Overhaul main isolation graph generation and management and control system and method
By generating and managing systems and methods, the problem of the disconnect between the main isolation diagram and the critical path water level diagram during major overhauls was solved, and the linkage between the main isolation diagram and the critical path diagram was realized, which improved the accuracy and efficiency of the major overhaul plan and reduced the risk of information transmission errors.
Patent Information
- Application Number
- CN202410905963.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-08
- Publication Date
- 2024-11-12
AI Technical Summary
The overhaul master isolation diagram and critical path water level diagram cannot be linked, resulting in a disconnect between the overhaul implementation plan and the overhaul work order task plan information. The system isolation maintenance window cannot issue early warnings when the work order task check does not meet the requirements.
This paper provides a system and method for generating and managing a master isolation diagram for overhauls. Through a master isolation plan preparation module, a data extraction module, a logic calculation module, and an automatic generation module, the system generates a master isolation diagram for overhauls and links it with the critical path diagram to track and provide feedback on implementation progress in real time and automatically adjust the plan.
This enabled the linkage between the main isolation diagram and the critical path diagram for major repairs, reducing errors from manual drawing, improving the accuracy and completeness of planning, reducing the risk of information transmission errors, and improving work efficiency and progress tracking capabilities.
Smart Images

Figure CN118941265A_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of nuclear power overhaul, and in particular to a system and method for generating and controlling an overhaul main isolation diagram. Background Art
[0002] Nuclear power plant overhaul is a highly complex systematic management project. Annual overhaul involves more than 10,000 tasks. Each system is isolated and maintenance work is carried out in an orderly manner under different unit conditions according to the operation technical specifications. The operation isolation manager integrates the maintenance work order of a process system into a system main isolation. According to the maintenance project and isolation requirements, the isolation boundary is set up, which is called the main isolation. The overhaul planning engineer schedules the work order tasks under the main isolation according to a certain logical relationship, determines the start and end time and duration of each work order, and determines the implementation / release time of the main isolation according to the system availability requirements of the operation technical specifications to meet the system shutdown maintenance requirements and unit operation requirements.
[0003] During the current overhaul, the overhaul planning engineer draws the main isolation diagram of the nuclear island / conventional island in an EXCEL table according to the critical path water level diagram, technical specification requirements and system maintenance items, and clarifies the start and end time of the main isolation implementation of each process system and the maintenance window duration to form the main isolation diagram of the overhaul. The operation isolation manager sets the system maintenance isolation boundary, i.e., the system main isolation, in the EAM, and then attaches the maintenance work order under the main isolation to the main isolation. The main isolation information is marked in the "isolation number" column of the work order attribute. Since the overhaul main isolation diagram cannot be associated with the isolation information of the work order task in the EAM, it is impossible to query and track the start / completion status of the work order task under the main isolation and whether the work order task scheduling meets the requirements of the main isolation maintenance window; since the main isolation diagram has no linkage relationship with the overhaul critical path water level diagram, the changes in the critical path during the overhaul implementation phase cause changes in the overhaul milestone nodes, and the main isolation information cannot be linked and tracked in time, resulting in the main isolation maintenance window being out of touch with the progress of the critical path implementation. Summary of the invention
[0004] The main purpose of the present invention is to provide a system and method for generating and controlling an overhaul main isolation diagram, so as to solve the problem that the overhaul main isolation diagram and the critical path water level diagram cannot be linked to each other, resulting in a disconnection between the overhaul implementation plan.
[0005] Another object of the present invention is to provide a system and method for generating and controlling a main isolation diagram for overhaul, so as to solve the problem that the main isolation diagram cannot be linked with the task planning information of the overhaul work order, and the work order task check does not meet the system isolation maintenance window and cannot issue an early warning.
