Ground splicing and hydraulic integral lifting construction method for aerial corridor

Through the prefabricated assembled steel corridor and hydraulic overall lifting method, combined with the design of lifting tracks and connecting tracks, the problems of low efficiency and safety hazards in air corridor construction are solved, and more efficient and more Safe lifting process.

CN118958479APending Publication Date: 2024-11-15CHINA CONSTR THIRD ENG BUREAU GRP SOUTH CHINA CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411049240.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-01
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The existing aerial corridor construction methods have low efficiency, low accuracy and high safety risks. Especially during the super high-rise hoisting process, the offset value accumulates greatly, and requires multiple pauses for fine adjustments, which increases safety risks.

Method used

The prefabricated assembled steel corridor and hydraulic overall lifting method are adopted. By setting up lifting tracks and connecting tracks, loading and unloading step by step, the stability and precise position of the steel corridor during the lifting process are ensured, and deformation is monitored by computer simulation and Displacement, dynamically adjust the lifting speed and unloading process.

Benefits of technology

It greatly reduces the offset accumulation value and safety hazards during the lifting process, shortens the lifting time, improves the lifting efficiency and quality, and ensures the smooth positioning of the steel corridor and the safety of lifting equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118958479A_ABST
    Figure CN118958479A_ABST
Patent Text Reader

Abstract

The invention relates to a ground splicing and hydraulic integral lifting construction method for an air corridor, which comprises the following steps: splicing a steel corridor structure on a floor, arranging a hoisting track above the spliced steel corridor, arranging a connecting track below a reserved section, arranging a lifting bracket above the reserved section, and mounting lifting equipment and a steel strand in the lifting bracket; debugging a lifting equipment system; after the steel corridor is assembled, after comprehensive inspection and acceptance are carried out, pre-lifting is carried out; carrying out integral lifting operation on the corridor; when the corridor is lifted to about 20 cm away from the designed height, the lifting speed is reduced, fine adjustment operation is conducted, and the corridor is accurately in place; mounting and welding of the steel corridor and the reserved section are completed; step-by-step unloading is carried out; according to the method, the safe, stable and accurate in-position of the aerial corridor is ensured by accurately controlling the lifting process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building construction, and in particular to a ground assembly and hydraulic overall lifting construction method for an aerial corridor, which ensures the safety, stability and precise positioning of the aerial corridor by precisely controlling the lifting process. Background Art

[0002] The existing aerial corridor construction method has problems such as low lifting efficiency, low precision, and potential safety hazards. In particular, the hoisting process of super-high-rise buildings is relatively long, and the accumulated offset value during the hoisting process is relatively large. It is necessary to pause several times in the middle to consume part of the accumulated offset value. When it is lifted to the design elevation, it is often necessary to hover to completely consume the accumulated offset value before the corridor can be fine-tuned in place. Due to the hoisting time process, the potential safety hazards of hoisting are further increased. In order to solve these problems, the present invention provides a new construction method. Summary of the invention

[0003] The present invention provides a method for ground assembly and hydraulic overall lifting of an aerial corridor, which is implemented by the following technical solutions:

[0004] A method for ground assembly and hydraulic overall lifting of an aerial corridor, wherein the corridor is arranged as a prefabricated steel corridor, the steel corridor is arranged between two buildings, a prefabricated reserved section is installed at the design position of each side building for docking with the steel corridor, and the construction also includes installing the steel corridor on the lower construction surface by assembling a tire frame, installing a lifting track and a connecting track, installing and correcting a lifting platform, lifting load test and formal lifting, unloading and steel corridor docking construction, including the following steps:

[0005] Step 1: Install the steel corridor assembly frame on the lower construction surface, and assemble the steel corridor as a whole on the frame. After the steel corridor is assembled, conduct a comprehensive inspection and acceptance.

