Large canopy with steel structure and construction method

By adopting rigid-connected and hinged design and modular installation methods in steel structure canopies, combined with hot-dip galvanized treatment and aluminum alloy panels, the deformation and corrosion problems of steel structure canopies are solved, and vibration resistance and installation accuracy are improved. , extends service life.

CN119041555AInactive Publication Date: 2024-11-29GUANGZHOU JISHI CONSTR GRP +2
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411310924.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-20
Publication Date
2024-11-29
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

During the installation process, large steel structure canopies are prone to internal force and temperature deformation, and have poor vibration resistance and low welding connection accuracy, which can easily lead to glass cracking, water leakage, steel corrosion and other problems.

Method used

Adopt the reasonable combination of rigid joints and hinges, and the steel frame structure is split in sections and split into diamond-shaped units for modular installation, reducing the workload of high-altitude welding, using hot-dip galvanized treatment and aluminum alloy panels for protection, and through multi-directional stainless steel joint claws Secure the glass and decorative panels and fill the gaps with sealant.

Benefits of technology

Effectively reduce temperature deformation, improve vibration resistance, ensure installation accuracy and safety, extend the service life of the steel structure, and prevent glass leakage and steel corrosion.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041555A_ABST
    Figure CN119041555A_ABST
Patent Text Reader

Abstract

The invention discloses a steel structure canopy and a construction method, and relates to the technical field of building construction, a steel frame structure is formed by splicing more than two steel frame units, and each steel frame unit comprises a rhombic stress main beam and a triangular stress secondary beam arranged on the inner side of the stress main beam; the stress main beams of the adjacent steel frame units are rigidly connected or hinged, the stress secondary beams are provided with multidirectional stainless steel connecting claws, the glass panels and the decoration panels are fixedly installed on the stress secondary beams through the multidirectional stainless steel connecting claws, and the glass panels and the decoration panels are evenly arranged in an alternating mode. According to the large canopy of the steel structure, through reasonable matching of rigid connection and hinge connection, temperature deformation is effectively reduced, and the anti-vibration capacity is improved; the steel frame structure is divided into the rhombic steel frame units in a segmented mode, modular installation is carried out, the high-altitude welding workload is reduced, meanwhile, high-altitude operation is reduced, and the installation precision and safety of the large steel structure canopy are guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of building construction, and more specifically, to a large steel structure canopy and a construction method thereof. Background Art

[0002] At present, the structural design of large steel canopies generally adopts a rigid structure, that is, it is fixed by welding or bolting. Large-span canopies are prone to internal force deformation and temperature deformation. Expansion joints are generally used to reduce the deformation of large-span canopies. If the expansion joints are set too short, it will be unsightly. If they are set too long, the internal force cannot be eliminated, which can easily cause the canopy glass to crack and leak, and the vibration resistance is poor.

[0003] However, the above scheme has the following defects: 1) The steel structure has a large span, and the canopy installation is prone to internal force deformation and temperature deformation; 2) The steel structure canopy requires welding of a large amount of steel, and the installation accuracy is low; 3) The steel structure canopy is exposed to the external environment for a long time, and the steel is prone to corrosion. Summary of the invention

[0004] In order to overcome the defects of the prior art, the present invention proposes a steel structure canopy and a construction method, which effectively reduces temperature deformation and improves vibration resistance by designing a reasonable combination of rigid connection and hinged connection; the steel frame structure is divided into diamond-shaped steel frame units and modularly installed, which greatly reduces the workload of high-altitude welding and high-altitude operations, ensures the installation accuracy and safety of the steel structure canopy, and improves construction efficiency; the steel frame structure is hot-dip galvanized, and an aluminum alloy panel is set on the surface for protection, which improves durability.

[0005] To achieve this object, the present invention adopts the following technical solutions:

[0006] The present invention provides a large steel structure canopy, comprising a steel frame structure, multi-directional stainless steel connecting claws, a glass panel and a decorative panel. The steel frame structure is composed of more than two steel frame units spliced ​​together. The steel frame unit comprises a rhombus-shaped load-bearing main beam and a triangular load-bearing secondary beam arranged on the inner side of the load-bearing main beam. The load-bearing main beams of adjacent steel frame units are rigidly connected or hinged. Multi-directional stainless steel connecting claws are arranged on the load-bearing secondary beams. The glass panel and the decorative panel are fixedly installed on the load-bearing secondary beams by the multi-directional stainless steel connecting claws, and the glass panel and the decorative panel are alternately and evenly arranged.

