Dangerous rock mass area highway tunnel portal tunneling method

By setting up drainage ditches and advanced pipe roof support at the tunnel entrance, combined with ring excavation and monitoring and measurement, the problem of tunnel entrance construction in dangerous rock mass areas was solved, construction efficiency and safety were improved, and construction risks were reduced.

CN118933831APending Publication Date: 2024-11-12SOUTH AFRICA SURVEY & DESIGN INST HUBEI
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411223788.2
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-03
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

In areas with unstable rock masses, tunnel entrance construction is difficult, environmentally restricted, and carries high safety risks. Traditional construction procedures cannot be implemented, especially since the tunnel entrance is a steep slope, making it impossible to construct advanced pipe roofs, resulting in serious construction safety hazards.

Method used

The project employs a method of setting up intercepting and drainage ditches on the slope of the tunnel to assist in the excavation of the traffic tunnel and to carry out advanced large pipe roof support. Inside the tunnel, a ring excavation method with reserved core soil is used for construction, and a small cross-section pilot tunnel is used for exiting the tunnel. Combined with monitoring and measurement and dangerous rock mass protection measures, including removal, wire mesh protection and shotcrete reinforcement, the project is carried out.

Benefits of technology

It reduced construction difficulty, minimized temporary land use and soil erosion, met environmental protection requirements, improved construction efficiency, reduced construction risks, and controlled the hazards posed by unstable rock masses.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933831A_ABST
    Figure CN118933831A_ABST
Patent Text Reader

Abstract

The invention provides a dangerous rock mass area highway tunnel portal tunneling method, which belongs to the technical field of tunnel construction, and comprises the following steps: S1, excavating an edge line at an upward slope of a tunnel edge, and arranging a C20 concrete intercepting and draining ditch at a position 5m away from the tunnel edge; s2, after the auxiliary traffic tunnel enters the main tunnel body section, tunneling is conducted in the tunnel opening direction where the dangerous rock mass is located, and when the auxiliary traffic tunnel is close to the tunnel opening, advanced large pipe shed supporting measures are taken in the tunnel; s3, a tunnel face in the tunnel is constructed through an annular excavation core soil reserving method; s4, after the side wall pilot tunnel goes out of the tunnel, the other side is excavated in an expanding mode, and the temporary support of the pilot tunnel is dismantled synchronously; and S5, dangerous rock mass protection and treatment are conducted in the hole. According to the construction method, by changing the working procedure of inward hole construction, the difficulty that a construction road and an advanced pipe shed cannot be built due to the steep terrain is overcome, and a construction platform is provided for dangerous rock mass treatment and bridge piers and abutments after the main line serves as the construction road and goes out of the hole from the inside of the hole.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of tunnel construction, and in particular relates to a method for excavating a highway tunnel portal in a dangerous rock mass area. Background Art

[0002] Dangerous rock mass is a common unfavorable geological condition in the construction of mountainous expressways, especially dangerous rock mass distributed above the tunnel entrance. Since the route design generally adopts the tunnel + bridge solution, the existence of dangerous rock mass brings challenges to expressway design and construction, especially the latter, which is mainly reflected in the following aspects:

[0003] (1) Difficulty in construction organization: Dangerous rock masses are generally located in mountainous canyon areas. The strata are hard rock with steep terrain. The tunnel entrances are all on slopes. The construction access roads are laid along the steep mountains and are difficult to build. It is impossible to work close to the tunnel entrances and treat the dangerous rock masses.

[0004] (2) Limited working environment: According to the traditional construction process from the tunnel entrance to the tunnel interior, the tunnel entrance generally needs to be supported by an advance pipe shed before entering the tunnel. However, due to the high and steep slope of the tunnel entrance, the advance pipe shed cannot be installed and the usual construction process cannot be implemented.

[0005] (3) High construction safety risk: Due to the distribution of dangerous rock masses above, the construction disturbance at the tunnel entrance below poses a huge safety hazard to the interference and safety of the bridge connected to the tunnel. Summary of the invention

[0006] The embodiment of the present invention provides a method for excavating the entrance of a highway tunnel in a dangerous rock area, which solves the problem that it is difficult to build a construction access road and construct an advance pipe shed due to steep terrain, and the construction disturbance of the tunnel entrance causes interference and safety hazards to the bridge connected to the tunnel.

