Risk-controllable economic dispatching method considering energy storage, equipment and storage medium
By establishing a risk-controllable economic scheduling method in the power system, combining thermal power units, renewable power supplies and energy storage equipment, optimizing the scheduling plan, the problem of power waste in renewable energy is solved, and the flexibility and reliability of the system are improved. Reduced energy waste.
Patent Information
- Application Number
- CN202411118721.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-15
- Publication Date
- 2024-11-12
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
In power systems, especially in extreme scenarios, the power waste problem of renewable energy leads to insufficient system flexibility and lack of scheduling capabilities, reflecting problems in system planning and management, and the energy storage technology is expensive and immature, making it difficult to Effectively utilize renewable energy.
A economic scheduling method that can be considered controllable in energy storage risks is proposed. By establishing a probabilistic economic scheduling model and a power-saving period optimization model, combining thermal power units, renewable power supplies and energy storage equipment, a hybrid integer planning solver is used to optimize the scheduling plan To minimize the amount of power abandonment and quantile changes, ensure system safety and stability.
It improves the utilization rate of renewable energy, reduces energy waste, ensures the reliability and stability of system operation, reduces the risk of power abandonment, and improves the rationality and completeness of scheduling through detailed constraints and optimization models.
Smart Images

Figure CN118944200A_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of power system operation control, and specifically relates to an economic dispatch method, device and storage medium that take into account the controllable risk of energy storage. Background Art
[0002] From the perspective of low carbon and environmental protection, power abandonment represents a waste of available power generation resources. It not only fails to fully utilize renewable energy, but also causes a huge waste of resources. Although using energy storage to reduce power abandonment can increase the proportion of renewable energy consumption and utilization, it is costly and the technology is not yet mature. From the perspective of power system operation, in certain specific periods and extreme scenarios, especially when key safety constraints cannot be met and the system's adjustable resources are insufficient, the abandonment of renewable energy is a helpless move, but it also exposes the lack of flexibility and dispatching capabilities of the power system. Therefore, although the abandonment of renewable energy cannot be ignored in the dispatch of the power system, it also reflects many problems in system planning and management. Summary of the invention
[0003] The present invention aims to address the deficiencies of the above-mentioned prior art and proposes an economic scheduling method, device and storage medium that take into account the controllable risk of energy storage, so as to provide a scheduling plan and an optimal power abandonment plan under the condition of considering the uncertainty of renewable energy to ensure that the safety risk of the system is controllable, thereby improving the reliability and stability of the system operation.
[0004] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme:
[0005] The risk-controllable economic dispatch method considering energy storage of the present invention is characterized in that it is applied to a system consisting of a thermal power unit, a renewable power source, an energy storage device and a load, and comprises the following steps:
[0006] Step 1: According to the power abandonment strategy, obtain the available power generation of all renewable power sources in period t The actual power generation ;in, represents the available power generation of renewable power at the jth node in period t, represents the actual power generation of the renewable power source at the jth node in period t, and , represents the power curtailment strategy function of the renewable power source at the jth node in period t, represents the adjustable parameters of the power curtailment strategy of renewable power sources at the jth node in period t;
[0007] Step 2: Based on the uncertainty of renewable energy and the characteristics of energy storage equipment, a probabilistic economic dispatch model with controllable risks of energy storage is established, including: objective function, deterministic constraints and two types of controllable risk opportunity constraints;
[0008] Step 3: Consider whether the system needs to abandon power in each period, and establish an optimization model for abandonment period with controllable risk of energy storage, including: an objective function of minimizing the weighted sum of quantile changes and a relaxation constraint with quantiles;
[0009] Step 4: Consider the optimal power curtailment plan of the system during the power curtailment period, and establish a risk-controllable power curtailment plan optimization model considering energy storage, including: an objective function of minimizing the sum of power curtailment penalty functions and a quantile change constraint;
[0010] Step 5: According to the probabilistic economic dispatch model, the power abandonment period optimization model and the power abandonment plan optimization model, a mixed integer programming solver is used to obtain the optimal dispatch plan for all time periods of the system.
