Hyperbolic curve type steel structure installation method suitable for building
By dividing the steel structure components into units and assembling them on the tire frame, combining lifting components and three-dimensional measurement technology, the accuracy and efficiency problems of traditional hyperbolic steel structure installation are solved, and a hyperbolic steel structure with high accuracy and smooth appearance is achieved Install.
Patent Information
- Application Number
- CN202411433526.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-10-15
- Publication Date
- 2024-11-15
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
The installation of traditional hyperbolic steel structures is difficult to achieve with high accuracy requirements, low installation efficiency, high cost, and difficult to adjust the attitude of aerial lifting, which makes it difficult to control the construction quality and the appearance is not smooth enough.
The steel structure components are divided into several steel structure units, assemble and adjust the posture on the tire frame, and ensure accurate position through precise lifting and three-dimensional coordinate measurement of the lifting components. The adjustable lifting rope and support frame structure are used to adapt to units of different sizes to ensure docking. Accurate and installation quality.
It improves installation accuracy and construction efficiency, avoids misalignment, ensures the overall streamline beauty and construction quality of steel structure components, and reduces material costs.
Smart Images

Figure CN118958500A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of buildings, relates to steel structures of buildings, and in particular to an installation method of a hyperbolic steel structure suitable for buildings. Background Art
[0002] With the advancement of science and technology and the continuous development of engineering technology, high-rise buildings have emerged. Various flexible hyperbolic steel structures are usually used for exterior design, which have unique spatial characteristics and aesthetic value. Traditional hyperbolic steel structures are assembled from several spatially bent and twisted steel pipe structural components, which have the following problems: 1. Several steel pipe structural components need to be hoisted to the designated location for installation in sequence. The installation accuracy requirements are high, and deviations are easy to occur during docking and fixing. In addition, the high-altitude welding workload of the assembled parts is large, the installation efficiency is low, and the cost is high; 2. The posture of steel pipe structural components hoisted in the air is inconvenient to adjust, and it is difficult to control and install. It is easy for two adjacent components to be misaligned when installed, and the construction quality is difficult to control, resulting in the overall appearance being not smooth enough, which affects the installation of other components.
[0003] Therefore, we propose a hyperbolic steel structure installation method suitable for buildings to solve the above problems. Summary of the invention
[0004] The purpose of the present invention is to overcome the deficiencies of the prior art and to provide a method for installing a hyperbolic steel structure suitable for buildings which is simple to install and has a precise posture.
[0005] To solve the above problems, the technical solution of the present invention is: A method for installing a hyperbolic steel structure applicable to a building, wherein the building comprises a core tube and a steel structure component, wherein the steel structure component is fixedly installed on the outer side of the core tube, and the method comprises the following steps: Step S101: Divide steel structure units Establish a model of the steel structure component and divide the steel structure component into several steel structure units in the model; Step S103: Assembling steel structure units Assembling the steel structure unit on the tire frame assembly; Step S105: Install the steel structure unit The assembled steel structure units are hoisted by hoisting components, and the posture of the steel structure units is adjusted during hoisting; Step S107: Detect the position of the steel structure unit The actual coordinates of several steel structure units are measured respectively and compared with the design coordinates, and the positions of the steel structure units are adjusted and fixedly installed on the core tube.
[0006] In a further embodiment, in step S103 of assembling the steel structure unit, the coordinates of the first coordinate point, the second coordinate point, the third coordinate point, and the fourth coordinate point at the end of the steel structure unit are converted into projection points on the X-axis and the Y-axis, and the positions of both sides of the tire frame assembly are adjusted to the projection points, which is suitable for installing steel structure units of different sizes.
[0007] In a further embodiment, in step S103 of assembling the steel structure unit, the tire frame assembly includes a first tire frame and a second tire frame which are arranged in sequence, and the steel structure unit is assembled on the first tire frame and the second tire frame respectively; After the assembly is completed, the steel structure unit on the first frame is lifted away, the steel structure unit on the second frame is moved to the first frame, and the next steel structure unit is assembled on the second frame; When assembling the steel structure unit, temporarily fix the two steel structure units on the first frame and the second frame, and release the temporary fixation after the assembly is completed; Repeat this step until all steel structure units are assembled.
