein, and all other embodiments obtained by ordinary technicians in the art without creative work based on the embodiments in the present invention belong to the scope of protection of the present invention.
Claims
1. A tower pile well drilling device for mountain areas, used for digging tower pile foundation holes, characterized in that: It comprises a support module, which is used to support and position a tower pile well drilling device used in mountainous areas; a diameter-changing mechanism is rotatably connected to the support module, and the diameter-changing mechanism can rotate around the support module; the diameter-changing mechanism can radially extend or fold back around the support module, so that the extended diameter of the diameter-changing mechanism increases or decreases; a drilling device is installed on the diameter-changing mechanism, and the drilling working end of the drilling device faces the working surface at the bottom of the pile hole of the tower pile foundation when working, and the drilling device can drill the working surface.
2. The device for drilling iron tower pile wells in mountainous areas according to claim 1, characterized in that: The support module includes a support column, a support shoe mechanism is fixed to the top of the support column, and the support shoe mechanism is used to tighten the inner wall of the pile hole of the iron tower pile foundation; the bottom of the support column has a pointed end, which is used to tighten the bottom of the pile hole of the iron tower pile foundation; the support shoe mechanism includes a support disk, which is a circular disk, and a plurality of support shoe plates are evenly arranged along the circumference of the support disk; a telescopic rod is fixed between each support shoe plate and the support disk, and the telescopic rod can be extended and retracted along the radial direction of the support disk.
3. The device for drilling iron tower pile wells in mountainous areas according to claim 1, characterized in that: The support module includes a support column, a support shoe mechanism is fixed on the top of the support column, and the support shoe mechanism is used to tighten the inner wall of the pile hole of the iron tower pile foundation; the bottom of the support column has a pointed end, which is used to tighten the bottom of the pile hole of the iron tower pile foundation; the support shoe mechanism includes a support plate, an adjustment telescopic rod and a support telescopic rod; the two ends of the adjustment telescopic rod are respectively hinged to the support plate and the middle section of the support telescopic rod; one end of the support telescopic rod is hinged to the support plate, and the other end of the support telescopic rod has a tightening head; the adjustment telescopic rod and the support telescopic rod can be telescoped respectively; a plurality of lifting ears are fixed on the top of the support plate, and each lifting ear is symmetrically distributed with the center of the support plate as the center of the circle.
4. The device for drilling iron tower pile wells in mountainous areas according to claim 2 or 3, characterized in that: A rotating assembly is provided in the middle section of the supporting column below the support shoe mechanism, and the rotating assembly includes an active rotating mechanism and a swivel seat which are rotatably connected to the supporting column respectively; the active rotating mechanism is close to the supporting plate and can be driven to rotate by external force, and the swivel seat is close to the bottom tip of the supporting column; the drilling device is installed on the reducing mechanism through a drill arm, and the drill arm includes a guide rail column, and the drilling device is slidably connected to the guide rail column, and a compensating telescopic rod is fixed on the side of the guide rail column away from the drilling device, and a built-in telescopic rod is fixed inside the corresponding guide rail column, and the fixed end of the built-in telescopic rod is fixedly connected to the telescopic end of the compensating telescopic rod, and the telescopic end of the built-in telescopic rod is fixedly connected to the drilling device.
5. The device for drilling iron tower pile wells in mountainous areas according to claim 4, characterized in that: The diameter-changing mechanism includes a first swing arm, and correspondingly, the active rotation mechanism includes a first rotation support seat, and one end of the first swing arm is hinged to the first rotation support seat; Correspondingly, one end of a swing arm telescopic rod is hinged on the swivel seat, and the other end of the swing arm telescopic rod and the other end of the first swing arm are hinged on the drill arm at the same time, and the drill arm can drive the drilling device to telescopic movement.
6. The device for drilling iron tower pile wells in mountainous areas according to claim 5, characterized in that: The variable diameter mechanism also includes a second swing arm, and correspondingly, the active rotation mechanism includes a second rotating support seat, one end of the second swing arm is hinged to the second rotating support seat; the other end of the second swing arm is hinged to the side of the guide rail column away from the drilling device, and the first swing arm and the second swing arm are equal in length and are arranged in parallel.
7. The device for drilling iron tower pile wells in mountainous areas according to claim 4, characterized in that: The variable diameter mechanism includes a first swing arm, and correspondingly, the active rotation mechanism includes a first rotating support seat, the two ends of the first swing arm are respectively hinged to the first rotating support seat and the side of the guide rail column away from the drilling device; the two ends of the first telescopic arm are respectively hinged between the first swing arm and the first rotating support seat; the two ends of the second telescopic arm are respectively hinged between the first swing arm and the side of the guide rail column away from the drilling device.
8. The tower pile drilling device for mountain areas according to claim 6 or 7, characterized in that: A plurality of diameter-changing mechanisms are rotatably connected to the support column, and a drilling device or a splitting device is installed on each of the diameter-changing mechanisms. When working, the splitting end of the splitting device faces the working surface at the bottom of the pile hole of the tower pile foundation, and the splitting device can split the rock on the working surface.
9. A method for constructing a mountain tower pile foundation, implemented using the mountain tower pile well drilling device as claimed in claim 8, characterized in that: The following steps are involved: S1. Carry out construction preparation and measurement and layout according to the design data; S2, excavate the earthwork of the first section of the pile hole, then carry out the construction of the lock and retaining wall, and the protection construction of the first section of the pile hole; S3, assembling the tower pile well drilling device for mountain areas; S4, lowering the mountain tower pile well drilling device to the bottom of the first pile hole, and adjusting the mountain tower pile well drilling device to a working ready state; S5. Start the drilling device to drill holes according to the designed drilling points; S6, starting the splitting device, and moving the splitting device to the corresponding drill hole to perform the splitting operation; S7, after the rock splitting is completed, the shoe support mechanism and the drill arm are retracted, and the mountain tower pile well drilling device is taken out from the pile hole; then the slag and gravel in the pile hole are cleaned, and the hole formation is checked. If it meets the design requirements, the operation is stopped and step S8 is executed. If it does not meet the requirements, steps S5 and S6 are repeated until the hole formation meets the requirements; S8. Make a steel cage and install it in the hole, then pour the pile core concrete to complete the construction of the mountain power tower pile foundation.
10. The method for constructing a mountain tower pile foundation according to claim 9, characterized in that: In step S5, the designed points include a plurality of drilling points at the outer edge of the working surface and a plurality of splitting hole points arranged in an array at the center of the working surface. The specific method of starting the drilling device to drill holes respectively according to the designed drilling points includes: S5.
1. The drilling device first drills holes in sequence along the outer edge of the working surface to form a free-standing surface; S5.2, the drilling device moves sequentially to a plurality of splitting hole points arranged in an array at the center of the working surface to drill splitting holes; S5.
3. After the drilling of each splitting hole is completed, the splitting module is driven to move to the splitting holes in the middle area to perform rock splitting in sequence.