Drilling and blasting method tunnel cast-in-place porous concrete anti-dislocation buffer layer structure and construction method

By setting up a porous concrete buffer layer in the plastic pipe in the tunnel, the problem of insufficient durability of the existing tunnel buffer layer material is solved, the improvement of the anti-fault function and the reduction of construction costs is achieved, and the structure of the tunnel under the active fault is ensured. Security.

CN118933843AActive Publication Date: 2024-11-12CHINA RAILWAY SIYUAN SURVEY & DESIGN GRP CO LTD

Patent Information

Application Number
CN202411088535.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-09
Publication Date
2024-11-12
Estimated Expiration
2044-08-09

AI Technical Summary

Technical Problem

The existing tunnel buffer layer materials are insufficient in durability when facing active faults, and the construction cost of traditional molded concrete structures is high and the safety is poor, especially in corrosive groundwater environments.

Method used

The drilling and explosion method uses the cast-in-place porous concrete in the tunnel to resist the fault breakage buffer layer structure. By setting up plastic pipes between the initial support and the secondary lining, the pipe is filled with porous concrete and fixed by steel clamps, combined with the isolation plate and waterproof layer design , realize the anti-fault function of the buffer layer.

Benefits of technology

It reduces the shearing effect of tunnel lining, avoids secondary lining damage, significantly saves construction costs, improves the durability and safety of the structure, and flexibly adjusts the buffer void ratio to optimize the design.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933843A_ABST
    Figure CN118933843A_ABST
Patent Text Reader

Abstract

The invention provides a drilling and blasting method tunnel cast-in-place porous concrete anti-dislocation buffer layer structure which comprises a buffer layer arranged between a primary support and a secondary lining, the buffer layer comprises a plurality of plastic pipes, the plastic pipes are sequentially distributed in the tunneling direction of a tunnel, the plastic pipes are fixed to the primary support, and the secondary lining is arranged between the primary support and the secondary lining. And porous concrete is filled in at least part of the plastic pipes. The invention further provides a construction method of the drilling and blasting method tunnel cast-in-place porous concrete anti-dislocation buffer layer structure. Construction can be fast and convenient, the cost and the construction period are not remarkably increased due to construction of the buffer layer, the porosity of the buffer layer can be adjusted through changes of the pipe diameter and arrangement according to needs, and therefore the effective dislocation-resistant buffer performance is achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of tunnels and underground engineering, and in particular to a drill-and-blast tunnel cast-in-place porous concrete anti-dislocation buffer layer structure and a construction method. Background Art

[0002] As the number of tunnels built increases, more and more tunnels cross active faults. How to deal with the damage to the tunnel structure caused by the displacement of active faults is an engineering problem that tunnel construction needs to face. Due to the huge shear effect of the strata, the use of lining reinforcement often brings more serious damage. More and more scholars and engineering researchers have begun to consider increasing the flexibility of the tunnel to reduce the direct shear effect of active faults on the tunnel lining. A common method is to add a buffer layer between the initial support and the secondary lining, and absorb the displacement of the active fault through the compression deformation of the buffer layer to reduce the pressure of the active fault on the lining.

[0003] The materials used for the buffer layer usually include organic materials such as rubber and polyurethane, and cement-based inorganic materials such as foam concrete and polystyrene foam concrete (EPS). Chemical products such as rubber and polyethylene do not need to be prepared on site, but the durability of the materials is difficult to meet the requirements of long-life tunnel structures; when foam concrete and EPS concrete are used for tunnel buffer layers, if the traditional cast concrete structure is used, it is necessary to erect the mold at the location of the second lining thickness outside the original second lining trolley, or to make an additional template trolley, which is expensive. In addition, due to the low density of foam concrete, the durability of the buffer structure in corrosive groundwater environments such as sulfates is difficult to meet the requirements. Some projects make the foam concrete buffer structure into prefabricated components encapsulated in plastic pipes and assemble them on site, but they need to be assembled on a stand, which has the disadvantages of difficult on-site assembly and poor safety.

