Sludge discharge pipeline device capable of being boosted by blowing and filling air

By designing gas sludge separation diversion, scrubbing, gas storage return and mud surface control mechanisms, the problems of unstable and high-pressure air return in the gas-filling and boosting mud discharge pipeline are solved, and the stable flow of mud and the improvement of the conveying effect is achieved. .

CN118935147APending Publication Date: 2024-11-12CCCC SDC (FUJIAN) COMM CONSTR ENG CO LTD +1

Patent Information

Application Number
CN202410982920.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-07-22
Publication Date
2024-11-12

AI Technical Summary

Technical Problem

The existing gas-boosting mud discharge pipes are difficult to form buffering and pressure relief when used, resulting in unstable transportation, damage to the pipeline, and it is difficult for high-pressure air to effectively return and mix, affecting the mud transport effect.

Method used

A blow-filled and air-filled and boosted mud discharge pipe device including an air-sludge separation guide mechanism, a gas sludge sludge mechanism, a gas storage and return mechanism and a mud surface control mechanism are designed to achieve separation, filtration, storage and Mix to form feedback and buffering, ensure stable flow of slurry and reduce conveying losses.

Benefits of technology

The stable flow of mud is achieved, the conveying loss and pipe wall friction is reduced, the distance is extended, the pipeline wear and clay agglomeration is reduced, and the effects of reducing drag, anti-scaling and wear resistance are achieved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118935147A_ABST
    Figure CN118935147A_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of desilting, and discloses a hydraulic filling air-entrapping boosting sludge discharge pipeline device which comprises an air-sludge separation flow guide mechanism, an air washing mechanism is fixedly arranged at the top of the air-sludge separation flow guide mechanism, and an air storage backflow mechanism is fixedly arranged at the top of the air washing mechanism. A gas-mud mixing mechanism is arranged between the gas-mud separation flow guide mechanism and the gas storage backflow mechanism, a mud surface control mechanism is arranged in the gas-mud separation flow guide mechanism, and the mud surface control mechanism is located below the gas washing mechanism. According to the dredger filling air-entrapping boosting sludge discharging pipeline device, through the arrangement of the air-sludge separation flow guide mechanism, the air washing mechanism, the air storage backflow mechanism, the air-sludge mixing mechanism and the sludge surface control mechanism, feedback and buffering can be formed when sludge is about to be discharged, and stable flowing of the sludge is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of dredging, and in particular to a blowing, filling, aeration and propelling mud discharge pipeline device. Background Art

[0002] In dredging and filling projects for rivers and lakes, due to restrictions on ship draft, dredging depth, environmental protection and other conditions, the main dredging equipment is often small and medium-sized dredging ships equipped with environmental protection equipment and small mud pumps. Due to the limitation of mud pump power, the slurry pipeline transportation capacity is limited. Due to the limitation of the equipment's own performance, there is a problem of insufficient pipeline transportation spacing. Generally, air-assisted mud pipelines are used for transportation. However, general air-assisted mud pipelines cannot form a buffer pressure relief in the middle of the pipeline during use, making it difficult to achieve relatively stable flow, causing greater damage to the mud delivery pipe. Summary of the invention

[0003] In view of the deficiencies in the prior art, the present invention provides a blowing, filling, aerating and propelling mud discharge pipeline device, which solves the problems mentioned in the above background.

[0004] The present invention provides the following technical solution: a blowing, filling, and aeration-assisted mud discharge pipeline device, comprising: an air-mud separation and diversion mechanism, a gas washing mechanism is fixedly arranged on the top of the air-mud separation and diversion mechanism, a gas storage and reflux mechanism is fixedly arranged on the top of the gas washing mechanism, an air-mud mixing mechanism is arranged between the air-mud separation and diversion mechanism and the gas storage and reflux mechanism, a mud surface control mechanism is arranged inside the air-mud separation and diversion mechanism, and the mud surface control mechanism is located below the gas washing mechanism.

[0005] Preferably, the air-mud separation and diversion mechanism includes an air-mud separation cylinder, a support frame, a mud inlet, a mud discharge port, a mud delivery pipe and a shift ring, the support frame is fixedly connected to the surface of the air-mud separation cylinder, the mud inlet is penetrated through the surface of the air-mud separation cylinder, the mud discharge port is penetrated through the bottom of the air-mud separation cylinder, and the inner diameter of the mud discharge port is larger than the inner diameter of the mud inlet, the number of the mud delivery pipes is multiple, and the multiple mud delivery pipes are respectively fixedly docked on one side of the mud inlet and the bottom of the mud discharge port, and the shift ring is integrally arranged on the inner wall of the air-mud separation cylinder.

