Construction structure and construction method of tunnel inverted arch penetrating karst stratum

Through the steel bar positioning tool and steel wire, the spacing and height of the steel bars on the back arch are controlled, and the drainage blind pipes and fixed water stops are installed accurately, which solves the uneven spacing of steel bars, uneven concrete, drainage deviation and poor waterproofness in the karst geological tunnel back arch construction. The problem has improved the stability and construction quality of the tunnel structure.

CN118933913APending Publication Date: 2024-11-12CHINA CONSTR EIGHT ENG DIV CORP LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411129612.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-16
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

During the construction of karst geological tunnels, there are problems such as uneven spacing of steel bars, uneven concrete filling, biased installation of drainage blind pipes and poor waterproofing of water stops, which affects the stability and safety of the tunnel structure.

Method used

The steel bar positioning tool is used to accurately control the spacing of the rectangular steel bars, and the steel wire is used to control the consistency of the steel bar height. The circular drainage blind pipe marking is delineated and the longitudinal drainage blind pipe is installed using the positioning steel bar rod. Several types of steel bar positioning cards are used to fix the buried water stop. and a control wire mesh is installed on the top surface of the backfill layer concrete to ensure that the top surface is flat.

Benefits of technology

The uniform spacing of the arch steel bars, flat concrete filling, precise installation of drainage blind pipes, improved the waterproofness of the water stop, and improved the construction quality and overall stability of the tunnel structure.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118933913A_ABST
    Figure CN118933913A_ABST
Patent Text Reader

Abstract

According to the inverted arch construction structure of the tunnel penetrating through the karst stratum and the construction method of the inverted arch construction structure, upper and lower reinforcing steel bars of an inverted arch are bent at a side wall and accurately positioned through a reinforcing steel bar positioning clamp, and a control steel wire is arranged on the side wall in a pulling mode to ensure that the bending and stretching lengths are consistent. Marked lines are marked on the side wall and the inverted arch primary support sprayed concrete to control the position of a drainage blind pipe, a steel wire mesh is arranged on the side wall in a pulling mode to control the height and flatness of the top face of an inverted arch backfill layer, and a novel n-shaped steel bar positioning clamp is used for fixing a middle-buried water stop belt. The main construction steps are as follows: spraying concrete to an inverted arch primary support; marking a side wall and nailing steel nails; mounting and positioning reinforcing steel bars; mounting a steel bar positioning fixture; inverted arch steel bars are installed; installing a drainage blind pipe; a middle-buried water stop belt is installed; inverted arch concrete is poured; pulling a steel wire mesh; constructing an inverted arch backfilling layer; and circularly constructing. Quality is guaranteed, waterproofness is improved, and technical and economic benefits are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction engineering, in particular to an invert construction structure of a tunnel passing through a karst stratum and a construction method thereof, and is mainly applicable to the invert construction of a tunnel, in particular to the invert construction of a karst geological tunnel. Background Art

[0002] The invert is one of the main components of the tunnel structure and is the foundation of the tunnel structure. The invert is set during tunnel construction to form a closed structural system for the support structure, improve the overall force performance, and control the tunnel convergence displacement and the plastic deformation development of the surrounding rock mass. During the use of the tunnel, the invert can effectively transfer the upper stratum pressure of the tunnel to the underground through the tunnel side wall structure or the road surface load, and can also effectively resist the reaction force from the lower stratum of the tunnel.

[0003] In the current industry, insufficient attention is paid to the invert, especially in karst geological tunnels. The following problems often exist in the invert construction process:

[0004] (1) The inverted arch steel bars are of different lengths, the lengths of the inverted arch steel bars at the tunnel side walls are different, and the spacing between the inverted arch steel bars is uneven;

[0005] (2) The inverted arch filling concrete has large fluctuations, the top surface elevation is inconsistent, and it is uneven, making it difficult to achieve a uniform level line.

[0006] (3) The installation position of the annular drainage blind pipe and the longitudinal drainage blind pipe is seriously offset, which affects the connection between the drainage blind pipes.

[0007] (4) The waterproof performance of the waterstop structure at the end formwork of the inverted arch is poor. When removing the formwork, the fixed structure installed with the waterstop needs to be removed, resulting in poor waterproof performance of the subsequent structure.

[0008] Under the long-term erosion of karst water in the later stage, the above problems will cause the tunnel invert to sink, the invert to become disconnected from the secondary lining, and water seepage will be serious, affecting the stability and safety of the overall tunnel structure.

[0009] The purpose of the present invention is to ensure that the spacing of the tunnel invert reinforcement is uniform, the height of the invert reinforcement at the tunnel side wall is kept flush, the flatness of the invert filling concrete and the installation accuracy of the drainage blind pipe are improved, the installation and removal of the water stop are convenient, and the waterproofness of the invert structure is improved. It is urgent to invent a simple and effective tunnel invert crossing a karst stratum and a construction method. Summary of the invention

[0010] In order to achieve the above technical objectives, the present invention adopts the following technical solutions:

[0011] The invention relates to an invert construction structure for a tunnel passing through a karst stratum, comprising a tunnel side wall, a highest steel bar control wire, a lowest steel bar control wire, a circumferential drainage blind pipe marking line, a highest steel bar, a lowest steel bar, a longitudinal drainage blind pipe, a positioning steel bar rod, a horizontal steel bar, a steel bar positioning fixture, and an invert initial support spraying concrete;

[0012] The inverted arch reinforcement is laid on the initial support shotcrete according to the designed spacing. The inverted arch reinforcement includes the upper layer reinforcement and the lower layer reinforcement. The inverted arch reinforcement is bent upward at the tunnel side wall. The upper layer reinforcement is the lowest reinforcement, and the lower layer reinforcement is the highest reinforcement. The inverted arch reinforcement is accurately positioned by the reinforcement positioning fixture, and the upper layer reinforcement and the lower layer reinforcement are respectively embedded in the reinforcement positioning groove;

[0013] The tunnel side wall is provided with a maximum reinforcement control wire and a minimum reinforcement control wire according to the designed height. The maximum reinforcement control wire is used to control the top surface height of the maximum reinforcement, and the minimum reinforcement control wire is used to control the top surface height of the minimum reinforcement.

