Small-span prefabricated segment T beam structure and construction method thereof
Through welding technology and waterproof coating filled T-beam segment structure, the problem of insufficient bonding strength in the splicing of T-beams with prefabricated segments is solved, rapid splicing and efficient construction are achieved, and shear bearing capacity and overall structure are improved. seismic resistance.
Patent Information
- Application Number
- CN202411136289.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-19
- Publication Date
- 2024-11-15
AI Technical Summary
The small span prefabricated segment T beam has the problem of insufficient bonding strength during the splicing process, resulting in poor structural integrity and seismic resistance. The traditional bonding method has deteriorated joint performance due to colloid aging, which affects the service life of the bridge.
Multiple prefabricated T-beam segments are quickly spliced through welding technology, using the T-shaped design of the front splicing plate and the rear splicing plate and the segment steel cage and the metal corrugated pipe structure, combined with waterproof coating and epoxy resin filling, forming a reliable The overall stress system is used to achieve rapid splicing by connecting bumps and grooves.
It realizes rapid splicing, improves construction efficiency, enhances shear bearing capacity, reduces temperature stress, extends the service life of the joints, and reduces transportation costs.
Smart Images

Figure CN118958118A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of segmental prefabricated bridge construction, and in particular to a small-span prefabricated segmental T-beam structure. Background Art
[0002] With the pursuit of green, low-carbon and sustainable development in modern society, segmental prefabrication and assembly bridge technology has been favored for its high-quality, high-efficiency and environmentally friendly construction. This technology follows the core concept of "distributed prefabrication, integrated assembly", divides the entire bridge into multiple segments, and transports them to the construction site for assembly after prefabrication in the factory. Under the joint action of prestress and shear keys, the prefabricated segmental beams form the overall structure of the bridge, which has greatly promoted the modernization and industrialization of bridge construction.
[0003] In segmental prefabricated bridges, joint treatment is a crucial link in the construction process of the entire bridge, which is directly related to the overall structural safety and service life of the bridge. In order to improve the integrity and seismic performance of the joints, the joints need to have certain tensile strength and shear strength; and considering the linear control of the structure during bridge construction, the joint construction cycle should not be too long, and the joint quality should be reliable and controllable. At present, epoxy resin synthetic adhesives are used to glue the joint sections in segmental prefabricated bridges. Although the gluing method can compensate for the uneven surface of the concrete joints and reduce the influence of hydration heat in the early stage, as the service life of the bridge structure increases, the aging of the colloid leads to the degradation of joint performance, which restricts the further development of segmental prefabricated bridges.
[0004] For small-span T-beam bridges, the advantage is that they can reduce the deadweight of the structure by reducing the concrete in the tension zone while ensuring a high load-bearing capacity. However, since the T-beam section reduces the concrete area in the tension zone, this is bound to affect the bonding strength of the joints during the segment prefabrication process. Therefore, in order to implement efficient and reliable segment prefabrication splicing technology in small-span T-beam bridges and effectively improve the problems existing in traditional adhesive joints, it is necessary to propose a rapid splicing construction technology for small-span prefabricated segment T-beams, which is suitable for the splicing of small-span prefabricated segment T-beams. Summary of the invention
[0005] In view of the shortcomings of the background technology, the technical problem to be solved by the present invention is to provide a small-span prefabricated segmental T-beam structure that can achieve rapid splicing, and to efficiently and reliably realize the prefabricated segmental T-beam splicing construction process.
[0006] The present invention is completed by adopting the following technical scheme: a small-span prefabricated segmental T-beam structure, which is composed of multiple prefabricated T-beam segments connected in sequence, the T-beam segment includes a front splicing plate, a rear splicing plate and a segmental steel cage, the front splicing plate and the rear splicing plate are respectively welded and fixed on both sides of the segmental steel cage, a plurality of metal corrugated pipes are reserved in the segmental steel cage, the front splicing plate and the rear splicing plate both have reserved holes adapted to the metal corrugated pipes, the segmental steel cage is formed by pouring concrete to form a concrete layer, the front splicing plate and the rear splicing plate are exposed in the concrete layer, when splicing, the rear splicing plate of the T-beam segment is aligned and spliced with the front splicing plate of its adjacent T-beam segment, and are welded and fixed along the outer periphery of the joint.
[0007] Furthermore, the segment steel cage is composed of a plurality of longitudinal steel bars and segment stirrups.
[0008] Furthermore, the welding points at the outer periphery of the seams are filled with waterproof coating and epoxy resin.