[0006] Preferably, the air washing mechanism includes a docking plate, an air washing cylinder, a water inlet pipe, a drain pipe, a water inlet solenoid valve, a drain solenoid valve, a communicating vessel and a water level observation window, the docking plate is fixedly connected to the top of the air-sludge separation cylinder, the air washing cylinder is fixedly connected to the upper surface of the docking plate, the water inlet pipe and the drain pipe are both fixedly connected to the surface of the air washing cylinder, and the water inlet pipe is located above the drain pipe, the water inlet solenoid valve is fixedly installed at one end of the water inlet pipe, the drain solenoid valve is fixedly installed at one end of the drain pipe, the communicating vessel is fixedly installed on the surface of the air washing cylinder, the water level observation window is fixedly installed on the surface of the communicating vessel, and the surface of the water level observation window is provided with scale lines.

[0007] Preferably, the air washing mechanism also includes an internal connecting plate, an air intake pipe, an air filter net and a non-return one-way valve, the internal connecting plate is fixedly connected to the inside of the air washing cylinder, the air intake pipe is fixedly connected between the internal connecting plate and the docking plate, and one end of the air intake pipe passes through the outside of the air washing cylinder and extends to the inside of the air washing cylinder, the air filter net is fixedly installed in the middle of the internal connecting plate, and the non-return one-way valve is fixedly installed inside the output end of the air intake pipe.

[0008] Preferably, the air storage reflux mechanism includes an intermediate casing, an air sealing cylinder, a sealing ring, an exhaust joint, a pressure relief protection valve, an air supply and intake check valve and an air return pipe. The intermediate casing is fixedly connected to the top of the air-mud separation cylinder through a docking plate, the air sealing cylinder is fixedly installed on the top of the intermediate casing by bolts, the sealing ring is arranged between the intermediate casing and the air sealing cylinder, the exhaust joint is fixedly installed on the top of the air sealing cylinder, the pressure relief protection valve and the air supply and intake check valve are both fixedly installed on the surface of the exhaust joint, and the return pipe is fixedly installed at one end of the exhaust joint.

[0009] Preferably, the air-mud mixing mechanism includes a mud discharge docking cone pipe, an isolation mud guide pipe, a mud inlet docking cone pipe, an air return external pipe and an air inlet external pipe. The mud discharge docking cone pipe is fixedly installed at the input end of the mud pipe away from one end of the air-mud separation cylinder, the isolation mud guide pipe is fixedly connected to one end of the mud discharge docking cone pipe through the air return external pipe, and the mud inlet docking cone pipe is fixedly connected to one end of the isolation mud guide pipe through the air inlet external pipe.

[0010] Preferably, the surface of the return air external passage pipe and the surface of the air intake external passage pipe are both integrally provided with spiral guide plates, and the surface of the return air external passage pipe and the surface of the air intake external passage pipe are both fixedly installed with an inflation air intake check valve, and one end of the two inflation air intake check valves is fixedly installed with an air intake joint, and the return air external passage pipe is fixedly connected to the return air pipe through the inflation air intake check valve and the air intake joint, and ventilation holes are provided inside the return air external passage pipe and inside the air intake external passage pipe.

[0011] Preferably, the mud surface control mechanism includes a lower edge closing block, a spring receiving groove, a downward pressure spring and a fixed sealing ring, the lower edge closing block is fixedly connected to the lower surface of the docking plate, the spring receiving groove is embedded in the bottom of the lower edge closing block, the downward pressure spring is movably arranged inside the spring receiving groove, and the fixed sealing ring is fixedly attached to the lower surface of the lower edge closing block.

[0012] Preferably, the mud surface control mechanism also includes a lifting and lowering sealing ring block, a lower connecting column, a sliding sealing ring, a dynamic sealing ring, a ventilation spring support and a spring protrusion. The lifting and lowering sealing ring block is movably arranged inside the air-mud separation cylinder, and the lifting and lowering sealing ring block is located between the lower edge sealing block and the gear ring. The lower connecting column is fixedly inserted into the bottom of the lifting and lowering sealing ring block, the sliding sealing ring is fixedly sleeved on the surface of the lifting and lowering sealing ring block, and the surface of the sliding sealing ring is slidably connected to the inner wall of the air-mud separation cylinder, the dynamic sealing ring is fixedly fitted on the top of the lifting and lowering sealing ring block, and the dynamic sealing ring corresponds to the fixed sealing ring, the ventilation spring support is fixedly connected to the inside of the lifting and lowering sealing ring block, the spring protrusion is integrally arranged on the top of the ventilation spring support, and the surface of the spring protrusion is movably connected to the inner wall of the downward pressure spring.

[0013] Preferably, the mud surface control mechanism also includes a hollow float barrel, a ventilation docking frame, a mud discharge adjustment block and a cone head, the hollow float barrel is fixedly connected to the bottom of the lifting sealing ring block through a lower connecting column, the ventilation docking frame is fixedly connected to the inner wall of the hollow float barrel, the mud discharge adjustment block is fixedly inserted into the bottom of the ventilation docking frame, and the cone head is integrally arranged at the bottom end of the mud discharge adjustment block, and the cone head is located inside the mud discharge port.

