Bidirectional pouring device and pouring method for photovoltaic micro pile foundation concrete

Through the symmetrical design of the two-way casting device for photovoltaic micro pile foundation concrete, the inclination and position deviation of the embedded parts caused by single-side casting are solved, and the stability and installation accuracy of the embedded parts are improved.

CN118958299APending Publication Date: 2024-11-15CSCEC INT CONSTR
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411312708.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

During the single-side pouring of the embedded parts of the photovoltaic power generation foundation steel pipes, existing concrete micro piles are prone to position deviation due to inclined force, which affects the installation accuracy and construction efficiency.

Method used

Design a two-way casting device for photovoltaic micro pile foundation concrete. By setting symmetrical discharge ports and abutment cavity on the main body, the concrete flows out from two symmetrical discharge ports, and evenly produces opposite and equal sizes on both sides of the embedded part. The force ensures the stability and perpendicularity of the embedded parts.

Benefits of technology

It effectively avoids the inclination and position deviation of the embedded parts during one-sided pouring, improves the installation accuracy and construction efficiency, and ensures the stability and installation accuracy of the embedded parts.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958299A_ABST
    Figure CN118958299A_ABST
Patent Text Reader

Abstract

According to the photovoltaic micro pile foundation concrete two-way pouring device and pouring method, on the construction site, the main body is tightly attached to the peripheral face of the embedded part through the abutting-against cavity, and the photovoltaic micro pile foundation concrete two-way pouring device is stably fixed. Concrete is poured into the containing cavity, and the concrete flows to the two symmetrical discharging openings under the action of gravity. And concrete flows out from the two symmetrical discharging ports and is uniformly poured towards the two opposite sides of the embedded part. Due to the fact that the discharging ports are symmetrically arranged, the acting force borne by the two sides of the embedded part in the pouring process is opposite and equal in size, and the position stability and perpendicularity of the embedded part are kept. And after pouring is completed, the two sides of the embedded part are evenly filled with concrete, and the stability and installation precision of the embedded part are guaranteed. And through the bidirectional symmetrical pouring design, the problems of inclination and position deviation generated in the single-side pouring process are effectively avoided, and the installation precision of the embedded part is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of construction, and in particular to a photovoltaic micro-pile foundation concrete bidirectional pouring device and pouring method. Background Art

[0002] With the application of new energy, energy is no longer limited to thermal power generation. At present, common power generation methods include wind power generation, hydropower generation, photovoltaic power generation and other clean energy power generation. Photovoltaic power generation generally adopts fixed, single-axis and dual-axis photovoltaic power generation, and various types of photovoltaic power generation require concrete micropiles as the basis.

[0003] During the erection process of the existing concrete micro-columns, it is first necessary to drill a hole in the installation ground to obtain the completed hole, and then insert the photovoltaic foundation steel pipe embedded parts into the hole, and make the photovoltaic foundation steel pipe embedded parts located in the middle of the hole, so that the axis of the photovoltaic foundation steel pipe embedded parts is colinear with the axis of the hole, and then fill the space between the photovoltaic foundation steel pipe embedded parts and the inner wall of the hole with concrete to complete the pouring.

[0004] The existing pouring method is to pour concrete from a single side of the embedded parts of the photovoltaic foundation steel pipe. Since the gap between the embedded parts and the inner wall of the hole is small, the falling concrete will directly contact the embedded parts during the falling process and create a force. Under the influence of the force, the embedded parts will tilt to the side of the impact force, causing the position and verticality of the embedded parts to deviate, and the installation accuracy cannot be achieved. Rework is often required to ensure the accuracy of the embedded parts, which in turn affects the construction efficiency. Summary of the invention

[0005] In view of this, it is necessary to provide a photovoltaic micropile foundation concrete bidirectional pouring device and pouring method to solve the above problems.

