Transient working condition bypass valve control system and transient working condition bypass valve control method
By designing a transient working condition bypass valve control system in a high-temperature gas-cooled relay and adjusting the pressure setting value of the bypass valve, the problem of helium pressure change rate protection during generator trip or shutdown is solved, and the water supply flow is achieved Change control avoids unplanned shutdowns and improves system stability and security.
Patent Information
- Application Number
- CN202411032977.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-30
- Publication Date
- 2024-11-12
AI Technical Summary
When a high-temperature gas-cooled relay occurs when a generator trip or a steam turbine generator is shut down, the protection of the negative rate of change of helium pressure leads to an unplanned shutdown event, causing non-essential losses.
Design a transient working condition bypass valve control system, including steam turbine generator, condenser, condensate pump, low pressure heater, deaerator, main water supply pump, high pressure heater and bypass valve, and adjust the bypass valve Pressure setting value ensures that the steam pressure is stable at the preset value and avoids the negative change rate of helium pressure too large.
It effectively avoids the occurrence of unplanned shutdowns, improves the stability and safety of high-temperature gas-cooled reactors, and reduces non-essential shutdown losses.
Smart Images

Figure CN118934189A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of main steam pressure control, and in particular to a transient operating condition bypass valve control system and a transient operating condition bypass valve control method. Background Art
[0002] The high-temperature gas-cooled reactor demonstration project uses a direct-flow steam generator, which has higher steam parameters and higher thermal efficiency than traditional pressurized water reactor nuclear power units. However, its heat capacity is small. When the unit is shut down or load is dumped, the closing time of the main steam valve and regulating valve of the steam turbine is faster than the opening time of the bypass valve, and the main steam pressure will rise more. As the bypass valve is adjusted to open, the steam is discharged to the condenser to form a new circulation loop. Therefore, the main feed water flow rate first drops rapidly and then rises rapidly.
[0003] In the related art, the high temperature gas-cooled reactor is equipped with a negative change rate protection for the helium pressure in the first circuit. This protection variable is more sensitive when the feed water flow and temperature in the second circuit change rapidly, which leads to the inevitable occurrence of turbine generator or power grid failure events, causing unplanned shutdown events and unnecessary losses. Therefore, a feed water flow change control method suitable for transient operating conditions of high temperature gas-cooled reactors is needed to avoid unplanned shutdown events. Summary of the invention
[0004] In view of this, the present invention provides a transient operating bypass valve control system and a transient operating bypass valve control method to solve the problem of triggering a reactor primary loop helium pressure negative change rate protection shutdown when a steam turbine or generator is shut down.
[0005] In a first aspect, the present invention provides a transient operating bypass valve control system, the system comprising: a steam turbine generator, a condenser, a condensate pump, a low-pressure heater, a deaerator, a main feed water pump, a high-pressure heater, a steam generator and a bypass valve, wherein the condenser is connected to the steam turbine generator, and the outlet end is connected to the condensate pump for condensing water;
[0006] The inlet end of the condensate pump is connected to the outlet end of the condenser, and the outlet end of the condensate pump is connected to the low-pressure heater;
[0007] The inlet end of the low-pressure heater is connected to the outlet end of the condensate pump, and the outlet end of the low-pressure heater is connected to the deaerator;
[0008] The inlet end of the deaerator is connected to the outlet end of the low-pressure heater, and the outlet end of the deaerator is connected to the inlet end of the main feed water pump;
[0009] The inlet end of the main feed water pump is connected to the outlet end of the deaerator, and the outlet end of the main feed water pump is connected to the inlet end of the high pressure heater;
[0010] The inlet end of the high-pressure heater is connected to the outlet end of the main feed water pump, and the outlet end of the high-pressure heater is connected to one end of the steam generator;
[0011] One end of the steam generator is connected to the outlet end of the high pressure heater, and the other end is connected to the steam turbine generator through the main steam valve;
[0012] The bypass valve has one end connected to the inlet end of the condenser and the other end arranged between the main steam valve and the steam turbine generator. It is used to respond to the system's instructions when the system generator trips or the steam turbine generator shuts down, adjust the bypass valve's pressure setting value according to the shutdown time, and discharge steam to the condenser to stabilize the system's steam pressure at a preset pressure value.
[0013] In the present invention, the system is designed to include: a steam turbine generator, a condenser, a condensate pump, a low-pressure heater, a deaerator, a main feedwater pump, a high-pressure heater, a steam generator and a bypass valve. When the system is operating normally, the condenser condensate → condensate pump → low-pressure heater → deaerator → feedwater pump → high-pressure heater → steam generator → steam turbine generator set → condenser forms a circulation loop. By designing a bypass valve in a high-temperature gas-cooled reactor, one end of the bypass valve is connected to the inlet end of the condenser, and the other end is arranged between the main steam valve and the steam turbine generator, and the bypass valve is controlled, and the pressure setting value of the bypass valve is adjusted to increase the control deviation, and ensure the rapid adjustment and opening of the bypass valve, thereby realizing the control of the feedwater flow change of the high-temperature gas-cooled reactor, avoiding the negative change rate of helium pressure in the primary circuit to protect the shutdown when the feedwater flow is restored after the system generator trips or the steam turbine generator is shut down, reducing the occurrence of unplanned shutdown events, and further improving the stability and safety of the high-temperature gas-cooled reactor.
[0014] In an optional embodiment, the main steam valve includes: a main steam isolation valve on the nuclear island side, one end of which is connected to the steam generator and the other end of which is connected to the conventional island side main steam isolation valve;
[0015] The main steam isolation valve on the conventional island side is connected to the main steam isolation valve on the nuclear island side at one end and connected to the steam turbine generator at the other end. The other end of the bypass valve is arranged between the main steam isolation valve on the conventional island side and the steam turbine generator.