[0014] Compared with the prior art, the present invention has the following beneficial effects:

[0015] 1. The blowing and filling gas-assisted mud discharge pipeline device can form feedback and buffer when the sludge is about to be discharged, thereby ensuring the stable flow of mud, through the arranged air-mud separation and diversion mechanism, air washing mechanism, air storage and reflux mechanism, air-mud mixing mechanism and mud surface control mechanism.

[0016] 2. The blowing and filling gas-assisted mud discharge pipeline device can separate the high-pressure air from the mud when it arrives through the air-mud separation cylinder, support frame, mud inlet, mud discharge port, mud delivery pipe and shift ring, and seal the mud discharge port through the mud liquid surface to ensure that the separated high-pressure air can remain in the air-mud separation cylinder.

[0017] 3. The blowing, filling, aerating and propelling mud discharge pipeline device, through the arranged docking plate, air washer, water inlet pipe, drain pipe, water inlet solenoid valve, drain solenoid valve, connecting vessel, water level observation window, internal connecting plate and air inlet pipe, air filter net and non-return one-way valve, can filter the precipitated high-pressure air through water injection and air filter net to ensure the cleanliness of the high-pressure air and realize the one-way water seal isolation effect of the clean air.

[0018] 4. The blowing, filling, aerating and propelling mud discharge pipeline device can temporarily store the cleaned high-pressure air and return it to the mud through the intermediate casing, air sealing cylinder, sealing ring, exhaust joint, pressure relief protection valve, air supply and air return pipe, thereby ensuring the high-pressure air feedback effect.

[0019] 5. The blowing and filling aeration-assisted mud discharge pipeline device can introduce the charged and returned high-pressure air into the mud for mixing through the mud discharge docking cone pipe, isolation mud guide pipe, mud inlet docking cone pipe, return air external passage pipe, air inlet external passage pipe, spiral guide plate, inflation air inlet check valve and air inlet joint, so as to destroy the flocculation structure of the mud and form a solid-liquid-gas three-phase mixed flow, while reducing the friction resistance in the mud and the side wall shear stress of the boundary layer near the pipe wall, thereby reducing the hydraulic loss in the mud transportation process and extending the discharge distance. At the same time, it also reduces the wear of the pipeline along the way and the condensation of the clay in the pipeline, and has the effects of drag reduction, scale prevention, wear resistance and extended discharge distance.

[0020] 6. The blowing, filling, aerating and propelling mud discharge pipeline device, through the lower edge closing block, spring receiving groove, downward pressure spring, fixed sealing ring, lifting sealing ring block, lower connecting column, sliding sealing ring, dynamic sealing ring, ventilation spring support and spring protrusion, can control the switch of high-pressure gas reflux by lifting and lowering the lifting and lowering sealing ring block, to ensure that the channel is closed in time by the close fit between the lifting and fixed sealing ring and the dynamic sealing ring when the mud liquid level is too high, thereby avoiding mud from entering the inside of the air inlet pipe and causing blockage, and at the same time closing the air intake of the air sealing cylinder to ensure that the air sealing cylinder forms a decompression feedback.

[0021] 7. Through the hollow float, ventilation docking frame, mud discharge regulating block and cone head, the mud discharge port can be filled through the mud discharge regulating block when the mud just reaches the air-mud separation cylinder to ensure mud aggregation. When the mud liquid level is too high, the hollow float drives the mud discharge regulating block to rise to increase the discharge space of the mud discharge port, and the mud is discharged in time, thereby ensuring that the mud liquid level is maintained at a suitable height to form a seal against the high-pressure air separated from above. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a schematic diagram of the structure of the present invention;

[0023] Figure 2 It is a structural schematic diagram of the gas-mud separation and diversion mechanism of the present invention;

[0024] Figure 3 It is a side sectional view of the position of the air washing mechanism of the present invention;

[0025] Figure 4 It is a schematic diagram of the internal explosion structure of the mud surface control mechanism of the present invention;

[0026] Figure 5 This is a schematic diagram of the structure of the lifting seal ring block of the present invention;

[0027] Figure 6 It is a structural schematic diagram of the air filter screen of the present invention;

[0028] Figure 7 It is a schematic diagram of the explosion structure at the position of the air-mud mixing mechanism of the present invention;

[0029] Figure 8 It is a cross-sectional view of the air-mud mixing mechanism of the present invention.