[0014] Positioning steel bars are also driven into the initial support of the inverted arch, and horizontal steel bars are also implanted in the tunnel side walls. The horizontal steel bars are welded and fixed to the positioning steel bars; steel bar positioning fixtures are welded to the horizontal steel bars, and the highest and lowest steel bars are embedded in the multiple steel bar positioning slots on the steel bar positioning fixtures. The spacing between the highest and lowest steel bars is accurately positioned by the steel bar positioning fixtures;

[0015] Circumferential drainage blind pipe markings are drawn on the tunnel side walls and the initial support shotcrete of the invert according to the designed positions, and longitudinal drainage blind pipes are installed between the positioning steel bars and the lowest steel bars.

[0016] Furthermore, it also includes a steel wire mesh for controlling the top surface of the backfill layer concrete, an inverted arch, an inverted arch backfill layer, a central ditch of the inverted arch, a left belt, a right belt, a central dividing rib, a narrow and long clip, a wide and short clip, a fixing plate, a screw hole, an equilateral angle steel, a screw, a lower inverted arch end mold, an upper inverted arch end mold, a middle buried water stop, and several types of steel bar positioning cards;

[0017] When pouring the concrete of the inverted arch, a combined structure of the lower inverted arch end formwork and the upper inverted arch end formwork is used;

[0018] The embedded waterstop is fixed by several types of steel bar positioning clips, and the left belt of the embedded waterstop is embedded in the narrow and long clip;

[0019] The central dividing rib is embedded in the wide and short clips, the fixing plate is connected to the equilateral angle steel by screws, the equilateral angle steel is located between the lower inverted arch end mold and the upper inverted arch end mold, and the right belt of the embedded water stop belt is embedded in the gap between the lower inverted arch end mold and the upper inverted arch end mold;

[0020] A steel wire mesh for controlling the top surface of the backfill layer concrete is installed on the side wall of the tunnel to control the top surface height and flatness of the invert backfill layer.

[0021] Furthermore, a plurality of steel bar positioning slots are evenly arranged on the steel bar positioning fixture, three steel bar positioning fixtures are longitudinally arranged on the initial support sprayed concrete of the inverted arch, and a steel bar positioning fixture is arranged on each of the two side tunnel walls. The upper steel bar positioning slot of the steel bar positioning fixture on the initial support sprayed concrete of the inverted arch penetrates into the upper layer of the inverted arch steel bar, and the lower steel bar positioning slot penetrates into the lower layer of the inverted arch steel bar. The highest steel bar is penetrated into the outer steel bar positioning slot of the steel bar positioning fixture at the side wall of the tunnel, and the lowest steel bar is penetrated into the inner steel bar positioning slot.

[0022] Furthermore, the highest reinforcement control wire and the lowest reinforcement control wire are nailed to the tunnel side wall by steel nails.

[0023] Furthermore, the embedded waterstop is composed of three parts: a left belt, a right belt, and a central dividing rib, and several types of steel bar positioning cards are composed of a narrow and long clip, a wide and short clip, a fixing plate, and a screw hole.

[0024] Furthermore, screw holes are drilled on the equilateral angle steel, one screw hole is respectively arranged on the upper and lower sides of the equilateral angle steel, and the screw holes are firmly embedded with the lower inverted arch end mold and the upper inverted arch end mold.

[0025] Furthermore, a plurality of several types of steel bar positioning cards are evenly spaced along the length direction of the equilateral angle steel, and the left belt of the embedded waterstop is fixed by the plurality of several types of steel bar positioning cards, and the left belt is buried by pouring inverted arch concrete on the side of the left belt.

[0026] Furthermore, the steel wire mesh for controlling the top surface of the backfill layer concrete is also fixed with steel nails. One steel wire is arranged along the longitudinal direction of the tunnel side wall and multiple steel wires are arranged along the transverse direction. The flatness of the backfill layer of the arch is controlled by the steel wires.

[0027] The construction method of the invert construction structure of a tunnel passing through a karst stratum comprises the following steps:

[0028] S00, tunnel invert initial support shotcrete

[0029] Excavate the tunnel invert base surface, remove the debris, mud and water at the tunnel bottom, and spray concrete at the tunnel bottom to form the initial support of the invert according to the design requirements;

[0030] Set up a steel arch frame on the initial support sprayed concrete of the inverted arch, align and connect the steel arch frame of the inverted arch with the steel arch frame inside the side wall, and use a connecting plate to connect the two to form a closed loop;

[0031] S10, side wall marking nails

[0032] Measure and lay out according to the designed spacing and position, drive steel nails at the measurement and layout points, pull the highest steel bar control wire and the lowest steel bar control wire through the steel nails, and draw the circumferential drainage blind pipe marking line on the tunnel side wall and the initial support shotcrete of the invert according to the layout points;

[0033] S20, install the positioning steel bar

[0034] Install positioning steel bars on the initial support shotcrete of the invert according to the measured points, and implant horizontal steel bars on the side walls of the tunnel. The horizontal steel bars are welded to the positioning steel bars.