[0006] The embodiment of the present application provides a photovoltaic micro-pile foundation concrete bidirectional pouring device, comprising:

[0007] The main body is provided with a containing cavity and two discharge ports communicated with the containing cavity, wherein the containing cavity is used to contain concrete;

[0008] One side of the main body is inwardly recessed to form an abutment portion, the abutment portion is formed with an abutment cavity for fitting the outer peripheral surface of the embedded component, the abutment cavity is communicated with the two discharge ports, and the abutment cavity is located between the two discharge ports;

[0009] During pouring, the concrete in the accommodating cavity flows out from the two discharge ports, which are symmetrical about the axis of the embedded part, and are poured toward the opposite sides of the embedded part to generate forces of opposite directions and magnitudes on the two sides of the embedded part.

[0010] In at least one embodiment of the present application, the distances between the two discharge ports and the axis of the abutment cavity are equal.

[0011] In at least one embodiment of the present application, the accommodating cavity has a bottom wall, the main body has a first side wall and a second side wall disposed away from the first side wall, and the abutting portion is disposed on the first side wall;

[0012] The bottom wall is arranged obliquely downward from the second side wall toward the first side wall.

[0013] In at least one embodiment of the present application, the angle between the bottom wall and the horizontal plane is α, which satisfies the relationship: 15°<α<30°.

[0014] In at least one embodiment of the present application, both ends of the first side wall have blocking portions, and the discharge port is formed between the two blocking portions and the abutting portion.

[0015] In at least one embodiment of the present application, the opening directions of the two discharge ports are arranged perpendicular to the first side wall.

[0016] In at least one embodiment of the present application, the axis of the embedded part is located on the line between the two discharge ports.

[0017] In at least one embodiment of the present application, the photovoltaic micropile foundation concrete bidirectional pouring device further includes:

[0018] The bracket is arranged at the bottom of the main body, and the corners of the bottom of the bracket are provided with rollers.

[0019] In at least one embodiment of the present application, the photovoltaic micropile foundation concrete bidirectional pouring device further includes:

[0020] A shovel handle has one end disposed on the main body.

[0021] A casting method is applied to the photovoltaic micropile foundation concrete bidirectional casting device described above, the method comprising:

[0022] Place the photovoltaic micropile foundation concrete bidirectional pouring device at the pouring position, so that the abutment cavity abuts against the peripheral surface of the embedded part, and the two discharge ports are located on both sides of the embedded part and face the two sides of the peripheral surface of the embedded part;

[0023] Concrete is injected into the accommodating cavity so that the concrete flows from the accommodating cavity to the two discharge ports, and then flows from the two discharge ports to the opposite sides of the embedded part, so as to generate forces of opposite directions and magnitudes on the two sides of the embedded part for pouring.

[0024] The photovoltaic micropile foundation concrete bidirectional pouring device and pouring method of this embodiment will have at least the following beneficial effects:

[0025] The photovoltaic micropile foundation concrete bidirectional pouring device and pouring method provided above, at the construction site, the main body closely fits the outer peripheral surface of the embedded part through the abutment cavity, and the photovoltaic micropile foundation concrete bidirectional pouring device is firmly fixed.

[0026] Pour concrete into the containing cavity, and the concrete flows to two symmetrical discharge ports under the action of gravity.

[0027] Concrete flows out from two symmetrical outlets and is poured evenly toward the opposite sides of the embedded parts.

[0028] Since the discharge ports are symmetrically arranged, the forces acting on both sides of the embedded parts during the pouring process are relative and equal, thus maintaining the position stability and verticality of the embedded parts.

[0029] After pouring, concrete is evenly filled on both sides of the embedded parts, ensuring the stability and installation accuracy of the embedded parts.

[0030] The bidirectional symmetrical casting design effectively avoids the problems of tilting and position deviation caused by one-sided casting, and improves the installation accuracy of embedded parts.