[0016] Safety valve, installed between the main steam isolation valve and the steam generator on the nuclear island side;
[0017] The atmospheric release valve is installed between the safety valve and the main steam isolation valve on the nuclear island side.
[0018] In this method, the steam pressure of the transient operating control system of the high-temperature gas-cooled reactor is stabilized by setting the main steam isolation valve on the nuclear island side and the main steam isolation valve on the conventional island side; and the safety valve and the atmospheric release valve are set as overpressure protection, which is beneficial to the safe and stable operation of the high-temperature gas-cooled reactor.
[0019] In an optional embodiment, when the system is operating normally, the bypass valve is in a closed state, the main steam isolation valve on the nuclear island side and the main steam isolation valve on the conventional island side are in an open state, and the safety valve and the atmospheric release valve are in a closed state;
[0020] The main steam pressure of the steam turbine generator control system is maintained at a preset pressure value, and the target setting value of the bypass valve is set by the system to a first pressure setting value, which is the sum of the preset pressure value and the first offset value.
[0021] In this mode, when the system is operating normally, the bypass valve is set in a closed state, the main steam isolation valve on the nuclear island side and the main steam isolation valve on the conventional island side are in an open state, and the safety valve and the atmospheric release valve are in a closed state, thereby ensuring the normal and stable operation of the system; by adjusting the first pressure setting value of the bypass valve to the sum of the preset pressure value and the first offset value, frequent opening of the bypass valve caused by main steam pressure fluctuations during normal operation is prevented.
[0022] In an optional implementation, when a generator trip occurs in the system or the steam turbine generator shuts down, the main steam valve and the regulating valve of the steam turbine generator are closed, and the bypass valve is opened.
[0023] In this mode, when the system generator trips or the steam turbine generator shuts down, the closing time of the main steam valve and regulating valve of the steam turbine generator is faster than the opening time of the bypass valve. Therefore, the main steam pressure will increase rapidly and the main feed water flow will decrease rapidly. By opening the bypass valve, the main steam pressure and main feed water flow of the system can be regulated, avoiding the occurrence of unplanned shutdown.
[0024] In an optional embodiment, the system further includes: an auxiliary electric boiler connected to the deaerator via an auxiliary steam regulating valve, and used for auxiliary heating of the deaerator to stabilize the temperature of the main feed water.
[0025] In this mode, the auxiliary electric boiler is used as a backup heating steam source for transient conditions to assist in heating the deaerator and stabilize the main feed water temperature of the high-temperature gas-cooled reactor.
[0026] In a second aspect, the present invention provides a transient operating bypass valve control method, which is applied to a transient operating bypass valve control system as described in any one of the first aspects, wherein the transient operating bypass valve control system includes a steam turbine generator, a condenser, a condensate pump, a low-pressure heater, a deaerator, a main feed water pump, a high-pressure heater, a steam generator, and a bypass valve, and the method includes:
[0027] Collect status information of the bypass valve control system under transient conditions;
[0028] Based on the status information, determine whether the system has a generator trip or a steam turbine generator shutdown;
[0029] When the generator tripping or the steam turbine generator shutdown does not occur in the system, the target setting value of the bypass valve is controlled to be a first pressure setting value, and the first pressure setting value is the sum of the preset pressure value and the first offset value;
[0030] When the generator trips or the turbine generator shuts down in the system, the pressure setting value of the bypass valve is adjusted according to the shutdown time, and the steam is discharged to the condenser to stabilize the steam pressure of the system at the preset pressure value.
[0031] In the present invention, by adjusting the bypass valve pressure setting value when the system has a generator trip or a steam turbine generator shutdown, the time and rate of feedwater flow recovery can be slowed down by changing different bypass valve setting values, so as to reduce the large-scale change of the negative change rate of helium pressure, prevent the protection shutdown, and avoid the occurrence of unplanned shutdown events. When the system is operating normally, by controlling the first pressure setting value of the bypass valve to be the sum of the preset pressure value and the first offset value, the bypass valve is prevented from being frequently opened due to the main steam pressure fluctuation during normal operation, thereby improving the safety and stability of the operation of the high-temperature gas-cooled reactor.
[0032] In an optional implementation, adjusting the pressure setting value of the bypass valve according to the downtime includes:
[0033] Taking the start time of generator tripping or turbine generator shutdown as the starting point, the shutdown time is divided into the initial transient state, the middle transient state and the late transient state;
[0034] At the initial stage of the transient state, the target setting value of the bypass valve is controlled to be a second pressure setting value, and the second pressure setting value is the difference between the first pressure setting value and the second offset value;
[0035] In the middle of the transient state, the target set value of the bypass valve is controlled to rise to a first pressure setting value at a first preset adjustment rate;
[0036] In the late transient state, the target set value of the bypass valve is controlled to drop to a third pressure setting value at a second preset adjustment rate. The third pressure setting value is the same as the preset pressure value, and the second preset adjustment rate is less than the first preset adjustment rate.
[0037] In this method, the control deviation is increased in the early stage of the transient to increase the bypass valve opening rate; in the middle stage of the transient, the bypass valve setting value is gradually increased to slow down the recovery of the feed water flow; in the late stage of the transient, the bypass valve setting value is gradually restored, and the feed water flow is finally stabilized, ensuring that the power on the reactor side is not reduced.