[0004] Therefore, it is necessary to design a cast-in-place porous concrete anti-fault buffer layer structure and construction method for a drill and blast tunnel to overcome the above problems. Summary of the invention

[0005] The purpose of the present invention is to overcome the defects of the prior art and provide a cast-in-place porous concrete anti-fault buffer layer structure and construction method for a tunnel using the drill and blast method. The present invention at least solves some of the problems in the prior art.

[0006] The present invention is achieved in that:

[0007] The present invention provides a cast-in-place porous concrete anti-fault buffer layer structure for a drill and blast tunnel, comprising a buffer layer arranged between an initial support and a secondary lining, wherein the buffer layer comprises a plurality of plastic pipes, each of which is distributed in sequence along the tunnel excavation direction, the plastic pipes are fixed on the initial support, and at least part of the plastic pipes are filled with porous concrete.

[0008] Furthermore, the plastic pipe includes a first sleeve arranged along the inverted arch and a second sleeve arranged along the arch wall. The first sleeve and the second sleeve are enclosed together to form a ring. The first sleeve and the second sleeve are butt-jointed and connected.

[0009] Furthermore, both the first sleeve and the second sleeve are provided with openings for pumping porous concrete into the sleeves, and the top of the second sleeve is provided with air holes.

[0010] Furthermore, the plastic pipe is fixed to the initial support through a steel bar clamp.

[0011] Furthermore, an isolation plate with a leveling function is provided between the plastic pipe and the secondary lining, and a waterproof layer is laid between the isolation plate and the secondary lining.

[0012] Furthermore, the isolation plate is arranged between two adjacent plastic tubes, and an arc-surface supporting portion which fits with the outer surface of the plastic tube is provided on the isolation plate.

[0013] The present invention also provides a construction method of a cast-in-place porous concrete anti-fault buffer layer structure for a tunnel using a drill and blast method, comprising the following steps:

[0014] S1. Determine the diameter of the plastic pipe: The diameter D of the circular plastic pipe is determined according to the thickness h0 of the buffer layer required for the engineering fracture resistance, where the diameter D = the thickness h0 of the buffer layer. The thickness h0 of the buffer layer is determined by the allowable compression deformation △h of the buffer layer structure and the compression height ratio α of the buffer layer structure, where h0 = △h / (1-α);

[0015] S2. Determine the arrangement spacing S of the plastic pipes along the longitudinal direction of the tunnel: The arrangement spacing S of the plastic pipes along the longitudinal direction of the tunnel is related to the diameter D of the plastic pipes, the volume change coefficient n of the concrete after destruction, and the compression height ratio α of the buffer layer structure. According to the principle that the volume of the remaining space after the buffer layer is compressed to allowable deformation △h is equal to the volume of the porous concrete after destruction, the arrangement spacing S of the plastic pipes along the longitudinal direction of the tunnel can be calculated to be S=nπD / 4α;

[0016] S3. Determine the material and model of the plastic pipe, and the pipe pressure level shall not be less than 0.6MPa;

[0017] S4. Determine the reasonable compressive strength of the buffer layer;

[0018] S5. Determine the method for preparing porous concrete;

[0019] S6. According to the lining profile and anti-fault buffer layer thickness determined by the design, tunnel excavation and initial support are carried out to ensure the stability of the surrounding rock;

[0020] S7. According to the cross-sectional shape of the tunnel and the designed diameter of the plastic pipe, the plastic pipe is processed or prefabricated in sections;

[0021] S8. According to the reasonable compressive strength of the buffer layer, test-mix the porous concrete and determine the mix ratio;

[0022] S9, laying the first sleeve at the inverted arch position, pumping porous concrete into the first sleeve from the opening until the slurry comes out from the end, and sealing the opening after the porous concrete is finally set;

[0023] S10, installing a second sleeve at the arch wall, the second sleeve is fixed on the initial support, and the porous concrete material is pumped through the openings on the second sleeve until the slurry flows out of the high-position pores. After the concrete is finally set, the openings and pores are sealed;

[0024] S11. Lay an isolation board with leveling function on the surface of the plastic pipe, lay a waterproof layer on the isolation board, and then apply secondary lining.