[0007] In a preferred technical solution of the present invention, the glass panel is tempered laminated glass, and the decorative panel is tempered colored glaze laminated glass.

[0008] In a preferred technical solution of the present invention, a connection gap between the glass panel and the decorative panel is filled with sealant.

[0009] In a preferred technical solution of the present invention, an aluminum alloy cover plate is further provided on the load-bearing secondary beam to cover the connection gap between the glass panel and the decorative panel.

[0010] The present invention also provides a construction method of a steel structure large rain canopy, comprising the following steps:

[0011] S1. Installation of embedded parts: After the reinforcement of the civil engineering slab surface is tied, the elevation is marked with a level, and the total station is used for positioning. The embedded parts are spot welded to the reinforcement and fixed, and the anchor bars are supported on the bottom mold to prevent the elevation from being affected when pouring concrete;

[0012] S2. Installation of steel columns: The steel columns are installed by rotating method. The lifting point, column foot and the center point of the foundation cup of the steel column are arranged on the operating radius line of the crane, so that when the crane is lifting, only the boom needs to be rotated to insert the column, and the crane does not need to move;

[0013] S3. The steel frame structure is divided into diamond-shaped steel frame units: the load-bearing main beams and the load-bearing secondary beams are processed and assembled into diamond-shaped steel frame units in the factory, and then transported to the site for installation;

[0014] S4. Steel frame units are hoisted in blocks and connected on site: After the steel frame units are transported to the site, first check whether the span between adjacent steel columns is consistent with the actual length of the steel frame units. When it is confirmed to be correct, use a level and a total station to lay out the elevation control line and coordinate axis of the steel frame units. The main beam bearing the load should also lay out the hoisting axis of the hoisting auxiliary line of the axis before starting to hoist each frame in sequence. Each steel frame unit hoisted must be fixed immediately before starting to hoist the second one; when the steel frame unit needs to be turned over and lifted, the two-point turning and lifting method is used, and short steel pipes and square wood are used to temporarily assist in lifting the board, and the on-site inspection is carried out;

[0015] S5. Install glass panels and decorative panels: ① Installation and welding of multi-directional stainless steel joint claws: pop up the vertical and horizontal lines and the design elevation according to the design size, clamp with a clamp, perform positioning spot welding, and after assembly, weld the glass claw base;

[0016] ②Glass installation: Both glass panels and decorative panels are triangular glass plates. After the multi-directional stainless steel joint claws are installed, the glass plates are installed. Gently move the glass plates to the left and right and push them into the pressure plate. Adjust them after the glass is temporarily fixed. The adjustment standards are horizontal, vertical, and flat, and the deviation must not exceed the specified deviation. After adjustment, tighten the bolts; glass plates are installed according to the plate number diagram, and plates with different numbers must not be interchanged during the construction process. At the same time, pay attention to the relationship between the inner and outer plates to prevent color variation after the glass is installed;

[0017] ③ Gluing glass: fully clean the gaps between glass panels, and there should be no water, oil stains, dust and other debris. The bonding surface should be fully cleaned and dried. The thickness of the glue should be 1 / 2 of the seam width. The glue must be applied evenly, and the continuous and full glue must be smooth. The joints should not have defects such as bumps and lines. The silicone building sealant should be bonded on two sides in the joints, not on three sides. The tape should be firmly and densely applied, and the corners and joints should be connected smoothly and close to the edge of the board. The tape should not be opened, fall off, or not straight when it is pasted. After gluing, the tape should be cleaned in time when the glue is about to dry, and the glue surface damaged by tearing the tape should be dealt with immediately. The thickness of the glue should not be too thin or too thick, and pay attention to the width-to-thickness ratio. After gluing, clean the glue that contaminates the board surface in time.

[0018] In a preferred technical solution of the present invention, in step S2, in order to improve the lifting efficiency, when stacking the steel columns, the binding points of the steel columns, the center of the column foot and the center of the foundation are made to form a common arc as much as possible.

[0019] In the preferred technical solution of the present invention, in step S4, before the steel frame unit is hoisted, the steel corbel beam along the original building is first installed, and the top support must be done before installing the first unit steel truss. The top support adopts φ219 round tube from the ground to the bottom elevation of the steel truss, and a temporary top support is set at an interval of 6m. During installation, ensure that each unit steel truss has 4 points of top support, that is, the 2 inner points are steel corbel supports, and the 2 outer points are temporary top supports of φ219 round tubes. After in place, wait until the 2 inner steel corbel beams are firmly welded before unhooking.