[0006] In order to achieve the above object, the present invention provides the following technical solutions:
[0007] In one aspect, the present invention provides a major repair main isolation diagram generation and control system, comprising:
[0008] The main isolation plan preparation module is used to prepare the system maintenance main isolation plan of the unit overhaul company and generate the overhaul information list as the basic data for generating the related information of the overhaul main isolation diagram; according to the water level changes and milestone nodes of the overhaul key path, operation technical specifications, maintenance items, and plan arrangements, the system maintenance main isolation plan is prepared and the overhaul main isolation information list is generated as the basic data for generating the related information of the overhaul main isolation diagram;
[0009] The overhaul key path diagram generation module is used to extract data from the main isolation information list generated by the main isolation plan preparation module to generate an information database, associate key path items, milestone nodes, water level change nodes, and main isolation information, and generate an overhaul main isolation diagram;
[0010] The main isolation implementation tracking and feedback module is used to track and control the implementation progress information of the overhaul key path project, and feed back the deviation information to the main isolation plan preparation module.
[0011] In some embodiments, in the main isolation plan preparation module, a system maintenance main isolation plan is prepared according to the water level changes and milestone nodes of the overhaul critical path, the operation technical specifications, and the maintenance items, and an overhaul main isolation information list is generated.
[0012] In some embodiments, the overhaul critical path diagram generation module includes:
[0013] A data extraction module is used to extract the overhaul critical path water level diagram information list and main isolation information list data generated by the critical path planning module into a data pool to generate an overhaul main isolation diagram information database;
[0014] A logic calculation module is used to arrange the main isolation information according to the planned start time and the planned completion time through logic calculation of the generated overhaul main isolation diagram information data, and generate an overhaul main isolation information list;
[0015] The automatic generation module is used to automatically generate the overhaul main isolation diagram below the overhaul critical path water level diagram using the generated logic calculation data results.
[0016] On the other hand, the present invention also provides a method for generating and controlling a major repair main isolation diagram, comprising the following steps:
[0017] Step 1: Prepare the master isolation plan and generate the master isolation information basic data;
[0018] Step 2: Set the system maintenance main isolation boundary, generate system main isolation boundary information data, attach the maintenance object work order task within the main isolation boundary to the corresponding main isolation, and generate system maintenance main isolation boundary information;
[0019] Step 3: Perform logical analysis on the system master isolation information data, generate overhaul master isolation items, determine the relationship between the master isolation items and the overhaul milestone nodes, and generate a list of overhaul master isolation items in chronological order;
[0020] Step 4: Generate a main isolation graph based on the logical relationship between the main isolation items and milestone nodes;
[0021] Step 5: Adjust the master isolation plan and work order plan;
[0022] Step 6: During the overhaul implementation phase, follow up and provide feedback on the main isolation maintenance plan.
[0023] In some embodiments, according to the requirements of the operating technical specifications and the overhaul plan, the process system maintenance main isolation implementation plan is logically linked to the milestone node or overhaul critical path project (set between the two projects); the overhaul main isolation plan is completed and a main isolation information list is generated.
[0024] In some embodiments, the system main isolation information data is analyzed and calculated through a logic calculation module (identifying the logical relationship between projects, calculating the main isolation duration, milestone node time, etc.), and by analyzing the planned start time and planned completion time of all maintenance work order tasks under the main isolation, the earliest planned start time is used as the main isolation planned start time, and the latest planned completion time is used as the main isolation planned completion time. The main isolation implementation window time is automatically calculated to generate the overhaul main isolation entry.
[0025] In some embodiments, a logic calculation module performs logic calculation on relevant information in the main isolation graph to check whether the main isolation start time and completion time meet the critical path milestone node requirements.
[0026] In some embodiments, a new work order task is added in the main isolation. If the planned start time and planned completion time of the work order task are not within the main isolation window, an alarm feedback message is automatically triggered.
[0027] On the other hand, the present invention also provides a computer device, including a memory and a processor, wherein the memory stores computer-readable instructions, and when the processor executes the computer-readable instructions, the steps of the overhaul main isolation diagram generation and control method are implemented.
[0028] On the other hand, the present invention also provides a computer-readable storage medium, on which computer-readable instructions are stored. When the computer-readable instructions are executed, the steps of the overhaul main isolation diagram generation and control method are implemented.