[0025] Further, in step S2, when S>2D, an empty plastic pipe with the same diameter is arranged between the two plastic pipes filled with porous concrete.

[0026] Furthermore, in step S4, the maximum allowable compressive strength of the buffer layer is related to multiple factors such as the size of the tunnel section, the shape of the section, the direction of the fault offset, the thickness, strength and reinforcement of the secondary lining concrete, etc. The minimum strength must meet the bearing requirements of the structure during normal use. The compressive strength of the buffer layer is generally 1 / 10 to 1 / 30 of the compressive strength of the secondary lining concrete.

[0027] Furthermore, in step S10, the second sleeve is fixed to the initial support by a steel bar clamp.

[0028] The buffer layer structure of cast-in-place porous concrete in plastic tube proposed by the present invention ensures that the secondary lining of the tunnel lining structure crossing the active fault will not be damaged under the action of large displacement active fault dislocation, thereby ensuring the structural safety of the tunnel crossing the active fault. Compared with the existing tunnel buffer layer structure, it has the following advantages:

[0029] (1) The plastic pipe is a component of the buffer structure and also serves as a casting mold for porous concrete. Compared with the traditional formwork cast-in-place method, it does not require a formwork trolley, which greatly saves construction costs. Compared with the prefabricated buffer structure, only plastic pipes need to be erected on site, and the pipe mass is small, which is simpler and safer than installing a prefabricated buffer structure.

[0030] (2) The porosity of the buffer layer structure can be adjusted by flexibly adjusting the pipe diameter and the arrangement spacing, thereby achieving an optimized design of the anti-fault buffer layer structure.

[0031] (3) The porous concrete is enclosed in a plastic pipe and does not come into contact with groundwater, which can prevent groundwater from corroding the porous concrete and improve the durability of the structure. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0033] Figure 1 A schematic cross-sectional view of a cast-in-place porous concrete anti-fault buffer layer structure for a drill-and-blast tunnel provided by an embodiment of the present invention;

[0034] Figure 2 A schematic longitudinal section diagram of a cast-in-place porous concrete anti-dislocation buffer layer structure for a drill-and-blast tunnel provided in an embodiment of the present invention (S<2D);

[0035] Figure 3 A schematic longitudinal section diagram of a cast-in-place porous concrete anti-dislocation buffer layer structure for a drill-and-blast tunnel provided in an embodiment of the present invention (S>2D);

[0036] Figure 4 A schematic diagram of installing a first sleeve of a plastic pipe provided in an embodiment of the present invention;

[0037] Figure 5 A schematic diagram of installing the second sleeve of the plastic pipe provided in an embodiment of the present invention;

[0038] Figure 6 A schematic diagram of fixing a U-shaped steel bar clamp provided in an embodiment of the present invention;

[0039] Figure 7 A schematic cross-sectional view of an isolation plate provided in an embodiment of the present invention;

[0040] Figure 8 This is a diagram of the installation position of the isolation plate provided in an embodiment of the present invention.

[0041] In the figure: initial support 1, buffer layer 2, secondary lining 3, tunnel excavation direction 4, plastic pipe 5, porous concrete 6, first sleeve 7, sleeve joint 8, opening 9, second sleeve 10, air hole 11, steel bar clamp 12, expansion bolt 13, isolation plate 14, waterproof layer 15 (geotextile, waterproof board), arc support part 16. DETAILED DESCRIPTION

[0042] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0043] In the description of the present invention, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship are based on the orientation or position relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0044] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features; in the description of the present invention, unless otherwise specified, "several" means two or more.