[0038] In an optional implementation, at the initial transient stage, controlling the target setting of the bypass valve to be the second pressure setting value comprises:
[0039] At the initial stage of the transient state, the bypass valve is controlled to be opened at a first opening degree, and the target setting value of the bypass valve is controlled to be a second pressure setting value;
[0040] Determine whether the system's water supply has reached the minimum range;
[0041] When the water supply of the system reaches the minimum range of the water supply, it is determined that the initial transient state ends and the middle transient state begins.
[0042] In this method, the bypass valve pressure setting value is automatically lowered at the initial transient stage to increase the adjustment deviation, improve the bypass valve response, reduce the main steam pressure increase, reduce the main feed water flow reduction range, and ensure the feed water flow increase range.
[0043] In an optional embodiment, in the mid-transient state, controlling the target set value of the bypass valve to rise to a first pressure setting value at a first preset adjustment rate includes:
[0044] In the middle of the transient state, based on the recovery of the system's feedwater flow, the bypass valve is controlled to open at a second opening, and the target setting value of the bypass valve rises to the first pressure setting value, wherein the second opening is greater than the first opening.
[0045] In this method, by gradually increasing the bypass valve pressure setting value, the bypass valve pressure control deviation is reduced, the bypass valve opening amplitude is reduced, the water supply flow rate is prevented from rising linearly, and the negative change rate of the helium pressure is too large, thereby improving the stability of the system.
[0046] In an optional embodiment, in the late transient state, controlling the target set value of the bypass valve to drop to a third pressure setting value at a second preset adjustment rate comprises:
[0047] In the later stage of transient state, based on the system's feed water flow returning to stability, the valve position of the bypass valve is adjusted to the target valve position corresponding to the reactor power and the bypass valve, and the target set value of the bypass valve is controlled to drop to the third pressure setting value so that the main steam pressure of the system is stabilized at the preset pressure value.
[0048] In this mode, in the late transient period, since the feedwater flow rate has basically returned to stability, the bypass valve pressure setting value is gradually and slowly reduced to ensure that the reactor side does not reduce power. Considering that the feedwater temperature in the late transient period may drop significantly due to the isolation of the steam extraction system, the rate of decrease of the bypass valve pressure setting value is lower than the rate of increase of the pressure setting value in the middle transient period, avoiding the increase in the negative change rate of helium pressure caused by the increase in feedwater flow rate and the drop in feedwater temperature. The valve position of the bypass valve is adjusted to change in a small range within the target valve position corresponding to the reactor power and the bypass valve, so as to achieve the final stabilization of the main steam pressure of the system. BRIEF DESCRIPTION OF THE DRAWINGS
[0049] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0050] Figure 1 It is a schematic diagram of the structure of the transient operating bypass valve control system according to an embodiment of the present invention. Among them, 1. steam turbine generator, 2. condenser, 3. condensate pump, 4. low-pressure heater, 5. deaerator, 6. main feed water pump, 7. high-pressure heater, 8 steam generator, 9. auxiliary electric boiler, 2.1. main steam isolation valve on the nuclear island side, 2.2. main steam isolation valve on the conventional island side, 2.3. bypass valve, 2.4. feed water heating system regulating valve, 2.5. auxiliary steam regulating valve, 2.6. safety valve, 2.7. atmospheric release valve, 3.1. primary circuit helium pressure negative change rate detection.
[0051] Figure 2 It is a flow chart of a method for controlling a bypass valve under transient conditions according to an embodiment of the present invention.
[0052] Figure 3 It is a flow chart of a method for controlling a bypass valve in transient condition of a high temperature reactor according to an embodiment of the present invention.
[0053] Figure 4 It is a schematic diagram of a simulation of main steam pressure according to an embodiment of the present invention.
[0054] Figure 5 It is a schematic diagram of a simulation of the valve position of a bypass valve according to an embodiment of the present invention.
[0055] Figure 6 It is a schematic diagram of a simulation of a negative pressure change rate according to an embodiment of the present invention. DETAILED DESCRIPTION
[0056] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those skilled in the art without creative work are within the scope of protection of the present invention.
[0057] In the related art, the high temperature gas-cooled reactor is equipped with a negative change rate protection for the helium pressure in the first circuit. This protection variable is more sensitive when the feed water flow and temperature in the second circuit change rapidly, which leads to the inevitable occurrence of turbine generator or power grid failure events, causing unplanned shutdown events and unnecessary losses. Therefore, a feed water flow change control method suitable for transient operating conditions of high temperature gas-cooled reactors is needed to avoid unplanned shutdown events.
[0058] In order to solve the above problems, a transient operating bypass valve control system is provided in an embodiment of the present invention. The transient operating bypass valve control system in this embodiment is suitable for use scenarios of large transient operating bypass valve control and operation such as shutdown of high-temperature gas-cooled reactors without stopping the reactor and load shedding. The present invention provides a transient operating bypass valve control system, and the system is designed to include: a steam turbine generator, a condenser, a condensate pump, a low-pressure heater, a deaerator, a main feed water pump, a high-pressure heater, a steam generator and a bypass valve. When the system operates normally, condenser condensate → condensate pump → low-pressure heater → deaerator → feed water pump → high-pressure heater → steam generator → steam turbine generator set → condenser forms a circulation loop. By designing a bypass valve in the high temperature gas-cooled reactor, one end of the bypass valve is connected to the inlet end of the condenser, and the other end is arranged between the main steam valve and the steam turbine generator. The bypass valve is controlled, and the pressure setting value of the bypass valve is adjusted to increase the control deviation, so as to ensure the rapid adjustment and opening of the bypass valve, thereby realizing the control of the feed water flow rate change of the high temperature gas-cooled reactor, avoiding the negative change rate of helium pressure in the primary circuit to protect the shutdown when the feed water flow is restored after the generator trips or the steam turbine generator stops in the system, reducing the occurrence of unplanned shutdown events, and further improving the stability and safety of the high temperature gas-cooled reactor.