[0011] The risk-controllable economic dispatch method considering energy storage described in the present invention is also characterized in that the step 2 comprises:
[0012] Step 2.1: Use formula (1) to construct an objective function that minimizes the total resource consumption of the system:
[0013] (1)
[0014] In formula (1), represents the number of time periods for the economic dispatch plan; Indicates the number of thermal power units in the system; represents the power generation fuel consumption of the thermal power unit at the i-th node in period t, and is obtained by formula (2); represents the reserve capacity consumption of the thermal power unit at the i-th node in period t, and is obtained by formula (3); Indicates the number of renewable power sources in the system; represents the power abandonment penalty of renewable power source at the jth node in period t, and is obtained by formula (4);
[0015] (2)
[0016] In formula (2), , and They represent the quadratic coefficient, linear coefficient and constant term of the power generation consumption of the thermal power unit at the i-th node respectively; represents the planned power generation of the thermal power unit at the i-th node in period t;
[0017] (3)
[0018] In formula (3), , They represent the upward reserve consumption coefficient and downward reserve consumption coefficient of the thermal power unit at the i-th node respectively; , They represent the upward reserve capacity and downward reserve capacity of the thermal power unit at the i-th node in period t respectively;
[0019] (4)
[0020] In formula (4), represents the power abandonment penalty coefficient of the renewable power source at the jth node; represents the installed capacity of renewable power at the jth node; represents the probability density function of the available power generation of renewable power at the jth node in period t; x represents the random variable The value of
[0021] Step 2.2: Determine the deterministic constraints of the probabilistic economic dispatch model, including:
[0022] Step 2.2.1: Use formula (5) to construct the power balance constraint:
[0023] (5)
[0024] In formula (5), represents the planned power generation of renewable power at the jth node in period t; Indicates the number of energy storage devices in the system; represents the charging and discharging power of the energy storage device at the mth node in time period t; Indicates the number of loads in the system; represents the power consumption of the load at the nth node in time period t;
[0025] Step 2.2.2: Use equations (6) to (9) to construct the power generation output and reserve capacity constraints of thermal power units:
[0026] (6)
[0027] (7)
[0028] (8)
[0029] (9)
[0030] In formula (6) to formula (9), , They represent the maximum power generation and minimum power generation of the thermal power unit at the i-th node respectively; , They represent the maximum upward reserve capacity and the maximum downward reserve capacity reserved for the thermal power unit at the i-th node respectively;
[0031] Step 2.2.3: Use equations (10) and (11) to construct the ramp constraints of the thermal power unit:
[0032] (10)
[0033] (11)
[0034] In formula (10)-formula (11), Indicated in The power generation of the thermal power unit at the i-th node in the time period; , They represent the upward climbing rate and downward climbing rate of the thermal power unit at the i-th node respectively; Indicates the time interval between adjacent time periods;
[0035] Step 2.2.4: Use equation (12) to construct the power constraint of renewable power source:
[0036] (12)
[0037] In formula (12), represents the expected value of the power generation power of the renewable power source at the jth node in period t;
[0038] Step 2.2.5: Use equations (13) to (16) to construct the power constraints of the energy storage device:
[0039] (13)
[0040] (14)
[0041] (15)
[0042] (16)
[0043] In formula (13) to formula (16), , are auxiliary binary variables representing the charging and discharging at the mth node in period t, respectively; , They represent the discharge power and charging power of the energy storage device at the mth node in time period t respectively; , They represent the minimum charging and discharging power and the maximum charging and discharging power allowed by the energy storage device at the mth node respectively; Indicated in The charging and discharging power of the energy storage device at the mth node in the time period; represents the maximum variable power specified by the energy storage device at the mth node;
[0044] Step 2.2.6: Use equations (17) to (19) to construct the energy constraints of the energy storage device:
[0045] (17)
[0046] (18)
[0047] (19)
[0048] In formula (17) to formula (19), Indicated in The initial energy of the energy storage device at the mth node in the time period; represents the energy of the energy storage device at the mth node in time period t; , , They represent the self-discharge efficiency, charging efficiency and discharge efficiency of the energy storage device at the mth node respectively; represents the installed capacity of the energy storage device at the mth node;
[0049] Step 2.3: Determine two types of risk-controllable opportunity constraints for the probabilistic economic dispatch model, including:
[0050] Step 2.3.1: Use equations (20) and (21) to construct an affine regulation strategy for the power generation of thermal power units:
[0051] (20)
[0052] (twenty one)
[0053] In formula (20)-formula (21), represents the actual power generation of the thermal power unit at the i-th node in period t; represents the participation coefficient of the thermal power unit at the i-th node;
[0054] Step 2.3.2: Use equations (22) and (23) to construct the affine adjustment reserve capacity constraint:
[0055] (twenty two)
[0056] (twenty three)
[0057] In formula (22)-formula (23), represents the probability that the safety constraint is established; , They represent the preset allowable risk levels of upward reserve capacity shortage and downward reserve capacity shortage respectively;
[0058] Step 2.3.3: Use equations (24) to (26) to construct the cross-section transmission power constraint:
[0059] (twenty four)
[0060] (25)
[0061] (26)
[0062] In formula (24) to formula (26), Indicates that in time period t The actual transmission power of each section; Indicates The maximum transmission capacity of each section; Indicates The permissible overload risk level for each section; , , , Respectively represent The power transfer distribution factor of each section relative to the bus at the i-th node, the j-th node, the m-th node and the n-th node.