[0029] Compared with the prior art, the overhaul main isolation diagram generation and control system and method provided by the present invention has the following beneficial effects:
[0030] The present invention automatically extracts overhaul plan information and automatically generates an overhaul main isolation diagram by setting a logical relationship between the main isolation of the overhaul system and the milestone nodes of the key path, thereby avoiding errors caused by manual drawing.
[0031] The present invention automatically generates the overhaul main isolation diagram and links it with the critical path diagram, so that the main line plan, the nuclear island plan and the conventional island plan share a single diagram, which reduces the changes in the critical path water level diagram due to the adjustment of the key path of the main line plan, resulting in repeated adjustments to the main isolation diagram headers of the nuclear island plan and the conventional island plan, thereby achieving automatic generation of the overhaul main isolation diagram and linkage with the critical path water level diagram.
[0032] The present invention links the overhaul main isolation information with the EAM work order information to clearly display the maintenance work order tasks under the main isolation, and promptly alarms and adjusts the plan if the progress requirements and the system isolation maintenance window requirements are not met, thereby improving the accuracy and completeness of the overhaul plan preparation.
[0033] The present invention automatically tracks the overhaul main isolation information and work order task information, so that each department can timely grasp the work plan arrangement and progress under the system main isolation, reduce the risk of delayed implementation of the work plan due to information transmission errors, and improve work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0034] In order to more clearly illustrate the technical solution of the present invention, the following briefly introduces the drawings required for the technical description.
[0035] Figure 1 A schematic diagram of the structure of the overhaul main isolation diagram generation and control system provided by the present invention;
[0036] Figure 2 A flow chart of the overhaul main isolation diagram generation and control method provided by the present invention. DETAILED DESCRIPTION
[0037] The following is further explained in detail through specific implementation methods.
[0038] like Figure 1 As shown, the present invention provides a major overhaul main isolation diagram generation and control system, including a main isolation plan preparation module, an overhaul key path diagram generation module, and a main isolation implementation tracking feedback module.
[0039] The main isolation plan preparation module is used to generate the basic data of the overhaul main isolation information. According to the water level changes and milestone nodes of the overhaul key path, the operation technical specifications, and the maintenance items, the system maintenance main isolation plan is prepared to generate the overhaul main isolation information list as the basic data for the generation of the overhaul main isolation diagram related information.
[0040] The overhaul main isolation diagram generation module is used to extract data from the main isolation information list generated by the main isolation plan preparation module to generate an information database, and then associate the key path items, milestone nodes, water level change nodes and main isolation information through a series of logical calculations, and finally generate the overhaul main isolation diagram.
[0041] The overhaul main isolation diagram generation module includes a data extraction module, a logic calculation module, and an automatic generation module.
[0042] The data extraction module is used to generate the overhaul main isolation diagram information database. The data extraction module extracts the main isolation information list data generated by the overhaul main isolation plan preparation module into the data pool to generate the overhaul main isolation diagram information database.
[0043] The logic calculation module is used to calculate and generate a list of major overhaul isolation information according to the logical relationship. The logic calculation module arranges the major isolation information according to the planned start time and the planned completion time through logical calculation for the major overhaul isolation diagram information data generated in the data extraction module, and generates a list of major overhaul isolation information.
[0044] The automatic generation module is used to generate the overhaul main isolation diagram from the overhaul main isolation information list. The logic calculation module automatically generates the overhaul main isolation diagram below the overhaul critical path water level diagram based on the logic calculation data results generated in the logic calculation module. The overhaul main isolation diagram display board makes the operation information of the overhaul system maintenance main isolation implementation window transparent and global, so that the overhaul plan and the execution department, the supervision department and other relevant personnel information can be shared synchronously. According to the overhaul main isolation information, the urgency of each system maintenance can be identified, human resources can be reasonably deployed, and the efficiency of overhaul system maintenance control can be effectively improved.
