Cross beam construction method for bridge

By setting up assembly platforms on the shore and using lifting and traction technologies, the precise placement of cross beams is solved, and the problem of low lifting efficiency of cross beams in traditional bridge construction is significantly shortened and efficiency is improved.

CN118958141APending Publication Date: 2024-11-15NO 1 ENG LIMITED OF CR20G +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411072766.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-06
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

In the construction of traditional steel structure bridges, the construction efficiency of cross beams is low, the working time is long, and the air sealing operation cannot be completed in a short time.

Method used

The assembly platform is set up on the shore, and multiple beams are assembled into beam sheets through longitudinal beams, and the beam sheets are accurately positioned to the ox leg on the main beam by lifting and traction technology. Through multi-point adjustment and measurement adjustment, Achieve rapid installation of crossbeams.

Benefits of technology

The installation and construction period of cross beams in the river channel has been greatly shortened, construction efficiency has been improved, and the installation of bridge cross beams has been completed within a shorter flight time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958141A_ABST
    Figure CN118958141A_ABST
Patent Text Reader

Abstract

The invention belongs to the technical field of bridge construction, and particularly discloses a bridge beam construction method which comprises the steps that S1, an assembly platform is arranged on the shore based on a preset finished bridge line shape; s2, on the basis of the splicing platform, a plurality of cross beams are assembled into cross beam pieces through longitudinal beams; s3, the cross beam piece is hoisted and dragged, the position of the cross beam piece is adjusted in a multi-point mode, and the cross beam piece is made to fall to the preset falling position of a bracket on the main straining beam; s4, measuring the positions of the cross beam sheet and the bracket, and adjusting the position of the cross beam sheet according to a measurement result; s5, the cross beam piece and the bracket are connected, and the cross beam piece and the bracket are connected into a whole; and S6, the steps S3-S5 are repeated for installation of the remaining cross beam pieces till installation of all the cross beam pieces is completed. According to the construction method disclosed by the invention, the cross beam mounting operation of the bridge can be completed within a relatively short navigation sealing operation time.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the technical field of bridge construction, and more specifically, relates to a method for constructing a crossbeam for a bridge. Background Art

[0002] As the process of social development accelerates, traffic congestion has become a major problem related to production and life. In order to make better use of the limited space in the shipping area and realize the rapid passage of water and land transportation, the planning and construction of various bridges across the waterway is increasing.

[0003] At present, in the traditional steel structure bridge construction plan, after the construction of the two beam-arch sections of the bridge is completed, the cross beams are usually hoisted one by one to the two beam-arch sections in the river channel, so that the cross beams and the main tie beams in the beam-arch sections are assembled one by one on site. In order to ensure safe navigation, the bridge is often only allowed to close the navigation for a short time during erection. The construction efficiency of hoisting the cross beams one by one on site is low, and the operation time is long, which makes it impossible to install the cross beams one by one on site. Summary of the invention

[0004] In response to the defects or improvement needs of the prior art, the present application provides a method for constructing bridge beams, aiming to solve the problems of low construction efficiency and long construction time when hoisting beams one by one into a river channel.

[0005] The present application provides a method for constructing a bridge beam, comprising the following steps:

[0006] S1. Arrange the assembly platform on the shore based on the preset bridge line shape;

[0007] S2. Based on the assembly platform, assemble multiple beams into beam pieces through longitudinal beams;

[0008] S3. Lift and pull the cross beam, and adjust the position of the cross beam through multiple points so that the cross beam falls to the corbel on the main tie beam;

[0009] S4. Measure the positions of the cross beam and the corbel, and adjust the position of the cross beam according to the measurement results;

[0010] S5. Connect the crossbeam and the corbel so that the crossbeam and the corbel are connected as one;

[0011] S6. Install the remaining cross beam pieces based on steps S3-S5 until all cross beam pieces are installed.

[0012] Through the above technical scheme conceived by the present application, compared with the prior art, the construction method can assemble multiple beams into beam pieces with a certain linear shape at the river bank by setting an assembly platform on the river bank side, and through lifting operations and traction operations, it can apply adjustment forces of multiple different angles to the beam pieces, so as to accurately position the beam pieces to the corbels on the main tie beams, thereby greatly shortening the installation and construction period of the beams in the river channel and improving the installation and construction efficiency of the beams, so as to complete the installation of the bridge beams within a shorter navigation closure time.