[0007] In view of the above problems, the technical solution proposed by the present invention is:

[0008] The present invention provides a method for excavating a highway tunnel portal in a dangerous rock mass area, comprising the following steps:

[0009] S1, excavate the edge line at the back slope of the tunnel, set up a C20 concrete intercepting drainage ditch 5m away, set a settlement joint every 10m to 15m in the intercepting ditch, the width of the joint is 2cm, and the joints are filled with high-density polyethylene foam boards;

[0010] S2, after entering the main tunnel through the auxiliary traffic tunnel, excavate towards the tunnel entrance where the dangerous rock mass is located. When approaching the tunnel entrance, take advanced large pipe shed support measures in the tunnel;

[0011] S3, the tunnel face is constructed by circular excavation and reserved core soil method. When the construction reaches 16m away from the tunnel entrance, a small-section pilot pit is used to exit the tunnel. Then the up and down step method is used for excavation. Temporary I-beam supports are installed in the pilot pit, and the steel frame spacing is 60cm;

[0012] S4, after the side wall pilot pit exits the cave, expand the other side and simultaneously remove the temporary support of the pilot pit until the cave exits. The monitoring and measurement should be strengthened near the exit surface;

[0013] S5, protection and treatment of dangerous rock masses in the tunnel, including removal of dangerous rock masses, mesh protection, shotcrete reinforcement and process monitoring.

[0014] As a preferred technical solution of the present invention, the advance large pipe shed support in step S2 is specifically as follows: the pipe shed size is φ108×6mm, the pipe shed length is 16m, the pipe shed work in the tunnel is located 10m from the main tunnel, the section arch is expanded by 80cm, the guide wall adopts I-beam and C25 shotcrete structure, the drilling adopts crawler pipe shed drilling rig, cement and water glass double slurry is injected, and an advance small guide tube is constructed at a section 6m away from the tunnel entrance. The advance small guide tube is drilled by an air-leg rock drill, and the grouting slurry is cement slurry.

[0015] As a preferred technical solution of the present invention, the circular excavation and reserved core soil method construction method of step S3 is specifically as follows:

[0016] Carry out circular excavation of the upper section, apply initial support to the upper section, excavate the core soil of the upper section, excavate the lower section by jumping trenches, apply initial support to the lower section, excavate the lower section by jumping trenches, apply initial support to the lower section, construct the invert, backfill the invert, and finally build the secondary lining as a whole.

[0017] As a preferred technical solution of the present invention, the method of guiding the small-section pit out of the hole in step S3 is specifically as follows:

[0018] When the excavation of the exit section is to 16m away from the tunnel entrance, the upper left pilot pit is constructed first to exit the tunnel. The upper and lower steps of the pilot pit are 5m long. The excavation progress of the upper step is not more than 1 steel frame spacing, and the excavation progress of the lower step is not more than 2 steel frame spacing. After the upper left pilot pit exits the tunnel, the other side is excavated. The size of the pilot pit is 7.1m×5m. The excavation progress of the upper step is not more than 1 steel frame spacing, and the excavation progress of the lower step is not more than 2 steel frame spacing.

[0019] As a preferred technical solution of the present invention, the monitoring measurement in step S3 is specifically as follows:

[0020] Step A: Conduct detailed surface survey before excavation, and carry out advanced geological forecast and monitoring and measurement of the surface and excavation section during construction;

[0021] Step B: geological sketching and digital imaging should be carried out promptly after tunnel excavation;

[0022] Step C: After the initial support is completed, observe and record the cracks on the sprayed layer surface and their development, water seepage, and deformation;

[0023] Step D, measuring the internal displacement of the surrounding rock, the axial force of the anchor, the initial support internal force and the anchor pull-out test;

[0024] Step E, measuring the water volume and pore water pressure of groundwater development, fault fracture zone and geological structure zone;

[0025] Step F, when there are structures near the tunnel that are affected by tunnel construction blasting, blasting vibration monitoring and measurement is performed;

[0026] Step G: Horizontal and vertical displacement monitoring points should be buried for each dangerous rock mass, and manual measurement should be performed using a high-precision total station;

[0027] Step H: Evaluate the environment and engineering safety based on the monitoring and measurement data to determine whether the environment and safety meet the requirements. If not, adjust the parameters and change the design.