[0031] The two discharge ports are arranged symmetrically so that both sides of the embedded parts are subjected to equal and opposite forces, thus maintaining the structural balance during the pouring process and preventing the embedded parts from tilting. BRIEF DESCRIPTION OF THE DRAWINGS

[0032] Figure 1 A three-dimensional diagram of a photovoltaic micropile foundation concrete bidirectional pouring device in one embodiment;

[0033] Figure 2 for Figure 1 Another angle stereoscopic view of the bidirectional pouring device for photovoltaic micropile foundation concrete;

[0034] Figure 3 for Figure 1 Reference diagram of the use status of the bidirectional pouring device for photovoltaic micropile foundation concrete;

[0035] Figure 4 for Figure 1 Another reference diagram of the usage status of the bidirectional pouring device for photovoltaic micropile foundation concrete.

[0036] Main component symbols

[0037] 100. Photovoltaic micropile foundation concrete bidirectional pouring device;

[0038] 110, main body; 110a, accommodating cavity; 110b, discharge port; 111, abutting portion; 111a, abutting cavity; 110c, bottom wall; 110d, first side wall; 110e, second side wall; 112, abutting portion;

[0039] 120, bracket; 121, roller;

[0040] 130, shovel handle;

[0041] 140a, forming a hole; 140 embedded parts;

[0042] 150. Pump tube. DETAILED DESCRIPTION

[0043] The embodiments of the present application will be described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, rather than all the embodiments.

[0044] It should be noted that when a component is considered to be "connected" to another component, it may be directly connected to the other component or there may be a central component at the same time. When a component is considered to be "located on" another component, it may be directly located on the other component or there may be a central component at the same time. The terms "top", "bottom", "upper", "lower", "left", "right", "front", "back", and similar expressions used herein are for illustrative purposes only.

[0045] Some embodiments of the present application are described in detail below in conjunction with the accompanying drawings. In the absence of conflict, the following embodiments and features in the embodiments can be combined with each other.

[0046] The embodiment of the present application provides a photovoltaic micropile foundation concrete bidirectional pouring device 100, comprising:

[0047] The main body 110 is provided with a receiving cavity 110a and two discharge ports 110b communicating with the receiving cavity 110a, wherein the receiving cavity 110a is used to receive concrete;

[0048] One side of the main body 110 is recessed inward to form an abutment portion 111, and the abutment portion 111 is formed with an abutment cavity 111a for fitting against the outer peripheral surface of the embedded component 140, and the abutment cavity 111a is communicated with the two discharge ports 110b, and the abutment cavity 111a is located between the two discharge ports 110b;

[0049] During pouring, the concrete in the accommodating cavity 110a flows out from the two discharge ports 110b, which are symmetrical about the axis of the embedded part 140 and are poured toward opposite sides of the embedded part 140 to generate forces of opposite directions and magnitudes on the two sides of the embedded part 140.

[0050] Please refer to Figure 1-Figure 4 In this embodiment, at the construction site, the main body 110 is tightly attached to the outer peripheral surface of the embedded part 140 through the abutment cavity 111a, so that the photovoltaic micropile foundation concrete bidirectional pouring device 100 is firmly fixed.

[0051] Concrete is poured into the accommodating chamber 110a, and the concrete flows toward two symmetrical discharge ports 110b under the action of gravity.

[0052] Concrete flows out from two symmetrical discharge ports 110b and is evenly poured toward opposite sides of the embedded component 140 and enters the formed hole 140a.

[0053] Since the discharge ports 110 b are symmetrically arranged, the forces acting on both sides of the embedded component 140 during the casting process are relative and equal in magnitude, thereby maintaining the position stability and verticality of the embedded component 140 .

[0054] After pouring is completed, concrete is evenly filled on both sides of the embedded part 140 , ensuring the stability and installation accuracy of the embedded part 140 .

[0055] The bidirectional symmetrical casting design effectively avoids the problems of tilting and position deviation caused by the single-sided casting process, and improves the installation accuracy of the embedded part 140.

[0056] The two discharge ports 110 b are symmetrically arranged so that both sides of the embedded component 140 are subjected to equal and opposite forces, thereby maintaining structural balance during the pouring process and preventing the embedded component 140 from tilting.

[0057] It should be noted that the main body 110 is roughly shaped like a "concave" box, the accommodating chamber 110a is a space formed by the side of the main body 110 facing away from the ground, the discharge port 110b is a through port, the discharge port 110b is connected to the accommodating chamber 110a and the external space, and the abutment portion 111 is an arc-shaped baffle that is concave inward on one side of the main body 110.