[0009] Furthermore, the outer end surface of the front splicing plate has a plurality of docking protrusions, and the outer end surface of the rear splicing plate has docking grooves matching the docking protrusions. When the T-beam segments are spliced, the docking protrusions of the front splicing plate are inserted into the docking grooves of the rear splicing plate of the adjacent T-beam segments.
[0010] Furthermore, the front splicing plate, the rear splicing plate and the segment reinforcement cage are all T-shaped in cross-section.
[0011] Beneficial effects of the present invention:
[0012] (1) By providing an end splicing plate with a butt protrusion and a butt groove on the prefabricated T-beam segment, the prefabricated T-beam segment can be quickly spliced, thereby saving the construction period of the prefabricated T-beam segment splicing.
[0013] (2) Welding technology is used to effectively splice the front and rear prefabricated T-beam segments to form a reliable overall force-bearing system, which can improve the problem of decreased integrity caused by colloid aging in traditional adhesive bonding methods.
[0014] (3) By applying waterproof coating and epoxy resin to the outside of the weld for filling treatment, its function is equivalent to the expansion joint in bridge engineering, which can reduce the temperature stress caused by temperature changes in the concrete of the precast T-beam segment and reduce the stress concentration caused by temperature gradient changes at the splicing position of the precast T-beam segment.
[0015] (4) By introducing the end splicing plate into the steel cage of the precast T-beam segment, the reinforcement ratio of the steel cage in the cross section of the precast T-beam segment is increased, which can effectively improve the shear bearing capacity of the precast segment T-beam, thereby reducing the use of shear stirrups in the precast T-beam segment.
[0016] (5) By casting and curing T-beam segments in the prefabrication plant and transporting them to the bridge construction site for splicing after they reach the required age, the concrete casting quality of the prefabricated T-beam segments can be ensured. At the same time, the small-span T-beam segments are easy to transport, which can reduce the transportation cost during the construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] The present invention has the following accompanying drawings:
[0018] Figure 1 It is a structural schematic diagram of a first embodiment of a small-span prefabricated segmental T-beam structure;
[0019] Figure 2 for Figure 1 Structural diagram of the middle T-beam segment frame;
[0020] Figure 3 It is a schematic diagram of the process of constructing a small-span prefabricated segmental T-beam;
[0021] Figure 4 It is a schematic cross-sectional structure diagram of a splicing position of a first embodiment of a small-span prefabricated segmental T-beam structure;
[0022] Figure 5 It is a schematic diagram of the structure of a second embodiment of a small-span prefabricated segmental T-beam structure after splicing;
[0023] Figure 6 It is a structural schematic diagram of a second embodiment of a small-span prefabricated segmental T-beam structure;
[0024] Figure 7 It is a structural schematic diagram of a third embodiment of a small-span prefabricated segmental T-beam structure;
[0025] Figure 8 It is a schematic diagram of the cross-sectional structure of the vertical end after splicing of the third embodiment of a small-span prefabricated segmental T-beam structure;
[0026] Fig. 9 It is a structural schematic diagram of a front splicing plate in a third embodiment of a small-span prefabricated segmental T-beam structure;
[0027] Fig.10 It is a structural schematic diagram of a rear splicing plate in a third embodiment of a small-span prefabricated segmental T-beam structure;
[0028] Fig.11 It is a structural schematic diagram of a T-beam segment frame in a fourth embodiment of a small-span prefabricated segment T-beam structure;
[0029] Fig.12 It is a structural schematic diagram of another view of the fourth embodiment of a small-span prefabricated segmental T-beam structure. DETAILED DESCRIPTION
[0030] The following will be combined with the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments in the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0031] Reference Figure 1-Figure 4 As shown, the first embodiment of the present invention provides a small-span prefabricated segmented T-beam structure, which is composed of multiple prefabricated T-beam segments connected in sequence, and is suitable for bridges and culverts with a span of 50m or less, and the number of prefabricated segments is at least 3 or more according to the design line shape of the T-beam bridge.
[0032] The T-beam segment includes a front splicing plate 1, a rear splicing plate 2 and a segment steel cage 3. The front splicing plate 1 and the rear splicing plate 2 are respectively welded and fixed on both sides of the segment steel cage 3. The cross-sections of the front splicing plate 1, the rear splicing plate 2 and the segment steel cage 3 are all T-shaped. Among them, the segment steel cage 3 is composed of a plurality of longitudinal steel bars 31 and a plurality of segment stirrups 32. A plurality of metal corrugated pipes 33 are reserved in the segment steel cage. The front splicing plate 1 and the rear splicing plate 2 both have reserved holes 4 adapted to the metal corrugated pipes. The segment steel cage 3 is formed by pouring concrete. In the T-beam segment that has been cast, the front splicing plate and the rear splicing plate are exposed on the casting layer 5, and the cross-section of the casting layer 5 is larger than the cross-sections of the front splicing plate and the rear splicing plate. During splicing, the rear splicing plate of the T-beam segment is aligned and spliced with the front splicing plate of its adjacent T-beam segment, and welded and fixed along the periphery of the joint. The outer peripheral welding area of the joint is filled with waterproof coating and epoxy resin 6 until it is flush with the casting layer 5.