[0006] Step 2: Set a lifting track above the assembled steel corridor, set a connecting track below the reserved section, set a lifting bracket above the reserved section, install the lifting equipment and steel strands in the lifting bracket, and debug the lifting equipment system;

[0007] Step 3: Pre-lift the steel corridor, i.e. load it in stages so that the entire steel corridor is about 100mm away from the frame. After confirming that there is no abnormality, mechanically lock the lifting equipment, let it stand for 18 hours, and conduct a comprehensive inspection again;

[0008] Step 4: During the comprehensive inspection, measure whether the steel corridor has any deformation, etc. After confirming that there is no abnormality, carry out the overall lifting operation of the steel corridor;

[0009] Step 5: Slowly lift the steel corridor at half the normal lifting speed, and make the ends of the steel beams of the steel corridor enter the lifting track. When the ends of the steel corridor move to the middle of the lifting track, smoothly accelerate the lifting speed to the normal lifting speed;

[0010] Step 6: When the steel corridor is lifted to 20cm below the connecting track, reduce the lifting speed to half of the normal lifting speed, so that the ends of the steel beams of the steel corridor enter the connecting track, and continue to lift the steel corridor;

[0011] Step 7: When the steel corridor is lifted to about 20 cm from the designed height, the lifting speed is further reduced to one-fourth of the normal lifting speed, and fine-tuning is started to ensure that the corridor is precisely in place;

[0012] Step 8: After the installation and welding of the steel corridor and the reserved section are completed and accepted, the lifting equipment is unloaded step by step to determine the stress changes of the unloading step by step. Computer simulation is used to perform data detection during the unloading process, including deformation monitoring of the steel corridor during the unloading stage, vertical displacement monitoring of the main structure at each unloading point, and three-dimensional absolute displacement monitoring of the structural control points;

[0013] Step 9: After the step-by-step unloading of the lifting equipment is completed, the steel corridor will enter the next process after acceptance, and the lifting bracket, connecting rail, lifting rail and tire frame will be dismantled.

[0014] Furthermore, in the second step, the lifting rails, connecting rails, lifting brackets and reserved sections corresponding to the ends of the steel beams of the same steel corridor are all in the same straight line.

[0015] Furthermore, in the second step, the lifting rail and the connecting rail both include a straight segment and an oblique segment, and guide wheels are provided in the two side plates of the straight segment and the oblique segment. There are multiple guide wheels and they are arranged at intervals. The oblique segment forms a trumpet mouth, and the distance between the two side plates of the oblique segment gradually decreases from bottom to top. The distance at the upper end is the same as the distance between the two side plates of the straight segment, and the guide wheels are made of silicone.

[0016] Furthermore, in the third step, by observing and monitoring the corridor structure, lifting facilities, and lifting equipment system during the trial lifting process, it is confirmed that the simulated working condition calculation and design conditions are met to ensure the safety of the lifting process; based on the reaction force values ​​of each lifting point calculated by computer simulation, the corridor steel structure unit is loaded in stages, and the extension cylinder pressure of the hydraulic lifting system at each lifting point should be slowly increased in stages, 20%, 40%, 60%, and 80% in sequence; after confirming that there are no abnormalities in each part, continue to load to 90%, 95%, and 100% until the steel corridor is completely separated from the assembly frame; in the process of graded loading, after each step of graded loading is completed, the deformation of the upper hanging point, the lower hanging point structure, and the corridor structure before and after loading, as well as the stability of the main building structure, are paused and checked; after completing the inspection, the next step of graded loading is continued; when the graded loading is completed to the point where the structure is about to leave the assembly frame, there are points that do not leave the ground at the same time, at this time, the lifting speed is reduced, and the ground separation of each point is closely observed, and "single-point movement" lifting is performed; ensure that the corridor is stable off the ground and each point is synchronized.

[0017] Furthermore, in the eighth step, the deformation of the steel corridor in the unloading stage, the vertical displacement of the main structure of each unloading point, and the three-dimensional absolute displacement of the structural control points are monitored during the step-by-step unloading of the lifting equipment to confirm that the simulation working condition calculation and design conditions are met to ensure the safety of the unloading process; based on the reaction force value of each lifting point calculated by computer simulation, the corridor steel is unloaded step by step, and the extension cylinder pressure of the hydraulic lifting system at each lifting point should be slowly reduced step by step, which is 80%, 60%, 40%, and 20% respectively; after confirming that there is no abnormality in each part, continue to unload to 10%, 5%, and 0%, until all the lower lifting points of the lifting equipment are separated from the steel corridor; in the step-by-step unloading process, after each step of unloading is completed, the deformation monitoring of the steel corridor, the vertical displacement monitoring of the main structure of each unloading point, and the three-dimensional absolute displacement monitoring of the structural control points are paused and the stability of the main building structure is checked; after the inspection is completed, continue to the next step of step-by-step unloading.