[0013] As further preferred, in step S1, the assembly platform includes a tire frame and a plurality of adjustment tubes, and the adjustment tubes are arranged on the tire frame and used for supporting the crossbeam pieces.

[0014] As further preferred, in step S2, the landing positions of the longitudinal beam and the transverse beam when they are positioned on the assembly platform are determined based on a pre-constructed zero-point coordinate system.

[0015] As a further preferred embodiment, in step S2, the positions of the longitudinal beams and the transverse beams placed on the assembly platform are adjusted based on the existing design coordinate system of the bridge.

[0016] As a further preference, in step S2, the crossbeam pieces are assembled with the road centerline as the reference line, and a welding shrinkage margin is reserved for the crossbeam end spacing.

[0017] As a further preference, in step S3, when installing the cross beams at both ends of the bridge, the cross beams are first preliminarily hoisted above the corbels, and then one end of the cross beam is pulled so that the cross beams are initially positioned at the corbels, and then the four corners of the cross beams are pulled and adjusted to adjust the position of the cross beams at the corbels.

[0018] As a further preferred embodiment, in step S3, when installing the cross beam piece in the middle part of the bridge, a cross support structure is installed between the middle sections of the two existing main tie beams, and the cross support structure is located above the corbel. The cross beam piece is then hoisted between the corbel and the cross support structure, and then the four corners of the cross beam piece are pulled and adjusted so that the cross beam piece falls into place at the corbel.

[0019] As a further preferred embodiment, a main lifting device is used to lift the cross beam, a main traction device is used to traction one end of the cross beam, and a plurality of secondary traction devices are used to traction the cross beam at multiple points, wherein:

[0020] The main lifting equipment is located beside the bridge, the main traction equipment is located in the river channel below the bridge, and the main traction equipment can be adjusted for displacement along the length direction of the bridge. The secondary traction equipment is installed at the built main tie beam of the bridge.

[0021] As a further preferred embodiment, a limiting structure is provided on the corbel and / or the crossbeam, and when one end of the crossbeam is pulled to initially position the crossbeam at the corbel, the pulled end of the crossbeam is positioned on the corbel through the limiting structure.

[0022] As further preferred, in step S4, based on a certain point in the center line of the road as a monitoring point, the position of the corbel with the cross beam piece hoisted in place and the cross beam piece on the corbel is measured.

[0023] In general, the above technical solutions conceived by this application have the following technical advantages compared with the prior art:

[0024] 1. By setting up an assembly platform on the river bank side, multiple beams can be assembled into beam pieces with a certain linear shape at the river bank, and through lifting and traction operations, multiple adjustment forces at different angles can be applied to the beam pieces, so that the beam pieces can be accurately positioned at the brackets on the main tie beams, thereby greatly shortening the construction period of the beams in the river channel and improving the efficiency of the beam construction in the river channel, so as to complete the installation of the bridge beams within a shorter navigation closure time.

[0025] 2. When installing the cross beams at both ends of the bridge, the cross beams were accurately positioned by means of preliminary lifting, preliminary traction and positioning, and multi-angle traction and adjustment. The main lifting equipment, main traction equipment and secondary traction equipment were gradually connected to the cross beams, which can not only provide multiple safety guarantees for the installation process of the cross beams, but also provide multiple ways to adjust the position of the cross beams, so that the cross beams can be flexibly positioned at the corbels.

[0026] 3. Based on the zero-point coordinate system, the longitudinal beams and transverse beams of the beam pieces are determined on the assembly platform, which can provide basic coordinates for the assembly of the beam pieces. After the longitudinal beams and transverse beams are positioned on the assembly platform according to the zero-point coordinate system, the positions of the longitudinal beams and transverse beams positioned on the assembly platform are adjusted based on the existing design coordinate system of the bridge, so that the final assembled structure of the longitudinal beams and transverse beams can match the linear shape of the bridge. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] Figure 1 It is a schematic diagram of a method for constructing a bridge beam provided in an embodiment of the present application;