[0008] In a further embodiment, the first tire frame includes a plurality of support frames and support frame connecting units, the plurality of support frames are arranged in two rows, the bottom ends of the two rows of support frames are fixedly installed together through the support frame connecting units, and the steel structure unit is placed on the support frames.
[0009] In a further embodiment, the support frame connection unit includes a plurality of sliding bars and a plurality of connecting bars, the sliding bars are fixedly installed between two rows of support frames, and the bottom ends of the plurality of support frames are fixedly installed together via the connecting bars.
[0010] In a further embodiment, the support frame includes a pair of vertical bars and a pair of horizontal bars, the pair of vertical bars are divided into upper and lower parts, the top end of the lower part of the vertical bar is fixedly mounted on the bottom end surface of the slide bar, the slide part is slidably mounted on the slide bar, and the upper part of the vertical bar is fixedly mounted on the slide part; A horizontal bar is fixedly installed between the upper parts and the lower parts of a pair of vertical bars respectively; Reinforcement plates are fixedly installed at both ends of the upper crossbar, which is suitable for limiting the steel structure unit.
[0011] In a further embodiment, the bottom end of the lifting member is fixedly mounted on the sliding portion, and the top end of the lifting member is fixedly mounted on the cross bar, which is suitable for driving the cross bar to move up and down.
[0012] In a further embodiment, in step S105 of installing the steel structure unit, the lifting assembly includes a pair of main lifting ropes and a pair of auxiliary lifting ropes, the pair of main lifting ropes are fixedly installed on both sides of the top end of the steel structure unit, and the pair of auxiliary lifting ropes are installed on both sides of the bottom end of the steel structure unit through a hand chain hoist; After the steel structure unit is lifted off the ground, the length of the auxiliary lifting rope is adjusted by the hand winch, and then the lifting posture of the steel structure unit is adjusted until it meets the designed posture of the steel structure unit.
[0013] In a further embodiment, in step S107, in detecting the position of the steel structure unit, a line is drawn between the center of the core tube and a plurality of steel structure units and extended, and control points are respectively set on the plurality of lines; A reflective sheet is fixedly installed on the top of the steel structure unit, and the three-dimensional coordinates of the reflective sheet are measured at the control point and compared with the theoretical coordinates of the reflective sheet. When the comparison results are consistent, the steel structure unit is welded and fixed.
[0014] In a further embodiment, in step S107 of detecting the position of the steel structure unit, the steps of establishing the three-dimensional coordinates of the reflective sheet are: Set the coordinates of the center of the core tube on the ground to (0,0,0), and set the coordinates of the reflector at the bottom to (0,Y,0), (X1,Y1,0), (X2,Y2,0)... (X n ,Y n ,0), the outer diameter reduction values from the ground to each steel structure unit are set to ΔS1, ΔS2, ΔS3...ΔS n ; The line connecting the steel structure unit and the center of the core tube has an angle with the north direction. The coordinates of each reflector are (X1-ΔS1×cosθ, Y1-ΔS1×sinθ, Z1), (X2-ΔS1×cosθ, Y2-ΔS1×sinθ, Z1)... (X n -ΔS1×cosθ,Y n -ΔS1×sinθ,Z1).
[0015] Compared with the prior art, the present invention has the following beneficial effects: 1. This installation method divides the steel structure components into several steel structure units, and welds the steel structure units in sequence on the tire frame. It can not only weld and form them in advance, reduce the workload of high-altitude welding, reduce the difficulty of installation, improve the installation accuracy and construction efficiency, but also ensure the precise docking of two adjacent steel structure units, avoid misalignment, ensure the overall streamline beauty of the steel structure components, and improve the construction quality.
[0016] 2. After the steel structure unit of this installation method is assembled, the steel structure unit is hoisted by a hoisting assembly, and the posture of the steel structure unit is adjusted in the air; the hoisting assembly includes a pair of main hoisting ropes and a pair of auxiliary hoisting ropes, the pair of main hoisting ropes are fixed in length and fixedly installed at the top end of the steel structure unit, and the pair of auxiliary hoisting ropes are adjustable in length and installed at the bottom end of the steel structure unit by a hand winch. The length of the pair of auxiliary hoisting ropes can be adjusted by the hand winch, and then the posture of the steel structure unit is adjusted, so that the hoisting posture of the steel structure unit conforms to the design posture, which is convenient for fixed installation on the core tube and improves the construction quality.