[0063] The step three comprises:
[0064] Step 3.1: Use equations (27) and (28) to construct an equivalent form of the affine regulation reserve capacity constraint with quantiles:
[0065] (27)
[0066] (28)
[0067] In formula (27)-formula (28), represents the quantile in period t;
[0068] Step 3.2: Use equations (29) to (33) to construct an equivalent form of the cross-sectional transmission power constraint with quantiles:
[0069] (29)
[0070] (30)
[0071] (31)
[0072] (32)
[0073] (33)
[0074] In formula (29) to formula (33), Indicates that in time period t The planned transmission power of each section; represents the affine adjustment strategy for the The correction amount of the power transfer distribution factor of each section; Indicates The equivalent power transfer distribution factor of the section relative to the actual power generation of the renewable power source at the jth node;
[0075] Step 3.3: Use equations (34) to (39) to construct a relaxed constraint with quantiles:
[0076] (34)
[0077] (35)
[0078] (36)
[0079] (37)
[0080] (38)
[0081] (39)
[0082] In formula (34) to formula (39), represents the quantile change of downward reserve constraint in period t; , Respectively represent the The quantile changes of the forward and reverse constraints of each section;
[0083] Step 3.4: Use formula (40) to construct an objective function that minimizes the weighted sum of quantile changes:
[0084] (40)
[0085] In formula (40), The weight coefficient representing the quantile change of downward adjustment of reserve constraints in period t; Indicates the number of sections in the system; Represents the weight coefficient of the quantile change of the lth section constraint in time period t.
[0086] The fourth step comprises:
[0087] Step 4.1: Use equation (41)-equation (42) to construct the upper bound of the power generation of renewable power sources:
[0088] (41)
[0089] (42)
[0090] In formula (41)-formula (42), represents the upper bound of the power generation of the renewable power source at the jth node in period t; Represents the set of serial numbers of renewable power sources participating in power abandonment during period t;
[0091] Step 4.2: Use equations (43) to (45) to construct the quantile change constraint:
[0092] (43)
[0093] (44)
[0094] (45)
[0095] Step 4.3: Use equations (46) and (47) to construct an objective function that minimizes the sum of the power abandonment penalty functions:
[0096] (46)
[0097] (47).
[0098] The step five comprises:
[0099] Step 5.1, use a mixed integer linear programming solver to optimize and solve the power abandonment period optimization model in step 3, and obtain the power abandonment period and the required quantile change. If there is no power abandonment period, directly proceed to step 5.3;
[0100] Step 5.2: For each period of time when power is to be abandoned, use a mixed integer nonlinear programming solver to optimize and solve the power abandonment plan optimization model of step 4 to obtain the optimal power abandonment plan of renewable energy in all periods;
[0101] Step 5.3: According to the optimal power curtailment plan of renewable energy in all power curtailment periods, the probability distribution of the actual power generation probability of all renewable power sources is obtained, and the probability distribution is substituted into the opportunity constraint of the probabilistic economic dispatch model in step 2 to calculate the quantile, thereby converting the opportunity constraint into a linear constraint;
[0102] Step 5.4: Use a mixed integer linear programming solver to optimize and solve the probabilistic economic dispatch model after linear constraints to obtain the optimal dispatch plan for all time periods of the system.
[0103] The electronic device of the present invention includes a memory and a processor, wherein the memory is used to store a program that supports the processor to execute the economic dispatch method, and the processor is configured to execute the program stored in the memory.
[0104] The present invention provides a computer-readable storage medium, wherein a computer program is stored on the computer-readable storage medium, and the computer program executes the steps of the economic dispatch method when executed by a processor.
[0105] Compared with the prior art, the present invention has the following beneficial effects:
[0106] 1. The present invention is aimed at a system composed of thermal power units, renewable power sources and energy storage devices, and comprehensively considers the characteristics and uncertainties of various types of power sources, making the scheduling method more comprehensive and accurate. By introducing the power abandonment strategy function and adjustable parameters, it can flexibly respond to the changes in renewable energy generation under different circumstances, minimize the amount of abandoned electricity, improve the utilization rate of renewable energy, reduce energy waste, and construct the constraints of thermal power units, renewable power sources and energy storage devices in detail, ensuring the completeness and rationality of the scheduling model.