[0028] Figure 2 This is a front view of assembling the cross beam pieces provided by the embodiment of the present application under the condition of limited space;

[0029] Figure 3 This is a front view of the assembly of the beam pieces under the wide field provided by the embodiment of the present application;

[0030] Figure 4is a top view of a beam arrangement site provided in an embodiment of the present application;

[0031] Figure 5 This is a front view of the main floating crane lifting beam provided in an embodiment of the present application;

[0032] Figure 6 It is a schematic diagram of a main floating crane hoisting beam provided in an embodiment of the present application;

[0033] Figure 7 It is a schematic diagram of the main floating crane, the secondary floating crane and the fall chain provided in the embodiment of the present application for the lifting operation of the crossbeam piece;

[0034] Figure 8 It is a layout diagram of the cross support structure and the cross beam provided in the embodiment of the present application;

[0035] Fig. 9 It is a schematic diagram of the connection between the corbel and the crossbeam provided in the embodiment of the present application;

[0036] Fig.10 This is a schematic diagram of measuring the position of a corbel provided in an embodiment of the present application;

[0037] Fig.11 This is a schematic diagram of measuring the position of the beam provided in an embodiment of the present application.

[0038] Throughout the drawings, the same reference numerals are used to denote the same elements or structures, wherein:

[0039] 1. Crossbeam; 2. Adjusting pipe; 3. Thermal pipe; 4. Temporary guardrail; 5. Main floating crane; 6. Secondary floating crane; 7. Falling chain; 8. Horizontal support structure; 10. Built main tie beam; 20. Corbel. DETAILED DESCRIPTION

[0040] In order to make the purpose, technical solution and advantages of the present application more clearly understood, the present application is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present application and are not used to limit the present application.

[0041] The following is combined with Figure 1-11 This application is described in further detail.

[0042] The present application embodiment discloses a method for constructing a bridge beam. Figure 1 The bridge beam construction method comprises the following steps:

[0043] S1. Arrange the assembly platform on the shore based on the preset bridge line shape.

[0044] Since the beam surface of the bridge is long, a large number of beams need to be arranged, and the bridge surface often presents linear changes such as arc and straight line, so the multiple beams required to be installed on the bridge also need to have a specific linear arrangement. To this end, the multiple beams required to be installed are divided into multiple groups, and multiple assembly platforms are arranged on the shore. The beams are spliced ​​by longitudinal beams at the assembly platforms, so that the multiple beams in each group are assembled into beam pieces 1 that meet the preset specific bridge linear shape.

[0045] Specifically, according to actual needs, multiple crossbeam 1 assembly areas are set up on the shore, and a tire frame is arranged in the crossbeam 1 assembly area. The tire frame has multiple support points with specific height and position distribution. The support points are used to support the crossbeams and / or longitudinal beams so that the linear shape of the crossbeams matches the planned linear shape of the bridge.

[0046] As a preferred method, the assembly area of ​​the cross beam piece 1 is divided into four sections, the tire frame is made of H350 I-beam, and a plurality of adjustment tubes 2 are fixed on the tire frame. The adjustment tubes 2 are preferably vertical round tubes, and their lengths are cut according to the target linear shape of the cross beam piece 1. The adjustment tubes 2 serve as the support points of the cross beam piece 1. That is, the positions and heights of the adjustment tubes 2 are arranged according to the relative positions of the plurality of cross beams in the design plan, so that the linear shape of the cross beam piece 1 assembled on the adjustment tubes 2 matches the preset bridge linear shape.

[0047] Further, the site for assembling the cross beam piece 1 can be set on one bank of the river, or on both banks of the river, and the arrangement is flexible. In some actual construction plans, the top position of the newly built retaining wall on the river bank and the concrete foundation on the top of the slope can be fully utilized to construct the tire frame.

[0048] When some venues are limited, such as Figure 2 As shown, when there are existing facilities such as thermal pipes 3 at the construction site that affect the site layout, the riverside access road and slope surface can be filled and compacted to harden the soil, widen the assembly site of the crossbeam 1, and if necessary, temporary guardrails 4 and other protective structures can be built at the existing facilities. Figure 3 As shown, when the site is relatively wide, the tire frame can be set up directly on a stable foundation such as a hardened road surface.