[0059] According to an embodiment of the present invention, a transient condition bypass valve control system embodiment is provided. Figure 1 is a schematic diagram of a structure of a transient bypass valve control system according to an embodiment of the present invention. Figure 1As shown, the system comprises: a steam turbine generator 1, a condenser 2, a condensate pump 3, a low-pressure heater 4, a deaerator 5, a main feed water pump 6, a high-pressure heater 7, a steam generator 8 and a bypass valve 2.3, wherein the condenser 2 is connected to the steam turbine generator 1, and its outlet end is connected to the condensate pump 3 for condensing water; the inlet end of the condensate pump 3 is connected to the outlet end of the condenser 2, and the outlet end of the condensate pump 3 is connected to the low-pressure heater 4; the inlet end of the low-pressure heater 4 is connected to the outlet end of the condensate pump 3, and the outlet end of the low-pressure heater 4 is connected to the deaerator 5; the inlet end of the deaerator 5 is connected to the outlet end of the low-pressure heater 4, and the outlet end of the deaerator 5 is connected to the inlet end of the main feed water pump 6; the inlet end of the main feed water pump 6 is connected to the deaerator 5 The outlet end of the main feed water pump 6 is connected to the inlet end of the high-pressure heater 7; the inlet end of the high-pressure heater 7 is connected to the outlet end of the main feed water pump 6, and the outlet end of the high-pressure heater 7 is connected to one end of the steam generator 8; one end of the steam generator 8 is connected to the outlet end of the high-pressure heater 7, and the other end is connected to the steam turbine generator 1 through the main steam valve; the bypass valve 2.3, one end of which is connected to the inlet end of the condenser 2, and the other end is arranged between the main steam valve and the steam turbine generator 1, and is used for responding to the system's instructions when the system generator trips or the steam turbine generator stops, adjusting the pressure setting value of the bypass valve 2.3 according to the shutdown time, and discharging steam to the condenser 2, so that the steam pressure of the system is stabilized at a preset pressure value.
[0060] In an optional embodiment, the main steam valve includes: a nuclear island side main steam isolation valve 2.1, one end of which is connected to the steam generator 8, and the other end of which is connected to a conventional island side main steam isolation valve 2.2;
[0061] The main steam isolation valve 2.2 on the conventional island side is connected to the main steam isolation valve 2.1 on the nuclear island side at one end, and is connected to the steam turbine generator 1 at the other end. The other end of the bypass valve 2.3 is arranged between the main steam isolation valve 2.2 on the conventional island side and the steam turbine generator 1; the safety valve 2.6 is arranged between the main steam isolation valve 2.1 on the nuclear island side and the steam generator 8; the atmospheric release valve 2.7 is arranged between the safety valve 2.6 and the main steam isolation valve 2.1 on the nuclear island side.
[0062] In this method, the steam pressure of the transient operating control system of the high-temperature gas-cooled reactor is stabilized by setting the main steam isolation valve on the nuclear island side and the main steam isolation valve on the conventional island side; and the safety valve and the atmospheric release valve are set as overpressure protection, which is beneficial to the safe and stable operation of the high-temperature gas-cooled reactor.
[0063] In an optional embodiment, when the system is operating normally, the bypass valve 2.3 is in a closed state, the main steam isolation valve 2.1 on the nuclear island side and the main steam isolation valve 2.2 on the conventional island side are in an open state, and the safety valve 2.6 and the atmospheric relief valve 2.7 are in a closed state; the main steam pressure of the system controlled by the steam turbine generator 1 is maintained at a preset pressure value, and the target setting value of the bypass valve 2.3 is set by the system to a first pressure setting value, and the first pressure setting value is the sum of the preset pressure value and the first offset value.
[0064] In this mode, when the system is operating normally, the bypass valve is set in a closed state, the main steam isolation valve on the nuclear island side and the main steam isolation valve on the conventional island side are in an open state, and the safety valve and the atmospheric release valve are in a closed state, thereby ensuring the normal and stable operation of the system; by adjusting the first pressure setting value of the bypass valve to the sum of the preset pressure value and the first offset value, frequent opening of the bypass valve caused by main steam pressure fluctuations during normal operation is prevented.
[0065] In an optional implementation, when a generator trip occurs in the system or the steam turbine generator shuts down, the main steam valve and the regulating valve of the steam turbine generator 1 are closed, and the bypass valve 2.3 is opened.
[0066] In this mode, when the system generator trips or the steam turbine generator shuts down, the closing time of the main steam valve and regulating valve of the steam turbine generator is faster than the opening time of the bypass valve. Therefore, the main steam pressure will increase rapidly and the main feed water flow will decrease rapidly. By opening the bypass valve, the main steam pressure and main feed water flow of the system can be regulated, avoiding the occurrence of unplanned shutdown.
[0067] In an optional embodiment, the system further includes: an auxiliary electric boiler 9, which is connected to the deaerator 5 via an auxiliary steam regulating valve 2.5 and is used for auxiliary heating of the deaerator 5 to stabilize the temperature of the main feed water.
[0068] In this mode, the auxiliary electric boiler is used as a backup heating steam source for transient conditions to assist in heating the deaerator and stabilize the main feed water temperature of the high-temperature gas-cooled reactor.