[0017] 3. This installation method splices steel structure units on a tire frame assembly. The tire frame assembly includes a first tire frame and a second tire frame. The steel structure unit on the first tire frame is assembled first, and then the steel structure unit on the second tire frame is assembled. During the assembly process, the two steel structure units are temporarily fixed. After the assembly is completed, the temporary fixation is released, the steel structure unit on the first tire frame is lifted off, and the steel structure unit on the second tire frame is moved to the first tire frame. Then, the next steel structure unit is assembled on the second tire frame, so that adjacent steel structure units are accurately docked to ensure the installation quality.
[0018] 4. The first tire frame and the second tire frame of the installation method have the same structure. The first tire frame includes two rows of support frames and a support frame connecting unit. The support frame connecting unit includes a plurality of sliding rods and a plurality of connecting rods. The sliding rods are fixedly installed between the two rows of support frames, and the connecting rods are fixedly installed between the plurality of support frames to form a whole. The support frame is divided into an upper part and a lower part. The lower part of the support frame is fixedly installed on the bottom end of the sliding rod. A sliding part is slidably installed on the sliding rod, and an upper part of the support frame is fixedly installed on the sliding part, so that the upper part of the support frame can move left and right along the sliding rod. A lifting member is fixedly installed on the sliding part, and the lifting member drives the cross bar on the upper part of the support frame to move up and down, so that the height of the support frame and the distance between the two rows of support frames can be adjusted. It can be suitable for steel structure units of different sizes, has strong versatility, and can be repeatedly used, thereby reducing material costs.
[0019] 5. When installing the steel structure unit according to this installation method, lines are connected and extended between the center of the core tube and several steel structure units, control points are set on several extension lines, and a station is established at the control points by means of a total station; a reflector is fixedly installed on the top of the steel structure unit, the three-dimensional coordinates of the reflector are obtained by means of the total station, and the three-dimensional coordinates of the reflector are compared with the design coordinates. After confirming that the position of the steel structure unit is correct, welding and fixing are performed to ensure that the installation position of the steel structure unit is accurate. BRIEF DESCRIPTION OF THE DRAWINGS
[0020] Figure 1 A flowchart of a method for installing a hyperbolic steel structure applicable to a building; Figure 2The overall structural diagram of a method for installing a hyperbolic steel structure applicable to a building is shown; Figure 3 A schematic diagram of step S103 of a method for installing a hyperbolic steel structure applicable to a building; Figure 4 A schematic diagram of a support frame for a method of installing a hyperbolic steel structure suitable for a building; Figure 5 A schematic diagram of step S103 of a method for installing a hyperbolic steel structure applicable to a building; Figure 6 A schematic diagram of step S105 of a method for installing a hyperbolic steel structure applicable to a building; Figure 7 It is a schematic diagram of step S107 of a method for installing a hyperbolic steel structure suitable for a building.
[0021] In the figure: 1. core tube; 2. steel structure component; 21. connecting piece; 22. steel structure unit; 221. main pipe; 2211. lifting plate; 3. tire frame component; 31. first tire frame; 311. support frame; 3111. vertical rod; 3112. horizontal rod; 3113. sliding part; 3114. lifting piece; 3115. reinforcing plate; 312. support frame connecting unit; 3121. sliding rod; 3122. connecting rod; 32. second tire frame; 4. lifting component; 41. main lifting rope; 42. auxiliary lifting rope; A. first coordinate point; B. second coordinate point; C. third coordinate point; D. fourth coordinate point; θ, angle. DETAILED DESCRIPTION
[0022] In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and the like are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, features defined as "first", "second", and the like may explicitly or implicitly include one or more of the features. In the description of the present invention, unless otherwise specified, "multiple" means two or more.
[0023] Embodiment 1:
[0024] A method for installing a hyperbolic steel structure suitable for a building, such as Figures 1 to 7As shown, the following steps are included: Step S101: Divide the steel structure unit 22 like Figure 2 , Figure 3 As shown, the building includes a core tube 1 and a steel structure component 2, and the steel structure component 2 is fixedly installed on the outer side of the core tube 1 through a connecting piece 21; according to the structural characteristics and the position of the structural connection point of the hyperbolic steel structure component 2, combined with the lifting capacity of the lifting machinery, the lifting environment of the work site and the assembly accuracy requirements, the steel structure component 2 is divided into a plurality of steel structure units 22, and each steel structure unit 22 is fixedly installed with a group of connecting pieces 21, and the steel structure unit 22 includes a plurality of main pipes 221, and the connecting piece 21 is fixedly installed on the main pipe 221, and a distance of 1 to 2 meters is left from the top of the main pipe 221; the size of the steel structure unit 22 is determined according to the number of the main pipes 221, and preferably, the steel structure unit 22 includes 2 to 3 groups of main pipes 221, and the corresponding width of the steel structure unit 22 is 10 to 20 meters.