[0107] 2. The present invention constructs a probabilistic economic dispatch model that takes into account the controllable risks of energy storage, adopts two types of risk-controllable opportunity constraints, ensures the safety and stability of system operation, and establishes a power abandonment period optimization model and a power abandonment plan optimization model to minimize the weighted sum of quantile changes and the sum of power abandonment penalty functions, thereby optimizing the power abandonment plan and reducing the system operation risk. In addition, a mixed integer linear programming solver and a nonlinear programming solver are used to solve the power abandonment period optimization model and the power abandonment plan optimization model, respectively, which improves the solution efficiency and ensures that the optimal scheduling plan of the system can be quickly obtained. BRIEF DESCRIPTION OF THE DRAWINGS
[0108] Figure 1 A flow chart of an economic dispatch method considering risk controllable energy storage according to the present invention;
[0109] Figure 2 It is a schematic diagram of the renewable power source abandonment plan of the present invention. DETAILED DESCRIPTION
[0110] In this embodiment, a risk-controllable economic dispatch method considering energy storage is applied to a system consisting of a thermal power unit, a renewable power source and an energy storage device, such as Figure 1 As shown, the main steps of the system include:
[0111] Step 1: According to the power abandonment strategy, obtain the available power generation of all renewable power sources in period t The actual power generation ;in, represents the available power generation of renewable power at the jth node in period t, represents the actual power generation of the renewable power source at the jth node in period t, and , represents the power curtailment strategy function of the renewable power source at the jth node in period t, represents the adjustable parameters of the power curtailment strategy of the renewable power source at the jth node in period t.
[0112] Step 2: Based on the uncertainty of renewable energy and the characteristics of energy storage equipment, a probabilistic economic dispatch model with controllable risks of energy storage is established, including: objective function, deterministic constraints and two types of risk-controllable opportunity constraints.
[0113] Step 2.1: Use formula (1) to construct an objective function that minimizes the total resource consumption of the system:
[0114] (1)
[0115] In formula (1), represents the number of time periods for the economic dispatch plan; Indicates the number of thermal power units in the system; represents the power generation fuel consumption of the thermal power unit at the i-th node in period t, and is obtained by formula (2); represents the reserve capacity consumption of the thermal power unit at the i-th node in period t, and is obtained by formula (3); Indicates the number of renewable power sources in the system; represents the power abandonment penalty of renewable power source at the jth node in period t, and is obtained by formula (4);
[0116] (2)
[0117] In formula (2), , and They represent the quadratic coefficient, linear coefficient and constant term of the power generation consumption of the thermal power unit at the i-th node respectively; represents the planned power generation of the thermal power unit at the i-th node in period t; when the thermal power unit is turned on ( ), fuel consumption is related to the unit's power generation A quadratic function; when the thermal power unit is shut down ( ), fuel consumption equals 0;
[0118] (3)
[0119] In formula (3), , They represent the upward reserve consumption coefficient and downward reserve consumption coefficient of the thermal power unit at the i-th node respectively; , They represent the upward reserve capacity and downward reserve capacity of the thermal power unit at the i-th node in period t respectively;
[0120] (4)
[0121] In formula (4), represents the power abandonment penalty coefficient of the renewable power source at the jth node; represents the installed capacity of renewable power at the jth node; represents the probability density function of the available power generation of renewable power at the jth node in period t; x represents the random variable The value of .
[0122] Step 2.2: Determine the deterministic constraints of the probabilistic economic dispatch model, including:
[0123] Step 2.2.1: Use formula (5) to construct the power balance constraint:
[0124] (5)
[0125] In formula (5), represents the planned power generation of renewable power at the jth node in period t; Indicates the number of energy storage devices in the system; represents the charging and discharging power of the energy storage device at the mth node in time period t; Indicates the number of loads in the system; Represents the power consumption of the load at the nth node in time period t.
[0126] Step 2.2.2: Use equations (6) to (9) to construct the power generation output and reserve capacity constraints of thermal power units:
[0127] (6)
[0128] (7)
[0129] (8)
[0130] (9)
[0131] In formula (6) to formula (9), , They represent the maximum power generation and minimum power generation of the thermal power unit at the i-th node respectively; , They respectively represent the maximum upward reserve capacity and the maximum downward reserve capacity reserved for the thermal power unit at the i-th node.