[0035] S30, install the steel bar positioning fixture

[0036] Install and fix three steel bar positioning fixtures on the initial support shotcrete of the invert according to the measured and laid-out positions, and weld a steel bar positioning fixture on the horizontal steel bars on the tunnel side walls on both sides;

[0037] S40, install the invert reinforcement

[0038] After the upper layer of the inverted arch reinforcement passes through the upper end reinforcement positioning slots of the three reinforcement positioning fixtures on the initial support of the inverted arch, it is bent upward at the tunnel side wall to form the lowest reinforcement. After the lowest reinforcement passes through the inner reinforcement positioning slot of a reinforcement positioning fixture on the horizontal reinforcement, it is kept flush with the lowest reinforcement control wire.

[0039] After the lower layer of the inverted arch reinforcement passes through the lower end reinforcement positioning slots of the three reinforcement positioning fixtures on the initial support of the inverted arch, it is bent upward at the tunnel side wall to form the highest reinforcement. After the highest reinforcement passes through the outer reinforcement positioning slot of a reinforcement positioning fixture on the horizontal reinforcement, it is kept flush with the highest reinforcement control wire;

[0040] S50, install drainage blind pipe

[0041] Install the annular drainage blind pipe according to the annular drainage blind pipe marking line drawn by the initial support of the tunnel side wall and the invert concrete, and install the longitudinal drainage blind pipe between the positioning steel bar and the lowest steel bar, and connect the longitudinal drainage blind pipe with the annular drainage blind pipe;

[0042] S60, installation of embedded water stop

[0043] Install the lower and upper inverted arch end forms on the initial support of the inverted arch sprayed concrete, embed the left belt of the embedded water stop into the narrow and long clamping piece of the several types of steel bar positioning card, embed the central dividing rib into the wide and short clamping piece, connect the fixing plate of the several types of steel bar positioning card with the equilateral angle steel by screws, and then extend the right belt of the embedded water stop into the gap between the lower and upper inverted arch end forms, and embed the equilateral angle steel into the gap between the lower and upper inverted arch end forms;

[0044] S70, pouring invert concrete

[0045] A new self-propelled inverted arch trestle is used to support the inverted arch arc formwork, and the concrete of the inverted arch is poured by pumping. The top surface of the concrete is leveled based on the elevation line of the top surface of the inverted arch concrete drawn on the side wall of the tunnel. The area near the buried water stop is vibrated and compacted, and the left belt and the central dividing rib are buried in the inverted arch concrete.

[0046] S80, pull and install the steel wire mesh on the top surface of the backfill layer concrete

[0047] According to the measured points, nail steel nails are nailed, and the steel wire mesh on the top surface of the backfill layer concrete is pulled through the steel nails. The steel wire mesh on the top surface of the backfill layer concrete is set with one steel wire along the longitudinal direction of the tunnel side wall and multiple steel wires are set in the transverse direction;

[0048] S90, construction of backfill layer of invert

[0049] After the concrete of the inverted arch is finally set, the top surface of the inverted arch is cleaned and moistened with water, and the bottom formwork and end formwork of the backfill layer of the inverted arch are supported. The formwork of the central ditch of the inverted arch is supported at the central position of the inverted arch;

[0050] The concrete pouring of the backfill layer of the inverted arch is carried out in layers, and the thickness of each layer does not exceed 50cm. The inserted tamping device is used for manual vibration, and the top surface height of the backfill layer is controlled by the steel wire mesh on the top surface of the backfill layer concrete and smoothed;

[0051] S100, Circular Construction

[0052] The tunnel invert construction is carried out cyclically according to the above process. The backfill layer of the invert lags behind the invert by one segment. The length of each segment is 30-50m. An embedded waterstop is set in the expansion joint at the junction of adjacent segments for waterproofing.

[0053] The present invention has the following characteristics and beneficial effects:

[0054] 1) The present invention adopts a steel bar positioning fixture to accurately control the spacing of the inverted arch steel bars, and adopts a steel wire pulled on the tunnel side wall to control the extension length of the inverted arch steel bars at the tunnel side wall, so as to keep the elevation consistent, thereby ensuring the installation quality of the inverted arch steel bars.

[0055] 2) The present invention marks the circumferential drainage blind pipe marking line on the tunnel side wall and the initial support shotcrete of the invert arch, and uses positioning steel bars to position the longitudinal drainage blind pipe, thereby ensuring that the installation positions of the circumferential drainage blind pipe and the longitudinal drainage blind pipe do not deviate, and realizing the precise installation and docking of the drainage blind pipe.

[0056] 3) The present invention adopts a novel type of steel bar positioning card to fix the buried water stop strip. After the upper and lower end forms and equilateral angle steels of the inverted arch are removed, the type of steel bar positioning card is directly left in the inverted arch without removal, thereby improving the waterproof performance.