[0018] After adopting the above technical solution, the beneficial effects of the present invention are:

[0019] 1. The construction method of the present invention provides a lifting track to adjust the stability of the steel corridor before it is lifted at a uniform speed, thereby ensuring the lifting stability and reducing the accumulated deviation value of the steel corridor during the lifting process, thereby greatly reducing the potential safety hazards of the lifting;

[0020] 2. The construction method of the present invention sets a connecting track so that when the steel corridor is about to reach the design elevation, the bell mouth of the connecting track can be directly and dynamically adjusted to ensure that the steel corridor is stably positioned when it is close to the design elevation, which greatly reduces the hoisting time of the steel corridor, improves the hoisting efficiency and further reduces the safety hazards of hoisting;

[0021] 3. The construction method of the present invention applies a lifting method of graded lifting and step-by-step unloading, which ensures the hoisting quality of the steel corridor and the safety of lifting, and greatly reduces the strain accumulation of the steel corridor during the lifting and positioning process. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the technical solutions in the implementation modes of the present application, the drawings required for use in the description of the implementation modes will be briefly introduced below. Obviously, the drawings described below are only some implementation modes of the present application. For those skilled in the art, other drawings can be obtained based on these drawings without creative work.

[0023] Figure 1 This is a schematic diagram of the ground assembly and hydraulic overall lifting construction method of the sky corridor.

[0024] Figure 2 Schematic diagram of the steel corridor entering the lifting track.

[0025] Figure 3 Schematic diagram of the steel corridor entering the connecting track.

[0026] Figure 4 A schematic diagram of the upper structure.

[0027] Figure 5 This is a schematic diagram of the steel corridor in place.

[0028] Description of reference numerals:

[0029] 100-steel corridor, 200-tire frame, 300-lifting rail, 400-reserved section, 500-connecting rail, 600-lifting bracket, 700-lifting equipment, 800-steel strand, 901-straight segment, 902-oblique segment, 903-guide wheel. DETAILED DESCRIPTION

[0030] The following description of the embodiments will help the public better understand the present invention, but the specific embodiments given by the applicant cannot and should not be regarded as limitations on the technical solutions of the present invention. Any changes to the definitions of components or technical features, or formal rather than substantive changes to the overall structure should be regarded as the scope of protection defined by the technical solutions of the present invention.

[0031] In this application, unless otherwise clearly specified or limited, the terms "installation", "connection", "fixation" and the like should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be internal communication between two elements, or it can be only surface contact, or surface contact connection through an intermediate medium. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0032] The present invention is implemented by the following technical solutions:

[0033] A method for ground assembly and hydraulic overall lifting of an aerial corridor, wherein the corridor is arranged as a prefabricated steel corridor, the steel corridor is arranged between two buildings, a prefabricated reserved section is installed at the design position of each side building for docking with the steel corridor, and the construction also includes installing the steel corridor on the lower construction surface by assembling a tire frame, installing a lifting track and a connecting track, installing and correcting a lifting platform, lifting load test and formal lifting, unloading and steel corridor docking construction, including the following steps:

[0034] The first step: installing the steel corridor 100 on the floor and assembling the tire frame 200, and assembling the steel corridor 100 on the tire frame 200. After the steel corridor 100 is assembled, a comprehensive inspection and acceptance is carried out;