[0045] like Figure 1-Figure 8 , Embodiment 1 of the present invention provides a cast-in-place porous concrete anti-dislocation buffer layer structure for a drill-and-blast tunnel, comprising a buffer layer 2 arranged between an initial support 1 and a secondary lining 3, wherein the buffer layer 2 comprises a plurality of plastic pipes 5, each of which is sequentially distributed along the tunnel excavation direction, and the plastic pipes 5 are arranged around the secondary lining 3, and the plastic pipes 5 are fixed on the initial support 1, and at least part of the plastic pipes 5 are filled with porous concrete 6. The porous concrete 6 adopts a large-porosity low-strength concrete, and in this embodiment, a porous concrete (SAP porous concrete) with saturated water beads is adopted. The plastic pipe 5 adopts a polyethylene pipe (PE) with good flexibility. The present invention provides a fast and convenient structural design and construction method for a cast-in-place tunnel buffer layer, which can be constructed quickly and conveniently without significantly increasing the cost and construction period due to the construction of the buffer layer, and the porosity of the buffer layer can be adjusted according to needs by changing the pipe diameter and arrangement, thereby achieving effective anti-dislocation buffer performance.

[0046] like Figure 4-Figure 5The plastic pipe 5 includes a first sleeve 7 arranged along the inverted arch and a second sleeve 10 arranged along the arch wall. The first sleeve 7 and the second sleeve 10 are enclosed to form a ring, and the first sleeve 7 and the second sleeve 10 are butt-jointed and connected. The end of the first sleeve 7 is provided with a sleeve joint 8 butt-jointed with the second sleeve 10. The first sleeve 7 and the second sleeve 10 are both provided with openings 9 for pumping porous concrete into the sleeves, and the top of the second sleeve 10 is provided with air holes 11.

[0047] like Figure 6 The plastic pipe 5 is fixed to the initial support 1 through a steel bar clamp 12. The steel bar clamp 12 is fixedly connected to the initial support 1 through an expansion bolt 13.

[0048] like Figure 7-Figure 8 A separation plate with a leveling function is provided between the plastic pipe 5 and the secondary lining 3, and a waterproof layer 15 is laid between the separation plate and the secondary lining 3. In this embodiment, the waterproof layer 15 is made of geotextile, waterproof board, etc. In this embodiment, the separation plate 14 is made of plastic board. The separation plate is provided between two adjacent plastic pipes 5, and a curved support part 16 is provided on the separation plate to fit the outer surface of the plastic pipe 5.

[0049] In order to facilitate the safe and rapid construction of the anti-fault buffer layer, the present invention provides a buffer layer structure of cast-in-place concrete in a plastic pipe 5. The buffer layer structure is arranged between the initial support 1 and the secondary lining 3. The plastic pipe 5 is arranged circumferentially along the inner surface of the initial support 1, and porous, large-porosity, low-strength concrete (foam concrete or SAP porous concrete can be used) is poured on-site in the plastic pipe 5.

[0050] The plastic pipe 5 is the template for the porous concrete pouring and is also a component of the anti-fault buffer layer structure. It can enhance the ductility of the porous concrete at the failure stage and isolate the porous concrete from groundwater to prevent concrete corrosion and damage. The design steps of the anti-fault buffer layer are as follows:

[0051] The first step is to determine the diameter of the plastic tube 5. The cross section of the plastic tube 5 is circular (e.g. Figure 2 ), the pipe diameter D is determined according to the buffer layer thickness h0 required for engineering fracture resistance (pipe diameter D = buffer layer thickness h0), and the buffer layer thickness h0 is determined by the allowable compression deformation △h of the buffer layer structure and the compression height ratio α of the buffer layer structure, h0 = △h / (1-α).