[0030] In the figure: 101, air-sludge separation cylinder; 102, support frame; 103, mud inlet; 104, mud outlet; 105, mud delivery pipe; 106, shift ring; 201, docking plate; 202, air washer; 203, water inlet pipe; 204, drain pipe; 205, water inlet solenoid valve; 206, drain solenoid valve; 207, communicating vessel; 208, water level observation window; 209, inner connecting plate; 210, air inlet pipe; 211, air filter net; 212, non-return one-way valve; 301, intermediate casing; 302, air sealing cylinder; 303, sealing ring; 304, exhaust joint; 305, pressure relief protection valve; 306, air supply and air inlet one-way valve; 307, air return pipe ;401, mud discharge conical pipe;402, isolation mud guide pipe;403, mud inlet conical pipe;404, return air external passage pipe;405, air inlet external passage pipe;406, spiral guide vane;407, inflatable air inlet check valve;408, air inlet joint;409, air vent;501, lower edge closing block;502, spring storage groove;503, downward pressure spring;504, fixed sealing ring;505, lifting sealing ring block;506, lower connecting column;507, sliding sealing ring;508, dynamic sealing ring;509, ventilation spring support;510, spring protrusion;511, hollow floating barrel;512, ventilation docking frame;513, mud discharge adjustment block;514, cone head. DETAILED DESCRIPTION

[0031] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0032] See also Figure 1-8 A blowing and filling aeration-assisted mud discharge pipeline device comprises: an air-mud separation and diversion mechanism, a gas washing mechanism is fixedly arranged on the top of the air-mud separation and diversion mechanism, a gas storage and reflux mechanism is fixedly arranged on the top of the gas washing mechanism, an air-mud mixing mechanism is arranged between the air-mud separation and diversion mechanism and the gas storage and reflux mechanism, a mud surface control mechanism is arranged inside the air-mud separation and diversion mechanism, and the mud surface control mechanism is located below the gas washing mechanism. By means of the arranged air-mud separation and diversion mechanism, the gas washing mechanism, the gas storage and reflux mechanism, the air-mud mixing mechanism and the mud surface control mechanism, feedback and buffering can be formed when the sludge is about to be discharged, thereby ensuring the stable flow of mud.

[0033] The air-mud separation guide mechanism includes an air-mud separation cylinder 101, a support frame 102, a mud inlet 103, a mud discharge port 104, a mud delivery pipe 105 and a shift ring 106. The support frame 102 is fixedly connected to the surface of the air-mud separation cylinder 101, the mud inlet 103 is penetrated and opened on the surface of the air-mud separation cylinder 101, the mud discharge port 104 is penetrated and opened at the bottom of the air-mud separation cylinder 101, and the inner diameter of the mud discharge port 104 is greater than the inner diameter of the mud inlet 103. There are multiple mud delivery pipes 105, and multiple delivery pipes 105 are provided. The mud pipe 105 is fixedly docked on one side of the mud inlet 103 and the bottom of the mud discharge port 104 respectively, and the shift ring 106 is integrally arranged on the inner wall of the air-mud separation cylinder 101. Through the arranged air-mud separation cylinder 101, support frame 102, mud inlet 103, mud discharge port 104, mud pipe 105 and shift ring 106, high-pressure air can be separated from the mud when it arrives, and the mud discharge port 104 can be sealed by the mud liquid surface to ensure that the separated high-pressure air can remain in the inside of the air-mud separation cylinder 101.

[0034] Among them; the air washing mechanism includes a docking plate 201, an air washing cylinder 202, an inlet pipe 203, a drain pipe 204, an inlet solenoid valve 205, a drain solenoid valve 206, a connecting vessel 207 and a water level observation window 208, the docking plate 201 is fixedly connected to the top of the air-sludge separation cylinder 101, the air washing cylinder 202 is fixedly connected to the upper surface of the docking plate 201, the inlet pipe 203 and the drain pipe 204 are both fixedly connected to the surface of the air washing cylinder 202, and the inlet pipe 203 is located above the drain pipe 204, the inlet solenoid valve 205 is fixedly installed at one end of the inlet pipe 203, the drain solenoid valve 206 is fixedly installed at one end of the drain pipe 204, the connecting vessel 207 is fixedly installed on the surface of the air washing cylinder 202, the water level observation window 208 is fixedly installed on the surface of the connecting vessel 207, and the surface of the water level observation window 208 is provided with scale lines.

[0035] The air washing mechanism further includes an inner connecting plate 209, an air inlet pipe 210, an air filter net 211 and a non-return one-way valve 212. The inner connecting plate 209 is fixedly connected to the inside of the air washing cylinder 202. The air inlet pipe 210 is fixedly connected between the inner connecting plate 209 and the docking plate 201. One end of the air inlet pipe 210 passes through the outside of the air washing cylinder 202 and extends to the inside of the air washing cylinder 202. The air filter net 211 is fixedly installed in the middle of the inner connecting plate 209. The non-return one-way valve 212 is fixedly installed in the air inlet pipe 2 Inside the output end of 10, through the arranged docking plate 201, air washer 202, water inlet pipe 203, drain pipe 204, water inlet solenoid valve 205, drain solenoid valve 206, connecting vessel 207, water level observation window 208, internal connecting plate 209 and air inlet pipe 210, air filter net 211 and non-return one-way valve 212, the precipitated high-pressure air can be filtered through water injection and air filter net 211 to ensure the cleanliness of the high-pressure air and realize the one-way water seal isolation effect of the clean air.