[0045] The main isolation implementation tracking and feedback module is used to track the implementation progress information of the overhaul critical path project. If the executed critical path project / main isolation maintenance project deviates from the plan (ahead of time or behind schedule), the deviation information will be fed back to the main isolation plan preparation module, and then after passing through the overhaul critical path diagram generation module, the overhaul main isolation diagram information display board will be updated to keep the overhaul critical path water level diagram consistent with the actual progress of the overhaul in real time. When the logic calculation module determines that the "planned completion time" of the main isolation is later than the corresponding milestone node time, the implementation tracking and feedback module will automatically trigger an alarm reminder message to the planning engineer, and the planning engineer will adjust the maintenance plan in the main isolation plan preparation module until the alarm is eliminated, so as to accurately and efficiently control the main isolation maintenance plan.
[0046] In addition, if Figure 2 As shown, the present invention provides a method for generating and controlling a major repair main isolation diagram, comprising the following steps:
[0047] Step 1: Prepare the master isolation plan and generate the basic data of the overhaul master isolation information.
[0048] Before the main isolation diagram is generated and the control system is used, the preparation of basic data needs to be completed. In the main isolation plan preparation module 100, according to the requirements of the operating technical specification and the overhaul plan, the process system maintenance main isolation implementation plan is connected (set between two projects) with the milestone node or overhaul critical path project. For example: set the RRI system main isolation ADT RRI 01, and implement the main isolation after the unit enters the refueling cold shutdown and loading according to the plan. Then the ADT RRI 01 main isolation is connected with the "filling the refueling pool with water to full water" critical path with the "FS" logical relationship (the completion time of the latter is the start time of the former), and the start time of the main isolation is the completion time of the "filling the refueling pool with water to full water" critical path project. And so on, complete the preparation of the overhaul main isolation plan and generate a main isolation information list.
[0049] Step 2: Set the system maintenance main isolation boundary, generate the system main isolation boundary information data, attach the maintenance object work order task within the main isolation boundary to the corresponding main isolation, and generate the system maintenance main isolation boundary information.
[0050] In the main isolation plan preparation module 100, the main isolation boundary of the system maintenance is set according to the maintenance content and isolation requirements of the process system, and the system main isolation boundary information data is generated. Then, the maintenance object work order tasks within the main isolation boundary are attached to the corresponding main isolation, and each work order task is given the planned start time and planned completion time information to generate the system maintenance main isolation boundary information.
[0051] Step 3: Perform logical analysis on the system main isolation information data, generate overhaul main isolation items, determine the relationship between the main isolation items and the overhaul milestone nodes, and generate a list of overhaul main isolation items in chronological order.
[0052] The system main isolation information data is logically analyzed through the logic calculation module 202 (identifying the logical relationship between projects, calculating the main isolation duration, milestone node time, etc.), and the planned start time and planned completion time of all maintenance work order tasks under the main isolation are analyzed. The earliest planned start time is used as the main isolation planned start time, and the latest planned completion time is used as the main isolation planned completion time. The main isolation implementation window time is automatically calculated, and then the overhaul main isolation entry is generated. By judging the relationship between the main isolation entry and the overhaul milestone node (SS: start at the same time, FS: the previous project ends and the subsequent project starts, FF: ends at the same time as the previous project), a list of overhaul main isolation entries is generated in chronological order.
[0053] Step 4: Generate a main isolation graph based on the logical relationship between the main isolation items and milestone nodes.
[0054] Through the automatic generation module 203, the main isolation item list of the overhaul is automatically generated into a main isolation diagram below the critical path water level diagram according to the logical relationship between the main isolation item and the milestone node (SS: start at the same time, FS: the end of the previous project, the start of the subsequent project, FF: end at the same time as the previous project). And each main isolation item contains the work order task information contained in the main isolation, and is classified according to the work order task status. By clicking the corresponding main isolation item, the corresponding information pops up.
[0055] Step 5: Adjust the master isolation plan and work order plan.