[0025] When dividing the steel structure unit 22, Tekla Structures software and AutoCAD software are used to model and assemble the steel structure component 2. AutoCAD software is used to build a model of the steel structure component 2, establish the axis network, set the view, establish the main components, and establish the secondary components. After each step is completed, a data check is performed. The data check includes axis network data, elevation data, depth of sight data, working surface settings, rod material section specifications and points, etc.; finally, TeklaStructures software and AutoCAD software are used to draw, extract processing data and divide the steel structure unit 22. The plate unit, small parts, frame component 3, and assembly processing drawings are output through TeklaStructures software, and the AutoCAD software is secondary developed based on JAVA language.
[0026] When dividing the steel structure unit 22, the division is carried out according to the structural linear direction and the position of the support points of the steel structure component 2 to ensure the integrity of the structural components and the overall stiffness of the steel structure component 2. Since the change in the sagittal height of the steel structure unit 22 should not be too large to avoid difficulties in the bending processing of the curved panel parts in the later stage, on this basis, detailed division is carried out according to the on-site lifting capacity, the in-plant processing lifting capacity, and the restrictions of the ultra-high and ultra-wide conditions of transportation. The relative coordinates of the endpoints of each steel structure unit 22 in the model are extracted through the Tekla Structures software to determine the curvature change of the steel structure unit 22 plate, and the three-dimensional coordinates of the control points of each steel structure unit 22 are measured. The segmented component contour model is assembled in the model. The machining accuracy of the arc structure components is checked through the relative coordinates of the steel structure unit 22, and the fitting comparison is carried out with the theoretical model of the in-depth design. The machining and assembly accuracy is checked and analyzed, and the adjustment information required for modification is obtained. Correction, modification and simulated assembly are carried out until the accuracy requirements are met.
[0027] Step S103: Assembling steel structure unit 22 like Figure 5 As shown, in the model of Tekla Structures software, the steps for constructing the relative coordinates of the endpoints of the steel structure unit 22 are as follows: the four endpoint positions of the steel structure unit 22 are respectively set as the first coordinate point A, the second coordinate point B, the third coordinate point C and the fourth coordinate point D, one of the endpoint positions is set as the origin, the distance between the origin and the remaining endpoint positions is measured, the coordinates of the remaining endpoints are obtained, the endpoint coordinates of each steel structure unit 22 are extracted, the curvature change of the steel structure unit 22 is determined, and it is ensured that the arrow height change meets the processing requirements.
[0028] The components of the hyperbolic steel structure assembly 2 are all arc-shaped steel pipes. The bending process of the steel pipes adopts a cold working bending process combining a hydraulic press and a special forming mold. The bending equipment uses a large hydraulic press. A special mold is assembled according to the required specifications of the arc-shaped steel pipe, and the mold position is adjusted. During the bending process, a special master template is used to detect the forming quality. When local quality deviation is found, a heat correction process is used in conjunction with a jack for correction.
[0029] The coordinates of the first coordinate point A, the second coordinate point B, the third coordinate point C and the fourth coordinate point D of the steel structure unit 22 are transformed according to the actual coordinate system. According to the transformed X-axis and Y-axis projection points, the chord rod is placed on the X-axis and Y-axis projection lines, the elevation line, the inspection line and the fulcrum position, and the tire frame assembly 3 is set at the corresponding coordinate position. The overall size of the tire frame assembly 3 is adjusted by the control point, the chord rod is positioned on the tire frame assembly 3, and the components are spliced to form the steel structure unit 22. The maximum width of the tire frame assembly 3 corresponds to the width of the maximum width of the steel structure unit 22, and the maximum length corresponds to the length of the maximum length of the steel structure unit 22. When assembling the steel structure unit 22, the support point coordinates are determined by the three-dimensional model, and then the movement and lifting of the support frame 311 are controlled by the background computer, so that the tire frame assembly 3 is suitable for steel structure units 22 of various shapes.