[0052] The second step is to determine the arrangement spacing of the plastic pipes along the longitudinal direction of the tunnel (the longitudinal direction of the tunnel is the tunnel excavation direction). The arrangement spacing S of the plastic pipes along the longitudinal direction of the tunnel is related to the diameter D of the plastic pipe, the volume change coefficient n after the concrete is damaged, and the compression height ratio α of the buffer layer structure. According to the principle that the volume of the remaining space after the anti-fracture buffer layer is compressed to allowable deformation △h is equal to the volume of the concrete after damage, the pipe spacing S = nπD / 4α can be calculated. When S>2D, an empty pipe of the same diameter can be set between the two concrete pipes (such as Figure 3 shown).

[0053] The third step is to determine the material and model of the plastic pipe. Commonly used plastic pipes and corrugated pipes include polyvinyl chloride (PVC), polyethylene (PE), polypropylene (PP) and other materials. According to the characteristics of the tunnel's anti-break buffer structure, polyethylene pipes (PE) with good flexibility are selected. Considering the pressure on the pipe during concrete pouring and its own stability as a cast-in-place concrete formwork, the pipe pressure level should not be less than 0.6MPa, and products with general specifications and models on the market should be selected.

[0054] The fourth step is to determine the reasonable compressive strength of the anti-slip buffer layer structure. According to the working principle of the anti-slip buffer layer structure, under the action of the stratum deformation allowed by the design, the buffer layer structure will be deformed or damaged, but the secondary lining of the tunnel will not be damaged under the action of the stratum deformation. Therefore, the maximum compressive strength of the buffer layer cannot be too high, otherwise it will cause the secondary lining to be damaged. The maximum allowable compressive strength of the buffer layer is related to many factors such as the size of the tunnel section, the shape of the section, the direction of the fault, the thickness, strength and reinforcement of the secondary lining concrete. The minimum strength must meet the bearing requirements of the structure in the normal use stage, and the reasonable strength must be determined through calculation and analysis in combination with the specific project. According to previous studies, the reasonable compressive strength of the anti-slip buffer layer structure is generally 1 / 10 to 1 / 30 of the compressive strength of the secondary lining concrete.

[0055] The fifth step is to determine the preparation method of porous concrete. There are many preparation processes for porous concrete, such as foamed concrete, polystyrene particle foamed concrete (EPS), super absorbent resin bead porous concrete (SAP), etc. According to the characteristics of long concrete transportation time during tunnel construction, super absorbent resin bead porous concrete (SAP) is preferred because of its easy-to-control pore stability and simple process.

[0056] In order to facilitate the realization of the above buffer layer structure at the construction site, a corresponding construction method is invented:

[0057] Step 1: According to the lining profile and anti-fault buffer layer thickness determined by the design, tunnel excavation and initial support 1 are carried out to ensure the stability of the surrounding rock.

[0058] Step 2: Process or prefabricate polypropylene (PE) plastic pipes in sections according to the tunnel cross-sectional shape and designed pipe diameter.

[0059] Step 3: According to the reasonable compressive strength of the buffer layer, test-mix the porous concrete and determine the mix ratio.

[0060] Step 4: Lay the first sleeve 7 at the inverted arch, pump porous concrete material into the first sleeve 7 from the opening until the slurry comes out of the high pores, and after the concrete is finally set, use thermoplastic welding to seal the casting holes and pores.

[0061] Step 5: Install the second sleeve 10 at the arch wall in sections and fix the second sleeve 10 with a steel bar clamp (such as Figure 6 ). The porous concrete material is pumped through the holes on both sides of the side wall of the second sleeve 10 until the slurry comes out of the high pores. After the concrete is finally set, the casting holes and pores are closed by thermoplastic welding.

[0062] Step 6: Lay a leveling isolation board (such as Figure 7-Figure 8 ), lay geotextile, waterproof board, drainage board and other drainage structures on the isolation board, and construct the secondary lining of the tunnel according to the conventional method.