[0058] The abutting cavity 111 a is an arc-shaped open space for accommodating the embedded component 140 , and abutting against the circumferential surface of the embedded component 140 to fix the main body 110 .

[0059] In at least one embodiment of the present application, the distances between the two discharge ports 110b and the axis of the abutting cavity 111a are equal.

[0060] Please refer to Figure 1-Figure 4 In this embodiment, before pouring, the main body 110 is attached to the outer peripheral surface of the embedded component 140 through the abutment cavity 111a. At this time, the axis of the abutment cavity 111a coincides with the axis of the embedded component 140.

[0061] Concrete is poured into the accommodating chamber 110a through a pump pipe 150 or manually, and the concrete flows to the two discharge ports 110b under the action of gravity.

[0062] Since the distances between the two discharge ports 110 b and the axis of the abutting cavity 111 a are equal, concrete will flow out from the two equidistant discharge ports 110 b at the same time and flow to the two sides of the embedded component 140 respectively.

[0063] The flow of concrete causes the pressure on both sides of the embedded component 140 to be balanced, thus ensuring that the embedded component 140 will not be tilted or deviated due to the uneven force on one side.

[0064] Since the distances from the two discharge ports 110b to the axis of the abutment cavity 111a are equal, the embedded component 140 can be evenly stressed during pouring, thereby reducing the deviation or tilting problem that may occur during the pouring process. The embedded component 140 can remain vertical, improving the installation accuracy.

[0065] Through the symmetrical layout of the discharge port 110b design, concrete can be evenly distributed on both sides of the embedded part 140, which greatly improves the pouring accuracy, avoids construction errors caused by unilateral pouring, and ensures the balance of force during the entire pouring process, so that the embedded part 140 always maintains a stable state during the entire pouring process, reduces unnecessary adjustments or rework during the construction process, and improves construction efficiency.

[0066] The two discharge ports 110b are equidistant from the axis of the abutment cavity 111a, so that the forces generated when the concrete flows out of the discharge ports 110b are opposite in direction and equal in magnitude, thereby forming a force balance state and avoiding tilting of the embedded part 140 due to uneven force.

[0067] In at least one embodiment of the present application, the accommodating cavity 110a has a bottom wall 110c, the main body 110 has a first side wall 110d and a second side wall 110e disposed away from the first side wall 110d, and the abutting portion 111 is disposed on the first side wall 110d;

[0068] The bottom wall 110c is disposed obliquely downward from the second side wall 110e toward the first side wall 110d.

[0069] In at least one embodiment of the present application, the angle between the bottom wall 110c and the horizontal plane is α, which satisfies the relationship: 15°<α<30°.

[0070] Please refer to Figure 1-Figure 4 In this embodiment, during construction, the device is attached to the outer peripheral surface of the embedded part 140 through the abutment portion 111, the first side wall 110d is close to the embedded part 140, and the second side wall 110e is located on the side away from the embedded part 140.

[0071] When concrete is poured into the accommodating cavity 110a, due to the inclination of the bottom wall 110c, the concrete naturally flows to a lower position under the action of gravity, and the lower position is close to the first side wall 110d (that is, close to the side of the embedded component 140).

[0072] The concrete flows along the inclined bottom wall 110 c and finally flows out from the two discharge ports 110 b to the two sides of the embedded component 140 respectively.

[0073] Since the concrete flows out from the two symmetrical discharge ports 110 b at the same time, and the inclined design of the bottom wall 110 c of the accommodating cavity 110 a helps the concrete to flow smoothly to the two sides of the embedded component 140 , the uniformity of pouring is ensured.

[0074] The bottom wall 110c is designed to be inclined from the second side wall 110e to the first side wall 110d, and gravity is used to make the concrete flow automatically toward the discharge port 110b. This reduces the possibility of concrete being retained in the accommodating cavity 110a, and ensures that the concrete can flow smoothly and evenly toward the discharge port 110b, thereby achieving a continuous pouring process.