[0028] As a preferred technical solution of the present invention, the specific contents of the environmental and engineering safety assessment in step H are as follows:

[0029] Step H1, geological structure safety, evaluates the stability of the geological structure where the tunnel is located, including the lithology, fault zones and rock mass strength of the geological structure;

[0030] Step H2, groundwater safety, evaluates the impact of groundwater during tunnel construction and operation, including the impact of groundwater inrush pressure and water level changes on tunnel structure;

[0031] Step H3, structural stability, evaluates the stability of the tunnel structure, including the design and construction quality of the tunnel's support structure and lining structure, as well as the safety of the tunnel structure under different load conditions;

[0032] Step H4, ventilation safety, evaluates the ventilation system during the tunnel construction phase;

[0033] Step H5, environmental safety, assessing the impact of the tunnel project on the surrounding environment;

[0034] Step H6, construction safety, evaluates the safety risks during tunnel construction.

[0035] As a preferred technical solution of the present invention, the details of the protection and treatment of dangerous rock mass in step S5 are as follows:

[0036] Step S51, the dangerous rock mass is cleared by using static expansion agent to crack the rock and manual pneumatic pick to crush the rock;

[0037] Step S52, laying a net for protection, laying an active protection net on the surface of the dangerous rock mass for protection;

[0038] Step S53, spraying concrete reinforcement in the rock body, using 5 cm thick C25 sprayed concrete reinforcement;

[0039] Step S54, process monitoring, adopts observation and monitoring measures, in addition to daily inspections of the condition of the dangerous rock mass, a monitoring point is buried on the top of the dangerous rock mass to regularly measure the displacement of the rock mass.

[0040] Compared with the prior art, the beneficial effects of the present invention are:

[0041] (1) The present invention overcomes the common difficulty of constructing construction access roads for tunnels in steep mountainous areas, especially in dangerous rock areas, reduces temporary land acquisition and soil erosion, further meets environmental protection requirements, reduces construction risks, and improves construction efficiency.

[0042] (2) The present invention reduces the difficulty of treating dangerous rock masses and controls the risk of dangerous rock masses causing harm to the project through an excavation method that combines blasting excavation with real-time monitoring and measurement.

[0043] The above description is only an overview of the technical solution of the present invention. In order to more clearly understand the technical means of the present invention, it can be implemented according to the contents of the specification. In order to make the above and other purposes, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are listed below. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] Figure 1 It is a schematic diagram of a process of a highway tunnel portal excavation method in a dangerous rock mass area disclosed by the present invention;

[0045] Figure 2 It is a schematic diagram of the monitoring and measuring process of a highway tunnel portal excavation method in a dangerous rock mass area disclosed by the present invention;

[0046] Figure 3 It is a front schematic diagram of a ring line excavation and reserved core soil construction of a highway tunnel portal excavation method in a dangerous rock mass area disclosed by the present invention;

[0047] Figure 4 It is a schematic diagram of advance support for a highway tunnel portal excavation method in a dangerous rock mass area disclosed in the present invention;

[0048] Figure 5 It is a schematic diagram of excavation of the upper left pilot pit of a tunnel body of a highway tunnel portal excavation method in a dangerous rock mass area disclosed by the present invention;

[0049] Figure 6The present invention discloses a schematic diagram of excavation of a right upper pilot pit of a tunnel body in a method for tunneling a highway tunnel in a dangerous rock mass area. DETAILED DESCRIPTION

[0050] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0051] Therefore, the following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0052] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0053] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0054] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0055] Embodiment 1

[0056] Refer to the attached Figure 1-6 As shown, the present invention provides a technical solution: a method for excavating a highway tunnel entrance in a dangerous rock mass area, comprising the following steps:

[0057] S1, excavate the edge line at the back slope of the tunnel, set up a C20 concrete intercepting drainage ditch 5m away, set a settlement joint every 10m to 15m in the intercepting ditch, the width of the joint is 2cm, and the joints are filled with high-density polyethylene foam boards;

[0058] S2, after entering the main tunnel through the auxiliary traffic tunnel, excavate towards the tunnel entrance where the dangerous rock mass is located. When approaching the tunnel entrance, the distance is generally 15 to 20 meters, and advance large pipe shed support measures are implemented in the tunnel;