[0036] The gas storage and reflux mechanism includes an intermediate casing 301, a gas sealing cylinder 302, a sealing ring 303, an exhaust joint 304, a pressure relief protection valve 305, an air supply and intake check valve 306 and an air return pipe 307. The intermediate casing 301 is fixedly connected to the top of the gas-mud separation cylinder 101 through a docking plate 201, and the gas sealing cylinder 302 is fixedly installed on the top of the intermediate casing 301 by bolts. The sealing ring 303 is arranged between the intermediate casing 301 and the gas sealing cylinder 302, and the exhaust joint 304 is fixedly installed on the sealing cylinder 304. At the top of the air cylinder 302, the pressure relief protection valve 305 and the air supply and intake check valve 306 are fixedly installed on the surface of the exhaust joint 304, and the return air pipe 307 is fixedly installed at one end of the exhaust joint 304. Through the intermediate protective tube 301, the air sealing cylinder 302, the sealing ring 303, the exhaust joint 304, the pressure relief protection valve 305, the air supply and intake check valve 306 and the return air pipe 307, the high-pressure air after cleaning can be temporarily stored and returned to the mud, thereby ensuring the feedback effect of the high-pressure air.

[0037] Among them, the air-mud mixing mechanism includes a mud discharge docking cone pipe 401, an isolation mud guide pipe 402, a mud inlet docking cone pipe 403, an air return external pipe 404 and an air inlet external pipe 405. The mud discharge docking cone pipe 401 is fixedly installed at the input end of the mud conveying pipe 105 away from one end of the air-mud separation cylinder 101, the isolation mud guide pipe 402 is fixedly connected to one end of the mud discharge docking cone pipe 401 through the air return external pipe 404, and the mud inlet docking cone pipe 403 is fixedly connected to one end of the isolation mud guide pipe 402 through the air inlet external pipe 405.

[0038] Among them, the surface of the return air outer pipe 404 and the surface of the intake air outer pipe 405 are both integrally provided with a spiral guide plate 406, the surface of the return air outer pipe 404 and the surface of the intake air outer pipe 405 are fixedly installed with an inflation air intake check valve 407, and one end of the two inflation air intake check valves 407 are fixedly installed with an intake connector 408, and the return air outer pipe 404 is fixedly connected to the return air pipe 307 through the inflation air intake check valve 407 and the intake connector 408, and the interior of the return air outer pipe 404 and the interior of the intake air outer pipe 405 are both provided with a vent hole 409, through the mud discharge docking cone pipe 401 and the isolation mud guide Pipe 402, mud inlet butt-jointed cone pipe 403, return air external passage pipe 404, air inlet external passage pipe 405, spiral guide vane 406, inflation air inlet check valve 407 and air inlet joint 408 can introduce the charging and returning high-pressure air into the mud for mixing, destroy the flocculation structure of the mud, form a solid-liquid-gas three-phase mixed flow, and at the same time reduce the friction resistance in the mud and the side wall shear stress of the boundary layer near the pipe wall, thereby reducing the hydraulic loss in the mud transportation process and playing the role of extending the row spacing. At the same time, it also reduces the wear of the pipeline along the way and reduces the condensation of the clay in the pipeline, and has the effects of drag reduction, scale prevention, wear resistance, and extended row spacing.

[0039] Among them; the mud surface control mechanism includes a lower edge closing block 501, a spring receiving groove 502, a downward pressure spring 503 and a fixed sealing ring 504, the lower edge closing block 501 is fixedly connected to the lower surface of the docking plate 201, the spring receiving groove 502 is embedded at the bottom of the lower edge closing block 501, the downward pressure spring 503 is movably arranged inside the spring receiving groove 502, and the fixed sealing ring 504 is fixedly attached to the lower surface of the lower edge closing block 501.

[0040] Among them, the mud surface control mechanism also includes a lifting sealing ring block 505, a lower connecting column 506, a sliding sealing ring 507, a dynamic sealing ring 508, a ventilation spring support frame 509 and a spring protrusion 510. The lifting sealing ring block 505 is movably arranged inside the gas-mud separation cylinder 101, and the lifting sealing ring block 505 is located between the lower edge sealing block 501 and the shift ring 106. The lower connecting column 506 is fixedly inserted at the bottom of the lifting sealing ring block 505. The sliding sealing ring 507 is fixedly sleeved on the surface of the lifting sealing ring block 505, and the surface of the sliding sealing ring 507 is slidably connected to the inner wall of the gas-mud separation cylinder 101. The dynamic sealing ring 508 is fixedly fitted on the top of the lifting sealing ring block 505, and the dynamic sealing ring 508 corresponds to the fixed sealing ring 504. The ventilation spring support frame 509 is fixedly connected to the inside of the lifting sealing ring block 505. The spring protrusion 510 is integrally arranged on the top of the ventilation spring support 509, and the surface of the spring protrusion 510 is movably connected to the inner wall of the downward pressure spring 503. Through the lower edge closing block 501, spring receiving groove 502, downward pressure spring 503, fixed sealing ring 504, lifting sealing ring block 505, lower connecting column 506, sliding sealing ring 507, dynamic sealing ring 508, ventilation spring support 509 and spring protrusion 510, the switch of high-pressure gas reflux can be controlled by lifting and lowering the lifting and lowering sealing ring block 505, so as to ensure that the channel is closed in time through the close fit between the lifting and fixed sealing ring 504 and the dynamic sealing ring 508 when the mud liquid level is too high, thereby preventing mud from entering the interior of the intake pipe 210 and causing blockage, and at the same time closing the air intake of the sealing cylinder 302 to ensure that the sealing cylinder 302 forms a decompression feedback.