[0049] Of course, when the site is limited, the layout of multiple assembly platforms can be flexibly adjusted based on the terrain conditions. Figure 4 As shown, three assembly platforms are arranged along the extending direction of the river channel at the river bank, and another assembly platform is arranged at one end of the three assembly platforms away from the river channel.

[0050] S2. Based on the assembly platform, multiple cross beams are assembled into a cross beam piece 1 through longitudinal beams to obtain multiple cross beam pieces 1.

[0051] In this step, before the longitudinal beams and cross beams are brought into the site, the support points of the cross beam piece 1 are laid out on the assembly platform based on the zero-point coordinate system to determine the position and height of each support point, providing basic coordinates for the assembly of the cross beam piece 1. In addition, settlement observation points are arranged for each support point, and settlement data are collected periodically to ensure construction safety. After determining that the settlement data meets the construction safety standards, the cross beams and longitudinal beams are hoisted to the assembly platform based on the layout results to achieve the preliminary assembly of the cross beams and longitudinal beams; then, the positions of the cross beams and longitudinal beams are adjusted based on the existing design coordinate system of the bridge, so that the relative positions of the multiple cross beams in the assembly platform match the relative positions of the multiple cross beams preset in the design coordinate system, and then the welding of the cross beams and longitudinal beams is carried out.

[0052] In the above process, when adjusting the position of the crossbeam and the longitudinal beam, the height of the crossbeam can be fine-tuned by setting a gasket, and the position of the crossbeam can be fine-tuned by setting a positioning plate in the crossbeam and / or the assembly platform, and the positioning plate is used to limit the relative position of the crossbeam and the assembly platform. Among them, the zero-point coordinate system is: a reference point (i.e., the zero point) is used as the origin of the coordinate system, and the positions of other points (layout points, measurement points) are defined relative to this origin. The design coordinate system is the coordinate system designed and established for the coordinate positions of each beam in the construction plan. The design coordinate system displays the preset relative position data between multiple beams.

[0053] Furthermore, in this step, before hoisting the cross beams and longitudinal beams to the assembly platform, it is necessary to check the dimensions of the cross beams and longitudinal beams. When a positioning plate is welded on the cross beams or longitudinal beams, it is also necessary to check whether the positioning plate is complete.

[0054] In addition, it is preferred to use the center line of the road as the reference line to control the horizontal, spacing, and diagonal dimensions of the crossbeam 1. After adjusting the positions of the crossbeam and longitudinal beam using the design coordinate system, the positions of the crossbeam and longitudinal beam are remeasured. Welding operations are performed only after the remeasurement results are qualified (i.e., the measured actual position deviation is less than the preset error allowable range).

[0055] Preferably, a certain welding shrinkage allowance is reserved for the end spacing of the cross beams in each piece, preferably a welding shrinkage allowance of 3 mm; in addition, a lifting lug is provided on the cross beam at the intersection of the side span and the longitudinal beams of the cross beam piece 1, and the lifting lug is used for subsequent lifting operations to reduce deformation during the subsequent lifting process.

[0056] S3. Lift and pull the cross beam 1, and adjust the position of the cross beam 1 so that the cross beam 1 falls to the corbel 20 on the main tie beam.

[0057] Before the hoisting operation, the bracket needs to be laid out according to the design coordinate system to determine the location of the crossbeam on the bracket 20. Figure 5-9As shown, when installing the cross beam pieces 1 at both ends of the length direction of the bridge, the cross beam piece 1 is first initially hoisted above the corbel 20, and then one end of the cross beam piece 1 is pulled to make the cross beam piece 1 initially fall to the corbel 20, and then the four corners of the cross beam piece 1 are pulled and adjusted to adjust the position of the cross beam piece 1 at the corbel 20 until it reaches the landing point.

[0058] When installing the cross beam 1 in the middle of the bridge, a cross beam 1 is installed between the middle sections of the two main tie beams 10. Figure 8 The transverse support structure 8 shown is located above the corbel 20 to prevent deformation of the existing steel structure where the two existing main tie beams 10 are located; the cross beam piece 1 is then hoisted between the corbel 20 and the transverse support structure 8, and then the four corners of the cross beam piece 1 are pulled and adjusted to make the cross beam piece 1 fall to the landing point of the corbel 20. Preferably, the transverse support structure 8 is preferably a supporting steel pipe, and both ends of the cross beam have steel adjustment heads for fixing with the middle cross beam section of the main tie beam.