[0059] S3, the tunnel face is constructed by circular excavation and reserved core soil method. When the construction reaches 16m away from the tunnel entrance, the small-section pilot pit is used for exit. When the exit section is excavated to 16m away from the tunnel entrance, the left upper pilot pit is used to exit the tunnel first. The upper and lower steps of the pilot pit are 5m long. The excavation footage of the upper step does not exceed the spacing of 1 steel frame, and the excavation footage of the lower step does not exceed the spacing of 2 steel frames. After the upper left pilot pit exits the tunnel, the other side is expanded. The pilot pit size is 7.1m×5m. The excavation footage of the upper step does not exceed the spacing of 1 steel frame, and the excavation footage of the lower step does not exceed the spacing of 2 steel frames. The pilot pit size is 5.4m×5m. Subsequently, the upper and lower steps method is used for excavation. Temporary I-beam supports are installed in the pilot pit, and the spacing between steel frames is 60cm.

[0060] S4, after the side wall pilot pit exits the cave, expand the other side and simultaneously remove the temporary support of the pilot pit until the cave exits. The monitoring and measurement should be strengthened near the exit surface;

[0061] S5, protection and treatment of dangerous rock masses in the tunnel, including removal of dangerous rock masses, mesh protection, shotcrete reinforcement and process monitoring, specifically including:

[0062] Step S51, the dangerous rock mass is removed by using static expansion agent to crack the rock and manually using a pneumatic pick to break the rock. Specifically, a hand pneumatic drill is used to drill a hole, and then an expansion agent is poured into the hole to form a transverse splitting crack. The worker uses a pneumatic pick to chisel out the rock blocks;

[0063] Step S52, netting protection, laying active protection nets on the surface of dangerous rock mass, the construction process is: erecting support → removing loose soil and pumice → determining hole position → drilling → cleaning holes → installing anchor rods → grouting → installing longitudinal and transverse support ropes → (laying and hanging steel wire grids) → laying steel wire rope nets;

[0064] Step S53, spraying concrete reinforcement in the rock body, using 5 cm thick C25 sprayed concrete reinforcement;

[0065] Step S54, process monitoring, adopts observation and monitoring measures, in addition to daily inspections of the condition of the dangerous rock mass, such as crack development and crack water flow, at the same time, monitoring points are buried on the top of the dangerous rock mass in the form of reflective stickers and steel frames to regularly measure the rock mass displacement.

[0066] The embodiment of the present invention is also implemented through the following technical solutions.

[0067] In the embodiment of the present invention, the advance large pipe shed support in step S2 is specifically as follows: the pipe shed size is φ108×6mm, the pipe shed length is 16m, the pipe shed work in the tunnel is placed at 10m of the main tunnel, the section arch is expanded by 80cm, the guide wall adopts I-beam and C25 shotcrete structure, the drilling adopts crawler pipe shed drilling rig, cement and water glass double slurry is injected, and an advance small guide tube is constructed at a section 6m away from the tunnel entrance. The advance small guide tube is drilled by an air-leg rock drill, and the grouting slurry is cement slurry.

[0068] Among them, Table 1 is the advanced support parameter table

[0069]

[0070]

[0071] In the embodiment of the present invention, the circular excavation and reserved core soil method construction method of step S3 is specifically as follows:

[0072] Carry out circular excavation of the upper section, apply initial support to the upper section, excavate the core soil of the upper section, excavate the lower section by jumping trenches, apply initial support to the lower section, excavate the lower section by jumping trenches, apply initial support to the lower section, construct the invert, backfill the invert, and finally build the secondary lining as a whole.

[0073] In the embodiment of the present invention, the monitoring and measurement in step S3 mainly strengthens the monitoring and measurement of the vault sinking in the tunnel, the surrounding convergence and the surface settlement observation, conducts advanced geological prediction and geological sketching, and timely analyzes and organizes data to guide the construction, as follows:

[0074] Step A: Conduct detailed surface survey before excavation, and carry out advanced geological forecast and monitoring and measurement of the surface and excavation section during construction;

[0075] Step B: geological sketching and digital imaging should be carried out promptly after tunnel excavation;

[0076] Step C: After the initial support is completed, observe and record the cracks on the sprayed layer surface and their development, water seepage, and deformation;

[0077] Step D, measuring the internal displacement of the surrounding rock, the axial force of the anchor, the initial support internal force and the anchor pull-out test;