[0069] In one example, if Figure 1 As shown, the transient operating bypass valve control system of the high temperature reactor includes: a steam turbine generator 1, a condenser 2, a condensate pump 3, a low-pressure heater 4, a deaerator 5, a main feed water pump 6, a high-pressure heater 7, a steam generator 8, an auxiliary electric boiler 9, a main steam isolation valve 2.1 on the nuclear island side, a main steam isolation valve 2.2 on the conventional island side, a bypass valve 2.3, a feed water heating system regulating valve 2.4, an auxiliary steam regulating valve 2.5, a safety valve 2.6, an atmospheric release valve 2.7 and a primary circuit helium pressure negative change rate detection device 3.1.
[0070] When the unit operates normally, the condensate from condenser 2 → condensate pump 3 → low-pressure heater 4 → deaerator 5 → main feed water pump 6 → high-pressure heater 7 → steam generator 8 → steam turbine generator 1 → condenser 2 forms a circulation loop.
[0071] When the system is operating normally, the steam source for the low-pressure heater 4, deaerator 5 and high-pressure heater 7 comes from steam extraction from the steam turbine, the feedwater heating system and the auxiliary electric boiler 9 are in hot standby state, the bypass valve 2.3 is in an automatically closed state, the main steam isolation valve 2.1 on the nuclear island side and the main steam isolation valve 2.2 on the conventional island side are in an open state, and the safety valve 2.6 and the atmospheric release valve 2.7 are in a closed state.
[0072] After the steam turbine or generator trips, the steam extraction system is isolated, and the feedwater loses the heating steam source, which will drop rapidly. At this time, the secondary circuit feedwater heating system is automatically put into operation to quickly restore the feedwater temperature to be stable, and avoid the large-scale reduction in feedwater temperature causing the helium pressure change rate to increase. The auxiliary electric boiler 9, as a backup heating steam source for transient conditions, can assist in heating the deaerator and stabilize the main feedwater temperature. The safety valve and atmospheric release valve also serve as overpressure protection. The feedwater heating system that is set can heat the deaerator feedwater to avoid the rapid drop in feedwater temperature when the steam turbine or generator trips, and the increase in feedwater flow causes the helium pressure negative change rate to stop the reactor. As another steam source for heating the deaerator, the auxiliary electric boiler can be put into operation in time to restore the main feedwater temperature to be stable, which is beneficial to the safe and stable operation of the steam generator.
[0073] The transient operating bypass valve control system provided in this embodiment is designed to include: a steam turbine generator, a condenser, a condensate pump, a low-pressure heater, a deaerator, a main feedwater pump, a high-pressure heater, a steam generator and a bypass valve. When the system is operating normally, the condenser condensate → condensate pump → low-pressure heater → deaerator → feedwater pump → high-pressure heater → steam generator → steam turbine generator set → condenser forms a circulation loop. By designing a bypass valve in a high-temperature gas-cooled reactor, one end of the bypass valve is connected to the inlet end of the condenser, and the other end is arranged between the main steam valve and the steam turbine generator, and the bypass valve is controlled, and the pressure setting value of the bypass valve is adjusted to increase the control deviation, and ensure the rapid adjustment and opening of the bypass valve, thereby realizing the control of the feedwater flow change of the high-temperature gas-cooled reactor, avoiding the negative change rate of helium pressure in the primary circuit to protect the shutdown when the feedwater flow is restored after the system generator trips or the steam turbine generator is shut down, reducing the occurrence of unplanned shutdown events, and further improving the stability and safety of the high-temperature gas-cooled reactor.
[0074] In this embodiment, a transient operating bypass valve control method is provided, which can be used for the above-mentioned transient operating bypass valve control system. The transient operating bypass valve control system includes a steam turbine generator, a condenser, a condensate pump, a low-pressure heater, a deaerator, a main feed water pump, a high-pressure heater, a steam generator and a bypass valve. Figure 2 is a flow chart of a method for controlling a bypass valve under transient conditions according to an embodiment of the present invention. Figure 2 As shown, the process includes the following steps:
[0075] Step S201, collecting status information of a bypass valve control system under transient conditions.
[0076] Step S202: Based on the status information, determine whether the system has a generator trip or a steam turbine generator shutdown.
[0077] Step S203, when the system does not experience a generator trip or a steam turbine generator shutdown, controlling the target setting value of the bypass valve to be a first pressure setting value.
[0078] In the embodiment of the present invention, the first pressure setting value is the sum of the preset pressure value and the first offset value.
[0079] In one example, Figure 3 FIG. 1 is a flow chart of a method for controlling a bypass valve of a high temperature reactor under transient operating conditions according to an embodiment of the present invention. Figure 3 As shown, the main steam pressure is controlled by the steam turbine generator to be in the constant pressure P mode, taking P as 11MPa as an example, the value of P is set according to the specific parameters of the steam turbine generator, and is not limited in the present invention. The bypass valve is automatically set to P+0.5=11.5MPa to prevent the bypass valve from being frequently opened due to the fluctuation of the main steam pressure during normal operation, and the first offset value is 0.5, which is set according to the specific parameters of the system, and is not limited in the present invention.
[0080] Step S204, when the system generator trips or the steam turbine generator shuts down, the bypass valve pressure setting value is adjusted according to the shutdown time, and the steam is discharged to the condenser to stabilize the system steam pressure at a preset pressure value.
[0081] Specifically, the above step S204 includes:
[0082] Step S2041, taking the start time of the system generator tripping or the turbine generator shutdown as the starting point, the shutdown time is divided into the transient early stage, the transient middle stage and the transient late stage.