[0057] 4) The present invention sets a steel wire mesh on the top surface of the backfill layer concrete on the tunnel side wall to control the top surface height of the invert backfill layer and smooth it, ensuring that the top surface of the invert backfill layer is flat and has no unevenness, thereby improving the construction quality of the invert. BRIEF DESCRIPTION OF THE DRAWINGS

[0058] Figure 1 This is the overall structural diagram of the tunnel invert reinforcement accurate installation, positioning and alignment of the present invention;

[0059] Figure 2 This is a structural diagram of the steel bar positioning fixture of the present invention;

[0060] Figure 3 The present invention is a structural diagram of the upper and lower layers of steel bars of the inverted arch, which are accurately fixed by the steel bar positioning fixture on the initial support concrete spraying of the inverted arch;

[0061] Figure 4 The invention is a structural diagram of the high and low steel bars that are extended out of the invert arch by the steel bar positioning fixture at the tunnel side wall;

[0062] Figure 5 It is a structural diagram of controlling the height of the top surface of the inverted arch backfill layer by controlling the steel wire mesh on the top surface of the concrete backfill layer of the inverted arch of the present invention;

[0063] Figure 6 It is a structural diagram of the buried water stop in the present invention;

[0064] Figure 7 This is a structural diagram of several types of steel bar positioning cards of the present invention;

[0065] Figure 8 It is a cross-sectional view of the embedded water stop fixed by several types of steel bar positioning clips of the present invention;

[0066] Fig. 9 It is a construction drawing of the segmental formwork casting of the inverted arch and the inverted arch backfill layer of the present invention;

[0067] Fig.10 It is a detailed structural drawing of the embedded waterstop fixed by several types of steel bar positioning clips of the present invention.

[0068] Among them: 1. Tunnel side wall; 2. Highest steel bar control wire; 3. Lowest steel bar control wire; 4. Circumferential drainage blind pipe marking line; 5. Highest steel bar; 6. Lowest steel bar; 7. Longitudinal drainage blind pipe; 8. Positioning steel bar rod; 9. Horizontal steel bar; 10. Steel bar positioning fixture; 11. Inverted arch primary support spraying concrete; 12. Inverted arch steel bar; 12-1. Inverted arch steel bar upper layer steel bar; 12-2. Inverted arch steel bar lower layer steel bar; 13. Steel bar positioning slot; 14. Steel nails; 15. Steel mesh for controlling the top surface of the backfill layer concrete; 16. Inverted arch; 17. Inverted arch backfill layer; 18. Inverted arch central ditch; 19. Left belt; 20. Right belt; 21. Central dividing rib; 22. Narrow and long clips; 23. Wide and short clips; 24. Fixed plate; 25. Screw holes; 26. Equilateral angle steel; 27. Screws; 28. Lower inverted arch end form; 29. ​​Upper inverted arch end form; 30. Middle buried waterstop; 31. Several types of steel bar positioning cards. DETAILED DESCRIPTION

[0069] The present invention will not repeat the composition of the tunnel invert structure, the connection method between the invert steel arch frame and the steel arch frame in the side wall, the diameter and spacing of the invert steel bars, the quality requirements for the installation of drainage blind pipes, the material of the buried water stop belt, the material of several types of steel bar positioning cards, the detailed structure of the invert end formwork, the formwork support method of the invert central ditch, the quality requirements for steel bar welding, the formwork support technology of the invert arc formwork, the concrete pouring process, etc., and will focus on elaborating the implementation method of the structure involved in the present invention.

[0070] Example 1

[0071] like Figure 1-4 The overall structure diagram of the tunnel inverted arch reinforcement accurate installation, positioning and alignment shown in the figure includes tunnel side wall 1, highest reinforcement control wire 2, lowest reinforcement control wire 3, circumferential drainage blind pipe marking line 4, highest reinforcement 5, lowest reinforcement 6, longitudinal drainage blind pipe 7, positioning reinforcement rod 8, horizontal reinforcement 9, reinforcement positioning fixture 10, inverted arch primary support sprayed concrete 11, inverted arch reinforcement 12, inverted arch reinforcement upper layer reinforcement 12-1, inverted arch reinforcement lower layer reinforcement 12-2, reinforcement positioning slot 13, steel nail 14, etc. The inverted arch reinforcement 12 is laid on the inverted arch primary support sprayed concrete 11 according to the designed spacing. The inverted arch reinforcement 12 includes the inverted arch reinforcement upper layer reinforcement 12-1, the inverted arch reinforcement lower layer reinforcement 12-2, and the inverted arch reinforcement 12 is laid on the inverted arch primary support sprayed concrete 11 according to the designed spacing. The inverted arch reinforcement 12 includes the inverted arch reinforcement upper layer reinforcement 12-1, the inverted arch reinforcement lower layer reinforcement 12-2, and the inverted arch reinforcement 12 is laid on the inverted arch primary support sprayed concrete 11 according to the designed spacing. The steel bar 12 is bent upward at the tunnel side wall 1, the upper steel bar 12-1 of the inverted arch steel bar is bent to be the lowest steel bar 6, and the lower steel bar 12-2 of the inverted arch steel bar is bent to be the highest steel bar 5; three steel bar positioning fixtures 10 are longitudinally arranged on the inverted arch primary support sprayed concrete 11, and one steel bar positioning fixture 10 is respectively arranged on the tunnel side walls 1 on both sides. The inverted arch steel bar 12 is accurately positioned by the steel bar positioning fixture 10, and a plurality of steel bar positioning grooves 13 are evenly arranged on the steel bar positioning fixture 10. The upper steel bar positioning groove 13 of the steel bar positioning fixture 10 on the inverted arch primary support sprayed concrete 11 penetrates into the upper steel bar 12-1 of the inverted arch steel bar, and the lower steel bar positioning groove 13 penetrates into the lower steel bar 12-2 of the inverted arch steel bar.

[0072] Preferably, a positioning steel bar 8 is driven into the initial support sprayed concrete 11 of the invert, and a horizontal steel bar 9 is implanted in the tunnel side wall 1, and the horizontal steel bar 9 is welded to the positioning steel bar 8; a steel bar positioning fixture 10 is welded to the horizontal steel bar 9, and the highest steel bar 5 is inserted into the outer steel bar positioning groove 13 of the steel bar positioning fixture 10 at the tunnel side wall 1, and the lowest steel bar 6 is inserted into the inner steel bar positioning groove 13; the spacing between the highest steel bar 5 and the lowest steel bar 6 is accurately positioned by the steel bar positioning fixture 10.