[0041] Among them, the mud surface control mechanism also includes a hollow float 511, a ventilation docking frame 512, a mud discharge regulating block 513 and a cone head 514. The hollow float 511 is fixedly connected to the bottom of the lifting sealing ring block 505 through the lower connecting column 506, the ventilation docking frame 512 is fixedly connected to the inner wall of the hollow float 511, the mud discharge regulating block 513 is fixedly plugged into the bottom of the ventilation docking frame 512, and the cone head 514 is integrally arranged at the bottom end of the mud discharge regulating block 513, and the cone head 514 is located inside the mud discharge port 104, and can fill the mud discharge port 104 through the mud discharge regulating block 513 when the mud just reaches the air-mud separation cylinder 101 to ensure mud aggregation. When the mud liquid level is too high, the hollow float 511 drives the mud discharge regulating block 513 to rise to increase the discharge space of the mud discharge port 104, and the mud is discharged in time, thereby ensuring that the mud liquid level is maintained at a suitable height to form a seal against the high-pressure air separated from above.

[0042] Working principle: connect the air inlet joint 408 above the air inlet external pipe 405 to the external high-pressure air charging pipe, connect one end of the drainage solenoid valve 206 to the external drainage channel, connect one end of the water inlet solenoid valve 205 to the external water inlet channel, and connect the mud inlet conical pipe 403 to the mud pipeline;

[0043] When in use, open the water inlet solenoid valve 205 to inject water into the air washer 202, observe the water level through the water level observation window 208, ensure that the water level submerges the inner plate 209, then close the water inlet solenoid valve 205, the mud enters the mud inlet conical pipe 403 and then passes through the air inlet external pipe 405, the isolation mud guide pipe 402, the return air external pipe 404, the mud discharge conical pipe 401 and the mud delivery pipe 105 in sequence, and the inflation pipe connected to the external high-pressure air inflates the mud through the air inlet external pipe 405, the high-pressure air enters between the spiral guide plates 406 from the vent 409, and then spirals forward along the spiral guide plates 406 and is broken into tiny bubbles at the end of the spiral guide plates 406 and dispersed in the mud flow to push the mud forward until the mud reaches the air-mud separation cylinder 1 from the mud inlet 103. 01, the mud falls to the bottom of the air-mud separation cylinder 101 due to gravity, and the high-pressure air is ejected and hit inside the air-mud separation cylinder 101, and then precipitates out from the inside of the mud and rises. Since the mud discharge regulating block 513 fills the mud discharge port 104, the flow rate of mud entering the air-mud separation cylinder 101 is greater than the flow rate of mud discharged from the air-mud separation cylinder 101, and the liquid level of the mud gradually rises inside the air-mud separation cylinder 101 until it rises to a certain height, and the mud lifts up the hollow float 511, and the hollow float 511 rises. When the hollow float 511 rises, it drives the mud discharge regulating block 513 to rise, until the mud discharge space of the mud discharge port 104 increases to a certain extent, and the mud entering the air-mud separation cylinder 101 and the mud discharged from the air-mud separation cylinder 101 reach a level. The mud liquid level is kept balanced, and at the same time, the high-pressure air separated from the mud passes through the gap beside the hollow float 511, and then passes through the ventilation spring support 509 to enter the interior of the air inlet pipe 210, and then pushes open the non-return one-way valve 212 to enter the interior of the air washer 202, and then the air enters the clean water to be cleaned and filtered by the air filter 211, and the cleaned high-pressure air rises to the inside of the air sealing cylinder 302 and is gathered. As the air pressure increases, the high-pressure gas gradually flows back to the air inlet joint 408 above the return air external pipe 404 through the return air pipe 307, and then passes through the inflation air inlet one-way valve 407 to enter the return air external pipe 404, and then enters between the spiral guide plates 406 from the vent 409 of the return air external pipe 404, and then flows along the spiral front of the spiral guide plates 406 The air entering the air-mud separation cylinder 101 is broken up into tiny bubbles at the end of the spiral guide vane 406 and dispersed in the mud flow to push the mud forward. At this time, the air pushing the mud is pushed by the inflation pipe of the external high-pressure air and the reflux high-pressure air at the same time. When the mud flow rate increases, the flow rate of the mud entering the air-mud separation cylinder 101 will increase, the hollow float barrel 511 will be lifted up, the mud discharge port 104 will increase, and the mud discharge will be accelerated. At the same time, the lifting sealing ring block 505 will rise, and the gap between the lifting sealing ring block 505 and the lower edge sealing block 501 will be reduced, the gas entering the air sealing cylinder 302 will be reduced, the air pressure inside the air sealing cylinder 302 will be reduced, the reflux high-pressure air will be reduced, the reflux air pushing the mud will be reduced, the mud flow rate will be reduced, and the mud will be decelerated to a normal state. At the same time,When the air pressure inside the air sealing cylinder 302 gradually increases to a certain level, the high pressure will push open the pressure relief protection valve 305 to release the pressure. When the mud flow rate decreases, the flow of mud entering the air-mud separation cylinder 101 will decrease, the hollow float 511 will drop, the mud discharge port 104 will decrease, and the mud discharge will decrease, thereby ensuring that the mud level will not be too low. At the same time, the lifting seal ring block 505 will drop, and the gap between the lifting seal ring block 505 and the lower edge sealing block 501 will increase. The gas entering the air sealing cylinder 302 will increase, and the air pressure inside the air sealing cylinder 302 will gradually increase. The reflux high-pressure air will increase, and the reflux air that pushes the mud will increase. The mud flow rate will increase, so that the mud is accelerated to a normal state, thereby ensuring the stable flow of the mud.