[0132] Step 2.2.3: Use equations (10) and (11) to construct the ramp constraints of the thermal power unit:
[0133] (10)
[0134] (11)
[0135] In formula (10)-formula (11), Indicated in The power generation of the thermal power unit at the i-th node in the time period; , They represent the upward climbing rate and downward climbing rate of the thermal power unit at the i-th node respectively; Indicates the time interval between adjacent time periods.
[0136] Step 2.2.4: Use equation (12) to construct the power constraint of renewable power source:
[0137] (12)
[0138] In formula (12), It represents the expected value of the power generation of the renewable power source at the jth node in period t.
[0139] Step 2.2.5: Use equations (13) to (16) to construct the power constraints of the energy storage device:
[0140] (13)
[0141] (14)
[0142] (15)
[0143] (16)
[0144] In formula (13) to formula (16), , The auxiliary binary variables represent the charging and discharging at the mth node in period t, respectively. The constraint ensures that the charging and discharging of the energy storage device will not be performed at the same time; , They represent the discharge power and charging power of the energy storage device at the mth node in time period t respectively; , They represent the minimum and maximum charging and discharging powers allowed by the energy storage device at the mth node, respectively, to ensure that the power flowing to the energy storage device remains within the allowable range specified by the manufacturer; Indicated in The charging and discharging power of the energy storage device at the mth node in the time period; Indicates the maximum variable power specified for the energy storage device at the mth node to avoid possible damage to the energy storage device.
[0145] Step 2.2.6: Use equations (17) to (19) to construct the energy constraints of the energy storage device:
[0146] (17)
[0147] (18)
[0148] (19)
[0149] In formula (17) to formula (19), Indicated in The initial energy of the energy storage device at the mth node in the time period; represents the energy of the energy storage device at the mth node in time period t; , , They represent the self-discharge efficiency, charging efficiency and discharge efficiency of the energy storage device at the mth node respectively; Represents the installed capacity of the energy storage device at the mth node.
[0150] Step 2.3: Determine two types of risk-controllable opportunity constraints for the probabilistic economic dispatch model, including:
[0151] Step 2.3.1: Use equations (20) and (21) to construct an affine regulation strategy for the power generation of thermal power units:
[0152] (20)
[0153] (twenty one)
[0154] In formula (20)-formula (21), represents the actual power generation of the thermal power unit at the i-th node in period t, and the actual power generation of the thermal power unit is Alternative planned power generation , considering the influence of affine adjustment on the cross-section transmission power; Represents the participation coefficient of the thermal power unit at the i-th node, in order to cope with the actual power generation of renewable energy Planned power generation The power deviation between them maintains the system power balance and the actual power generation power of the thermal power unit. In the planned power generation On the basis of participating in bearing part of the power imbalance.
[0155] Step 2.3.2: Use equations (22) and (23) to construct the affine adjustment reserve capacity constraint:
[0156] (twenty two)
[0157] (twenty three)
[0158] In formula (22)-formula (23), represents the probability that the safety constraint is established; , They respectively represent the preset allowable risk levels of upward and downward reserve capacity shortage.
[0159] Step 2.3.3: Use equations (24) to (26) to construct the cross-section transmission power constraint:
[0160] (twenty four)
[0161] (25)
[0162] (26)
[0163] In formula (24) to formula (26), Indicates that in time period t The actual transmission power of each section is the contribution of the actual power generation of thermal power units, the contribution of the actual power generation of renewable power sources, the contribution of energy storage equipment power and the contribution of load power. Representation of cross section The maximum transmission capacity of Indicates The permissible overload risk level for each section; , , , Respectively represent The power transfer distribution factor of each section relative to the bus at the ith node, the jth node, the mth node and the nth node is calculated based on the network topology and parameters.
[0164] Step 3: Consider whether the system needs to abandon power in each period, and establish an optimization model for abandonment period with controllable risk of energy storage, including: the objective function of minimizing the weighted sum of quantile changes and relaxation constraints with quantiles.
[0165] Step 3.1: Use equations (27) and (28) to construct an equivalent form of the affine regulation reserve capacity constraint with quantiles:
[0166] (27)
[0167] (28)
[0168] In formula (27)-formula (28), represents the quantile in time period t.
[0169] Step 3.2: Use equations (29) to (33) to construct an equivalent form of the cross-sectional transmission power constraint with quantiles:
[0170] (29)
[0171] (30)
[0172] (31)
[0173] (32)
[0174] (33)
[0175] In formula (29) to formula (33), Indicates that in time period t The planned transmission power of each section is the contribution of the planned power generation of thermal power units, the contribution of the planned power generation of renewable power sources, the contribution of energy storage equipment power and the contribution of load power. represents the affine adjustment strategy for the The correction amount of the power transfer distribution factor of each section; It means that after considering the affine adjustment correction, The equivalent power transfer distribution factor of the j-th section relative to the actual generated power of the renewable power source at the j-th node.