[0073] Preferably, the highest steel bar control wire 2 and the lowest steel bar control wire 3 are arranged on the tunnel side wall 1 according to the designed height, the highest steel bar control wire 2 is used to control the top surface height of the highest steel bar 5, and the lowest steel bar control wire 3 is used to control the top surface height of the lowest steel bar 6. The highest steel bar control wire 2 and the lowest steel bar control wire 3 are nailed to the tunnel side wall 1 by steel nails 14.

[0074] Preferably, a circumferential blind drainage pipe marking line 4 is drawn on the tunnel side wall 1 and the initial support shotcrete 11 of the invert according to the designed position, and a longitudinal blind drainage pipe 7 is installed between the positioning steel bar 8 and the lowest steel bar 6.

[0075] like Figure 6 The structure diagram of the embedded waterstop shown includes a left belt 19, a right belt 20, and a central dividing rib 21. The embedded waterstop 30 is mainly composed of three parts: the left belt 19, the right belt 20, and the central dividing rib 21.

[0076] like Figure 7 The structure diagram of the several types of steel bar positioning cards shown includes a narrow and long clip 22, a wide and short clip 23, a fixing plate 24, and a screw hole 25. The several types of steel bar positioning cards 31 are mainly composed of a narrow and long clip 22, a wide and short clip 23, a fixing plate 24, and a screw hole 25.

[0077] like Figure 8 , 10 The structure diagram of the embedded waterstop fixed by several types of steel bar positioning cards shown in the figure includes an inverted arch 16, a left belt 19, a right belt 20, a central dividing rib 21, a narrow and long clip 22, a wide and short clip 23, a fixing plate 24, a screw hole 25, an equilateral angle steel 26, a screw 27, a lower inverted arch end form 28, an upper inverted arch end form 29, an embedded waterstop 30, several types of steel bar positioning cards 31, etc. When the concrete of the inverted arch 16 is poured, a combined structure of the lower inverted arch end form 28 and the upper inverted arch end form 29 is adopted, and the embedded waterstop 30 is fixed by means of several types of steel bar positioning cards 31.

[0078] The left belt 19 of the embedded water stop 30 is embedded in the narrow and long clip 22, the central dividing rib 21 is embedded in the wide and short clip 23, the fixing plate 24 is connected to the equilateral angle steel 26 by screws 27, and the equilateral angle steel 26 is drilled with screw holes 25; the equilateral angle steel 26 is located between the lower inverted arch end mold 28 and the upper inverted arch end mold 29, and one equilateral angle steel 26 is provided on the upper and lower sides, and is firmly embedded with the lower inverted arch end mold 28 and the upper inverted arch end mold 29. The right belt 20 of the embedded water stop 30 is embedded in the gap between the lower inverted arch end mold 28 and the upper inverted arch end mold 29.

[0079] Preferably, a plurality of several types of steel bar positioning cards 31 are evenly spaced along the length direction of the equilateral angle steel 26, and the left belt 19 of the embedded water stop belt 30 is fixed by the plurality of several types of steel bar positioning cards 31, and the left belt 19 is buried by pouring the concrete of the invert arch 16 on the side of the left belt 19.

[0080] like Figure 5 , 9 The structure diagram of the top surface height of the inverted arch backfill layer controlled by the steel wire mesh shown in the figure includes a tunnel side wall 1, a steel nail 14, a steel wire mesh 15 for controlling the top surface height of the backfill layer concrete, an inverted arch 16, an inverted arch backfill layer 17, etc. The steel wire mesh 15 for controlling the top surface height of the backfill layer concrete is pulled on the tunnel side wall 1 to control the top surface height and flatness of the backfill layer 17. The steel wire mesh 15 for controlling the top surface height of the backfill layer concrete is fixed by the steel nail 14. The steel wire mesh 15 for controlling the top surface height of the backfill layer concrete is provided with one steel wire each along the longitudinal direction of the tunnel side wall 1 and multiple steel wires are provided along the transverse direction, and the flatness of the backfill layer 17 is controlled by the steel wires.

[0081] Example 2

[0082] A tunnel invert through karst strata and a construction method thereof, comprising the following steps:

[0083] (1) Shotcrete spraying of the initial support of the tunnel arch

[0084] Excavate the tunnel invert base surface, clean up the debris, mud, accumulated water, etc. at the tunnel bottom, spray concrete at the tunnel bottom according to the design requirements to form the initial support of the invert 11, and erect a steel arch frame on the initial support of the invert 11. The steel arch frame of the invert must be aligned and connected with the steel arch frame in the side wall, and the two are connected by a connecting plate to form a closed loop.

[0085] (2) Side wall marking nails

[0086] Measure and lay out according to the designed spacing and position, drive steel nails 14 according to the measurement and layout points, pull the highest reinforcement control wire 2 and the lowest reinforcement control wire 3 through the steel nails 14, and draw annular drainage blind pipe marking lines 4 on the tunnel side wall 1 and the initial support concrete spraying 11 of the invert according to the layout points.

[0087] (3) Install positioning steel bars

[0088] According to the measured and laid-out points, the positioning steel bars 8 are installed on the initial support sprayed concrete 11 of the invert arch, and at the same time, the horizontal steel bars 9 are implanted on the tunnel side wall 1, and the horizontal steel bars 9 and the positioning steel bars 8 are welded.