[0030] like Figure 3 , Figure 4As shown, the tire frame assembly 3 includes a first tire frame 31 and a second tire frame 32 which are arranged in sequence. The first tire frame 31 includes a plurality of support frames 311 and support frame connecting units 312. The plurality of support frames 311 are arranged in two rows, and the plurality of support frames 311 in each row have different heights, so that the top ends of the two rows of support frames 311 form a curved structure corresponding to the curvature of the steel structure unit 22; the support frame connecting units 312 are fixedly installed between the support frames 311, and the support frame connecting units 312 include a plurality of sliding bars 3121 and a plurality of connecting bars 3122. The sliding bars 3121 which are arranged transversely are fixedly installed between the two rows of support frames 311 at intervals, and the connecting bars 3122 are fixedly installed between the bottom ends of the plurality of support frames 311, so that the plurality of support frames 3 11 forms an integral body; the main pipe 221 of the steel structure unit 22 is placed on the support frame 311, and the support frame 311 includes a pair of vertical rods 3111 and a pair of cross rods 3112. The cross rods 3112 are fixedly installed between the upper and lower ends of the pair of vertical rods 3111, respectively. The pair of vertical rods 3111 are separated from the middle, and the lower parts of the pair of vertical rods 3111 are fixedly installed on the bottom end surface of the sliding rod 3121. The upper parts of the pair of vertical rods 3111 are fixedly installed on the sliding part 3113. The sliding part 3113 is an inverted U-shaped structure and is slidably installed on the sliding rod 3121. A number of pulleys are rotatably installed on the inner sides of the sliding part 3113. The sliding rod 3121 is an I-beam structure. The pulleys are located on both sides of the web of the I-beam and between a pair of wing plates. The upper part of the rod 3111 is positioned to adapt to the size of the steel structure unit 22; a lifting piece 3114 is fixedly installed in the middle of the top surface of the sliding part 3113, and a cross bar 3112 located above is fixedly installed on the top part of the lifting piece 3114. A reinforcing plate 3115 is fixedly installed between the cross bar 3112 located above and a pair of vertical bars 3111. The reinforcing plate 3115 is a triangular structure, which strengthens the cross bar 3112 to improve the load-bearing capacity of the cross bar 3112 and limits the main pipe 221 to prevent the main pipe 221 from being misplaced during the assembly process, and a rubber strip is fixedly installed on the bevel edge of the reinforcing plate 3115 to prevent the reinforcing plate 3115 from wearing the main pipe 221; the lifting piece 3114 can be a hydraulic cylinder or a jack, etc. The lifting component can drive the cross bar 3112 to move up and down, thereby adapting to the curvature of the steel structure unit 22. The upper part of a pair of vertical rods 3111 can be set as a telescopic rod structure, or a slide groove can be set on the inner side of the upper part of the pair of vertical rods 3111, so that the cross bar 3112 and the reinforcing plate 3115 can slide up and down in the slide groove, which is convenient for the cross bar 3112 to move up and down; the structure of the second tire frame 32 is the same as that of the first tire frame 31, and it will not be repeated; the tire frame assembly 3 can be adjusted according to the size of the steel structure unit 22, and has strong applicability; when the curvatures of different steel structure units 22 are inconsistent, the heights of each support frame 311 are adjusted, and supported by the lifting member 3114, which is suitable for steel structure units 22 with different curvatures;When the widths of different steel structure units 22 are inconsistent, the position of the support frame 311 is adjusted by the slide bar 3121 and the sliding part 3113 to be suitable for steel structure units 22 of different widths. Preferably, the main pipe 221 is made of Q235B and has a size of 150mm×150mm×5mm. ;
[0031] When assembling the steel structure unit 22, the steel structure unit 22 is spliced on the first tire frame 31, and the bent main pipe 221 is hoisted, and the reflective patch is fixedly installed on the top of the main pipe 221. According to the preset first coordinate point A, second coordinate point B, third coordinate point C and fourth coordinate point D of the steel structure unit 22, the relative position of the main pipe 221 is checked. After the adjustment is correct, the remaining components are hoisted in sequence, and all nodes are fixed by welding to form the steel structure unit 22, and the connecting piece 21 is fixedly installed on the steel structure unit 22; after the steel structure unit 22 of the first tire frame 31 is spliced, the second tire frame 32 is used to fix the connecting piece 21 on the second tire frame 32. The same steps are followed to splice the next steel structure unit 22, and the main pipes 221 of the two steel structure units 22 are temporarily fixed by welding or other methods, so that the adjacent steel structure units 22 can be accurately docked and closed, ensuring the overall linear beauty of the steel structure assembly 2. After the steel structure units 22 of the second tire frame 32 are spliced, the temporary fixation of the two adjacent steel structure units 22 is released, the steel structure unit 22 of the first tire frame 31 is lifted off, and the steel structure unit 22 on the second tire frame 32 is lifted onto the first tire frame 31. Then, the same steps are followed to assemble the next steel structure unit 22 on the second tire frame 32, and this step is repeated until all the steel structure units 22 are assembled.