[0059] Specifically, if Figure 7 As shown, a main lifting device is used to lift the cross beam 1, a main traction device is used to tow one end of the cross beam 1, and a plurality of secondary traction devices are used to tow the cross beam 1 at multiple points.

[0060] Among them, the main lifting equipment is located beside the bridge, preferably a main floating crane 5 arranged in the river channel beside the bridge (i.e. one side in the width direction of the bridge). The lifting capacity of the main floating crane 5 is selected according to the weight of the crossbeam 1 to be lifted and the lifting angle and distance. For example, the rated lifting capacity of the main floating crane 5 is preferably 500 tons.

[0061] The main traction equipment is located in the river channel below the bridge, and the main traction equipment can be adjusted in displacement along the length direction of the bridge. The main traction equipment is preferably a secondary floating crane 6, and its lifting capacity is also selected according to the lifting requirements. For example, a floating crane with a rated traction capacity of 80 tons is selected, and the floating crane needs to be able to be arranged in the river channel below the bridge. Preferably, when the secondary floating crane 6 is used, the secondary floating crane 6 uses a winch to pull one end of the cross beam 1. The secondary traction equipment is installed at the built main tie beam 10 of the bridge. The secondary traction equipment preferably uses a fall chain 7. Two fall chains 7 are installed on each of the two built main tie beams 10, which are used to pull the four corners of the cross beam 1.

[0062] As a preferred example, Fig. 9 As shown, in some embodiments, the upper ends of the cross beam in the cross beam sheet 1 are protruded to form upper convex edges, and the lower ends are provided with lower notches. The upper part of the corbel 20 has an upper notch, and the lower part has a lower convex edge, the upper notch is matched with the upper convex edge, and the lower convex edge is matched with the lower notch, so that the cross beam and the corbel 20 have a larger contact surface and a larger welding connection surface.

[0063] Preferably, in some embodiments, the corbel 20 and / or the crossbeam are further provided with a limiting structure, and the limiting structure is preferably a limiting plate welded on the corbel 20 and / or the crossbeam. When one end of the crossbeam piece 1 is pulled to make the crossbeam piece 1 initially fall to the corbel 20, the pulled end of the crossbeam piece 1 forms a conflict with the corbel 20 through the limiting plate, thereby improving the installation stability of the crossbeam piece 1. For example, the limiting plates are welded on both the corbel 20 and the crossbeam, and when the crossbeam reaches the target position, the limiting plate on the crossbeam forms a conflicting limit with the limiting plate on the corbel 20.

[0064] S4. Measure the positions of the cross beam 1 and the corbel 20, and adjust the position of the cross beam 1 according to the measurement results.

[0065] like Figure 10-11 As shown, in this step, it is preferred to use the road centerline as the reference line, and based on a certain point in the road centerline as the monitoring origin, the position of the bracket 20 with the cross beam 1 hoisted in place and the cross beam 1 on the bracket 20 is measured. Preferably, a total station is used for measurement.

[0066] In this step, the positions of the cross beam 1 and the corbel 20 are checked based on the measurement results to see if they match the designed positions. If the deviation between the actual measured position and the designed position is greater than the preset allowable range, the actual position is adjusted until it is within the design allowable range.

[0067] S5. Connect the cross beam 1 and the corbel 20 so that the cross beam 1 and the corbel 20 are connected as one.

[0068] In this step, the cross beam piece 1 and the corbel 20 are welded and firmly welded using a yard plate. After the welding is completed, the hoisting and traction equipment connected to the cross beam piece 1 is evacuated.

[0069] S6. Install the remaining cross beam pieces 1 based on steps S3-S5 until all cross beam pieces 1 are installed.

[0070] It should be understood that expressions such as "include" and "may include" used in this application indicate the existence of the disclosed functions, operations or constituent elements, and do not limit one or more additional functions, operations and constituent elements. In this application, terms such as "include" and / or "have" may be interpreted as indicating specific characteristics, numbers, operations, constituent elements, components or combinations thereof, but may not be interpreted as excluding the existence or possibility of adding one or more other characteristics, numbers, operations, constituent elements, components or combinations thereof.