[0075] The tilt angle α is set between 15° and 30° to ensure that the concrete has a moderate flow rate during the pouring process and reduce the impact force when the concrete falls. A too small angle may cause the concrete to flow slowly, affecting the construction efficiency; while a too large angle may cause the concrete to flow too fast, making it difficult to control the pouring process and affecting the pouring accuracy. This ensures the balance of concrete flow, which can ensure smooth flow and maintain precise control of the pouring process.

[0076] Concrete will preferentially flow around the embedded part 140 and be poured simultaneously through two symmetrical discharge ports 110b, which not only makes the concrete evenly distributed on both sides of the embedded part 140, but also avoids the tilting problem of the embedded part 140 that may occur during the one-side pouring process, thereby improving the stability and accuracy of the overall construction.

[0077] In at least one embodiment of the present application, the first side wall 110 d has a blocking portion 112 at both ends, and the discharge port 110 b is formed between the two blocking portions 112 and the abutting portion 111 .

[0078] Please refer to Figure 1-Figure 4 In this embodiment, the main body 110 is fitted with the outer peripheral surface of the embedded part 140 through the abutment portion 111 on the first side wall 110d, and the flow path is physically restricted by the abutment portion 112 to ensure that the discharge port 110b can be in the correct position of the embedded part 140.

[0079] After pouring concrete into the accommodating chamber 110a, the concrete begins to flow toward the discharge port 110b under the action of gravity. At this time, the blocking portion 112 restricts the concrete from flowing out of the two sides of the accommodating chamber 110a, and guides the concrete to the two predetermined discharge ports 110b.

[0080] Concrete flows out through two symmetrical discharge ports 110b and is poured toward the two sides of the embedded part 140. The blocking portion 112 ensures that the flow path of the concrete does not deviate, the flow direction is controlled, and the pouring process is more stable.

[0081] Since the blocking portion 112 blocks the lateral outflow of concrete, it is ensured that the concrete can be evenly distributed near the discharge port 110b and accurately enter the two sides of the embedded part 140, ensuring the symmetry and stability during the pouring process.

[0082] The setting of the blocking portion 112 effectively prevents excessive loss of concrete from both sides during the pouring process, so that the concrete can only flow out from the discharge port 110b, ensuring accurate control of the flow path, which helps to improve the effectiveness of concrete pouring and avoid waste or uncontrolled flow.

[0083] Since the blocking portion 112 guides the concrete to two symmetrical discharge ports 110b, the uniformity and symmetry of the flow are ensured. Compared with the traditional one-way pouring method, the balance of the pouring process is improved, the tilt or deviation of the embedded part 140 caused by uneven pouring is reduced, and the installation accuracy is improved.

[0084] The stopper 112 also plays a role in strengthening the structure. By providing the stopper 112 at both ends of the first side wall 110d, the overall structure of the main body 110 is strengthened, so that it can better withstand the flow pressure of concrete during the pouring process, ensuring that the device is not easily deformed or displaced.

[0085] The arrangement of the abutment portion 112, the abutment portion 111 and the discharge port 110b ensures that the force of the concrete on both sides of the embedded part 140 is balanced. The balanced force can prevent the embedded part 140 from tilting due to the lateral force, so that the embedded part 140 can better maintain verticality and improve the stability of the construction.

[0086] It should be noted that the blocking portion 112 is a vertically arranged plate.

[0087] In at least one embodiment of the present application, the opening directions of the two discharge ports 110b are perpendicular to the first side wall 110d.

[0088] Please refer to Figure 1-Figure 4In this embodiment, the opening direction of the discharge port 110b is perpendicular to the first side wall 110d, and the direction of the discharge port 110b (i.e. the direction of the concrete flowing out) is to flow outward from the first side wall 110d, and is perpendicular to the first side wall 110d. This ensures that the concrete can flow directly and evenly to both sides of the embedded part 140, rather than flowing along the side of the first side wall 110d.