[0020] In the preferred technical solution of the present invention, after the temporary support top is installed, the steel frame unit is hoisted, and it is necessary to conduct multiple trial hoists and re-tie the lifting cables in time. During the trial hoisting, the crane must rise slowly to ensure that the force at each lifting point is evenly distributed and the steel frame unit is not deformed as the best state. After meeting the requirements, it is hoisted and rotated to the designed position, and then the control rope pre-fastened on the load-bearing main beam of the steel frame unit is pulled manually on the ground. After it is rotated into place, the column beam hole position can be determined with a pliers and fixed with high-strength bolts.

[0021] In a preferred technical solution of the present invention, in step S4, a review is required when hoisting the steel frame unit, and the wire rope cable is checked by a hoist, and the cable can be released only after the load-bearing main beam of the steel frame unit is installed.

[0022] In a preferred technical solution of the present invention, in step S5, the glass panels are adjusted according to the grid steel wires, the height difference between adjacent glass panels is controlled to be <1 mm, and the seam width is controlled to be ±1 mm.

[0023] The beneficial effects of the present invention are:

[0024] A large steel structure canopy proposed in the present invention effectively reduces temperature deformation and improves vibration resistance by designing a reasonable combination of rigid connection and hinge connection; the steel frame structure is divided into diamond-shaped steel frame units and modularly installed, which greatly reduces the workload of high-altitude welding and high-altitude operations, ensures the installation accuracy and safety of the large steel structure canopy, and improves construction efficiency; the steel frame structure is hot-dip galvanized, and an aluminum alloy panel is used on the surface of the steel beam for protection to avoid contact with the external environment, thereby improving durability and providing an empirical basis for similar canopies in the future. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a structural schematic diagram of a large steel structure canopy provided by a specific embodiment of the present invention;

[0026] Figure 2 yes Figure 1 A partial enlarged view of the middle A;

[0027] Figure 3 yes Figure 1 A cross-sectional view of

[0028] Figure 4 yes Figure 3 A partial enlarged view of point B in the middle;

[0029] Figure 5 The present invention provides a flowchart of a construction method for a large steel structure canopy according to a specific embodiment of the present invention.

[0030] In the figure:

[0031] 1. Steel frame structure; 11. Load-bearing main beam; 12. Load-bearing secondary beam; 2. Multi-directional stainless steel connecting claws; 3. Glass panel; 4. Decorative panel; 5. Aluminum alloy cover plate. DETAILED DESCRIPTION

[0032] The technical solution of the present invention is further described below with reference to the accompanying drawings and through specific implementation methods.

[0033] like Figure 1-5As shown, a steel structure canopy is provided in the embodiment, including a steel frame structure 1, a multi-directional stainless steel docking claw 2, a glass panel 3 and a decorative panel 4. The steel frame structure 1 is composed of two or more steel frame units. The steel frame unit includes a diamond-shaped load-bearing main beam 11 and a triangular load-bearing secondary beam 12 arranged inside the load-bearing main beam 11. The load-bearing main beams 11 of adjacent steel frame units are rigidly connected or hinged. The load-bearing secondary beams 12 are provided with multi-directional stainless steel docking claws 2. The glass panels 3 and the decorative panels 4 are fixedly installed on the load-bearing secondary beams 12 through the multi-directional stainless steel docking claws 2, and the glass panels 3 and the decorative panels 4 are alternately and evenly arranged. In this embodiment, the load-bearing main beam 11 is designed as a diamond-shaped steel structure, which mainly bears all the loads of the canopy. The load-bearing secondary beam 12 is a triangular steel structure, which mainly bears the load of the canopy glass. The steel frame structure 1 composed of a plurality of load-bearing main beams 11 and a plurality of load-bearing secondary beams 12 is a mesh structure. By designing a reasonable combination of rigid connection and hinge, the temperature deformation of the steel frame structure 1 can be effectively reduced and the earthquake resistance can be improved. The load-bearing secondary beam 12 separates the inner side of the load-bearing main beam 11 into more than two glass grids. The glass grids are designed as equilateral triangles of 1.5m, and the glass panels 3 and decorative panels 4 correspond to the glass grids one by one. The multi-directional stainless steel docking claws 2 are used to fix the glass panels 3 and the decorative panels 4. The multi-directional stainless steel docking claws 2 are composed of a docking claw base, a docking claw body and a stainless steel docking head. The docking claw base is fixed to the load-bearing secondary beam 12 by welding, and the stainless steel docking head is clamped in the fixing hole on the glass to fix the glass. The glass panels 3 and the decorative panels 4 are arranged alternately and evenly, which helps to improve the aesthetics of the canopy.