[0078] Step E, measuring the water volume and pore water pressure of groundwater development, fault fracture zone and geological structure zone;

[0079] Step F, when there are structures near the tunnel that are affected by tunnel construction blasting, blasting vibration monitoring and measurement is performed;

[0080] Step G: Horizontal and vertical displacement monitoring points should be buried for each dangerous rock mass, and manual measurement should be performed using a high-precision total station;

[0081] Step H: Evaluate the environment and engineering safety based on the monitoring and measurement data to determine whether the environment and safety meet the requirements. If not, adjust the parameters and change the design. The specific contents of the environment and engineering safety evaluation are as follows:

[0082] Step H1, geological structure safety, evaluates the stability of the geological structure where the tunnel is located, including the lithology, fault zones and rock mass strength of the geological structure, to determine the geological safety risk of the tunnel;

[0083] Step H2, groundwater safety, evaluates the impact of groundwater during tunnel construction and operation, including the impact of groundwater inrush pressure and water level changes on tunnel structure, to ensure groundwater safety in the tunnel;

[0084] Step H3, structural stability, evaluates the stability of the tunnel structure, including the design and construction quality of the tunnel's support structure and lining structure, as well as the safety of the tunnel structure under different load conditions;

[0085] Step H4, ventilation safety, evaluates the ventilation system during the tunnel construction phase, including ventilation volume, wind speed, and oxygen content, to ensure that the air quality in the tunnel meets safety standards and the health and safety of construction workers;

[0086] Step H5, environmental safety, evaluates the impact of the tunnel project on the surrounding environment, including the risk of soil and groundwater pollution, and the impact of noise and vibration on nearby residents;

[0087] Step H6, construction safety, evaluates the safety risks during tunnel construction, including the safety of construction processes and site safety management.

[0088] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

[0089] It should be understood that the specific order or hierarchy of steps in the disclosed process is an example of an exemplary method. Based on design preferences, it should be understood that the specific order or hierarchy of steps in the process can be rearranged without departing from the scope of protection of the present disclosure. The attached method claims present the elements of the various steps in an exemplary order and are not intended to be limited to the specific order or hierarchy described.

[0090] In the above detailed description, various features are grouped together in a single embodiment to simplify the disclosure. This method of disclosure should not be interpreted as reflecting an intention that the embodiments of the claimed subject matter require more features than are clearly stated in each claim. On the contrary, as reflected in the appended claims, the invention is in a state of having less than all the features of the disclosed individual embodiments. Therefore, the appended claims are hereby expressly incorporated into the detailed description, with each claim standing on its own as a separate preferred embodiment of the invention.

Claims

1. A method for tunneling a highway tunnel in a dangerous rock mass area, characterized in that: The following steps are involved: S1, excavate the edge line at the back slope of the tunnel, set up a C20 concrete intercepting drainage ditch 5m away, set a settlement joint every 10m to 15m in the intercepting ditch, the width of the joint is 2cm, and the joints are filled with high-density polyethylene foam boards; S2, after entering the main tunnel through the auxiliary traffic tunnel, excavate towards the tunnel entrance where the dangerous rock mass is located. When approaching the tunnel entrance, take advanced large pipe shed support measures in the tunnel; S3, the tunnel face is constructed by circular excavation and reserved core soil method. When the construction reaches 16m away from the tunnel entrance, a small-section pilot pit is used to exit the tunnel. Then the up and down step method is used for excavation. Temporary I-beam supports are installed in the pilot pit, and the steel frame spacing is 60cm; S4, after the side wall pilot pit exits the cave, expand the other side and simultaneously remove the temporary support of the pilot pit until the cave exits. The monitoring and measurement should be strengthened near the exit surface; S5, protection and treatment of dangerous rock masses in the tunnel, including removal of dangerous rock masses, mesh protection, shotcrete reinforcement and process monitoring.

2. A method for tunneling a highway tunnel in a dangerous rock mass area according to claim 1, characterized in that: The advance large pipe shed support in step S2 is specifically as follows: the pipe shed size is φ108×6mm, the pipe shed length is 16m, the pipe shed work in the tunnel is located 10m away from the main tunnel, the section arch is expanded by 80cm, the guide wall adopts I-beam and C25 shotcrete structure, the drilling adopts crawler pipe shed drilling rig, cement and water glass double slurry is injected, and an advance small guide tube is constructed at a section 6m away from the tunnel entrance. The advance small guide tube is drilled by an air-leg rock drill, and the grouting slurry is cement slurry.