[0176] Step 3.3: Use equations (34) to (39) to construct a relaxed constraint with quantiles:
[0177] (34)
[0178] (35)
[0179] (36)
[0180] (37)
[0181] (38)
[0182] (39)
[0183] In formula (34) to formula (39), represents the quantile change of downward reserve constraint in period t; , Respectively represent the The quantile changes of the positive and negative constraints of each section reflect the impact of power abandonment on the feasible domain of opportunity constraints, and are also the relaxation of opportunity constraints under the assumption of no power abandonment.
[0184] Step 3.4: Use formula (40) to construct an objective function that minimizes the weighted sum of quantile changes:
[0185] (40)
[0186] In formula (40), The weight coefficient representing the quantile change of downward adjustment of reserve constraints in period t; Indicates the number of sections in the system; Represents the weight coefficient of the quantile change of the lth section constraint in time period t.
[0187] Step 4: Consider the optimal power curtailment plan of the system during the power curtailment period. For any period t during which power curtailment is required, there is an infeasible constraint within the period, namely, the quantile change , , Non-zero, a risk-controlled power curtailment optimization model considering energy storage is established, including: the objective function of minimizing the sum of power curtailment penalty functions and the quantile change constraint.
[0188] Step 4.1: According to Figure 2 As shown in Figure 4, when the actual power generation of renewable energy far exceeds the planned reference value, the excess power generation cannot be absorbed. In order to maintain the balance between power generation and supply, the power abandonment plan gives the upper limit of the power generation of each renewable power source. The part exceeding the planned reference value generates potential power abandonment. The upper limit of the power generation of renewable power sources is constructed using equations (41) and (42):
[0189] (41)
[0190] (42)
[0191] In formula (41)-formula (42), represents the upper bound of the power generation of the renewable power source at the jth node in period t; It represents the set of renewable power source numbers participating in power curtailment in period t. This set can be automatically selected according to the infeasible constraints of the period, or it can be manually selected by the dispatcher as a known input.
[0192] Step 4.2: Use equation (43)-(44) to construct an objective function with the goal of minimizing the sum of the power abandonment penalty functions:
[0193] (43)
[0194] (44)
[0195] Step 4.3: Use equations (45) to (47) to construct the quantile change constraint:
[0196] (45)
[0197] (46)
[0198] (47)
[0199] Step 5: According to the probabilistic economic dispatch model, the power abandonment period optimization model and the power abandonment plan optimization model, a mixed integer programming solver is used to obtain the optimal dispatch plan for all time periods of the system.
[0200] Step 5.1, use a mixed integer linear programming solver to optimize and solve the power abandonment period optimization model in step 3, and obtain the power abandonment period and the required quantile change. If there is no power abandonment period, directly proceed to step 5.3;
[0201] Step 5.2: For each period of time when power is to be abandoned, use a mixed integer nonlinear programming solver to optimize and solve the power abandonment plan optimization model of step 4 to obtain the optimal power abandonment plan of renewable energy in all periods;
[0202] Step 5.3: According to the optimal power curtailment plan of renewable energy in all power curtailment periods, the probability distribution of the actual power generation probability of all renewable power sources is obtained, and the probability distribution is substituted into the opportunity constraint of the probabilistic economic dispatch model in step 2 to calculate the quantile, thereby converting the opportunity constraint into a linear constraint;
[0203] Step 5.4: Use a mixed integer linear programming solver to optimize and solve the probabilistic economic dispatch model after linear constraints to obtain the optimal dispatch plan for all time periods of the system.
[0204] In this embodiment, an electronic device includes a memory and a processor, wherein the memory is used to store a program that supports the processor to execute the above method, and the processor is configured to execute the program stored in the memory.
[0205] In this embodiment, a computer-readable storage medium stores a computer program on the computer-readable storage medium, and the computer program executes the steps of the above method when executed by a processor.