[0089] (4) Install the steel bar positioning fixture

[0090] Three steel bar positioning fixtures 10 are installed and fixed on the initial support sprayed concrete 11 of the inverted arch according to the measured and laid-out positions, and at the same time, a steel bar positioning fixture 10 is welded on the horizontal steel bars 9 on the tunnel side walls 1 on both sides.

[0091] (5) Install the invert reinforcement

[0092] After the upper layer of the inverted arch steel bar 12-1 passes through the upper end steel bar positioning grooves 13 of the three steel bar positioning fixtures 10 on the initial support sprayed concrete 11 of the inverted arch in sequence, it is bent upward at the tunnel side wall 1 to form the lowest steel bar 6, and the lowest steel bar 6 passes through the inner steel bar positioning groove 13 of a steel bar positioning fixture 10 on the horizontal steel bar 9 and keeps the height flush with the lowest steel bar control wire 3; after the lower layer of the inverted arch steel bar 12-2 passes through the lower end steel bar positioning grooves 13 of the three steel bar positioning fixtures 10 on the initial support sprayed concrete 11 of the inverted arch in sequence, it is bent upward at the tunnel side wall 1 to form the highest steel bar 5, and the highest steel bar 5 passes through the outer steel bar positioning groove 13 of a steel bar positioning fixture 10 on the horizontal steel bar 9 and keeps the height flush with the highest steel bar control wire 2.

[0093] (6) Install drainage blind pipe

[0094] The circumferential drainage blind pipe is installed according to the circumferential drainage blind pipe marking line 4 marked by the tunnel side wall 1 and the initial support concrete spraying 11 of the invert arch, and the longitudinal drainage blind pipe 7 is installed between the positioning steel bar 8 and the lowest steel bar 6 to effectively connect the longitudinal drainage blind pipe 7 with the circumferential drainage blind pipe.

[0095] (7) Install the buried waterstop

[0096] Install the lower arch end formwork 28 and the upper arch end formwork 29 on the initial support concrete spraying 11 of the arch, embed the left band 19 of the embedded waterstop 30 into the narrow and long clamping piece 22 of the several-type steel bar positioning card 31, embed the central dividing rib 21 into the wide and short clamping piece 23, connect the fixing plate 24 of the several-type steel bar positioning card 31 with the equilateral angle steel 26 by screws 27, and then extend the right band 20 of the embedded waterstop 30 into the gap between the lower arch end formwork 28 and the upper arch end formwork 29, and embed the equilateral angle steel 26 into the gap between the lower arch end formwork 28 and the upper arch end formwork 29.

[0097] (8) Pouring of invert concrete

[0098] A new self-propelled inverted arch trestle is used to support the inverted arch arc formwork, and the inverted arch 16 concrete is pumped and poured. The top surface of the concrete is leveled based on the elevation line of the top surface of the inverted arch 16 concrete marked on the tunnel side wall 1, and the area near the buried water stop 30 is vibrated and compacted. The left belt 19 and the central dividing rib 21 are buried in the inverted arch 16 concrete.

[0099] (9) Install the steel wire mesh on the top surface of the backfill concrete

[0100] According to the measured and laid out points, steel nails 14 are nailed, and the top surface control steel wire mesh 15 of the backfill layer concrete is pulled through the steel nails 14. The top surface control steel wire mesh 15 of the backfill layer concrete is respectively provided with one steel wire along the longitudinal direction of the tunnel side wall 1 and multiple steel wires are provided along the transverse direction.

[0101] (10) Construction of backfill layer of invert

[0102] After the concrete of the inverted arch 16 is finally set, the top surface of the inverted arch 16 is cleaned and moistened with water. The bottom template and end template of the inverted arch backfill layer 17 are set up. The template of the central ditch 18 of the inverted arch is set up at the central position of the inverted arch 16. The concrete of the inverted arch backfill layer 17 is poured. The pouring is carried out in layers, and the thickness of each layer does not exceed 50cm. The inserted tamping device is used for manual vibration. The top surface height of the inverted arch backfill layer 17 is controlled by the steel wire mesh 15 on the top surface of the backfill layer concrete and smoothed.

[0103] (11) Circular construction

[0104] The tunnel invert construction is carried out in a cycle according to the above process. The invert backfill layer 17 lags behind the invert 16 by one segment. The length of each segment varies from about 30 to 50 m. An embedded waterstop 30 is arranged in the expansion joint at the junction of adjacent segments for waterproofing.