[0034] Specifically, the glass panel 3 is a tempered laminated glass, and the decorative panel 4 is a tempered colored glaze laminated glass.

[0035] Specifically, the connection gap between the glass panel 3 and the decorative panel 4 is filled with sealant. In this embodiment, the sealant is silicone building sealant, and the sealant can prevent rainwater from leaking through the gap.

[0036] Specifically, an aluminum alloy cover plate 5 is also provided on the stress-bearing secondary beam 12 to cover the connection gap between the glass panel 3 and the decorative panel 4. In this embodiment, the aluminum alloy cover plate 5 is located on the top surface of the glass panel 3 and the decorative panel 4, and the aluminum alloy cover plate 5 is connected to the stress-bearing secondary beam 12 through a 4 mm thick stainless steel plate. The aluminum alloy cover plate 5 is provided to cover the gap and improve the aesthetics on the one hand, and to assist in fixing the glass panel 3 and the decorative panel 4 on the other hand.

[0037] This embodiment also provides a construction method of a steel structure canopy, comprising the following steps:

[0038] S1. Installation of embedded parts: After the reinforcement of the civil engineering slab surface is tied, the elevation is marked with a level, and the total station is used for positioning. The embedded parts are spot welded to the reinforcement and fixed, and the anchor bars are supported on the bottom mold to prevent the elevation from being affected when pouring concrete;

[0039] S2. Installation of steel columns: The steel columns are hoisted by the rotation method. The lifting points, column feet and the center point of the foundation cup of the steel columns are arranged on the operating radius line of the crane, so that when the crane is hoisted, only the boom rotation is required to insert the column without the need for the crane to move. To improve the hoisting efficiency, when stacking the steel columns, try to make the binding points of the steel columns, the center of the column feet and the center of the foundation coexist in a circular arc;

[0040] S3. The steel frame structure is divided into diamond-shaped steel frame units: the load-bearing main beam and the load-bearing secondary beam are processed and assembled into diamond-shaped steel frame units in the factory. The side length of the equilateral diamond steel frame structure is 4.5m, and the inside of the diamond is 18 equilateral triangles with a side length of 1.5m. After the assembly is completed, it is transported to the site for installation;

[0041] S4. Steel frame units are hoisted in blocks and connected on site: After the steel frame units are transported to the site, first check whether the span between adjacent steel columns is consistent with the actual length of the steel frame units. When you are sure that it is correct, use a level and a total station to lay out the elevation control line and coordinate axis of the steel frame unit. The load-bearing main beam must also lay out the hoisting axis of the hoisting auxiliary line of the axis before you can start hoisting each frame in sequence. Each hoisted steel frame unit must be fixed immediately before you can start hoisting the second one; when the steel frame unit needs to be turned over and lifted for straightening, the two-point turning and lifting method is used, and short steel pipes and square wood are used to temporarily assist in lifting the board, and on-site inspection is carried out; before the steel frame unit is hoisted, the steel corbel beam along the original building is first installed. Before installing the first unit steel truss, the top support must be done. The top support uses a φ219 round tube from the ground to the bottom elevation of the steel truss, and a temporary top support is set up at intervals of 6m, and During installation, ensure that each unit steel truss has 4 points of support, that is, the 2 points on the inner side are supported by steel bull legs, and the 2 points on the outer side are temporarily supported by φ219 round tubes. After they are in place, wait until the 2 inner steel bull leg beams are welded firmly before unhooking; after the temporary support is installed, the steel frame unit needs to be hoisted for many times and the slings need to be re-tied in time. During the trial hoisting, the crane must rise slowly to ensure that the force at each lifting point is even and the steel frame unit is not deformed as the best state. After meeting the requirements, it will be hoisted and rotated to the designed position, and then the control rope pre-fastened on the main beam of the steel frame unit will be pulled manually on the ground. After it is rotated into place, the column beam hole position can be determined with a pliers, and fixed with high-strength bolts; when hoisting the steel frame unit, it must be reviewed and checked with a hoist to pull the wire rope cable. The cable can be released only after the main beam of the steel frame unit is installed;

[0042] S5. Install glass panels and decorative panels: ① Installation and welding of multi-directional stainless steel joint claws: pop up the vertical and horizontal lines and the design elevation according to the design size, clamp with a clamp, perform positioning spot welding, and after assembly, weld the glass claw base;