[0063] The buffer layer structure of cast-in-place porous concrete in plastic tube proposed by the present invention ensures that the secondary lining of the tunnel lining structure crossing the active fault will not be damaged under the action of large displacement active fault dislocation, thereby ensuring the structural safety of the tunnel crossing the active fault. Compared with the existing tunnel buffer layer structure, it has the following advantages:

[0064] (1) The plastic pipe is a component of the buffer structure and also serves as a casting mold for porous concrete. Compared with the traditional formwork cast-in-place method, it does not require a formwork trolley, which greatly saves construction costs. Compared with the prefabricated buffer structure, only plastic pipes need to be erected on site, and the pipe mass is small, which is simpler and safer than installing a prefabricated buffer structure.

[0065] (2) The porosity of the buffer layer structure can be adjusted by flexibly adjusting the pipe diameter and the arrangement spacing, thereby achieving an optimized design of the anti-fault buffer layer structure.

[0066] (3) The porous concrete is enclosed in a plastic pipe and does not come into contact with groundwater, which can prevent groundwater from corroding the porous concrete and improve the durability of the structure.

[0067] Combined with specific engineering examples, the design method is further explained:

[0068] (1) The maximum vertical displacement of a tunnel project crossing an active fault section is predicted to be 0.5 m, and the required compression △h of the buffer layer structure is 0.5 m; the secondary lining uses 60 cm thick C50 reinforced concrete.

[0069] (2) The loose volume coefficient of porous concrete after crushing is n = 1.1.

[0070] (3) Assuming that the thickness of the buffer layer is 0.8 m, that is, the pipe diameter D is 0.8 m, the compression height ratio α is calculated to be 0.375.

[0071] (4) Pipe spacing S = nπD / 4α = 1.84 m. The pipe spacing is greater than twice the pipe diameter D, so an empty pipe can be arranged in the middle.

[0072] (5) The plastic pipe is a PE pipe with a nominal diameter of 800 mm, a pressure of 0.6 MPa and a wall thickness of 30.6 mm, which is commonly used in the market.

[0073] (6) Based on the cross-sectional dimensions and shape of the tunnel structure, a model calculation is established. When the strength of the buffer layer structure is less than 4 MPa, the safety factor of the secondary lining structure can meet the requirements. The compressive strength of the porous concrete is 3 MPa, and SAP concrete is used.

[0074] The contents not described in detail in this specification belong to the prior art known to professional and technical personnel in this field.

[0075] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims

1. A cast-in-place porous concrete anti-fault buffer layer structure for a drill-and-blast tunnel, characterized in that: It comprises a buffer layer arranged between the initial support and the secondary lining, wherein the buffer layer comprises a plurality of plastic pipes, each of which is distributed in sequence along the tunnel excavation direction, the plastic pipes are fixed on the initial support, and at least part of the plastic pipes are filled with porous concrete.

2. The cast-in-place porous concrete anti-fault buffer layer structure of the drill and blast tunnel as claimed in claim 1, characterized in that: The plastic pipe comprises a first sleeve arranged along the inverted arch and a second sleeve arranged along the arch wall. The first sleeve and the second sleeve are combined to form a ring. The first sleeve and the second sleeve are butt-jointed and connected.

3. The cast-in-place porous concrete anti-fault buffer layer structure of the drill and blast tunnel as claimed in claim 2, characterized in that: The first sleeve and the second sleeve are both provided with openings for pumping porous concrete into the sleeves, and the top of the second sleeve is provided with air holes.

4. The cast-in-place porous concrete anti-fault buffer layer structure of the drill and blast tunnel according to claim 1, characterized in that: The plastic pipe is fixed to the initial support through a steel bar clamp.

5. The cast-in-situ porous concrete anti-fault buffer layer structure of the drill and blast tunnel according to claim 1, characterized in that: An isolation plate with a leveling function is arranged between the plastic pipe and the secondary lining, and a waterproof layer is laid between the isolation plate and the secondary lining.