3. A method for tunneling a highway tunnel in a dangerous rock mass area according to claim 2, characterized in that: The construction method of the circular excavation and reserved core soil method in step S3 is specifically as follows: Carry out circular excavation of the upper section, apply initial support to the upper section, excavate the core soil of the upper section, excavate the lower section by jumping trenches, apply initial support to the lower section, excavate the lower section by jumping trenches, apply initial support to the lower section, construct the invert, backfill the invert, and finally build the secondary lining as a whole.

4. A method for tunneling a highway tunnel in a dangerous rock mass area according to claim 3, characterized in that: The method of guiding the small-section pit out of the hole in step S3 is specifically as follows: When the excavation of the exit section is to 16m away from the tunnel entrance, the upper left pilot pit is constructed first to exit the tunnel. The upper and lower steps of the pilot pit are 5m long. The excavation progress of the upper step is not more than 1 steel frame spacing, and the excavation progress of the lower step is not more than 2 steel frame spacing. After the upper left pilot pit exits the tunnel, the other side is excavated. The size of the pilot pit is 7.1m×5m. The excavation progress of the upper step is not more than 1 steel frame spacing, and the excavation progress of the lower step is not more than 2 steel frame spacing.

5. A method for tunneling a highway tunnel in a dangerous rock mass area according to claim 4, characterized in that: The monitoring and measurement in step S3 are specifically as follows: Step A: Conduct detailed surface survey before excavation, and carry out advanced geological forecast and monitoring and measurement of the surface and excavation section during construction; Step B: geological sketching and digital imaging should be carried out promptly after tunnel excavation; Step C: After the initial support is completed, observe and record the cracks on the sprayed layer surface and their development, water seepage, and deformation; Step D, measuring the internal displacement of the surrounding rock, the axial force of the anchor, the initial support internal force and the anchor pull-out test; Step E, measuring the water volume and pore water pressure of groundwater development, fault fracture zone and geological structure zone; Step F, when there are structures near the tunnel that are affected by tunnel construction blasting, blasting vibration monitoring and measurement is performed; Step G: Horizontal and vertical displacement monitoring points should be buried for each dangerous rock mass, and manual measurement should be performed using a high-precision total station; Step H: Evaluate the environment and engineering safety based on the monitoring and measurement data to determine whether the environment and safety meet the requirements. If not, adjust the parameters and change the design.

6. A method for excavating a highway tunnel portal in a dangerous rock mass area according to claim 5, characterized in that: The specific contents of the environmental and engineering safety assessment in step H are as follows: Step H1, geological structure safety, evaluates the stability of the geological structure where the tunnel is located, including the lithology, fault zones and rock mass strength of the geological structure; Step H2, groundwater safety, evaluates the impact of groundwater during tunnel construction and operation, including the impact of groundwater inrush pressure and water level changes on tunnel structure; Step H3, structural stability, evaluates the stability of the tunnel structure, including the design and construction quality of the tunnel's support structure and lining structure, as well as the safety of the tunnel structure under different load conditions; Step H4, ventilation safety, evaluates the ventilation system during the tunnel construction phase; Step H5, environmental safety, assessing the impact of the tunnel project on the surrounding environment; Step H6, construction safety, evaluates the safety risks during tunnel construction.

7. A method for tunneling a highway tunnel in a dangerous rock mass area according to claim 6, characterized in that: The details of the protection and treatment of dangerous rock masses in step S5 are as follows: Step S51, the dangerous rock mass is cleared by using static expansion agent to crack the rock and manual pneumatic pick to crush the rock; Step S52, laying a net for protection, laying an active protection net on the surface of the dangerous rock mass for protection; Step S53, spraying concrete reinforcement in the rock body, using 5 cm thick C25 sprayed concrete reinforcement; Step S54, process monitoring, adopts observation and monitoring measures, in addition to daily inspections of the condition of the dangerous rock mass, monitoring points are buried on the top of the dangerous rock mass to regularly measure the displacement of the rock mass.

Citation Information

Cited By

  • Tunnel entering construction method for steep rock-soil body tunnel in complex terrain

    CN119981955A