[0033] The construction method of the above-mentioned small-span prefabricated segmental T-beam structure comprises the following steps:
[0034] S1. Prefabricated T-beam segments, transport the prefabricated T-beam segments that have been cast and cured to the bridge construction site. The prefabricated T-beam segments are cast and cured in a concrete prefabricated beam factory using standardized templates.
[0035] S2. Splicing T-beam segments,
[0036] According to the splicing of the exposed front splicing plates and rear splicing plates of the front prefabricated T-beam segment 7 and the rear prefabricated T-beam segment 8, welding is performed along the outer periphery of the joint between the front splicing plates and the rear splicing plates, and the splicing grooves are filled with waterproof coating and epoxy resin 6 until they are flush with the concrete layer of the prefabricated T-beam segment.
[0037] Specifically, when the front splicing plate 1 and the rear splicing plate 2 are welded, the weld is required to be smooth without welding defects such as pores and slag inclusions. If defects are found, they should be repaired in time. The welding technology is used to effectively splice the front and rear prefabricated T-beam segments to form a reliable overall force-bearing system, which can improve the problem of reduced integrity caused by colloid aging in traditional adhesive bonding methods. Waterproof coating and epoxy resin are applied to the outside of the weld for filling treatment. Its function is equivalent to the expansion joint in the bridge project, which can reduce the temperature stress caused by temperature changes in the concrete of the prefabricated T-beam segment, and reduce the stress concentration caused by temperature gradient changes in the prefabricated T-beam segment at the splicing position.
[0038] S3. Tension anchoring
[0039] After all T-beam segments are spliced, prestressed tendons are passed through the reserved metal corrugated tubes and prestressed anchorage is applied at both ends of the designed T-beam to form the overall force system of the small-span prefabricated segmental T-beam;
[0040] S4. Use the bridge erection machine to lift the integral prefabricated segmental T-beam to the bridge pier position.
[0041] Reference Figure 5-Figure 6 As shown, the third embodiment of the present invention provides a small-span prefabricated segmental T-beam structure, which is basically the same as the first embodiment, except that: the outer end face of the front splicing plate 1 has a plurality of docking protrusions 11, and the outer end face of the rear splicing plate has a plurality of docking grooves 21 that match the docking protrusions. Among them, the docking protrusions 11 and the docking grooves 21 are one-half of the thickness of the steel plate of the splicing plate, and the docking protrusions are preferably distributed in the middle and lower positions of the front splicing plate. When the T-beam segments are spliced, the docking protrusions 11 of the front splicing plate are inserted into the docking grooves 21 of the rear splicing plate of the adjacent T-beam segment. Through the cooperation of the docking protrusions 11 and the docking grooves 21, the rapid splicing of the prefabricated T-beam segments is achieved, saving the construction period of the splicing of the prefabricated T-beam segments.
[0042] When splicing T-beam segments in the above-mentioned construction method S2, the exposed front splicing plates 11 and the rear splicing plates 21 of the front prefabricated T-beam segment 7 and the rear prefabricated T-beam segment 8 are quickly spliced together, welding is performed along the outer periphery of the joint between the front splicing plates and the rear splicing plates, and the splicing grooves are filled with waterproof coating and epoxy resin 6 until they are flush with the concrete layer of the prefabricated T-beam segment.
[0043] In the construction method of the above-mentioned small-span prefabricated segmental T-beam structure, the prefabricated T-beam segment in S1 is cast and cured in a concrete prefabricated beam factory using a standardized formwork, and the specific steps are as follows:
[0044] S1-1 According to the design requirements of the prefabricated T-beam, the segment longitudinal steel bars 31 and segment stirrups 32 are cut by mechanical automation equipment, and the steel cage of the prefabricated T-beam segment is welded and formed through the front splicing plate 1 and the rear splicing plate 2. Among them, the front splicing plate and the rear splicing plate are made of 5-20mm thick steel plates, and the strength of the steel plates is not lower than the strength grade of the stirrups used in the segmental beam.