[0043] ②Glass installation: Both glass panels and decorative panels are made of triangular glass plates. After the multi-directional stainless steel joint claws are installed, the glass plates are installed. The glass plates are gently moved left and right and pushed into the pressure plate. After the glass is temporarily fixed, they are adjusted. The adjustment standards are horizontal, vertical, and flat, and the deviation must not exceed the specified deviation. The glass plates are adjusted according to the grid steel wires. After adjustment, the bolts are tightened. The height difference of adjacent glass plates is controlled within <1mm, and the seam width is controlled within ±1mm; the glass plates are installed according to the plate number diagram, and plates with different numbers must not be interchanged during the construction process. At the same time, pay attention to the relationship between the inner and outer plates to prevent color variation after the glass is installed;

[0044] ③ Gluing glass: fully clean the gaps between glass panels, and there should be no water, oil stains, dust and other debris. The bonding surface should be fully cleaned and dried. The thickness of the glue should be 1 / 2 of the seam width. The glue must be applied evenly, and the continuous and full glue must be smooth. The joints should not have defects such as bumps and lines. The silicone building sealant should be bonded on two sides in the joints, not on three sides. The tape should be firmly and densely applied, and the corners and joints should be connected smoothly and close to the edge of the board. The tape should not be opened, fall off, or not straight when it is pasted. After gluing, the tape should be cleaned in time when the glue is about to dry, and the glue surface damaged by tearing the tape should be dealt with immediately. The thickness of the glue should not be too thin or too thick, and pay attention to the width-to-thickness ratio. After gluing, clean the glue that contaminates the board surface in time.

[0045] The present invention is described by preferred embodiments, and those skilled in the art will appreciate that various changes or equivalent substitutions may be made to these features and embodiments without departing from the spirit and scope of the present invention. The present invention is not limited to the specific embodiments disclosed herein, and other embodiments falling within the claims of this application are within the scope of protection of the present invention.

Claims

1. A steel structure canopy, characterized by: The invention comprises a steel frame structure (1), a multi-directional stainless steel connecting claw (2), a glass panel (3) and a decorative panel (4), wherein the steel frame structure (1) is composed of two or more steel frame units spliced ​​together, wherein the steel frame unit comprises a rhombus-shaped load-bearing main beam (11) and a triangular load-bearing secondary beam (12) arranged inside the load-bearing main beam (11), and the load-bearing main beams (11) of adjacent steel frame units are rigidly connected or hinged, and the load-bearing secondary beam (12) is provided with a multi-directional stainless steel connecting claw (2), and the glass panel (3) and the decorative panel (4) are fixedly mounted on the load-bearing secondary beam (12) through the multi-directional stainless steel connecting claw (2), and the glass panel (3) and the decorative panel (4) are alternately and evenly arranged.

2. A steel structure canopy according to claim 1, characterized in that: The glass panel (3) is tempered laminated glass, and the decorative panel (4) is tempered colored glaze laminated glass.

3. The steel structure canopy according to claim 1, characterized in that: The connection gap between the glass panel (3) and the decorative panel (4) is filled with sealant.

4. A steel structure canopy according to claim 3, characterized in that: An aluminum alloy cover plate (5) is also provided on the load-bearing secondary beam (12) for covering the connection gap between the glass panel (3) and the decorative panel (4).