6. The cast-in-situ porous concrete anti-fault buffer layer structure of the drill and blast tunnel as claimed in claim 5, characterized in that: The isolation plate is arranged between two adjacent plastic tubes, and an arc surface supporting portion which is in contact with the outer surface of the plastic tube is arranged on the isolation plate.

7. A construction method for a cast-in-place porous concrete anti-fault buffer layer structure in a tunnel using a drill and blast method, characterized in that: The steps include: S1. Determine the diameter of the plastic pipe: The diameter D of the plastic pipe is determined according to the thickness h0 of the buffer layer required for the engineering fracture resistance. The diameter D = the thickness h0 of the buffer layer. The thickness h0 of the buffer layer is determined by the allowable compression deformation △h of the buffer layer structure and the compression height ratio α of the buffer layer structure. h0 = △h / (1-α); S2. Determine the arrangement spacing S of the plastic pipes along the longitudinal direction of the tunnel: The arrangement spacing S of the plastic pipes along the longitudinal direction of the tunnel is related to the diameter D of the plastic pipes, the volume change coefficient n of the concrete after destruction, and the compression height ratio α of the buffer layer structure. According to the principle that the volume of the remaining space after the buffer layer is compressed to allowable deformation △h is equal to the volume of the porous concrete after destruction, the arrangement spacing S of the plastic pipes along the longitudinal direction of the tunnel can be calculated to be S=nπD / 4α; S3. Determine the material and model of the plastic pipe, and the pipe pressure level shall not be less than 0.6MPa; S4. Determine the reasonable compressive strength of the buffer layer; S5. Determine the method for preparing porous concrete; S6. According to the lining profile and anti-fault buffer layer thickness determined by the design, tunnel excavation and initial support are carried out to ensure the stability of the surrounding rock; S7. According to the cross-sectional shape of the tunnel and the designed diameter of the plastic pipe, the plastic pipe is processed or prefabricated in sections; S8. According to the reasonable compressive strength of the buffer layer, test-mix the porous concrete and determine the mix ratio; S9, laying the first sleeve at the inverted arch position, pumping porous concrete into the first sleeve from the opening until the slurry comes out from the end, and sealing the opening after the porous concrete is finally set; S10, installing a second sleeve at the arch wall, the second sleeve is fixed on the initial support, and the porous concrete material is pumped through the openings on the second sleeve until the slurry flows out of the high-position pores. After the concrete is finally set, the openings and pores are sealed; S11. Lay an isolation board with leveling function on the surface of the plastic pipe, lay a waterproof layer on the isolation board, and then apply secondary lining.

8. The construction method of the cast-in-situ porous concrete anti-fault buffer layer structure of the tunnel by the drill and blast method as claimed in claim 7, characterized in that: In step S2, when S>2D, an empty plastic pipe of the same diameter is arranged between the two plastic pipes filled with porous concrete.

9. The construction method of the cast-in-situ porous concrete anti-fault buffer layer structure of the tunnel by the drill and blast method as claimed in claim 7, characterized in that: In step S4, the compressive strength of the buffer layer is 1 / 10 to 1 / 30 of the compressive strength of the secondary lining concrete.

10. The construction method of the cast-in-situ porous concrete anti-fault buffer layer structure of the tunnel by the drill and blast method as claimed in claim 7, characterized in that: In step S10, the second sleeve is fixed to the initial support by a steel bar clamp.

Citation Information

Patent Citations

  • Secondary lining deformation control method and structure for soft rock tunnels with extremely high ground stress

    CN108518230A

  • Fault fracture zone crossing tunnel anti-dislocation connecting device and construction method thereof

    CN112727502A

  • Soft rock tunnel inverted arch anti-floating and anti-cracking buffer supporting structure, construction method and tunnel

    CN118423091A

  • Grout material for adhesion of waterproof sheet, and construction method

    JP2009249818A

  • Method for constructing extra-large variable cross section tunnel

    WO2016095630A1

Cited By

  • Mounting structure and filling method of assembly type foam concrete pipe

    CN119686772A