[0045] Specifically, the front and rear splicing plates are cut as a whole by laser cutting controlled by a computer terminal to ensure the accuracy and quality of steel plate cutting. A certain number of holes are reserved on the end splicing plate, which are determined according to the position of the prestressed tendons arranged in the prefabricated segmental T-beams, and are used for the connection of the metal corrugated pipes, so as to facilitate the prestressed tensioning and anchoring after the prefabricated segmental T-beams are spliced.
[0046] The segment longitudinal steel bars 31 and segment stirrups 32 are formed into a steel cage skeleton by automated resistance spot welding, and the front splicing plate 1 and the rear splicing plate 2 are respectively welded at the ends of the segment longitudinal steel bars. The number of segment longitudinal steel bars or the spacing of segment stirrups can be adjusted according to the needs of design calculation to meet the normal stress state of the overall structure. By introducing the front splicing plate and the rear splicing plate into the steel cage of the prefabricated T-beam segment, the reinforcement ratio of the steel cage on the cross section of the prefabricated T-beam segment is increased, which can effectively improve the shear bearing capacity of the prefabricated segment T-beam, thereby reducing the use of shear stirrups in the prefabricated T-beam segment.
[0047] S1-2 Reserve metal bellows 33. During the pouring of precast T-beam segment concrete, reserve metal bellows for prestressing tendons of small-span precast segment T-beams. Adjust the metal bellows 4 according to the arrangement of the prestressed tendons and let it pass through the front splicing plate and the rear splicing plate;
[0048] S1-3 concrete pouring, the finished prefabricated T-beam segments need to be kept warm, moisturized and watered until the strength of the components reaches the standard and the formwork is removed. After reaching the age, they are transported to the bridge construction site for splicing, which can ensure the concrete pouring quality of the prefabricated T-beam segments. At the same time, the small-span T-beam segments are easy to transport, which can reduce the transportation cost during the construction process.
[0049] Reference Figure 7-Figure 10 As shown, the third embodiment of the present invention provides a small-span prefabricated segmental T-beam structure, which is basically the same as the first embodiment, except that: both ends of the vertical end 22 of the rear splicing plate have edges 23 extending outward, and the edges on both sides form slots 24 with the vertical end surface of the rear splicing plate, and the slots 24 are adapted to the vertical end 12 of the front splicing plate. Among them, the length of the edge is smaller than the vertical end of the front splicing plate, and the width of the edge is adapted to the thickness of the side of the front splicing plate. The vertical end of the front splicing plate has limiting grooves 13 on both sides of the top, and the limiting grooves are for the top of the edge 23 to be inserted.
[0050] Furthermore, the vertical end side of the front splicing plate has multiple threaded holes 14, and the edges of the two sides of the rear splicing plate have through holes 25 matching the threaded holes. The vertical end 12 of the current splicing plate is inserted into the slot 24 of the rear splicing plate, and the screw 8 passes through the through hole 25 and the threaded hole in turn, and the two sides of the screw are fastened by nuts 9.
[0051] The splicing steps are as follows (this step replaces S2 in the first embodiment): 1) Use a crane to lift the rear T-beam segment to the front T-beam, and the vertical end of the front splicing plate of the rear T-beam segment is inserted into the slot to achieve preliminary positioning. 2) Move downward along the slot until the upper end along the edge is inserted into the limit grooves on both sides to complete the splicing and achieve precise positioning. 3) Pass the screw through the through hole 25 and the threaded hole 14 in turn, and tighten the two sides of the screw with nuts. 4) Weld the overlap between the front splicing plate and the rear splicing plate. 5) Apply waterproof paint and epoxy resin on the outside of the weld to fill the splicing groove.
[0052] Reference Figure 7-Figure 10 As shown, the third embodiment of the present invention provides a small-span prefabricated segmental T-beam structure, which is basically the same as the first embodiment, the first embodiment and the third embodiment, except that: a plurality of reinforcing longitudinal ribs 34 are arranged at the front bottom of the segmental reinforcement cage 3, one end of the reinforcing longitudinal ribs 34 is welded and fixed to the longitudinal reinforcement 31 at the bottom of the segmental reinforcement cage 3, and the other end of the reinforcing longitudinal ribs 31 passes through the front splicing plate and extends outward. The bottom of the rear splicing plate has a through hole 26, and the concrete layer is reserved with a grouting groove 51 on one side close to the rear splicing plate, the front opening of the grouting groove is mutually conductive with the through hole of the rear splicing plate, and the side of the grouting groove has a reserved grouting groove hole 52. When adjacent prefabricated T-beam segments are spliced, the reinforcing longitudinal reinforcement 34 of the rear prefabricated T-beam segment 8 is inserted into the rear end of the steel cage of the preceding prefabricated T-beam segment 7 through the through hole 26. The staff uses the reserved grouting slots to tie and weld the reinforcing longitudinal reinforcement to the rear end of the steel cage of the preceding prefabricated T-beam segment 7, and then casts them together through the reserved grouting slots, so that the adjacent prefabricated T-beam segments are spliced more tightly and their firmness is enhanced.