[0089] The main body 110 is attached to the outer peripheral surface of the embedded component 140 through the abutment portion 111 on the first side wall 110d. At this time, the two discharge ports 110b are arranged perpendicular to the first side wall 110d, ready to guide the concrete to the two sides of the embedded component 140 when it is injected.

[0090] After being injected from the accommodating cavity 110a, concrete flows through the discharge port 110b to both sides of the embedded component 140. Since the discharge port 110b is perpendicular to the first side wall 110d, the concrete will flow out vertically and be evenly distributed on both sides of the embedded component 140.

[0091] The direction in which the concrete flows out of the discharge port 110b is perpendicular to the first side wall 110d, ensuring that the concrete directly acts on both sides of the embedded part 140. This prevents the concrete from rubbing against the side wall or losing control during the flow process, ensuring that the flow path is clear and controlled.

[0092] The vertical flow ensures that the concrete is evenly distributed on both sides of the embedded part 140, completing a stable bidirectional pouring process.

[0093] The arrangement of the discharge port 110b perpendicular to the first side wall 110d ensures that when the concrete flows out of the accommodating cavity 110a, it will not spread along the side wall or get out of control, but will flow precisely toward both sides of the embedded part 140. The vertical flow direction makes the pouring of concrete more precise and reduces the deviation of the flow path.

[0094] The arrangement of the discharge port 110b perpendicular to the side wall ensures symmetrical flow of concrete on both sides, thereby forming a uniform pouring effect on both sides of the embedded part 140. Compared with inclined or lateral flow, this design effectively avoids excessive force on one side or uneven pouring, and improves the overall pouring accuracy.

[0095] In at least one embodiment of the present application, the axis of the embedded component 140 is located on the line connecting the two discharge ports 110b.

[0096] In this embodiment, the abutting cavity of the main body 110 is fitted with the outer peripheral surface of the embedded part 140, ensuring that the axis of the embedded part 140 is accurately located on the line between the two discharge ports 110b, and after the concrete is poured into the accommodating cavity 110a, it flows out through the two symmetrical discharge ports 110b. Since the axis of the embedded part 140 is located on the line between the two discharge ports 110b, the flow of concrete will act on both sides of the embedded part 140 at the same time.

[0097] The discharge ports 110b are arranged symmetrically, and the concrete acts evenly on both sides of the embedded part 140 from both sides to maintain symmetry. Since the axis of the embedded part 140 is located between these two points, the force generated by the concrete acts along the connecting line, ensuring that the embedded part 140 is always in a balanced state during the entire pouring process.

[0098] The symmetrical relationship between the axis of the embedded component 140 and the discharge port 110b ensures that the concrete is evenly distributed during pouring, and the force balance enables the embedded component 140 to remain vertical without tilting.

[0099] The axis of the embedded part 140 is located on the line between the discharge ports 110b, ensuring that the forces on both sides are uniform during pouring. Since the concrete flows out from two symmetrical discharge ports 110b, the forces on the embedded part 140 during the pouring process are symmetrical and equal. This avoids the tilt or deviation caused by the uneven force on the embedded part 140, ensuring the stability and verticality of the embedded part 140.

[0100] Since the axis of the embedded part 140 is located on the line between the two discharge ports 110b, it is ensured that it will not deviate from the predetermined position during the pouring process. Precise control is provided during the construction process, so that the embedded part 140 maintains good verticality and symmetry after the pouring is completed.

[0101] By locating the axis of the embedded part 140 on the line between the discharge ports 110b, it is ensured that the concrete is evenly distributed around the embedded part 140. The uniform pouring not only improves the installation accuracy of the embedded part 140, but also improves the overall structural strength of the concrete foundation, ensuring its long-term stability.

[0102] In at least one embodiment of the present application, the photovoltaic micropile foundation concrete bidirectional pouring device 100 further includes:

[0103] The bracket 120 is disposed at the bottom of the main body 110 , and rollers 121 are disposed at the corners of the bottom of the bracket 120 .

[0104] In at least one embodiment of the present application, the photovoltaic micropile foundation concrete bidirectional pouring device 100 further includes:

[0105] One end of the shovel handle 130 is disposed on the main body 110 .