[0032] Step S105: Install the steel structure unit 22 like Figure 3 , Figure 6 As shown, the steel structure unit 22 is hoisted by four points, and hoisting plates 2211 are fixedly installed at both ends of the main pipe 221, wherein the main hoisting rope 41 is arranged on the two hoisting plates 2211 located at the upper end of the main pipe 221, and the main hoisting rope 41 is of fixed length, and the auxiliary hoisting rope 42 is arranged on the two hoisting plates 2211 located at the lower end of the main pipe 221, and the length of the auxiliary hoisting rope 42 is adjustable, and a hand chain hoist is arranged at the connection position between the auxiliary hoisting rope 42 and the hoisting plate 2211, and the length of the auxiliary hoisting rope 42 is adjusted by the hand chain hoist, and the model of the hand chain hoist matches the tension borne by the auxiliary hoisting rope 42 during the hoisting process of the steel structure unit 22; the steel structure unit 22 located below the curve vertex of the steel structure component 2, its hoisting plate 2211 is located outside the main pipe 221, and the steel structure unit 22 located above the curve vertex of the steel structure component 2, its hoisting plate 2211 is located inside the main pipe 221. Preferably, the length of the main hoisting rope 41 is 6m, 8m, etc.
[0033] Before assembling the steel structure unit 22, a combination of Tekla Structures software and AutoCAD software is used to pre-assemble the steel structure unit 22 through information simulation of Tekla Structures software, and AutoCAD software is used to draw three views of each steel structure unit 22, mark the center of gravity position, draw the component posture in the CAD drawing, and determine the length of the main lifting rope 41 and the auxiliary lifting rope 42.
[0034] During the lifting process, the hook of the lifting machinery always coincides with the center of gravity of the steel structure unit 22. The posture of the steel structure unit 22 in the air is adjusted by adjusting the length of the auxiliary lifting rope 42 to achieve the predetermined design posture of the steel structure unit 22. Before lifting, the steel structure unit 22 is lifted 10 cm from the ground, and the length of the auxiliary lifting rope 42 is adjusted by a hand winch until the posture of the steel structure unit 22 basically matches the design posture. Then, the steel structure unit 22 is moved to the designed position, and the posture of the steel structure unit 22 is fine-tuned again by the auxiliary lifting rope 42 to ensure that the steel structure unit 22 is accurately installed and positioned, and the posture is correct.
[0035] Step S107: Detect the position of the steel structure unit 22 During the hoisting process, a positioning and measuring device is used to adjust the installation position of the steel structure unit 22. The positioning and measuring device includes an infrared transmitting device, an infrared receiving device, a signal transmitting device, a signal receiving device, a power supply and a computer. The infrared transmitting device transmits infrared rays to the reflective patch of the main pipe 221. After the infrared receiving device receives the infrared signal reflected by the reflective patch, the infrared signal is transmitted to the remote end through the signal transmitting device. After the signal receiving device receives the signal at the remote end, it is transmitted to the computer. Through computer simulation calculation, the position relationship of the main pipe 221 of adjacent steel structure units 22 can be measured in real time and fed back to the construction workers. The construction workers operate the hand winch to adjust the posture of the steel structure unit 22, so as to better control the overall shape of the hyperbola; the power supply is used to power the entire system, and the power supply adopts a battery.