Claims
1. A risk-controllable economic dispatch method considering energy storage, characterized in that: It is applied to a system consisting of thermal power units, renewable power sources, energy storage equipment and loads, and includes the following steps: Step 1: According to the power abandonment strategy, obtain the available power generation of all renewable power sources in period t The actual power generation ;in, represents the available power generation of renewable power at the jth node in period t, represents the actual power generation of the renewable power source at the jth node in period t, and , represents the power curtailment strategy function of the renewable power source at the jth node in period t, represents the adjustable parameters of the power curtailment strategy of renewable power sources at the jth node in period t; Step 2: Based on the uncertainty of renewable energy and the characteristics of energy storage equipment, a probabilistic economic dispatch model with controllable risks of energy storage is established, including: objective function, deterministic constraints and two types of controllable risk opportunity constraints; Step 3: Consider whether the system needs to abandon power in each period, and establish an optimization model for abandonment period with controllable risk of energy storage, including: an objective function of minimizing the weighted sum of quantile changes and a relaxation constraint with quantiles; Step 4: Consider the optimal power curtailment plan of the system during the power curtailment period, and establish a risk-controllable power curtailment plan optimization model considering energy storage, including: an objective function of minimizing the sum of power curtailment penalty functions and a quantile change constraint; Step 5: According to the probabilistic economic dispatch model, the power abandonment period optimization model and the power abandonment plan optimization model, a mixed integer programming solver is used to obtain the optimal dispatch plan for all time periods of the system.
2. The risk-controllable economic dispatch method considering energy storage as claimed in claim 1, characterized in that: The second step comprises: Step 2.1: Use formula (1) to construct an objective function that minimizes the total resource consumption of the system: (1) In formula (1), represents the number of time periods for the economic dispatch plan; Indicates the number of thermal power units in the system; represents the power generation fuel consumption of the thermal power unit at the i-th node in period t, and is obtained by formula (2); represents the reserve capacity consumption of the thermal power unit at the i-th node in period t, and is obtained by formula (3); Indicates the number of renewable power sources in the system; represents the power abandonment penalty of renewable power source at the jth node in period t, and is obtained by formula (4); (2) In formula (2), , and They represent the quadratic coefficient, linear coefficient and constant term of the power generation consumption of the thermal power unit at the i-th node respectively; represents the planned power generation of the thermal power unit at the i-th node in period t; (3) In formula (3), , They represent the upward reserve consumption coefficient and downward reserve consumption coefficient of the thermal power unit at the i-th node respectively; , They represent the upward reserve capacity and downward reserve capacity of the thermal power unit at the i-th node in period t respectively; (4) In formula (4), represents the power abandonment penalty coefficient of the renewable power source at the jth node; represents the installed capacity of renewable power at the jth node; represents the probability density function of the available power generation of renewable power at the jth node in period t; x represents the random variable The value of Step 2.2: Determine the deterministic constraints of the probabilistic economic dispatch model, including: Step 2.2.1: Use formula (5) to construct the power balance constraint: (5) In formula (5), represents the planned power generation of renewable power at the jth node in period t; Indicates the number of energy storage devices in the system; represents the charging and discharging power of the energy storage device at the mth node in time period t; Indicates the number of loads in the system; represents the power consumption of the load at the nth node in time period t; Step 2.2.2: Use equations (6) to (9) to construct the power generation output and reserve capacity constraints of thermal power units: (6) (7) (8) (9) In formula (6) to formula (9), , They represent the maximum power generation and minimum power generation of the thermal power unit at the i-th node respectively; , They represent the maximum upward reserve capacity and the maximum downward reserve capacity reserved for the thermal power unit at the i-th node respectively; Step 2.2.3: Use equations (10) and (11) to construct the ramp constraints of the thermal power unit: (10) (11) In formula (10)-formula (11), Indicated in The power generation of the thermal power unit at the i-th node in the time period; , They represent the upward climbing rate and downward climbing rate of the thermal power unit at the i-th node respectively; Indicates the time interval between adjacent time periods; Step 2.2.4: Use equation (12) to construct the power constraint of renewable power source: (12) In formula (12), represents the expected value of the power generation power of the renewable power source at the jth node in period t; Step 2.2.5: Use equations (13) to (16) to construct the power constraints of the energy storage device: (13) (14) (15) (16) In formula (13) to formula (16), , are auxiliary binary variables representing the charging and discharging at the mth node in period t, respectively; , They represent the discharge power and charging power of the energy storage device at the mth node in time period t respectively; , They represent the minimum charging and discharging power and the maximum charging and discharging power allowed by the energy storage device at the mth node respectively; Indicated in The charging and discharging power of the energy storage device at the mth node in the time period; represents the maximum variable power specified by the energy storage device at the mth node; Step 2.2.6: Use equations (17) to (19) to construct the energy constraints of the energy storage device: (17) (18) (19) In formula (17) to formula (19), Indicated in The initial energy of the energy storage device at the mth node in the time period; represents the energy of the energy storage device at the mth node in time period t; , , They represent the self-discharge efficiency, charging efficiency and discharge efficiency of the energy storage device at the mth node respectively; represents the installed capacity of the energy storage device at the mth node; Step 2.3: Determine two types of risk-controllable opportunity constraints for the probabilistic economic dispatch model, including: Step 2.3.1: Use equations (20) and (21) to construct an affine regulation strategy for the power generation of thermal power units: (20) (21) In formula (20)-formula (21), represents the actual power generation of the thermal power unit at the i-th node in period t; represents the participation coefficient of the thermal power unit at the i-th node; Step 2.3.2: Use equations (22) and (23) to construct the affine adjustment reserve capacity constraint: (22) (23) In formula (22)-formula (23), represents the probability that the safety constraint is established; , They represent the preset allowable risk levels of upward reserve capacity shortage and downward reserve capacity shortage respectively; Step 2.3.3: Use equations (24) to (26) to construct the cross-section transmission power constraint: (24) (25) (26) In formula (24) to formula (26), Indicates that in time period t The actual transmission power of each section; Indicates The maximum transmission capacity of each section; Indicates The permissible overload risk level for each section; , , , Respectively represent The power transfer distribution factor of each section relative to the bus at the i-th node, the j-th node, the m-th node and the n-th node.