Claims

1. A tunnel invert construction structure passing through a karst stratum, characterized in that: It comprises a tunnel side wall (1), a highest steel bar control wire (2), a lowest steel bar control wire (3), a circumferential drainage blind pipe marking line (4), a highest steel bar (5), a lowest steel bar (6), a longitudinal drainage blind pipe (7), a positioning steel bar rod (8), a horizontal steel bar (9), a steel bar positioning fixture (10), and an inverted arch primary support shotcrete (11); An inverted arch steel bar (12) is laid on the inverted arch primary support shotcrete (11) at a designed interval, the inverted arch steel bar (12) comprising an inverted arch steel bar upper layer bar (12-1) and an inverted arch steel bar lower layer bar (12-2), the inverted arch steel bar (12) is bent upward at the tunnel side wall (1), the inverted arch steel bar upper layer bar (12-1) is bent to form the lowest steel bar (6), and the inverted arch steel bar lower layer bar (12-2) is bent to form the highest steel bar (5); the inverted arch steel bar (12) is accurately positioned by a steel bar positioning fixture (10), and the inverted arch steel bar upper layer bar (12-1) and the inverted arch steel bar lower layer bar (12-2) are respectively embedded in the steel bar positioning slot (13); The tunnel side wall (1) is provided with a highest reinforcement control wire (2) and a lowest reinforcement control wire (3) at a designed height, wherein the highest reinforcement control wire (2) is used to control the top surface height of the highest reinforcement (5), and the lowest reinforcement control wire (3) is used to control the top surface height of the lowest reinforcement (6); A positioning steel bar (8) is also driven into the primary support shotcrete (11) of the inverted arch, and a horizontal steel bar (9) is also implanted into the tunnel side wall (1), and the horizontal steel bar (9) is welded and fixed to the positioning steel bar (8); a steel bar positioning fixture (10) is welded to the horizontal steel bar (9), and a plurality of steel bar positioning slots (13) on the steel bar positioning fixture (10) are embedded with the highest steel bar (5) and the lowest steel bar (6), and the spacing between the highest steel bar (5) and the lowest steel bar (6) is accurately positioned by the steel bar positioning fixture (10); Circumferential drainage blind pipe marking lines (4) are drawn on the tunnel side walls (1) and the initial support concrete spraying (11) of the inverted arch according to the designed positions, and a longitudinal drainage blind pipe (7) is installed between the positioning steel bar (8) and the lowest steel bar (6).

2. The invert construction structure for a tunnel through a karst stratum as claimed in claim 1, characterized in that: The invention also comprises a backfill layer concrete top surface control steel wire mesh (15), an inverted arch (16), an inverted arch backfill layer (17), an inverted arch central ditch (18), a left belt (19), a right belt (20), a central dividing rib (21), a narrow and long clip (22), a wide and short clip (23), a fixing plate (24), a screw hole (25), an equilateral angle steel (26), a screw (27), a lower inverted arch end mold (28), an upper inverted arch end mold (29), a buried water stop strip (30), and several types of steel bar positioning cards (31); When pouring concrete for the inverted arch (16), a combined structure of a lower inverted arch end form (28) and an upper inverted arch end form (29) is adopted; The embedded water stop strip (30) is fixed by several types of steel bar positioning clips (31), and the left strip (19) of the embedded water stop strip (30) is embedded in the narrow and long clamping piece (22); The central partition rib (21) is embedded in the wide and short clip (23), the fixing plate (24) is connected to the equilateral angle steel (26) through screws (27), the equilateral angle steel (26) is located between the lower inverted arch end mold (28) and the upper inverted arch end mold (29), and the right belt (20) of the embedded water stop belt (30) is embedded in the gap between the lower inverted arch end mold (28) and the upper inverted arch end mold (29); The tunnel side wall (1) is provided with a backfill layer concrete top surface control steel wire mesh (15) for controlling the top surface height and flatness of the invert backfill layer (17).

3. The invert construction structure of a tunnel passing through a karst stratum as claimed in claim 2, characterized in that: A plurality of steel bar positioning slots (13) are evenly arranged on the steel bar positioning fixture (10); three steel bar positioning fixtures (10) are longitudinally arranged on the inverted arch primary support sprayed concrete (11); and one steel bar positioning fixture (10) is respectively arranged on the tunnel side walls (1) on both sides; the upper steel bar positioning slot (13) of the steel bar positioning fixture (10) on the inverted arch primary support sprayed concrete (11) penetrates the upper steel bar (12-1) of the inverted arch steel bar, and the lower steel bar positioning slot (13) penetrates the lower steel bar (12-2) of the inverted arch steel bar; the highest steel bar (5) is penetrated into the outer steel bar positioning slot (13) of the steel bar positioning fixture (10) at the tunnel side wall (1), and the lowest steel bar (6) is penetrated into the inner steel bar positioning slot (13).

4. The invert construction structure for a tunnel passing through a karst stratum as claimed in claim 3, characterized in that: The highest reinforcement control steel wire (2) and the lowest reinforcement control steel wire (3) are both nailed to the tunnel side wall (1) via steel nails (14).

5. The invert construction structure for a tunnel passing through a karst stratum as claimed in claim 4, characterized in that: The buried water stop strip (30) is composed of three parts: a left strip (19), a right strip (20), and a central dividing rib (21); the several types of steel bar positioning clips (31) are composed of a narrow and long clip (22), a wide and short clip (23), a fixing plate (24), and a screw hole (25).

6. The invert construction structure for a tunnel passing through a karst stratum as claimed in claim 5, characterized in that: The equilateral angle steel (26) is drilled with a screw hole (25). The equilateral angle steel (26) is provided with one screw hole at the top and one screw hole at the bottom, and is firmly embedded with the lower inverted arch end mold (28) and the upper inverted arch end mold (29).

7. The invert construction structure for a tunnel passing through a karst stratum as claimed in claim 6, characterized in that: A plurality of the several types of steel bar positioning clips (31) are evenly spaced along the length direction of the equilateral angle steel (26), and the left belt (19) of the buried water stop belt (30) is fixed by the plurality of the several types of steel bar positioning clips (31), and the left belt (19) is buried by pouring the concrete of the inverted arch (16) on the side of the left belt (19).

8. The invert construction structure for a tunnel passing through a karst stratum as claimed in claim 7, characterized in that: The backfill layer concrete top surface control steel wire mesh (15) is also fixed by steel nails (14). The backfill layer concrete top surface control steel wire mesh (15) is provided with one steel wire each along the longitudinal direction of the tunnel side wall (1) and multiple steel wires along the transverse direction, and the flatness of the invert backfill layer (17) is controlled by the steel wires.