5. A construction method for a steel structure canopy according to any one of claims 1 to 4, characterized in that: The following steps are involved: S1. Installation of embedded parts: After the reinforcement of the civil engineering slab surface is tied, the elevation is marked with a level, and the total station is used for positioning. The embedded parts are spot welded to the reinforcement and fixed, and the anchor bars are supported on the bottom mold to prevent the elevation from being affected when pouring concrete; S2. Installation of steel columns: The steel columns are installed by rotating method. The lifting point, column foot and the center point of the foundation cup of the steel column are arranged on the operating radius line of the crane, so that when the crane is lifting, only the boom needs to be rotated to insert the column, and the crane does not need to move; S3. The steel frame structure is divided into diamond-shaped steel frame units: the load-bearing main beams and the load-bearing secondary beams are processed and assembled into diamond-shaped steel frame units in the factory, and then transported to the site for installation; S4. Steel frame units are hoisted in blocks and connected on site: After the steel frame units are transported to the site, first check whether the span between adjacent steel columns is consistent with the actual length of the steel frame units. When it is confirmed to be correct, use a level and a total station to lay out the elevation control line and coordinate axis of the steel frame units. The main beam bearing the load should also lay out the hoisting axis of the hoisting auxiliary line of the axis before starting to hoist each frame in sequence. Each steel frame unit hoisted must be fixed immediately before starting to hoist the second one; when the steel frame unit needs to be turned over and lifted, the two-point turning and lifting method is used, and short steel pipes and square wood are used to temporarily assist in lifting the board, and the on-site inspection is carried out; S5. Install glass panels and decorative panels: ① Installation and welding of multi-directional stainless steel joint claws: pop up the vertical and horizontal lines and the design elevation according to the design size, clamp with a clamp, perform positioning spot welding, and after assembly, weld the glass claw base; ②Glass installation: Both glass panels and decorative panels are triangular glass plates. After the multi-directional stainless steel joint claws are installed, the glass plates are installed. Gently move the glass plates to the left and right and push them into the pressure plate. Adjust them after the glass is temporarily fixed. The adjustment standards are horizontal, vertical, and flat, and the deviation must not exceed the specified deviation. After adjustment, tighten the bolts; glass plates are installed according to the plate number diagram, and plates with different numbers must not be interchanged during the construction process. At the same time, pay attention to the relationship between the inner and outer plates to prevent color variation after the glass is installed; ③ Gluing glass: fully clean the gaps between glass panels, and there should be no water, oil stains, dust and other debris. The bonding surface should be fully cleaned and dried. The thickness of the glue should be 1 / 2 of the seam width. The glue must be applied evenly, and the continuous and full glue must be smooth. The joints should not have defects such as bumps and lines. The silicone building sealant should be bonded on two sides in the joints, not on three sides. The tape should be firmly and densely applied, and the corners and joints should be connected smoothly and close to the edge of the board. The tape should not be opened, fall off, or not straight when it is pasted. After gluing, the tape should be cleaned in time when the glue is about to dry, and the glue surface damaged by tearing the tape should be dealt with immediately. The thickness of the glue should not be too thin or too thick, and pay attention to the width-to-thickness ratio. After gluing, clean the glue that contaminates the board surface in time.

6. The construction method of a steel structure canopy according to claim 5, characterized in that: In step S2, in order to improve the lifting efficiency, when stacking the steel columns, try to make the binding points of the steel columns, the center of the column foot and the center of the foundation share a common arc.

7. The construction method of a steel structure canopy according to claim 5, characterized in that: In step S4, before the steel frame unit is hoisted, the steel corbel beam along the original building is first installed. Before installing the first unit steel truss, support must be done. The support uses a φ219 round tube from the ground to the bottom elevation of the steel truss, and a temporary support is set at an interval of 6m. During installation, ensure that each unit steel truss has 4 points of support, that is, the 2 inner points are steel corbel support, and the 2 outer points are φ219 round tube temporary support. After in place, wait until the 2 inner steel corbel beams are welded firmly before unhooking.

8. The construction method of a steel structure canopy according to claim 7, characterized in that: After the temporary support top is installed, the steel frame unit is hoisted. It is necessary to conduct multiple trial lifts and re-tie the lifting cables in time. During the trial lift, the crane must rise slowly to ensure that the force at each lifting point is evenly distributed and the steel frame unit is not deformed. After meeting the requirements, it is lifted and rotated to the designed position, and then the control rope pre-fastened on the load-bearing main beam of the steel frame unit is pulled manually on the ground. After it is rotated into place, the column beam hole position can be determined with a pliers and fixed with high-strength bolts.

9. The construction method of a steel structure canopy according to claim 5, characterized in that: In step S4, a review is required when the steel frame unit is hoisted, and the wire rope cable is checked by using a hoist, and the cable can be released only after the load-bearing main beam of the steel frame unit is installed.

10. The construction method of a steel structure canopy according to claim 5, characterized in that: In step S5, the glass panels are adjusted according to the grid steel wires, and the height difference between adjacent glass panels is controlled to be <1 mm, and the seam width is controlled to be ±1 mm.

Citation Information

Patent Citations

  • Yarn ball spherical curtain wall structure

    CN110397196A

  • Fabricated building bottom layer combined floor and connecting method thereof

    CN111270801A

  • Large daylighting roof type canopy and construction method thereof

    CN112695964A

  • Novel space quadrilateral mesh structure for single-layer latticed shell

    CN204356969U

  • Connection structure of stone material curtain middling pressure roof piece

    CN205000515U