3. The risk-controllable economic dispatch method considering energy storage as claimed in claim 2, characterized in that: The step three comprises: Step 3.1: Use equations (27) and (28) to construct an equivalent form of the affine regulation reserve capacity constraint with quantiles: (27) (28) In formula (27)-formula (28), represents the quantile in period t; Step 3.2: Use equations (29) to (33) to construct an equivalent form of the cross-sectional transmission power constraint with quantiles: (29) (30) (31) (32) (33) In formula (29) to formula (33), Indicates that in time period t The planned transmission power of each section; represents the affine adjustment strategy for the The correction amount of the power transfer distribution factor of each section; Indicates The equivalent power transfer distribution factor of the section relative to the actual power generation of the renewable power source at the jth node; Step 3.3: Use equations (34) to (39) to construct a relaxed constraint with quantiles: (34) (35) (36) (37) (38) (39) In formula (34) to formula (39), represents the quantile change of downward reserve constraint in period t; , Respectively represent the The quantile changes of the forward and reverse constraints of each section; Step 3.4: Use formula (40) to construct an objective function that minimizes the weighted sum of quantile changes: (40) In formula (40), The weight coefficient representing the quantile change of downward adjustment of reserve constraints in period t; Indicates the number of sections in the system; Represents the weight coefficient of the quantile change of the lth section constraint in time period t.
4. The risk-controllable economic dispatch method considering energy storage as claimed in claim 3, characterized in that: The fourth step comprises: Step 4.1: Use equation (41)-equation (42) to construct the upper bound of the power generation of renewable power sources: (41) (42) In formula (41)-formula (42), represents the upper bound of the power generation of the renewable power source at the jth node in period t; Represents the set of serial numbers of renewable power sources participating in power abandonment during period t; Step 4.2: Use equations (43) to (45) to construct the quantile change constraint: (43) (44) (45) Step 4.3: Use equations (46) and (47) to construct an objective function that minimizes the sum of the power abandonment penalty functions: (46) (47)。 5. The risk-controllable economic dispatch method considering energy storage as claimed in claim 1, characterized in that: The step five comprises: Step 5.1, use a mixed integer linear programming solver to optimize and solve the power abandonment period optimization model in step 3, and obtain the power abandonment period and the required quantile change. If there is no power abandonment period, directly proceed to step 5.3; Step 5.2: For each period of time when power is to be abandoned, use a mixed integer nonlinear programming solver to optimize and solve the power abandonment plan optimization model of step 4 to obtain the optimal power abandonment plan of renewable energy in all periods; Step 5.3: According to the optimal power curtailment plan of renewable energy in all power curtailment periods, the probability distribution of the actual power generation probability of all renewable power sources is obtained, and the probability distribution is substituted into the opportunity constraint of the probabilistic economic dispatch model in step 2 to calculate the quantile, thereby converting the opportunity constraint into a linear constraint; Step 5.4: Use a mixed integer linear programming solver to optimize and solve the probabilistic economic dispatch model after linear constraints to obtain the optimal dispatch plan for all time periods of the system.
6. An electronic device, comprising a memory and a processor, characterized in that: The memory is used to store a program that supports the processor to execute the economic dispatch method described in any one of claims 1 to 5, and the processor is configured to execute the program stored in the memory.
7. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the economic dispatch method according to any one of claims 1 to 5 are executed.