[0044] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A blowing, filling, aeration and boosting mud discharge pipeline device, It is characterized in that include: An air-mud separation and diversion mechanism, wherein an air scrubbing mechanism is fixedly arranged on the top of the air scrubbing mechanism, an air storage and reflux mechanism is fixedly arranged on the top of the air scrubbing mechanism, an air-mud mixing mechanism is arranged between the air-mud separation and diversion mechanism and the air storage and reflux mechanism, a mud surface control mechanism is arranged inside the air-mud separation and diversion mechanism, and the mud surface control mechanism is located below the air scrubbing mechanism.

2. A blowing, filling, gas-assisted, and mud-discharging pipeline device according to claim 1, It is characterized in that The air-mud separation and diversion mechanism comprises an air-mud separation cylinder (101), a support frame (102), a mud inlet (103), a mud discharge port (104), a mud delivery pipe (105) and a shift ring (106); the support frame (102) is fixedly connected to the surface of the air-mud separation cylinder (101); the mud inlet (103) is provided through the surface of the air-mud separation cylinder (101); the mud discharge port (104) is provided through the bottom of the air-mud separation cylinder (101); the inner diameter of the mud discharge port (104) is larger than the inner diameter of the mud inlet (103); there are a plurality of mud delivery pipes (105), and the plurality of mud delivery pipes (105) are fixedly docked at one side of the mud inlet (103) and the bottom of the mud discharge port (104) respectively; and the shift ring (106) is integrally arranged on the inner wall of the air-mud separation cylinder (101).

3. A blowing, filling, aeration and mud discharge pipeline device according to claim 2, It is characterized in that The air washing mechanism comprises a docking plate (201), an air washing cylinder (202), a water inlet pipe (203), a drain pipe (204), a water inlet solenoid valve (205), a drain solenoid valve (206), a communicating vessel (207) and a water level observation window (208); the docking plate (201) is fixedly connected to the top of the air-sludge separation cylinder (101); the air washing cylinder (202) is fixedly connected to the upper surface of the docking plate (201); the water inlet pipe (203) and the drain pipe (204) are both fixedly connected to the air washing cylinder (101); The water inlet pipe (203) is located above the drain pipe (204), the water inlet solenoid valve (205) is fixedly mounted on one end of the water inlet pipe (203), the drain solenoid valve (206) is fixedly mounted on one end of the drain pipe (204), the communicating vessel (207) is fixedly mounted on the surface of the air washer (202), the water level observation window (208) is fixedly mounted on the surface of the communicating vessel (207), and the surface of the water level observation window (208) is provided with scale lines.

4. A blowing, filling, aeration and boosting mud discharge pipeline device according to claim 3, It is characterized in that The air washing mechanism further comprises an inner connecting plate (209), an air inlet pipe (210), an air filter net (211) and a non-return one-way valve (212); the inner connecting plate (209) is fixedly connected to the inside of the air washing cylinder (202); the air inlet pipe (210) is fixedly connected between the inner connecting plate (209) and the docking plate (201); one end of the air inlet pipe (210) passes through the outside of the air washing cylinder (202) and extends to the inside of the air washing cylinder (202); the air filter net (211) is fixedly installed in the middle of the inner connecting plate (209); and the non-return one-way valve (212) is fixedly installed inside the output end of the air inlet pipe (210).

5. A blowing, filling, aeration and mud discharge pipeline device according to claim 3, It is characterized in that The gas storage reflux mechanism comprises an intermediate casing (301), an air sealing cylinder (302), a sealing ring (303), an exhaust joint (304), a pressure relief protection valve (305), an air supply and intake check valve (306) and an air return pipe (307). The intermediate casing (301) is fixedly connected to the top of the gas-mud separation cylinder (101) via a docking plate (201). The air sealing cylinder (302) is fixedly installed on the top of the intermediate casing (301) via bolts. The sealing ring (303) is arranged between the intermediate casing (301) and the air sealing cylinder (302). The exhaust joint (304) is fixedly installed on the top of the air sealing cylinder (302). The pressure relief protection valve (305) and the air supply and intake check valve (306) are both fixedly installed on the surface of the exhaust joint (304). The air return pipe (307) is fixedly installed on one end of the exhaust joint (304).