[0071] It should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0072] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0073] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0074] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present application and is not intended to limit the present application. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present application shall be included in the scope of protection of the present application.

Claims

1. A method for constructing a bridge beam, characterized in that: The following steps are involved: S1. Arrange the assembly platform on the shore based on the preset bridge line shape; S2. Based on the assembly platform, multiple beams are assembled into beam pieces (1) through longitudinal beams; S3 hoisting and pulling the beam piece (1), by multi-point adjustment of the position of the beam piece (1), so that the beam piece (1) falls to the main tie beam on the bracket (20) in the preset landing point; S4. Measure the position of the crossbeam (1) and the bracket (20), and adjust the position of the crossbeam (1) according to the measurement results; S5. Connecting the crossbeam (1) and the corbel (20) so that the crossbeam (1) and the corbel (20) are connected as one; S6. Repeat steps S3-S5 to install the remaining cross beam pieces (1) until the installation of all cross beam pieces (1) is completed.

2. The method for constructing a bridge beam according to claim 1, characterized in that: In step S1, the assembly platform comprises a tire frame and a plurality of adjustment tubes (2), wherein the adjustment tubes (2) are arranged on the tire frame and are used to support the crossbeam piece (1).

3. The method for constructing a bridge beam according to claim 1, characterized in that: In step S2, the locations of the longitudinal beam and the transverse beam when they are placed on the assembly platform are determined based on the pre-constructed zero-point coordinate system.

4. The method for constructing a bridge beam as claimed in claim 3, characterized in that: In step S2, the positions of the longitudinal beams and the transverse beams placed on the assembly platform are adjusted and corrected based on the existing design coordinate system of the bridge.

5. The method for constructing a bridge beam according to claim 1, characterized in that: In step S2, the cross beam pieces (1) are assembled with the road centerline as the reference line, and a welding shrinkage margin is reserved for the cross beam end spacing.

6. The method for constructing a bridge beam according to claim 1, characterized in that: In step S3, when installing the cross beams (1) at both ends of the length direction of the bridge, the cross beams (1) are first hoisted above the corbels (20), and then one end of the cross beam (1) is pulled so that the cross beam (1) is initially positioned at the corbels (20), and then the four corners of the cross beam (1) are pulled and adjusted respectively to adjust the position of the cross beam (1) at the corbels (20).

7. The method for constructing a bridge beam according to claim 1, characterized in that: In step S3, when installing the cross beam piece (1) in the middle of the bridge, a transverse support structure (8) is installed between the middle sections of the two existing main tie beams (10), and the transverse support structure (8) is located above the corbel (20). The cross beam piece (1) is then hoisted between the corbel (20) and the transverse support structure (8), and then the four corners of the cross beam piece (1) are pulled and adjusted respectively, so that the cross beam piece (1) falls to the corbel (20).

8. The method for constructing a bridge beam according to claim 6, characterized in that: A main lifting device is used to lift the cross beam piece (1), a main traction device is used to traction one end of the cross beam piece (1), and a plurality of secondary traction devices are used to traction the four corners of the cross beam piece (1), wherein: The main lifting equipment is located beside the bridge, the main traction equipment is located in the river channel below the bridge, and the main traction equipment can be adjusted for displacement along the length direction of the bridge, and the secondary traction equipment is installed at the built main tie beam (10) of the bridge.

9. The method for constructing a bridge beam according to any one of claims 1 to 8, characterized in that: A limiting structure is provided on the corbel (20) and / or the crossbeam, and when one end of the crossbeam piece (1) is pulled so that the crossbeam piece (1) is initially positioned at the corbel (20), the pulled end of the crossbeam piece (1) is positioned on the corbel (20) through the limiting structure.

10. The method for constructing a bridge beam according to any one of claims 1 to 8, characterized in that: In step S4, based on a certain point in the center line of the road as a monitoring point, the position of the bracket (20) with the cross beam piece (1) hoisted in place and the cross beam piece (1) on the bracket (20) are measured.