[0106] Please refer to Figure 1-Figure 4 In this embodiment, at the actual construction site, the operator first moves the photovoltaic micropile foundation concrete bidirectional pouring device 100 to a designated pouring position through the roller 121 at the bottom of the bracket 120 .

[0107] When the photovoltaic micropile foundation concrete bidirectional pouring device 100 reaches the preset position, the operator can accurately adjust the position and direction of the device through the shovel handle 130 to ensure that the discharge port 110b can align with the correct position of the embedded part 140. The shovel handle 130 allows the device to be easily pushed and pulled, thereby reducing the trouble during the adjustment process.

[0108] After the photovoltaic micropile foundation concrete bidirectional pouring device 100 reaches the designated pouring position, the photovoltaic micropile foundation concrete bidirectional pouring device 100 can be stably fixed by the bracket 120, ensuring that the device will not slide or shift at will during the pouring process.

[0109] Through the convenient movement of the roller 121 and the precise control of the shovel handle 130, the photovoltaic micropile foundation concrete bidirectional pouring device 100 can quickly complete the pre-positioning and installation operations, and then start the bidirectional pouring of concrete.

[0110] The roller 121 enables the entire photovoltaic micropile foundation concrete bidirectional pouring device 100 to be easily moved, reducing the need for manual handling or the use of heavy machinery. This not only reduces the labor intensity of construction workers, but also improves the mobility of the photovoltaic micropile foundation concrete bidirectional pouring device 100, which is particularly suitable for large construction sites and improves construction efficiency.

[0111] The bracket 120 provides a solid support structure. While the roller 121 provides mobility, the bracket 120 ensures the stability of the device during the pouring process. This allows the device to move flexibly and remain stable during pouring, and will not cause the device to deviate or become unstable due to uneven force during the pouring process.

[0112] It should be noted that the bracket 120 is a right-angled triangle frame, so that the bottom wall 110 c of the main body 110 is inclined relative to the horizontal plane.

[0113] A casting method is applied to the photovoltaic micropile foundation concrete bidirectional casting device 100 described above, the method comprising:

[0114] The photovoltaic micropile foundation concrete bidirectional pouring device 100 is placed at the pouring position, so that the abutting cavity abuts against the circumference of the embedded part 140, and the two discharge ports 110b are located on both sides of the embedded part 140 and face both sides of the circumference of the embedded part 140;

[0115] Concrete is injected into the accommodating cavity 110a so that the concrete flows from the accommodating cavity 110a to the two discharge ports 110b and then flows from the two discharge ports 110b to the opposite sides of the embedded component 140, so as to generate forces of opposite directions and magnitudes on the two sides of the embedded component 140 for pouring.

[0116] In this embodiment, the operator first places the photovoltaic micropile foundation concrete bidirectional pouring device 100 around the embedded part 140 to ensure that the abutment cavity is tightly fitted with the outer peripheral surface of the embedded part 140. The two discharge ports 110b are aligned with both sides of the embedded part 140 to ensure that the concrete can be poured evenly.

[0117] Concrete is poured into the accommodating chamber 110a, and the concrete flows downward along the inclined bottom wall 110c of the accommodating chamber 110a to the two discharge ports 110b. The discharge ports 110b are symmetrically located on both sides of the embedded part 140, and the concrete flows evenly to the embedded part 140.

[0118] Concrete flows out symmetrically from the two discharge ports 110b, respectively, to opposite sides of the embedded component 140. In this process, since the two discharge ports 110b are symmetrically designed, the force generated by the concrete is balanced on both sides of the embedded component 140, and the embedded component 140 will not tilt or deflect.

[0119] After pouring, concrete is evenly filled on both sides of the embedded part 140, and the embedded part 140 is stably and vertically fixed to the ground.

[0120] By setting the discharge port 110b on both sides of the embedded part 140 and ensuring that the force of the concrete on the embedded part 140 is opposite and equal in magnitude, the problem of uneven force caused by one-sided pouring is eliminated. The two-way symmetrical pouring method greatly improves the installation accuracy and stability of the embedded part 140 and avoids deflection caused by uneven pouring.