6. A blowing, filling, aeration and mud discharge pipeline device according to claim 5, It is characterized in that The air-mud mixing mechanism comprises a mud discharge butt joint conical pipe (401), an isolation mud guide pipe (402), a mud inlet butt joint conical pipe (403), an air return external communication pipe (404) and an air inlet external communication pipe (405); the mud discharge butt joint conical pipe (401) is fixedly installed at the input end of the mud delivery pipe (105) at one end away from the air-mud separation cylinder (101); the isolation mud guide pipe (402) is fixedly connected to one end of the mud discharge butt joint conical pipe (401) through the air return external communication pipe (404); and the mud inlet butt joint conical pipe (403) is fixedly connected to one end of the isolation mud guide pipe (402) through the air inlet external communication pipe (405).

7. A blowing, filling, gas-assisted, and mud-discharging pipeline device according to claim 6, It is characterized in that The surface of the return air external passage pipe (404) and the surface of the intake air external passage pipe (405) are both integrally provided with spiral guide plates (406), and the surface of the return air external passage pipe (404) and the surface of the intake air external passage pipe (405) are both fixedly installed with an inflation air intake check valve (407), and one end of the two inflation air intake check valves (407) is fixedly installed with an intake connector (408), and the return air external passage pipe (404) is fixedly connected to the return air pipe (307) through the inflation air intake check valve (407) and the intake connector (408), and ventilation holes (409) are opened inside the return air external passage pipe (404) and the intake air external passage pipe (405).

8. The blowing, filling, gas-assisted and mud-discharging pipeline device according to claim 3, It is characterized in that The mud surface control mechanism comprises a lower edge closing block (501), a spring receiving groove (502), a downward pressure spring (503) and a fixed sealing ring (504); the lower edge closing block (501) is fixedly connected to the lower surface of the docking plate (201); the spring receiving groove (502) is embedded in the bottom of the lower edge closing block (501); the downward pressure spring (503) is movably arranged inside the spring receiving groove (502); and the fixed sealing ring (504) is fixedly attached to the lower surface of the lower edge closing block (501).

9. A blowing, filling, aeration and mud discharge pipeline device according to claim 8, It is characterized in that The mud surface control mechanism further comprises a lifting sealing ring block (505), a lower connecting column (506), a sliding sealing ring (507), a dynamic sealing ring (508), a ventilation spring support (509) and a spring protrusion (510); the lifting sealing ring block (505) is movably arranged inside the air-mud separation cylinder (101), and the lifting sealing ring block (505) is located between the lower edge sealing block (501) and the shift ring (106); the lower connecting column (506) is fixedly inserted into the bottom of the lifting sealing ring block (505); the sliding sealing ring (507) is fixedly sleeved on the lifting sealing ring block (505); 505), and the surface of the sliding seal ring (507) is slidably connected to the inner wall of the gas-mud separation cylinder (101), the dynamic seal ring (508) is fixedly fitted on the top of the lifting seal ring block (505), and the dynamic seal ring (508) corresponds to the fixed seal ring (504), the ventilation spring support (509) is fixedly connected to the inside of the lifting seal ring block (505), the spring protrusion (510) is integrally arranged on the top of the ventilation spring support (509), and the surface of the spring protrusion (510) is movably connected to the inner wall of the downward pressure spring (503).

10. The blowing, filling, aeration and mud discharge pipeline device according to claim 1, It is characterized in that The mud surface control mechanism also includes a hollow floating barrel (511), a ventilation docking frame (512), a mud discharge regulating block (513) and a cone head (514); the hollow floating barrel (511) is fixedly connected to the bottom of the lifting sealing ring block (505) through a lower connecting column (506); the ventilation docking frame (512) is fixedly connected to the inner wall of the hollow floating barrel (511); the mud discharge regulating block (513) is fixedly plugged into the bottom of the ventilation docking frame (512); the cone head (514) is integrally arranged at the bottom end of the mud discharge regulating block (513), and the cone head (514) is located inside the mud discharge port (104).

Citation Information

Patent Citations

  • Gas-stripping mud discharging device

    CN103977607A

  • Ventilation pipe mud supercharging device

    CN106195642A

  • Experimental device for researching gas feeding and conveying of slurry pipeline

    CN109029912A

  • Equipment for qichong row mud under water

    CN204543668U

  • Drainage building water supply and drainage pipeline convenient to dredge

    CN209742025U

Cited By

  • Slurry pipeline pigging valve of shield tunneling machine and use method of slurry pipeline pigging valve

    CN120701359A