[0083] In one example, when the generator trips or the steam turbine shuts down, the main steam pressure of the system will increase rapidly and the main feedwater flow rate will decrease rapidly because the closing time of the main steam valve and the regulating valve of the steam turbine generator is faster than the opening time of the bypass valve. Taking the bypass valve fully open time of 7s as an example, the shutdown start time is the starting point, the initial transient state is 0-5s, the middle transient state is 5-10s, and the late transient state is 10-20s. The specific time is not limited in the present invention and is only used for illustration.
[0084] Step S2042: At the initial transient stage, the target setting of the bypass valve is controlled to be the second pressure setting value.
[0085] In the embodiment of the present invention, the second pressure setting value is the difference between the first pressure setting value and the second offset value.
[0086] In some optional implementations, the above step S2042 includes:
[0087] Step a1: at the initial transient stage, the bypass valve is controlled to open at a first opening, and a target setting value of the bypass valve is controlled to be a second pressure setting value.
[0088] Step a2, determining whether the water supply of the system has reached the minimum range of water supply.
[0089] Step a3, when the water supply of the system reaches the minimum range of the water supply, it is determined that the initial transient state ends and the intermediate transient state begins.
[0090] In one example, in order to increase the control deviation and ensure the rapid adjustment and opening of the bypass valve, during the initial transient period of 0 to 5 seconds, at the 0th second, the target setting of the bypass valve is automatically reduced by 2 times the offset value, and the target setting of the bypass valve is 10.5MPa. As the water supply flow rate drops rapidly, it reaches the lowest value in about 5 seconds, and an inflection point of the water supply flow change occurs. The system water supply is within the minimum range of the water supply. At the inflection point of the system water supply flow change, it is determined that the initial transient state ends and the intermediate transient state begins. At this time, the bypass valve opening can be opened to about 40%. The values of the first opening and the second offset value of the bypass valve are set according to the specific parameters of the system, and are not limited in the present invention.
[0091] In this method, the bypass valve pressure setting value is automatically lowered at the initial transient stage to increase the adjustment deviation, improve the bypass valve response, reduce the main steam pressure increase, reduce the main feed water flow reduction range, and ensure the feed water flow increase range.
[0092] Step S2043, in the middle of the transient state, the target set value of the bypass valve is controlled to rise to the first pressure setting value at a first preset adjustment rate.
[0093] In some optional implementations, the above step S2042 includes:
[0094] Step b1, in the middle of the transient state, based on the recovery of the system's water supply flow, the bypass valve is controlled to open with a second opening, wherein the second opening is greater than the first opening, so that the target set value of the bypass valve reaches the first pressure setting value.
[0095] In one example, in the middle of the transient period of 5 to 10 seconds, due to the rapid recovery of the feed water flow, the bypass valve pressure setting value is gradually increased to slow down the bypass valve pressure control deviation, reduce the bypass valve opening amplitude, and avoid the feed water flow from rising linearly. The bypass valve pressure setting value gradually increases from 10.5MPa to 11.5MPa at a rising rate of 0.2MPa / s. Taking the reactor power at a single stack full power state as an example, the bypass valve is opened to the valve position corresponding to the single stack full power, and the second opening is about 60%. The second opening of the bypass valve, the value of the first preset adjustment rate, and the reactor power are set according to the specific parameters of the system, and are not limited in the present invention.
[0096] In this method, by gradually increasing the bypass valve pressure setting value, the bypass valve pressure control deviation is reduced, the bypass valve opening amplitude is reduced, the water supply flow rate is prevented from rising linearly, and the negative change rate of the helium pressure is too large, thereby improving the stability of the system.
[0097] Step S2044, in the late transient state, the target set value of the bypass valve is controlled to drop to a third pressure setting value at a second preset adjustment rate.
[0098] In the embodiment of the present invention, the third pressure setting value is the same as the preset pressure value, and the second preset adjustment rate is less than the first preset adjustment rate.
[0099] In some optional implementations, the above step S2044 includes:
[0100] Step c1, in the late transient state, based on the system's feed water flow returning to stability, adjust the valve position of the bypass valve to the target valve position corresponding to the reactor power and the bypass valve, and control the target set value of the bypass valve to drop to the third pressure setting value, so that the main steam pressure of the system is stabilized at the preset pressure value.
[0101] In one example, in the late transient period of 10 to 20 seconds, since the feedwater flow rate has basically returned to stability, the bypass valve pressure setting value is gradually and slowly reduced, and the target setting value of the bypass valve is restored to 11MPa to ensure that the reactor side does not reduce power. Considering that the feedwater temperature may drop significantly due to the isolation of the steam extraction system at around 10 to 20 seconds, the bypass valve pressure setting value decreases by 0.1MPa / s at the second preset adjustment rate, which is lower than the first rising preset adjustment rate of 0.2MPa / s of the transient mid-term pressure setting value, thereby avoiding the increase in feedwater flow and the drop in feedwater temperature, which leads to an increase in the negative change rate of helium pressure. In the late transient period, the valve position of the bypass valve changes in a small range within the target valve position corresponding to the reactor power and the bypass valve, and the main steam pressure is finally controlled to stabilize at 11MPa. The value of the second preset adjustment rate of the bypass valve is set according to the specific parameters of the system, and is not limited in the present invention.