[0121] In the traditional single-sided pouring, the embedded part 140 is easily deflected by the unidirectional impact force, resulting in subsequent rework. However, this method balances the forces on both sides of the embedded part 140 through bidirectional symmetrical pouring, avoiding the deviation phenomenon. This effectively improves the construction quality and reduces the possibility of rework.

[0122] The bidirectional symmetrical pouring method ensures that the concrete on both sides of the embedded part 140 is evenly distributed, making the foundation strength around the embedded part 140 more balanced and stable, thereby enhancing the overall structural strength of the photovoltaic foundation and increasing the stability for long-term use.

[0123] The above is only an implementation method of the present application. It should be pointed out that a person skilled in the art can make improvements without departing from the inventive concept of the present application, but these improvements are within the scope of protection of the present application.

Claims

1. A photovoltaic micropile foundation concrete bidirectional pouring device, characterized in that: include: The main body is provided with a containing cavity and two discharge ports communicated with the containing cavity, wherein the containing cavity is used to contain concrete; One side of the main body is inwardly recessed to form an abutment portion, the abutment portion is formed with an abutment cavity for fitting the outer peripheral surface of the embedded component, the abutment cavity is communicated with the two discharge ports, and the abutment cavity is located between the two discharge ports; During pouring, the concrete in the accommodating cavity flows out from the two discharge ports, which are symmetrical about the axis of the embedded part, and are poured toward the opposite sides of the embedded part to generate forces of opposite directions and magnitudes on the two sides of the embedded part.

2. The photovoltaic micropile foundation concrete bidirectional pouring device according to claim 1, characterized in that: The distances between the two discharge ports and the axis of the abutment cavity are equal.

3. The photovoltaic micropile foundation concrete bidirectional pouring device according to claim 1, characterized in that: The accommodating cavity has a bottom wall, the main body has a first side wall and a second side wall disposed away from the first side wall, and the abutting portion is disposed on the first side wall; The bottom wall is arranged obliquely downward from the second side wall toward the first side wall.

4. The photovoltaic micropile foundation concrete bidirectional pouring device according to claim 3, characterized in that: The angle between the bottom wall and the horizontal plane is α, which satisfies the relationship: 15°<α<30°.

5. The photovoltaic micropile foundation concrete bidirectional pouring device according to claim 3, characterized in that: The first side wall has a blocking portion at both ends, and the discharge port is formed between the two blocking portions and the abutting portion.

6. The photovoltaic micropile foundation concrete bidirectional pouring device according to claim 3, characterized in that: The opening directions of the two discharge ports are arranged perpendicular to the first side wall.

7. The photovoltaic micropile foundation concrete bidirectional pouring device according to claim 1, characterized in that: The axis of the embedded part is located on the connecting line between the two discharge ports.

8. The photovoltaic micropile foundation concrete bidirectional pouring device according to claim 1, characterized in that: The photovoltaic micro-pile foundation concrete bidirectional pouring device also includes: The bracket is arranged at the bottom of the main body, and the corners of the bottom of the bracket are provided with rollers.

9. The photovoltaic micropile foundation concrete bidirectional pouring device according to claim 1, characterized in that: The photovoltaic micro-pile foundation concrete bidirectional pouring device also includes: A shovel handle has one end disposed on the main body.

10. A casting method, applied to the photovoltaic micropile foundation concrete bidirectional casting device according to any one of claims 1 to 9, characterized in that: The method comprises: Place the photovoltaic micropile foundation concrete bidirectional pouring device at the pouring position, so that the abutment cavity abuts against the peripheral surface of the embedded part, and the two discharge ports are located on both sides of the embedded part and face the two sides of the peripheral surface of the embedded part; Concrete is injected into the accommodating cavity so that the concrete flows from the accommodating cavity to the two discharge ports, and then flows from the two discharge ports to the opposite sides of the embedded part, so as to generate forces of opposite directions and magnitudes on the two sides of the embedded part for pouring.