[0035] Step 2: A lifting track 300 is set above the assembled steel corridor 100, a connecting track 500 is set below the reserved section 400, and a lifting bracket 600 is set above the reserved section 400. The lifting track 300, the connecting track 500, the lifting bracket 600 and the reserved section 400 at the end of the steel beam of the same steel corridor 100 are all in the same straight line, and the lifting equipment 700 and the steel strand 800 are installed in the lifting bracket 600, and the lifting equipment 700 system is debugged; and the lifting track 300 and the connecting track 500 both include a straight line segment 901 and an oblique line segment 902, and both side plates of the straight line segment 901 and the oblique line segment 902 are A guide wheel 903 is provided, and a plurality of guide wheels 903 are provided and are arranged at intervals. The oblique line segment 902 forms a trumpet mouth, and the distance between the two side plates of the oblique line segment 902 gradually decreases from bottom to top, and the distance at the upper end is the same as the distance between the two side plates of the straight line segment 901. The guide wheel 903 is made of silicone. By setting the guide wheel 903, the lifting of the steel corridor 100 can be limited and the lifting can be made more stable. The trumpet mouth setting can pre-adjust the steel corridor 100 before entering the track. The silicone guide wheel 903 is elastic, and can protect the steel corridor 100 while softly limiting it, thereby improving the hoisting stability of the steel corridor 100.

[0036] The third step: pre-lift the steel corridor 100, that is, load in stages to make the steel corridor 100 as a whole separate from the tire frame 200 by about 100mm. Through observation and monitoring of the corridor structure, lifting facilities, and lifting equipment 700 system during the trial lifting process, it is confirmed that it meets the simulated working condition calculation and design conditions to ensure the safety of the lifting process; based on the reaction force value of each lifting point calculated by computer simulation, the corridor steel structure unit is loaded in stages, and the extension cylinder pressure of the hydraulic lifting system at each lifting point should be slowly increased in stages, in the order of 20%, 40%, 60%, and 80%; after confirming that there is no abnormality in each part, continue to load to 90%, 95%, and 100%. Until all the steel corridors 100 are separated from the assembly frame 200; during the graded loading process, after each step of graded loading is completed, the deformation of the upper and lower hanging points, the lower hanging point structure, and the corridor structure before and after loading, as well as the stability of the main building structure, are paused and checked; after the inspection is completed, the next step of graded loading is continued; when the graded loading is to the point where the structure is about to leave the assembly frame 200, there are points that are not lifted off the ground at the same time, at this time, the lifting speed is reduced, and the lifting situation of each point is closely observed, and "single-point movement" lifting is performed; ensure that the corridor is stable off the ground and each point is synchronized; after confirming that there is no abnormality, the lifting equipment 700 is mechanically locked, left to stand for 18 hours, and a comprehensive inspection is performed again;

[0037] Step 4: During the comprehensive inspection, the steel corridor 100 is measured for deformation and the like. After confirming that there is no abnormality, the overall lifting operation of the steel corridor 100 is performed;

[0038] Step 5: slowly lift the steel corridor 100 at a speed half the normal lifting speed, and make the ends of the steel beams of the steel corridor 100 enter the lifting track 300. When the ends of the steel corridor 100 move to the middle section of the lifting track 300, smoothly accelerate the lifting speed to the normal lifting speed;

[0039] Step 6: When the steel corridor 100 is lifted to 20 cm below the connecting track 500, the lifting speed is reduced to half of the normal lifting speed, so that the ends of the steel beams of the steel corridor 100 all enter the connecting track 500, and the steel corridor 100 is continued to be lifted;

[0040] Step 7: When the steel corridor is lifted 100 to about 20 cm from the designed height, the lifting speed is further reduced to one-fourth of the normal lifting speed, and fine-tuning is started to ensure that the corridor is accurately positioned;

[0041] Step 8: After the installation and welding of the steel corridor 100 and the reserved section 400 are completed and accepted, the lifting equipment 700 is unloaded step by step to determine the stress changes of the unloading step by step. Computer simulation is used to perform data detection during the unloading process, including deformation monitoring of the steel corridor 100 during the unloading stage, vertical displacement monitoring of the main structure of each unloading point, and three-dimensional absolute displacement monitoring of the structural control points. Through the step-by-step unloading of the lifting equipment 700, the deformation monitoring of the steel corridor 100 during the unloading stage, the vertical displacement monitoring of the main structure of each unloading point, and the three-dimensional absolute displacement monitoring of the structural control points are carried out to confirm that the simulation working condition calculation and design conditions are met to ensure the safety of the unloading process. Based on the reaction force values ​​of each lifting point calculated by simulation, the corridor steel is unloaded step by step. The extension cylinder pressure of the hydraulic lifting system at each lifting point should be slowly reduced step by step, in the order of 80%, 60%, 40%, and 20%; after confirming that there is no abnormality in each part, continue to unload to 10%, 5%, and 0%, until all the lower lifting points of the lifting equipment 700 are separated from the steel corridor 100; in the step-by-step unloading process, each step of unloading is completed, and the deformation monitoring of the steel corridor 100, the vertical displacement monitoring of the main structure of each unloading point, and the three-dimensional absolute displacement monitoring of the structural control points are paused and the stability of the main building structure is checked; after the inspection is completed, continue to the next step of step-by-step unloading;