[0053] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any brief modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solution of the present invention are still within the scope of the technical solution of the present invention.
Claims
1. A small-span prefabricated segmental T-beam structure, characterized by: It is composed of multiple prefabricated T-beam segments connected in sequence, and the T-beam segment includes a front splicing plate, a rear splicing plate and a segment steel cage. The front splicing plate and the rear splicing plate are respectively welded and fixed on both sides of the segment steel cage. A plurality of metal corrugated pipes are reserved in the segment steel cage. The front splicing plate and the rear splicing plate both have reserved holes adapted to the metal corrugated pipes. The segment steel cage is poured with concrete to form a concrete layer, and the front splicing plate and the rear splicing plate are exposed in the concrete layer. When splicing, the rear splicing plate of the T-beam segment is aligned and spliced with the front splicing plate of the adjacent T-beam segment, and are welded and fixed along the outer periphery of the joint.
2. The small-span prefabricated segmental T-beam structure according to claim 1 is characterized by: The segment steel cage is composed of a plurality of longitudinal steel bars and segment stirrups.
3. The small-span prefabricated segmental T-beam structure according to claim 1 is characterized by: The welded parts at the outer periphery of the seams are filled with waterproof coating and epoxy resin.
4. A small-span prefabricated segmental T-beam structure according to claim 1, 2 or 3, characterized in that: The outer end surface of the front splicing plate has a plurality of docking protrusions, and the outer end surface of the rear splicing plate has a plurality of docking grooves matching the docking protrusions. When the T-beam segments are spliced, the docking protrusions of the front splicing plate are inserted into the docking grooves of the rear splicing plate of the adjacent T-beam segment.
5. The small-span prefabricated segmental T-beam structure according to claim 4 is characterized by: The front splicing plate, the rear splicing plate and the segment steel cage cross-section are all T-shaped in design.
6. The small-span prefabricated segmental T-beam structure according to claim 1 is characterized by: Both ends of the vertical end of the rear splicing plate have edges extending outward, and the two side edges and the vertical end face of the rear splicing plate form a slot, and the two sides of the top of the vertical end of the front splicing plate are provided with limiting grooves. During splicing, the rear T-beam segment is lifted to the front T-beam by a crane, and the vertical end of the front splicing plate of the rear T-beam segment is inserted into the slot, and moves downward along the slot until the upper end of the edge is inserted into the limiting grooves on both sides to complete the splicing.
7. The small-span prefabricated segmental T-beam structure according to claim 6 is characterized by: The vertical end side of the front splicing plate has multiple threaded holes, and the edges of the two sides of the rear splicing plate have through holes matching the threaded holes. The vertical end of the current splicing plate is inserted into the slot of the rear splicing plate, and the screw passes through the through hole and the threaded hole in turn, and the two sides of the screw are fastened by nuts.
8. The construction method of a small-span prefabricated segmental T-beam structure according to claim 1 is characterized by: The steps are as follows, S1. Prefabricate T-beam segments and transport them to the bridge construction site; S2. Splicing T-beam segments, According to the front splicing plate and the rear splicing plate exposed outside of the front prefabricated T-beam segment and the rear prefabricated T-beam segment, the seams are welded along the outer periphery of the end splicing plate, and the splicing grooves are filled with waterproof coating and epoxy resin; S3. Tension anchoring After all T-beam segments are spliced, prestressed tendons are passed through the reserved metal corrugated tubes and prestressed anchorage is applied at both ends of the designed T-beam to form the overall force system of the small-span prefabricated segmental T-beam; S4. Use the bridge erection machine to lift the integral prefabricated segmental T-beam to the bridge pier position.
9. A construction method for a small-span prefabricated segmental T-beam structure according to claim 8, characterized in that: in S2, the rear splicing plate of the front prefabricated T-beam segment and the front splicing plate of the rear prefabricated T-beam segment are quickly spliced together by cooperating with the docking protrusions and the docking grooves.
Citation Information
Cited By
Large-section prefabricated T-beam with split-ranging beam distribution and splicing method of large-section prefabricated T-beam
CN119372994A