[0056] The logical calculation module is used to perform logical calculations on the relevant information in the main isolation diagram to check whether the start time and completion time of the main isolation meet the requirements of the critical path milestone nodes. For example, if the ADT RRI 01 main isolation requires the isolation to be implemented after the critical path project "filling the water tank for material replacement" is completed, the main isolation start time is automatically calculated to see if it is later than the completion time of the critical path project "filling the water tank for material replacement". If it is not satisfied, an automatic alarm is sent to the planning engineer through email feedback for adjustment. Check whether the earliest start time and the latest completion time of the work order task are within the range of the start time and completion time of the main isolation. If it is not satisfied, the system automatically alarms and sends an email feedback to the planning engineer for adjustment.
[0057] Step 6: During the overhaul implementation phase, follow up and provide feedback on the main isolation maintenance plan.
[0058] Through the main isolation implementation tracking feedback module 300, the main isolation maintenance plan is tracked and fed back during the overhaul implementation phase. If a new work order task is in the main isolation, and the start / completion time of the work order task is not within the main isolation window range, an automatic alarm feedback is generated so that the planning engineer can adjust the plan; if according to the progress of the overhaul implementation, the "reverse" milestone node is earlier than the original plan, resulting in the ADT RRI 01 main isolation completion time being later than the "reverse" milestone node time, an automatic alarm feedback is generated so that the planning engineer can adjust the main isolation completion time in time and promote the progress of the work order tasks under the main isolation; if the main isolation window is about to end, there are still unstarted work order tasks or unfinished work order tasks that cannot be started under the main isolation, the overhaul main isolation diagram generation and control system automatically triggers the alarm feedback information to remind the planning engineer and the implementation department to promote the progress of the work order tasks in time.
[0059] In addition, the present invention also provides a computer device, including a memory and a processor, wherein the memory stores computer-readable instructions, and when the processor executes the computer-readable instructions, the steps of the above-mentioned overhaul main isolation diagram generation and control method are implemented.
[0060] In addition, the present invention also provides a computer-readable storage medium, on which computer-readable instructions are stored. When the computer-readable instructions are executed, the steps of the above-mentioned overhaul main isolation diagram generation and control method are implemented.
[0061] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic tape magnetic disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device.
[0062] The present invention extracts the information related to the overhaul plan, automatically generates and links the overhaul critical path water level diagram and the overhaul system main isolation diagram, and issues an alarm in real time to remind the planning engineer to adjust the plan if the system maintenance window time does not meet the critical path progress project. By extracting the information related to the EAM work order task, the overhaul system main isolation diagram is associated with the work order task, so that the work plan arrangement under the main isolation system is clear and concise. If the work order task plan arrangement does not meet the system main isolation maintenance window, an alarm is issued in real time to remind the planning engineer to adjust the plan or advance the progress of the work. During the overhaul implementation, the critical path project is tracked in real time, and the completion status of the work tasks on the system that is about to be released from isolation is timely understood, which helps the overhaul planning engineer to promptly advance the progress of the work tasks under the main isolation.
[0063] The present invention solves the problem of disconnection in implementation plan caused by the inability to link the main isolation diagram with the critical path water level diagram. The main isolation diagram is automatically generated and linked with the critical path water level diagram, so as to realize the linkage of the main line plan, the nuclear island plan and the conventional island plan. The three plans are jointly promoted to reduce repeated adjustments of the main isolation diagram and improve work efficiency.
[0064] The present invention gets rid of the inability to link the main isolation diagram with the EAM. The system realizes a detailed display of the maintenance work order under the main isolation of the process system, and promptly alarms and reminds the planning engineer to adjust the plan when the work order task scheduling does not meet the system isolation maintenance window, thereby realizing timely tracking and closed-loop management of the overhaul progress.
[0065] The present invention reduces the number of personnel interfaces and the risk of information transmission distortion. During the overhaul implementation process, the system master isolation work order task plan and completion status can be queried in real time, which is convenient for each implementation department to sort out the work tasks.
[0066] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any changes or substitutions that can be easily thought of by a person skilled in the art within the technical scope disclosed by the present invention should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention should be based on the protection scope of the claims.