[0102] In this mode, in the late transient period, since the feedwater flow rate has basically returned to stability, the bypass valve pressure setting value is gradually and slowly reduced to ensure that the reactor side does not reduce power. Considering that the feedwater temperature in the late transient period may drop significantly due to the isolation of the steam extraction system, the rate of decrease of the bypass valve pressure setting value is lower than the rate of increase of the pressure setting value in the middle transient period, avoiding the increase in the negative change rate of helium pressure caused by the increase in feedwater flow rate and the drop in feedwater temperature. The valve position of the bypass valve is adjusted to change in a small range within the target valve position corresponding to the reactor power and the bypass valve, so as to achieve the final stabilization of the main steam pressure of the system.
[0103] In one implementation scenario, taking the reactor power as a single stack full power state as an example, Figure 4 is a schematic diagram of a simulation of main steam pressure according to an embodiment of the present invention, Figure 5 is a schematic diagram of a simulation of a valve position of a bypass valve according to an embodiment of the present invention, Figure 6 is a schematic diagram of a simulation of a negative pressure change rate according to an embodiment of the present invention, such as Figure 4 , 5 As shown in Figure 6, the bypass valve set value curve can be set as follows: Take the bypass valve adjustment full opening time of 7s as an example, and the shutdown start time is the starting point. From 0 to 5s, the bypass valve set value automatically decreases by 2 times the offset value, and the control target is 10.5MPa. From 5 to 10s, the bypass valve pressure set value gradually increases from 10.5MPa to 11.5MPa at a rising rate of 0.2MPa / s. During 10 to 20s, the bypass valve pressure set value gradually decreases from 11.5MPa to 11MPa at a decreasing rate of 0.1MPa / s, where Figure 6 Where X is time in seconds, y is the real-time value of the negative change rate of the primary pressure in KPa / Min, and the protection value is 60.
[0104] Specifically, during the initial transient period of 0 to 5 seconds, the water flow rate drops rapidly and reaches the minimum value in about 5 seconds, and an inflection point of the water flow rate change occurs. At this time, the bypass valve can be opened to about 40%.
[0105] In the middle of the transient state, 5 to 10 seconds, the feedwater flow rate recovers rapidly. At this time, the bypass valve pressure setting value is gradually increased to slow down the bypass valve pressure control deviation and reduce the bypass valve opening amplitude to avoid a linear increase in the feedwater flow rate. At this time, the bypass valve has been opened to the valve position corresponding to the full power of a single stack, about 60%.
[0106] In the late transient period of 10 to 20 seconds, the feedwater flow rate has basically returned to stability, and the bypass valve pressure setting value is gradually reduced slowly, and the control pressure is gradually restored to 11MPa to ensure that the reactor side does not reduce power. Considering that the feedwater temperature may drop significantly due to the isolation of the steam extraction system around 10 to 20 seconds, the bypass valve pressure setting value decrease rate of 0.1MPa / s is lower than the transient mid-term pressure setting value increase rate of 0.2MPa / s, avoiding the increase in feedwater flow and the drop in feedwater temperature, which leads to an increase in the negative change rate of helium pressure. In the late transient period of the bypass valve, the valve position changes in a small range within the valve position corresponding to the full power steam flow of a single stack, and the main steam pressure is finally controlled to stabilize at 11MPa.
[0107] Specific effects include: The bypass valve control method for transient conditions of high-temperature reactors can avoid the negative change rate of helium pressure in the first circuit to protect the shutdown of the reactor when the feedwater flow is restored. By changing the different set values of the bypass valve, the pressure setting value of the bypass valve can be automatically reduced at the beginning of the transient to increase the deviation of the PID adjustment, improve the response of the bypass valve, reduce the increase in the main steam pressure, and reduce the reduction in the main feedwater flow. This also ensures the increase in the feedwater flow. In the middle of the transient, the bypass valve setting value gradually increases, slowing down the recovery of the feedwater flow. In the late transient, the bypass valve setting value gradually recovers, the feedwater flow is finally stabilized, and the reactor side does not reduce power.
[0108] The transient operating bypass valve control method provided in this embodiment adjusts the bypass valve pressure setting value when the system has a generator trip or a steam turbine generator shutdown. By changing the bypass valve setting value, the time and rate of feedwater flow recovery can be slowed down, so as to reduce the large-scale change of the negative change rate of helium pressure, prevent the protection shutdown, and avoid the occurrence of unplanned shutdown events. When the system is operating normally, by controlling the first pressure setting value of the bypass valve to be the sum of the preset pressure value and the first offset value, the main steam pressure fluctuation during normal operation prevents the bypass valve from opening frequently, thereby improving the safety and stability of the high-temperature gas-cooled reactor operation. In the early stage of the transient, the control deviation is increased to increase the bypass valve opening rate; in the middle stage of the transient, the bypass valve setting value is gradually increased to slow down the speed of feedwater flow recovery; in the late stage of the transient, the bypass valve setting value is gradually restored, and the feedwater flow is finally stable, ensuring that the reactor side does not reduce power.
[0109] Although the embodiments of the present invention have been described in conjunction with the accompanying drawings, those skilled in the art may make various modifications and variations without departing from the spirit and scope of the present invention, and such modifications and variations are all within the scope defined by the appended claims.