[0042] Step 9: After the step-by-step unloading of the lifting equipment 700 is completed, the steel corridor 100 is inspected and accepted and then enters the next process to dismantle the lifting bracket 600, the connecting rail 500, the lifting rail 300 and the tire frame 200.

[0043] In addition, when the lifting equipment lifts the steel corridor to the reserved section for installation, it is necessary to perform fine-tuning through the lifting equipment to align the positions of the steel corridor and the reserved section. Since the steel corridor is heavy, the up and down positions are generally adjusted manually after the lifting equipment is fixed, which may cause tilting or centering problems. Therefore, when setting the connecting rails, friction parts and locking parts are provided on the straight sections thereof. When the steel corridor gradually approaches the centering position of the reserved section, the friction parts and the docking position of the steel corridor have buffering friction, which reduces its lifting rate and ensures the effect of fine-tuning. Locking with the locking parts can reduce the separate force of the upper lifting equipment. In addition, the locking parts can be set as pins and movable hooks for temporary support.

[0044] Those skilled in the art should understand that those skilled in the art can implement variations by combining the prior art and the above embodiments, which will not be described in detail here. Such variations do not affect the essential content of the present invention, and will not be described in detail here.

[0045] The above describes the preferred embodiments of the present invention. It should be understood that the present invention is not limited to the above-mentioned specific embodiments, and the devices and structures that are not described in detail should be understood to be implemented in a common manner in the art; any technician familiar with the art can use the above-disclosed methods and technical contents to make many possible changes and modifications to the technical solutions of the present invention without departing from the scope of the technical solutions of the present invention, or modify them into equivalent embodiments of equivalent changes, which does not affect the essential content of the present invention. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments based on the technical essence of the present invention without departing from the content of the technical solutions of the present invention are still within the scope of protection of the technical solutions of the present invention.

Claims

1. A construction method for ground assembly and hydraulic overall lifting of an aerial corridor, wherein the corridor is arranged as a prefabricated steel corridor, the steel corridor is arranged between two buildings, and a prefabricated reserved section is installed at the design position of each side building for docking with the steel corridor. The construction also includes installing the steel corridor on the lower construction surface by assembling a tire frame, installing a lifting track and a connecting track, installing and correcting a lifting platform, lifting load test and formal lifting, unloading and steel corridor docking construction, characterized in that: The following steps are involved: Step 1: Install the steel corridor assembly frame on the lower construction surface, and assemble the steel corridor as a whole on the frame. After the steel corridor is assembled, conduct a comprehensive inspection and acceptance. Step 2: After the steel corridor is assembled, the hoisting track is installed between the buildings on both sides, the connecting track is installed below the reserved section, the lifting bracket is installed above the reserved section, the lifting equipment and steel strands are installed in the lifting bracket, and the lifting equipment system is debugged; Step 3: Pre-lift the steel corridor, i.e. load it in stages so that the entire steel corridor is about 100mm away from the frame. After confirming that there is no abnormality, mechanically lock the lifting equipment, let it stand for 18 hours, and conduct a comprehensive inspection again; Step 4: During the comprehensive inspection, measure whether the steel corridor has any deformation, etc. After confirming that there is no abnormality, carry out the overall lifting operation of the steel corridor; Step 5: Slowly lift the steel corridor at half the normal lifting speed, and make the ends of the steel beams of the steel corridor enter the lifting track. When the ends of the steel corridor move to the middle of the lifting track, smoothly accelerate the lifting speed to the normal lifting speed; Step 6: When the steel corridor is lifted to 20cm below the connecting track, reduce the lifting speed to half of the normal lifting speed, so that the ends of the steel beams of the steel corridor enter the connecting track, and continue to lift the steel corridor; Step 7: When the steel corridor is lifted to about 20 cm from the designed height, the lifting speed is further reduced to one-fourth of the normal lifting speed, and fine-tuning is started to ensure that the corridor is precisely in place; Step 8: After the steel corridor and the reserved section are installed and welded, the lifting equipment is unloaded step by step to determine the stress changes of the unloading step by step. Computer simulation is used to perform data detection during the unloading process, including deformation monitoring of the steel corridor during the unloading stage, vertical displacement monitoring of the main structure at each unloading point, and three-dimensional absolute displacement monitoring of the structural control points; Step 9: After the step-by-step unloading of the lifting equipment is completed, the steel corridor will enter the next process after acceptance, and the lifting bracket, connecting rail, lifting rail and tire frame will be dismantled.