[0036] like Figure 7 As shown in the figure, a coordinate system is established on the ground, and the coordinates of the center position of the core tube 1 on the ground are set to (0,0,0). Starting from the north direction, the coordinates of the column foot or the bottom end of the main tube 221 at the bottom are set to (0,Y,0), (X1,Y1,0), (X2,Y2,0)... (X n ,Y n ,0), are calculated according to the outer diameter of the steel pipe; from the ground upward to each steel structure unit 22, the outer diameter reduction value of the steel structure is set to ΔS1, ΔS2, ΔS3...ΔS n, taking the first steel structure unit 22 (at an elevation of 13.5m) as an example, the coordinate point to be measured is connected with the origin, and the angle between the connecting line and the true north direction is set to θ. The coordinates of the endpoints of each steel structure unit 22 can be obtained as (X1-ΔS1×cosθ, Y1-ΔS1×sinθ, Z1), (X2-ΔS1×cosθ, Y2-ΔS1×sinθ, Z1)... (X n -ΔS1×cosθ,Y n -ΔS1×sinθ, Z1), and so on, to find the coordinates of each measuring point of each steel structure unit 22.
[0037] The center of the core tube 1 and the design positions of the main pipes 221 of several steel structure units 22 are connected and extended to obtain several axes, and control points are set on the axes, and the number of control points corresponds to the number of main pipes 221; a total station is used to measure the three-dimensional coordinates of the control points and a station is established at the control points, and the design coordinates of the reflective patches of the main pipes 221 are calculated by AutoCAD software. During the measurement process, the located reflective patches are used as monitoring points, and the three-dimensional coordinates of the reflective patches are read by the total station and compared with the design coordinates of the reflective patches. The steel structure unit 22 is adjusted to the design position, and after confirmation, it is welded and fixed, thereby realizing the precise positioning and installation of the steel structure unit 22.
[0038] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A method for installing a hyperbolic steel structure suitable for a building, the building comprising a core tube (1) and a steel structure component (2), the steel structure component (2) being fixedly installed on the outside of the core tube (1), characterized in that: The following steps are involved: Step S101: Divide the steel structure into units (22) Establishing a model of the steel structure component (2), and dividing the steel structure component (2) into a plurality of steel structure units (22) in the model; Step S103: Assembling steel structure units (22) Assembling the steel structure unit (22) on the tire frame assembly (3); Step S105: Installing the steel structure unit (22) Hoisting the assembled steel structure unit (22) using a hoisting assembly (4), and adjusting the posture of the steel structure unit (22) during the hoisting; Step S107: Detect the position of the steel structure unit (22) The actual coordinates of a plurality of the steel structure units (22) are measured respectively and compared with the design coordinates, and the positions of the steel structure units (22) are adjusted and fixedly mounted on the core tube (1).
2. A method for installing a hyperbolic steel structure suitable for a building according to claim 1, characterized in that: In the step S103 of assembling the steel structure unit (22), the coordinates of the first coordinate point (A), the second coordinate point (B), the third coordinate point (C), and the fourth coordinate point (D) at the end of the steel structure unit (22) are converted into projection points on the X-axis and the Y-axis, and the positions of both sides of the tire frame assembly (3) are adjusted to the projection points, so as to be suitable for installing steel structure units (22) of different sizes.
3. A method for installing a hyperbolic steel structure suitable for a building according to claim 2, characterized in that: In the step S103 of assembling the steel structure unit (22), the tire frame assembly (3) comprises a first tire frame (31) and a second tire frame (32) which are arranged in sequence, and the steel structure unit (22) is assembled on the first tire frame (31) and the second tire frame (32) respectively; After the assembly is completed, the steel structure unit (22) on the first tire frame (31) is lifted away, the steel structure unit (22) on the second tire frame (32) is moved to the first tire frame (31), and the next steel structure unit (22) is assembled on the second tire frame (32); When assembling the steel structure units (22), temporarily fixing the two steel structure units (22) on the first tire frame (31) and the second tire frame (32), and releasing the temporary fixing after the assembly is completed; This step is repeated until all the steel structure units (22) are assembled.
4. A method for installing a hyperbolic steel structure suitable for a building according to claim 3, characterized in that: The first tire frame (31) comprises a plurality of support frames (311) and support frame connecting units (312); the plurality of support frames (311) are arranged in two rows; the bottom ends of the two rows of support frames (311) are fixedly mounted together via the support frame connecting units (312); and the steel structure unit (22) is placed on the support frames (311).