Claims
1. A transient operating bypass valve control system, characterized in that: The system includes: a steam turbine generator, a condenser, a condensate pump, a low-pressure heater, a deaerator, a main feed water pump, a high-pressure heater, a steam generator and a bypass valve, wherein: The condenser is connected to the steam turbine generator, and the outlet end is connected to the condensate pump for condensing water; The inlet end of the condensate pump is connected to the outlet end of the condenser, and the outlet end of the condensate pump is connected to the low-pressure heater; The inlet end of the low-pressure heater is connected to the outlet end of the condensate pump, and the outlet end of the low-pressure heater is connected to the deaerator; The inlet end of the deaerator is connected to the outlet end of the low-pressure heater, and the outlet end of the deaerator is connected to the inlet end of the main feed water pump; The inlet end of the main feed water pump is connected to the outlet end of the deaerator, and the outlet end of the main feed water pump is connected to the inlet end of the high pressure heater; The inlet end of the high-pressure heater is connected to the outlet end of the main feed water pump, and the outlet end of the high-pressure heater is connected to one end of the steam generator; One end of the steam generator is connected to the outlet end of the high-pressure heater, and the other end is connected to the steam turbine generator through a main steam valve; A bypass valve, one end of which is connected to the inlet end of the condenser, and the other end of which is arranged between the main steam valve and the steam turbine generator. The bypass valve is used to respond to the system's instructions when the generator trips or the steam turbine generator shuts down, adjust the pressure setting value of the bypass valve according to the shutdown time, and discharge steam to the condenser to stabilize the steam pressure of the system at a preset pressure value.
2. The system according to claim 1, characterized in that The main steam valve comprises: a main steam isolation valve on the nuclear island side, one end of which is connected to the steam generator, and the other end is connected to a conventional island side main steam isolation valve; The conventional island side main steam isolation valve has one end connected to the nuclear island side main steam isolation valve and the other end connected to the steam turbine generator, and the other end of the bypass valve is arranged between the conventional island side main steam isolation valve and the steam turbine generator; A safety valve is provided between the main steam isolation valve on the nuclear island side and the steam generator; The atmospheric release valve is arranged between the safety valve and the main steam isolation valve on the nuclear island side.
3. The system according to claim 2, characterized in that When the system is operating normally, the bypass valve is in a closed state, the main steam isolation valve on the nuclear island side and the main steam isolation valve on the conventional island side are in an open state, and the safety valve and the atmospheric release valve are in a closed state; The main steam pressure of the system is controlled by the steam turbine generator to be maintained at the preset pressure value, and the target setting value of the bypass valve is set by the system to a first pressure setting value, which is the sum of the preset pressure value and a first offset value.
4. The system according to claim 2, characterized in that When the generator trips in the system or the steam turbine generator shuts down, the main steam valve and the regulating valve of the steam turbine generator are closed, and the bypass valve is opened.
5. The system according to claim 4, characterized in that The system further comprises: The auxiliary electric boiler is connected to the deaerator through the auxiliary steam regulating valve and is used for auxiliary heating of the deaerator to stabilize the temperature of the main feed water.
6. A method for controlling a bypass valve under transient conditions, characterized in that: Applied to the transient operating bypass valve control system according to any one of claims 1 to 5, the transient operating bypass valve control system comprises a steam turbine generator, a condenser, a condensate pump, a low-pressure heater, a deaerator, a main feed water pump, a high-pressure heater, a steam generator and a bypass valve, the method comprising: Collecting status information of the transient operating bypass valve control system; Based on the status information, determining whether a generator trip occurs in the system or the steam turbine generator shuts down; When the generator tripping does not occur in the system or the steam turbine generator is shut down, controlling the target setting value of the bypass valve to be a first pressure setting value, wherein the first pressure setting value is the sum of the preset pressure value and a first offset value; When the generator trips or the steam turbine generator shuts down in the system, the pressure setting value of the bypass valve is adjusted according to the shutdown time, and the steam is discharged to the condenser so that the steam pressure of the system is stabilized at a preset pressure value.
7. The method according to claim 6, characterized in that The step of adjusting the pressure setting value of the bypass valve according to the downtime includes: Taking the start time of the generator tripping of the system or the shutdown of the steam turbine generator as the starting point, the shutdown time is divided into the transient early stage, the transient middle stage and the transient late stage; At the initial stage of the transient state, the target setting value of the bypass valve is controlled to be a second pressure setting value, wherein the second pressure setting value is a difference between the first pressure setting value and a second offset value; In the middle of the transient state, controlling the target set value of the bypass valve to rise to the first pressure setting value at a first preset adjustment rate; In the late transient state, the target set value of the bypass valve is controlled to drop to a third pressure setting value at a second preset adjustment rate, wherein the third pressure setting value is the same as the preset pressure value, and the second preset adjustment rate is less than the first preset adjustment rate.
8. The method according to claim 7, characterized in that In the initial transient state, controlling the target setting value of the bypass valve to be a second pressure setting value comprises: At the initial stage of the transient state, the bypass valve is controlled to be opened at a first opening degree, and a target setting value of the bypass valve is controlled to be a second pressure setting value; Determining whether the water supply of the system reaches the minimum water supply range; When the water supply of the system reaches the minimum range of the water supply, it is determined that the initial transient state ends and the middle transient state begins.
9. The method according to claim 8, characterized in that In the intermediate transient state, controlling the target set value of the bypass valve to rise to the first pressure setting value at a first preset adjustment rate comprises: In the mid-transient state, based on the recovery of the water supply flow of the system, the bypass valve is controlled to open with a second opening, and the target set value of the bypass valve rises to the first pressure setting value, wherein the second opening is greater than the first opening.
10. The method according to claim 7, characterized in that In the late transient state, controlling the target set value of the bypass valve to decrease to the third pressure setting value at a second preset adjustment rate comprises: In the late transient stage, based on the system's feed water flow returning to stability, the valve position of the bypass valve is adjusted to the target valve position corresponding to the reactor power and the bypass valve, and the target set value of the bypass valve is controlled to drop to the third pressure setting value, so that the main steam pressure of the system is stabilized at the preset pressure value.