9. The construction method of the invert construction structure of a tunnel passing through a karst stratum according to claim 8, characterized in that: The following steps are involved: S00, tunnel invert initial support shotcrete Excavating the tunnel invert base, clearing away debris, mud and accumulated water at the tunnel bottom, and spraying concrete at the tunnel bottom to form the initial support of the invert according to design requirements (11); A steel arch frame is erected on the initial support sprayed concrete (11) of the inverted arch, and the steel arch frame of the inverted arch is aligned and connected with the steel arch frame in the side wall, and the two are connected by a connecting plate to form a closed loop; S10, side wall marking nails Measure and lay out the lines according to the designed spacing and position, drive steel nails (14) according to the measurement and layout points, pull the highest reinforcement control wire (2) and the lowest reinforcement control wire (3) through the steel nails (14), and draw the annular drainage blind pipe marking line (4) on the tunnel side wall (1) and the initial support shotcrete (11) of the invert according to the layout points; S20, install the positioning steel bar According to the measured and set-out points, the positioning steel bar (8) is installed on the initial support shotcrete (11) of the inverted arch, and at the same time, the horizontal steel bar (9) is implanted on the tunnel side wall (1), and the horizontal steel bar (9) is welded to the positioning steel bar (8); S30, install the steel bar positioning fixture Three steel bar positioning fixtures (10) are installed and fixed on the initial support shotcrete (11) of the inverted arch according to the measured and laid-out positions, and at the same time, a steel bar positioning fixture (10) is welded on the horizontal steel bars (9) on the tunnel side walls (1) on both sides; S40, install the invert reinforcement After the upper layer of the inverted arch reinforcement bars (12-1) are sequentially passed through the upper end reinforcement positioning grooves (13) of three reinforcement positioning fixtures (10) on the inverted arch primary support sprayed concrete (11), they are bent upward at the tunnel side wall (1) to form the lowest reinforcement bars (6); the lowest reinforcement bars (6) are passed through the inner reinforcement positioning grooves (13) of a reinforcement positioning fixture (10) on the horizontal reinforcement bars (9) and are kept in a high level with the lowest reinforcement control wire (3); After the lower layer of inverted arch steel bars (12-2) are sequentially passed through the lower end steel bar positioning grooves (13) of three steel bar positioning fixtures (10) on the inverted arch primary support sprayed concrete (11), they are bent upward at the tunnel side wall (1) to form the highest steel bar (5); the highest steel bar (5) passes through the outer steel bar positioning groove (13) of a steel bar positioning fixture (10) on the horizontal steel bar (9) and is kept in a high level with the highest steel bar control wire (2); S50, install drainage blind pipe Install the annular drainage blind pipe according to the annular drainage blind pipe marking line (4) marked by the tunnel side wall (1) and the initial support shotcrete (11) of the invert, and install the longitudinal drainage blind pipe (7) between the positioning steel bar (8) and the lowest steel bar (6), and connect the longitudinal drainage blind pipe (7) with the annular drainage blind pipe; S60, installation of buried water stop The lower layer inverted arch end formwork (28) and the upper layer inverted arch end formwork (29) are installed on the initial support spraying concrete (11) of the inverted arch, the left band (19) of the buried water stop belt (30) is embedded in the narrow and long clamping piece (22) of the several types of steel bar positioning card (31), the central dividing rib (21) is embedded in the wide and short clamping piece (23), the fixing plate (24) of the several types of steel bar positioning card (31) is connected with the equilateral angle steel (26) by screws (27), the right band (20) of the buried water stop belt (30) is then extended into the gap between the lower layer inverted arch end formwork (28) and the upper layer inverted arch end formwork (29), and the gaps between the equilateral angle steel (26) and the lower layer inverted arch end formwork (28) and the upper layer inverted arch end formwork (29) are firmly embedded; S70, pouring invert concrete A new self-propelled inverted arch trestle is used to support an inverted arch arc formwork, and concrete of the inverted arch (16) is pumped and poured. The top surface of the concrete is smoothed based on the elevation line of the top surface of the inverted arch (16) concrete drawn on the tunnel side wall (1), and the vibrating compaction is performed near the buried water stop belt (30). The left belt (19) and the central partition rib (21) are buried in the concrete of the inverted arch (16); S80, pull and install the steel wire mesh on the top surface of the backfill layer concrete According to the measured and set-out points, steel nails (14) are nailed, and a steel wire mesh (15) is pulled through the steel nails (14) to control the top surface of the backfill layer concrete. The steel wire mesh (15) for controlling the top surface of the backfill layer concrete is provided with one steel wire each along the longitudinal direction of the tunnel side wall (1) and multiple steel wires are provided in the transverse direction; S90, construction of backfill layer of invert After the concrete of the inverted arch (16) is finally set, the top surface of the inverted arch (16) is cleaned and moistened with water, and a bottom formwork and an end formwork of the inverted arch backfill layer (17) are supported, and a formwork of the central ditch (18) of the inverted arch is supported at the central position of the inverted arch (16); Concrete pouring of the inverted arch backfill layer (17) is carried out in layers, and the thickness of each layer does not exceed 50 cm. The layer is vibrated manually using an inserted tamping device, and the top surface height of the inverted arch backfill layer (17) is controlled by a steel wire mesh (15) on the top surface of the backfill layer concrete and smoothed; S100, Circular Construction The tunnel invert construction is carried out in a cycle according to the above steps, the invert backfill layer (17) lags behind the invert (16) by one segment, each segment is 30-50m long, and an embedded water stop (30) is arranged in the expansion joint at the junction of adjacent segments for waterproofing.