5. A method for installing a hyperbolic steel structure suitable for a building according to claim 4, characterized in that: The support frame connection unit (312) comprises a plurality of sliding rods (3121) and a plurality of connecting rods (3122); the sliding rods (3121) are fixedly installed between two rows of the support frames (311); and the bottom ends of the plurality of support frames (311) are fixedly installed together via the connecting rods (3122).
6. A method for installing a hyperbolic steel structure suitable for a building according to claim 5, characterized in that: The support frame (311) comprises a pair of vertical rods (3111) and a pair of horizontal rods (3112); the pair of vertical rods (3111) are divided into an upper part and a lower part; the top end of the lower part of the vertical rod (3111) is fixedly mounted on the bottom end surface of the sliding rod (3121); a sliding part (3113) is slidably mounted on the sliding rod (3121); and the upper part of the vertical rod (3111) is fixedly mounted on the sliding part (3113); The cross bar (3112) is fixedly mounted between the upper parts and the lower parts of a pair of vertical bars (3111), respectively; Reinforcement plates (3115) are fixedly mounted on both ends of the cross bar (3112) located at the top, and are suitable for limiting the position of the steel structure unit (22).
7. A method for installing a hyperbolic steel structure suitable for a building according to claim 6, characterized in that: The bottom end of the lifting member (3114) is fixedly mounted on the sliding portion (3113), and the top end of the lifting member (3114) is fixedly mounted on the cross bar (3112), which is suitable for driving the cross bar (3112) to move up and down.
8. A method for installing a hyperbolic steel structure suitable for a building according to claim 7, characterized in that: In the step S105 of installing the steel structure unit (22), the hoisting assembly (4) comprises a pair of main hoisting ropes (41) and a pair of auxiliary hoisting ropes (42), wherein the pair of main hoisting ropes (41) are fixedly installed on both sides of the top end of the steel structure unit (22), and the pair of auxiliary hoisting ropes (42) are installed on both sides of the bottom end of the steel structure unit (22) via a hand chain hoist; After the steel structure unit (22) is lifted off the ground, the length of the auxiliary lifting rope (42) is adjusted by the hand chain hoist, thereby adjusting the lifting posture of the steel structure unit (22) until it meets the designed posture of the steel structure unit (22).
9. A method for installing a hyperbolic steel structure suitable for a building according to claim 8, characterized in that: In the step S107, in detecting the position of the steel structure unit (22), a connecting line is drawn between the center of the core tube (1) and a plurality of the steel structure units (22) and the connecting lines are extended, and control points are respectively set on the plurality of connecting lines; A reflective sheet is fixedly mounted on the top end of the steel structure unit (22), the three-dimensional coordinates of the reflective sheet are measured at the control point, and compared with the theoretical coordinates of the reflective sheet; when the comparison results are consistent, the steel structure unit (22) is welded and fixed.
10. A method for installing a hyperbolic steel structure suitable for a building according to claim 9, characterized in that: In the step S107 of detecting the position of the steel structure unit (22), the steps of establishing the three-dimensional coordinates of the reflective sheet are as follows: The coordinates of the center position of the core tube (1) on the ground are set to (0, 0, 0), and the coordinates of the reflective sheet at the bottom are set to (0, Y, 0), (X1, Y1, 0), (X2, Y2, 0) ... (X n ,Y n ,0), the outer diameter reduction values from the ground upward to each of the steel structure units (22) are set to ΔS1, ΔS2, ΔS3...ΔS in sequence. n ; The line connecting the steel structure unit (22) and the center of the core tube (1) has an angle (θ) with the north direction, and the coordinates of each of the reflective sheets are respectively (X1-ΔS1×cosθ, Y1-ΔS1×sinθ, Z1), (X2-ΔS1×cosθ, Y2-ΔS1×sinθ, Z1)...(X n -ΔS1×cosθ,Y n -ΔS1×sinθ,Z1).
Citation Information
Patent Citations
Lotus tower steel structure construction method
CN115162520A
Double-curved-surface metal curtain wall unit type installation construction method capable of achieving error compensation
CN117569610A
Design and construction method of flower basket type steel structure between buildings
CN118531896A
Truss position adjusting device of double-curved-surface steel structure dome
CN219411915U
Mounting device for variable-cross-section special-shaped steel tower crown
CN219604164U
Cited By
Membrane structure for variable cross-section observatory
CN122061614A
A membrane structure for a variable cross-section observatory
CN122061614B