2. The method for ground assembly and hydraulic overall lifting of an aerial corridor according to claim 1 is characterized in that: In the second step, the lifting rails, connecting rails, lifting brackets and reserved sections corresponding to the ends of the steel beams of the same steel corridor are all in the same straight line.

3. The method for ground assembly and hydraulic overall lifting of an aerial corridor according to claim 2 is characterized in that: In the second step, the lifting track and the connecting track both include a straight segment and an oblique segment. Guide wheels are provided in both side plates of the straight segment and the oblique segment. There are multiple guide wheels and they are arranged at intervals. The oblique segment forms a bell mouth. The distance between the two side plates of the oblique segment gradually decreases from bottom to top, and the distance at the upper end is the same as the distance between the two side plates of the straight segment. The guide wheels are made of silicone.

4. The method for ground assembly and hydraulic overall lifting of an aerial corridor according to claim 3 is characterized in that: In the third step, by observing and monitoring the corridor structure, lifting facilities, and lifting equipment system during the trial lifting process, it is confirmed that the simulated working condition calculation and design conditions are met to ensure the safety of the lifting process; Based on the reaction force value of each lifting point calculated by computer simulation, the steel structure unit of the corridor is loaded in stages. The extension cylinder pressure of the hydraulic lifting system at each lifting point should be slowly increased in stages, 20%, 40%, 60%, and 80% in sequence; after confirming that there is no abnormality in each part, continue to load to 90%, 95%, and 100% until the steel corridor is completely separated from the assembly frame; in the process of graded loading, after each step of graded loading is completed, pause and check the deformation of the upper and lower hanging points, the lower hanging point structure, and the corridor structure before and after loading, as well as the stability of the main building structure; after completing the inspection, continue to the next step of graded loading; when the graded loading is completed to the point where the structure is about to leave the assembly frame, there are points that do not leave the ground at the same time. At this time, reduce the lifting speed, closely observe the ground conditions of each point, and perform "single-point movement" lifting to ensure that the corridor is stable and all points are synchronized.

5. The method for ground assembly and hydraulic overall lifting of an aerial corridor according to claim 4 is characterized in that: In the eighth step, the deformation of the steel corridor during the unloading stage, the vertical displacement of the main structure of each unloading point, and the three-dimensional absolute displacement of the structural control point are monitored during the step-by-step unloading of the lifting equipment to confirm that the simulation working condition calculation and design conditions are met to ensure the safety of the unloading process; based on the reaction force value of each lifting point calculated by computer simulation, the corridor steel is unloaded step by step, and the extension cylinder pressure of the hydraulic lifting system at each lifting point should be slowly reduced step by step, in order of 80%, 60%, 40%, and 20%; after confirming that there are no abnormalities in each part, continue to unload to 10%, 5%, and 0%, until all the lower lifting points of the lifting equipment are separated from the steel corridor; in the step-by-step unloading process, after each step of unloading is completed, the deformation monitoring of the steel corridor, the vertical displacement monitoring of the main structure of each unloading point, and the three-dimensional absolute displacement monitoring of the structural control point are paused and the stability of the main building structure is checked; After the inspection is complete, proceed to the next step to uninstall step by step.