Claims
1. A major repair main isolation diagram generation and control system, characterized in that: include: The main isolation plan preparation module is used to generate the basic data of the main isolation information for overhaul; The overhaul main isolation diagram generation module is used to extract data from the main isolation information list generated by the main isolation plan compilation module to generate an information database, associate key path items, milestone nodes, water level change nodes, and main isolation information, and generate an overhaul main isolation diagram; The main isolation implementation tracking and feedback module is used to track the implementation progress information of the overhaul key path project and feed back the deviation information to the main isolation plan preparation module.
2. The overhaul main isolation diagram generation and control system according to claim 1 is characterized in that: In the main isolation plan preparation module, the system maintenance main isolation plan is prepared according to the water level changes and milestone nodes of the overhaul key path, operation technical specifications, and maintenance projects, and the overhaul main isolation information list is generated.
3. The overhaul main isolation diagram generation and control system according to claim 1 is characterized in that: The overhaul main isolation map generation module includes: A data extraction module is used to extract the main isolation information list data into a data pool to generate an overhaul main isolation diagram information database; A logic calculation module is used to arrange the main isolation information according to the planned start time and the planned completion time through logic calculation of the generated overhaul main isolation diagram information data, and generate an overhaul main isolation information list; The automatic generation module is used to automatically generate the overhaul main isolation diagram below the overhaul critical path water level diagram using the generated logic calculation data results.
4. A method for generating and controlling a major overhaul main isolation diagram, characterized in that: The following steps are involved: Step 1: Prepare the master isolation plan and generate the master isolation information basic data; Step 2: Set the system maintenance main isolation boundary, generate system main isolation boundary information data, attach the maintenance object work order task within the main isolation boundary to the corresponding main isolation, and generate system maintenance main isolation boundary information; Step 3: Perform logical analysis on the system master isolation information data, generate overhaul master isolation items, determine the relationship between the master isolation items and the overhaul milestone nodes, and generate a list of overhaul master isolation items in chronological order; Step 4: Generate a main isolation graph based on the logical relationship between the main isolation items and milestone nodes; Step 5: Adjust the master isolation plan and work order plan; Step 6: During the overhaul implementation phase, follow up and provide feedback on the main isolation maintenance plan.
5. The overhaul main isolation diagram generation and control method according to claim 4 is characterized in that: In step 1, according to the requirements of the operation technical specification and the overhaul plan, the main isolation implementation plan of the process system overhaul is logically linked to the milestone nodes or overhaul key path items; Complete the preparation of the overhaul main isolation plan and generate basic data for main isolation information.
6. The overhaul main isolation diagram generation and control method according to claim 4 is characterized in that: In step 3, the system main isolation information data is logically analyzed through the logic calculation module. By analyzing the planned start time and planned completion time of all maintenance work order tasks under the main isolation, the earliest planned start time is used as the main isolation planned start time, and the latest planned completion time is used as the main isolation planned completion time. The main isolation implementation window time is automatically calculated to generate the overhaul main isolation entry.
7. The overhaul main isolation diagram generation and control method according to claim 4 is characterized in that: In step 5, the logic calculation module performs logic calculation on the relevant information in the main isolation diagram to check whether the start time and completion time of the main isolation meet the requirements of the critical path milestone nodes.
8. The overhaul main isolation diagram generation and control method according to claim 4 is characterized in that: In step 6, a new work order task is added in the main isolation. If the planned start time and planned completion time of the work order task are not within the main isolation window range, an alarm feedback message will be automatically triggered.
9. A computer device comprising a memory and a processor, wherein the memory stores computer-readable instructions, characterized in that: When the processor executes the computer-readable instructions, the steps of the overhaul main isolation diagram generation and control method described in any one of claims 4-8 are implemented.
10. A computer-readable storage medium having computer-readable instructions stored thereon, characterized in that: When the computer-readable instructions are executed, the steps of the overhaul main isolation diagram generation and control method described in any one of claims 4-8 are implemented.